CN105605308B - Municipal blow-off line laying construction method - Google Patents

Municipal blow-off line laying construction method Download PDF

Info

Publication number
CN105605308B
CN105605308B CN201510559943.2A CN201510559943A CN105605308B CN 105605308 B CN105605308 B CN 105605308B CN 201510559943 A CN201510559943 A CN 201510559943A CN 105605308 B CN105605308 B CN 105605308B
Authority
CN
China
Prior art keywords
concrete
briquetting
cushion block
piece
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510559943.2A
Other languages
Chinese (zh)
Other versions
CN105605308A (en
Inventor
随路路
孟令刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Stecol Corp
Original Assignee
Sinohydro Tianjin Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Tianjin Engineering Co Ltd filed Critical Sinohydro Tianjin Engineering Co Ltd
Priority to CN201510559943.2A priority Critical patent/CN105605308B/en
Publication of CN105605308A publication Critical patent/CN105605308A/en
Application granted granted Critical
Publication of CN105605308B publication Critical patent/CN105605308B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Sewage (AREA)
  • Foundations (AREA)

Abstract

Municipal blow-off line laying construction method, laid by the way of zonal cooling construction, prefabricated in advance lower concrete cushion block and top concrete briquetting are employed in each section of process of deployment;Each section of process of deployment is:Poured on ground at the construction field (site), prefabricated polylith lower concrete cushion block and polylith top concrete briquetting;Digging groove, form foundation trench;Foundation trench supporting construction is installed;Pre- polylith lower concrete cushion block, one or more pipe and polylith top concrete briquetting are successively placed in foundation trench, the both ends of every pipe are made to be respectively supported in the semi-circular recesses of one piece of lower concrete cushion block, and be pressed in respectively in the semi-circular recesses of one piece of top concrete briquetting, and polyethylene expansion joint plate is placed between the combining structure of adjacent two groups of lower concrete cushion blocks and top concrete briquetting;Pipe external wrapping concrete is poured into foundation trench;Backfill groove.This construction method simplifies process, shortens the construction period, accelerates efficiency of construction.

Description

Municipal blow-off line laying construction method
Technical field
The invention belongs to sewage conduct technical field of construction, more particularly to a kind of municipal blow-off line laying construction method.
Background technology
At present, municipal blow-off line is generally laid by the way of zonal cooling construction, and each section using following Construction technological process:
S1, digging groove, form foundation trench;
S2, installation foundation trench supporting construction, generally use steel plate box supporting, the purpose is to:On the one hand it is the peace for ensureing foundation trench Entirely, the security of operation in workmen's subsequent pit is on the other hand improved;
S3, to the bottom of foundation trench ttom of pipe concrete is poured, one of polyethylene expansion joint plate, stretched polyethylene are set every 6 meters Contracting seam plate is fixed by specialized structure, and the ttom of pipe concrete to pouring is by manually carrying out leveling;
After the tentatively solidification of S4, the ttom of pipe concrete after pouring, the time generally tentatively solidified is 4-8 hours, by rising Hang equipment one or more pipe is placed on the ttom of pipe concrete after solidification, and pipe is fixed on by ttom of pipe by iron wire and mixed On solidifying soil, when can so avoid follow-up concreting, pipe floats;
S5, the linearity for adjusting pipe, can use wedge-shaped concrete block or larger stone;
S6, pipe shaft, tube top concrete are poured, the surrounding up and down of pipe is wrapped by concrete;
S7, backfill groove, so far complete the construction of one section of sewage conduct.
In above-mentioned construction technological process, when carrying out the artificial equating of the 3rd work step, the blow-off line of the 4th work step of progress When fixed and when carrying out the pipe straightening of the 5th work step, it is required to workmen and enters progress in groove, workmen is in ditch Time in groove is longer, on the one hand causes construction period longer, and another aspect operation is dangerous big, and it is hidden to there is more safety Suffer from, such as, when the both sides not support template of groove or when supporting is not in place, it there is the hidden danger of groove landslide.In addition, it is necessary to Carry out concrete twice to pour, the hardening time of provided pipe base concrete is wanted in centre, so, causes that the engineering time is longer, apply Work efficiency rate is low.
The content of the invention
The present invention for solve known technology present in technical problem provide a kind of simplified process, shortening the construction period, Be used in turn rate, raising working security and the guarantee for accelerating efficiency of construction, reduction material cost, raising foundation trench supporting construction are applied The municipal blow-off line laying construction method of working medium amount.
The present invention is adopted the technical scheme that to solve technical problem present in known technology:
Municipal blow-off line laying construction method, the construction method are laid by the way of zonal cooling construction, its It is characterised by:Prefabricated in advance lower concrete cushion block and and lower concrete are employed in each section of process of deployment Top concrete briquetting that cushion block is engaged, in the upper surface medium position and top concrete briquetting of lower concrete cushion block The medium position of lower surface is respectively equipped with the semi-circular recesses to match with the external diameter of sewage conduct to be laid, and two halves circle is recessed Groove can be spliced into a full circle positioning through hole;Each section of process of deployment comprises the following steps successively:
Poured on S1, ground at the construction field (site), prefabricated polylith lower concrete cushion block and polylith top concrete briquetting;
S2, digging groove, form foundation trench;
S3, installation foundation trench supporting construction;
S4, by lifting appliance and human assistance by prefabricated polylith lower concrete cushion block, one or more pipe And prefabricated polylith top concrete briquetting is successively placed in foundation trench, one piece of top concrete briquetting and one piece of bottom coagulation Native cushion block forms combining structure up and down, the both ends of every pipe is respectively supported at the semicircle recessed of one piece of lower concrete cushion block In groove, and it is pressed in respectively in the semi-circular recesses of one piece of top concrete briquetting;And in two groups of adjacent lower concretes Polyethylene expansion joint plate is directly placed between the combining structure of cushion block and top concrete briquetting;
S5, pipe external wrapping concrete, the top surface of concreting to top concrete briquetting are poured into foundation trench;
S6, backfill groove, so far complete the laying of one section of sewage conduct.
The technical scheme that the present invention can also take is:
The caliber of used pipe is D, and the length of every pipe is 6 meters, the height of every piece of lower concrete cushion block and every The height of block top concrete briquetting takes δ, then δ=D/2+300mm, the width of every piece of lower concrete cushion block and every piece of top The width of concrete blocks takes L1, then L1=D+600mm, the length and every piece of top concrete of every piece of lower concrete cushion block The length of briquetting takes L2, then L2 >=1m.
The top concrete briquetting at every pipe both ends and the prefabricated dosage of lower concrete cushion block are every with corresponding in S5 The proportionate relationship of the amount of pouring of the concrete of root pipe is 33:67.
The present invention has the advantages and positive effects of:
1st, each section of construction shorten to six procedures by existing seven procedure, and concrete is poured by subtracting twice It is few to arrive once, so, the preliminary setting time of centre is eliminated, ensure that construction is carried out continuously, so as to improve efficiency of construction With shorten the construction time, improve 60% or so through preresearch estimates efficiency, the duration reduces 60% or so.
2nd, using the combining structure of cushion block and briquetting, amount of concrete 33% is to pour on the ground corresponding to every pipe Build, be prefabricated, so improving security and efficiency simultaneously, security improves 33% or so, on the ground with the efficiency comparison of underground Improve 50% or so.
3rd, using this construction method, it is not necessary to carry out in foundation trench artificial levelling and pipe is fixed with iron wire, this Sample, activity duration of the people in foundation trench is drastically reduce the area, improve the security of construction and ensure that personal safety.
4th, pipe need not be fixed with iron wire in this construction technology, so reduces the dosage of material, reduce Material cost.
5th, foundation trench generally use steel plate box supporting, using existing construction method, every piece of steel plate box at least needs 2 day time It can down have enough to meet the need, and use this construction method, every piece of steel plate box only needs 1 day time down to have enough to meet the need, circulation material utilization rate 50% is improved, benefit accordingly improves.
6th, place polyethylene expansion joint plate needs specially to be fixed in existing construction method, and uses this construction party Method, polyethylene expansion joint plate are directly sandwiched between adjacent cushion block and the combining structure of briquetting, so, avoid the need for setting specially The fixed structure of door, this improves efficiency and the security of operation.
Brief description of the drawings
Fig. 1 is the construction flow chart of the present invention;
Fig. 2 is the attachment structure schematic diagram between pipe in the step working procedure of this construction method the 4th.
In figure:1st, lower concrete cushion block;2nd, top concrete briquetting;3rd, foundation trench;4th, foundation trench supporting construction;5th, pipe; 6th, polyethylene expansion joint plate;7th, concrete.
Embodiment
In order to further understand the content, features and effects of the present invention, hereby enumerating following examples, and coordinate accompanying drawing Describe in detail as follows:
Fig. 1 and 2, municipal blow-off line laying construction method are referred to, the construction method uses the side of zonal cooling construction Formula is laid, and is the characteristics of the construction method:Bottom coagulation prefabricated in advance is employed in each section of process of deployment Native cushion block 1 and the top concrete briquetting 2 being engaged with lower concrete cushion block.In the middle part of the upper surface of lower concrete cushion block The medium position of position and the lower surface of top concrete briquetting is respectively equipped with to match with the external diameter of sewage conduct to be laid Semi-circular recesses, two halves circular groove can be spliced into a full circle positioning through hole.Each section of process of deployment successively include with Lower step:
Poured on S1, ground at the construction field (site), prefabricated polylith lower concrete cushion block and polylith top concrete briquetting. The quantity of lower concrete cushion block and top concrete briquetting will be matched with follow-up using the quantity of pipe.Specifically, every The both ends of pipe correspond to one piece of lower concrete cushion block and one piece of top concrete briquetting respectively.
S2, digging groove, foundation trench 3 is formed, with specific reference to existing form of construction work.
S3, installation foundation trench supporting construction 4, referring specifically to existing form of construction work.
S4, by lifting appliance and human assistance by prefabricated polylith lower concrete cushion block, one or more pipe 5 And prefabricated polylith top concrete briquetting is successively placed in foundation trench, one piece of top concrete briquetting and one piece of bottom coagulation Native cushion block forms combining structure up and down, the both ends of every pipe is respectively supported at the semicircle recessed of one piece of lower concrete cushion block In groove, and it is pressed in respectively in the semi-circular recesses of one piece of top concrete briquetting;And in two groups of adjacent lower concretes Polyethylene expansion joint plate 6 is directly placed between the combining structure of cushion block and top concrete briquetting.Usual polyethylene expansion joint plate It is made up of the polyethylene expansion joint plate positioned at top half and the polyethylene expansion joint plate positioned at the latter half, wherein positioned at upper half Partial polyethylene expansion joint plate is clamped by two adjacent top concrete briquettings, the polyethylene expansion joint plate positioned at the latter half By two adjacent lower concrete block grips.Above-mentioned lower concrete cushion block, pipe, top concrete briquetting and stretched polyethylene Contracting seam plate Specific construction process be:Lifting appliance is first passed through to wait to spread according to the section by prefabricated polylith lower concrete cushion block If the length of sewage conduct and the length of single cell of selection be placed on the bottom surface of foundation trench, polylith lower concrete is in base When riding position in groove bottom will ensure follow-up down tube, both ends one piece of lower concrete cushion block of each correspondence of every pipe, and Adjust the elevation and linearity of polylith lower concrete cushion block;Then more pipes are supported on by bottom by lifting appliance one by one In half plate arc groove in concrete pad, it is attached between pipe using spigot-and-socket;To be more finally by lifting appliance Block top concrete briquetting is placed on multiple lower concrete cushion blocks in foundation trench one by one, and two so in every pipe End is equipped with the combining structure of one group of top concrete briquetting and lower concrete cushion block;Meanwhile mixed in the bottom of a pipe After solidifying native cushion block installs, it is necessary to the polyethylene positioned at the latter half before the lower concrete cushion block of installation adjacent pipe Before expansion joint plate is attached to corresponding to a pipe on the side of lower concrete cushion block;Positioned at the polyethylene expansion joint of top half Plate installs the installation referring to the above-mentioned polyethylene expansion joint plate positioned at the latter half, will not be repeated here.
S5, pipe external wrapping concrete 7, the top surface of concreting to top concrete briquetting are poured into foundation trench;
S6, backfill groove, so far complete the laying of one section of sewage conduct.
Using above-mentioned applying method, the parameter of used pipe and the parameter of lower concrete cushion block and top concrete pressure The parameter of block is preferably as follows relation, uses the caliber of pipe as D, and the length of every pipe is 6 meters, every piece of lower concrete pad The height of block and the height of every piece of top concrete briquetting take δ, then δ=D/2+300mm, the width of every piece of lower concrete cushion block Degree and the width of every piece of top concrete briquetting take L1, then L1=D+600mm, the length of every piece of lower concrete cushion block and every The length of block top concrete briquetting takes L2, then L2 >=1m.
Using above-mentioned construction method, the top concrete briquetting at every pipe both ends and the prefabricated use of lower concrete cushion block The proportionate relationship of the amount of pouring of concrete of the amount with corresponding to every pipe in S5 is preferably 33:67.

Claims (3)

1. municipal blow-off line laying construction method, the construction method is laid by the way of zonal cooling construction, and it is special Sign is:Employed in each section of process of deployment lower concrete cushion block prefabricated in advance and with lower concrete pad The top concrete briquetting that block is engaged, under the upper surface medium position and top concrete briquetting of lower concrete cushion block The medium position of end face is respectively equipped with the semi-circular recesses to match with the external diameter of sewage conduct to be laid, two halves circular groove A full circle positioning through hole can be spliced into;Each section of process of deployment comprises the following steps successively:
Poured on S1, ground at the construction field (site), prefabricated polylith lower concrete cushion block and polylith top concrete briquetting;
S2, digging groove, form foundation trench;
S3, installation foundation trench supporting construction;
S4, by lifting appliance and human assistance by prefabricated polylith lower concrete cushion block, one or more pipe and pre- The polylith top concrete briquetting made is successively placed in foundation trench, one piece of top concrete briquetting and one piece of lower concrete pad Block forms combining structure up and down, the both ends of every pipe is respectively supported at the semi-circular recesses of one piece of lower concrete cushion block It is interior, and be pressed in respectively in the semi-circular recesses of one piece of top concrete briquetting;And in two groups of adjacent lower concrete pads Polyethylene expansion joint plate is directly placed between the combining structure of block and top concrete briquetting;
S5, pipe external wrapping concrete, the top surface of concreting to top concrete briquetting are poured into foundation trench;
S6, backfill groove, so far complete the laying of one section of sewage conduct.
2. municipal blow-off line laying construction method according to claim 1, it is characterised in that:The caliber of used pipe For D, the length of every pipe is 6 meters, and the height of every piece of lower concrete cushion block and the height of every piece of top concrete briquetting are equal δ being taken, then δ=D/2+300mm, the width of every piece of lower concrete cushion block and the width of every piece of top concrete briquetting take L1, Then L1=D+600mm, the length of every piece of lower concrete cushion block and the length of every piece of top concrete briquetting take L2, then L2 >= 1m。
3. municipal blow-off line laying construction method according to claim 1, it is characterised in that:The top at every pipe both ends The amount of pouring of concrete of the prefabricated dosage of portion's concrete blocks and lower concrete cushion block with corresponding to every pipe in S5 Proportionate relationship is 33:67.
CN201510559943.2A 2015-09-06 2015-09-06 Municipal blow-off line laying construction method Active CN105605308B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510559943.2A CN105605308B (en) 2015-09-06 2015-09-06 Municipal blow-off line laying construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510559943.2A CN105605308B (en) 2015-09-06 2015-09-06 Municipal blow-off line laying construction method

Publications (2)

Publication Number Publication Date
CN105605308A CN105605308A (en) 2016-05-25
CN105605308B true CN105605308B (en) 2017-12-29

Family

ID=55985485

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510559943.2A Active CN105605308B (en) 2015-09-06 2015-09-06 Municipal blow-off line laying construction method

Country Status (1)

Country Link
CN (1) CN105605308B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107882152A (en) * 2017-12-04 2018-04-06 瑞安市东南市政工程建设有限公司 A kind of municipal blow-off pipe laying and construction method
CN109281379B (en) * 2018-11-10 2020-11-24 温州市龙湾大地绿化有限公司 Municipal sewage pipeline laying construction method
CN109898548A (en) * 2019-02-14 2019-06-18 济南城建集团有限公司 Exempt from the assembling module and construction method of compacting in a kind of municipal pipeline basis
CN110594488B (en) * 2019-08-14 2021-02-09 中国电建集团华东勘测设计研究院有限公司 Underground pipeline groove supporting and monitoring integrated structure and construction method
CN113324097A (en) * 2021-04-20 2021-08-31 中国水利水电第九工程局有限公司 Deep groove excavation construction process

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19849142A1 (en) * 1998-10-24 2000-04-27 Sander Karl Heinz Gmbh & Co Kg Sub-surface concrete water pipe supported at ends in concrete muffs simplifying manufacture and installation, muffs being made of two halves bolted together
CN1712643A (en) * 2004-06-14 2005-12-28 胡彦彬 Foundation construction of precast concrete pipes
CN102155585B (en) * 2011-04-12 2012-08-15 中国十九冶集团有限公司 Method for laying mine slurry pipeline in long and narrow section
KR101180451B1 (en) * 2012-02-15 2012-09-06 박건호 A connecting block for pipe and constructing method using it
KR101262964B1 (en) * 2012-09-11 2013-05-09 주식회사 건축사사무소도아 Braket for supporting water and waste pipe of apartment house

Also Published As

Publication number Publication date
CN105605308A (en) 2016-05-25

Similar Documents

Publication Publication Date Title
CN105605308B (en) Municipal blow-off line laying construction method
CN104594348B (en) Enlarged footing bellows anchor pole and construction method thereof
CN103981898B (en) A kind of inverse underground engineering construction method done of overall open cut node
CN107059903A (en) Bottom plate plugging dewatering well construction method is worn in foundation ditch
CN103628885A (en) Tunnel exit cover-excavation construction method of Ultra-shadow buried tunnel
CN108532649A (en) A kind of compressive static load test method of bored concrete pile
CN102587663A (en) Concrete construction process of steel tube columns of super-high-rise building
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN107587884A (en) Tunnel double-lining concrete vault backfills grouting device
CN110700237A (en) Construction method of diaphragm wall for preventing concrete from flowing around
CN107794942A (en) Riverbed comprehensive pipe gallery structure and its construction method are worn under one kind
CN207297034U (en) Tunnel double-lining concrete vault backfills grouting device
CN209369832U (en) Steel pipe behind fill concrete structure in a kind of tunnel
CN110206071A (en) A kind of diaphram wall seam reinforcement means and device
CN107542086B (en) Anchor cable construction method for filling slope
CN107268675A (en) The laying method and structure of a kind of many storehouse underground pipe galleries of combined type
CN106917358B (en) A kind of cable-stayed bridge main-beam combination constructing method thereof and its counter weight construction system
CN110552378A (en) Underground space roof subsides post-cast strip and seals structure in advance
CN206513380U (en) A kind of tunnel double-lining vault with rubber seal reserves Grouting Pipe
CN106193279B (en) Time building method of main structure wall prestressed structure and main structure wall
CN208717918U (en) The enclosure structure of foundation pit of subway station of high-voltage line or overpass is worn under a kind of
CN105673933A (en) Waterproof sealing device for post-through-wall pipeline and construction method
CN207974149U (en) Pre-buried skeleton strength core masonry cable duct
CN205975592U (en) Subway goes out to wear a waterline support structure under lambda line shield method
CN109505629A (en) Steel pipe behind fill concrete structure and construction method in a kind of tunnel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 300384 the Binhai New Area of Tianjin Huayuan Industrial Zone Rong Yuan Road No. 2 4-2101

Patentee after: China Construction Municipal Construction Group Co., Ltd.

Address before: 300384 Tianjin City Huayuan Industrial Zone Binhai Rong Yuan Road No. 2 4-2101

Patentee before: Sinohydro Tianjin Engineering Co.,Ltd.

CP03 Change of name, title or address