CN105515166B - 110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can back brake maintenance voltage allocation plan - Google Patents

110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can back brake maintenance voltage allocation plan Download PDF

Info

Publication number
CN105515166B
CN105515166B CN201610032836.9A CN201610032836A CN105515166B CN 105515166 B CN105515166 B CN 105515166B CN 201610032836 A CN201610032836 A CN 201610032836A CN 105515166 B CN105515166 B CN 105515166B
Authority
CN
China
Prior art keywords
busbar
sections
combining unit
intervals
secondary device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610032836.9A
Other languages
Chinese (zh)
Other versions
CN105515166A (en
Inventor
陈雅云
庄小河
陈瑞章
吴玉婷
关少锋
杨敏敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Quanzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Quanzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd, Quanzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610032836.9A priority Critical patent/CN105515166B/en
Publication of CN105515166A publication Critical patent/CN105515166A/en
Application granted granted Critical
Publication of CN105515166B publication Critical patent/CN105515166B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/02Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which an auxiliary distribution system and its associated lamps are brought into service

Landscapes

  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention disclose a kind of 110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can back brake maintenance voltage allocation plan, by increasing all intervals 110kV combining unit and wall secondary device to the optical cable circuit of 110kVII sections of busbar combining units, and all intervals 110kV combining unit and wall secondary device are accessed into II sections of busbar combining units of 110kV by newly-increased optical cable circuit and export optical port, when under any busbar PT combining unit fault conditions, all intervals are poured into another section of bus run by substation's operation maintenance personnel by busbar grid switching operation, ensure all intervals still normal operation, reinform repair and maintenance personnel on site's inspection processing.Any busbar PT combining units maintenance again may be by the formula of falling maternal arrangement, avoid that accompanying for running equipment is caused to stop.

Description

110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can fall The voltage allocation plan of lock maintenance
Technical field
The present invention relates to a kind of 110 kilovolts of system voltage allocation plans, especially a kind of intelligent substation double bus schemes 110 kilovolts of system busbar combining units of mode can back brake maintenance voltage allocation plan.
Background technology
It is well known that double bus scheme mode busbar PT powers to multiple interval multiple equipments simultaneously, once it breaks down Influence face is very big, deteriorated area protection seting cooperation, in some instances it may even be possible to cause power grid large number of equipment refused action or tripping of bypassing the immediate leadership.It is close several Year, it puts into operation with intelligent substation Accelerating The Construction and constantly, combining unit and intelligent terminal are extensively using changing tradition change Power station output, way of output research and development and design concept, and for 110 kilovolts of system lists of Intelligent transformer station double bus scheme mode Equipment is configured, the mono- protections configured of all 110kV of 220kV intelligent stations at present and automatic safety device are by I sections of busbares of 110kV Combining unit cascade, which is drawn, takes busbar voltage, such as Fig. 1, shown in 2.DC power supply designs:110kV I, II sections of busbar combining units are straight Galvanic electricity source is drawn respectively takes I, II sections of power supplys of DC power system, the protection of 110kV line segregations, observing and controlling, control and intelligent assembly electricity Source carries out power distribution according to odd even interval numbers.General odd-numbered interval takes I sections of DC power supply, and even-numbered interval takes II Section power supply.As shown in Figure 3.The bus bar configuration scheme of the prior art has main having:1)110kVI sections of busbares merge single Element device failure causes all 110kV line segregations voltages for cascading its busbar voltage to lose, distance protection and with directional element Quick fraction zero-sequenceprotection be blocked, only retain long delay PT broken string overcurrent protection and zero-sequenceprotection(When generally adjusting action Between be 3 ~ 4 seconds), any circuit or element fault under this power system operating mode certainly will be got over caused by protection seting coordinates difficulty Grade action, expands fault coverage, in some instances it may even be possible to cause a plurality of circuit while trip.2)Protection, the control at even-numbered interval System and intelligent assembly are mounted with cascade busbar combining unit not on same section DC power supply, and DC power supply I segment faults lose feelings Under condition, all 110kV route protections voltages lose, and the influence of generation is the same as 1)Analysis.
Invention content
It is an object of the invention to overcome the deficiencies in the prior art places, and provide one kind in any busbar PT combining units Under fault condition, all intervals are poured into another section of bus run by substation's operation maintenance personnel by busbar grid switching operation, ensure institute There is interval still normal operation, then the 110 kilovolts of system voltage arrangements of intelligent substation double bus scheme mode processed.
A kind of 110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can the voltage of back brake maintenance match Scheme is set, all intervals 110kV combining unit and wall secondary device are cascaded or are directly connected to by optical cable circuit To 110kVI sections of busbar combining units, it is characterised in that:Further include that increase all intervals 110kV combining unit and wall are secondary Equipment is set to the optical cable circuit of 110kVII sections of busbar combining units, and by all intervals 110kV combining unit and wall are secondary It is standby that II sections of busbar combining units output optical ports of 110kV, I sections of busbar combining units of 110kV are accessed by newly-increased optical cable circuit And protection, observing and controlling, control and the intelligent assembly of odd-numbered line segregation are articulated in I sections of DC power supplies, II sections of 110kV Protection, observing and controlling, control and the intelligent assembly of busbar combining unit and even-numbered line segregation are articulated in II sections of direct currents Source;The voltage of all intervals 110kV combining unit and wall secondary device cascades or the configuration of the virtual terminator of directly-attached loop I sections of busbar combining units, II are taken to input cascade or drawing all intervals 110kV combining unit and wall secondary device mother I Mother's input, which cascades or draws, takes II sections of busbar combining units.Each interval combining unit is received and cascades different combining unit information progress Software differentiates upgrading processing, and mounting busbar is distinguished by being spaced the judgement of disconnecting link location status information, is cascaded when for mounting busbar When the chain rupture of SV links, error code, these exceptions of invalid bit occurs in circuit, protects the equipment such as observing and controlling to receive combining unit at this time and send It is judged as that PT breaks after stating information, breaks according to PT and carry out logic discrimination and processing, goes out if the cascaded loop of non-mounting busbar When existing aforementioned exception information, protect at this time at equal intervals layer equipment the information is not handled, pass through and be spaced layer combining unit hair Non- mounting busbar cascades SV exception information alarm prompts, after regulation and control O&M operator on duty obtains the information by monitoring system Notice repair and maintenance personnel are handled to site inspection in time;Take the wall of voltage secondary for directly drawing from busbar combining unit Equipment also requires that and carries out software upgrading to control source testing mechanism, the input of two sections of busbar voltages is detected respectively and Judge, including SV links, error code and invalid bit these exception informations, then secondary device occurs after above-mentioned exception in certain section of busbar voltage Logic discrimination and processing, concurrent correspondent section busbar voltage SV alarm signals are carried out according to this section of busbar PT broken string.
The wall secondary device refers to such as bus protection, public observing and controlling, fault oscillograph equipment.
The present invention mounts direct current to busbar combining unit and each interval protection observing and controlling, control and intelligent assembly DC power supply Source paragraph is strictly configured, i.e. protection, observing and controlling, the control of 110kV I sections of busbar combining units and odd-numbered line segregation System and intelligent assembly are articulated in I sections of DC power supplies, II sections of busbar combining units of 110kV and even-numbered line segregation Protection, observing and controlling, control and intelligent assembly are articulated in II sections of DC power supplies.Double loop line segregation is articulated in I, II sections respectively DC power supply.It can ensure under normal operating mode in this way, the voltage at odd-numbered interval merges list from I sections of busbares of 110kV Member obtains mother's I voltage, and the voltage at even intervals number interval obtains mother's II voltage from II sections of busbar combining units of 110kV, no Understand and lost in either segment DC power supply because of power supply cross-over configuration, the spaced protection control function of institute is caused to lose.
The virtual terminator concrete configuration is:System integrator designs according to the modification virtual terminator that designing unit provides first Table utilizes SCD(Whole station system configuration file Substation Configuration Description)Configuration file is to institute There is the configuration of the intervals 110kV combining unit and secondary device to modify, deletes all intervals 110kV combining unit and wall Secondary device links all intervals 110kV and merges list to the II section busbar voltage SMV lines of I sections of busbar combining units of 110kV Member and wall secondary device configure SMV lines to the II section busbar voltage SMV lines of II sections of busbar combining units of 110kV When, for recipient, it is necessary to first add external signal, then add internal signal.It is as follows to add external signal configuration sequence:1) Select the physical address of SMV recipient;2)Selection SMV recipient corresponds to LD(SVLD);3)The LN where SMV lines is selected,(One As be fixed in LLNO);4)Select Inputs options(Virtual terminator line);5)Select external signal;6)By the SMV of sending device The FCDA that transmission data under accessing points is concentrated is dragged to middle window, and discharges in order.Select internal signal configuration sequence: In reception device, the LD-- under SMV accessing points》LN--》FC--》Under DO, corresponding DA is selected, is dragged in middle window Row where corresponding external signal completes the connection of external signal and internal signal, namely completes a SMV line, i.e., The modification for completing SCD file configuration generates.
After modification generates above-mentioned SCD file, then all intervals 110kV combining unit and wall secondary device producer CID files are generated after being extracted with this IED relevant informations in SCD file with the configuration tool of IED devices, and work is configured by device It is attached to specific IED equipment under tool, that is, completes virtual terminator configuration.
It completes after being filled under above-mentioned configuration virtual terminator configuration and CID files, finally by II sections of busbar combining unit grades of 110kV The spare optical port for joining or being connected to all intervals 110kV combining unit and wall secondary device opens, that is, completes all empty ends Son configuration and optical port configuration output.The intervals 110kV combining unit cascade voltage and directly drawing for wall secondary device take voltage Configuration differs only in the difference of voltage transport protocol, and the agreement of cascade voltage transmission is IEC60044-8, directly draws the electricity taken Pressure transport protocol is IEC61850-9-2, and classification configurations are needed in configuration process.
Virtual terminator describes IED(Intelligent electronic device Intelligent Electronic Device)GOOSE(Face To the transformer substation case Generic object oriented substation events of general object)、 SV (Sampled value Sampled value)Input, output signal tie point general name, to identification procedure layer, wall and its between contact two Minor loop signal is equal to the screen terminal of traditional substation.
In summary, the present invention following advantage compared with prior art:
The present invention 110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can back brake maintenance electricity Allocation plan is pressed, under any busbar PT combining unit fault conditions, substation's operation maintenance personnel is by busbar grid switching operation by institute There is interval to pour into another section of bus run, ensures all intervals still normal operation, reinform repair and maintenance personnel on site inspection department Reason.Any busbar PT combining units maintenance again may be by the formula of falling maternal arrangement, avoid that accompanying for running equipment is caused to stop.
Description of the drawings
Fig. 1 is I sections of busbar combining unit wiring schematic diagrams of 110kV of the prior art.
Fig. 2 is II sections of busbar combining unit wiring schematic diagrams of 110kV of the prior art.
Fig. 3 is 110kV system interval DC power supply wiring schematic diagrams.
Fig. 4 is I sections of busbar combining unit wiring schematic diagrams of 110kV of the present invention.
Fig. 5 is II sections of busbar combining unit wiring schematic diagrams of 110kV of the present invention.
Specific implementation mode
The present invention is described in more detail with reference to embodiment.
Embodiment 1
A kind of 110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can the voltage of back brake maintenance match Scheme is set, all intervals 110kV combining unit and wall secondary device are cascaded or are directly connected to by optical cable circuit To 110kVI sections of busbar combining units, it is characterised in that:Further include that increase all intervals 110kV combining unit and wall are secondary Equipment is set to the optical cable circuit of 110kVII sections of busbar combining units, and by all intervals 110kV combining unit and wall are secondary It is standby that II sections of busbar combining units output optical ports of 110kV, wiring such as Fig. 4,5 are accessed by newly-increased optical cable circuit;;I sections of 110kV Protection, observing and controlling, control and the intelligent assembly of busbar combining unit and odd-numbered line segregation are articulated in I sections of direct currents Source, protection, observing and controlling, control and the intelligent assembly mounting of II sections of busbar combining units of 110kV and even-numbered line segregation In II sections of DC power supplies, double loop line segregation is articulated in I, II sections of DC power supplies respectively;All intervals 110kV combining unit and The voltage of wall secondary device cascades or the virtual terminator of directly-attached loop is configured to all intervals 110kV combining unit and Wall secondary device mother I, which inputs cascade or draws, takes I sections of busbar combining units, and mother II, which inputs cascade or draws, takes II sections of busbares to merge Unit.Each interval combining unit is received and cascades different combining unit information progress softwares differentiation upgrading processings, passes through and is spaced knife Gate position status information judges to distinguish mounting busbar, when there is SV links chain rupture, error code, invalid for mounting busbar cascaded loop When these exceptions of position, protects the equipment such as observing and controlling to receive after combining unit sends above- mentioned information at this time and is judged as that PT breaks, according to PT Broken string carries out logic discrimination and processing, when there is aforementioned exception information if the cascaded loop of non-mounting busbar, protection etc. at this time Bay device is not handled the information, is sent out non-and mount busbar is cascaded the alarm of SV exception informations by being spaced layer combining unit Prompt message, regulation and control O&M operator on duty notify repair and maintenance personnel to be examined to scene in time after obtaining the information by monitoring system Investigate and prosecute reason;The wall secondary device that voltage is taken for directly drawing from busbar combining unit is also required that and is detected to control source Mechanism carries out software upgrading, and two sections of busbar voltage inputs are detected and are judged respectively, including SV links, error code and invalid bit There is after above-mentioned exception then secondary device and carry out logic according to this section of busbar PT broken string sentencing in these exception informations, certain section of busbar voltage Not and handle, concurrent correspondent section busbar voltage SV alarm signals.
The virtual terminator concrete configuration is:System integrator designs according to the modification virtual terminator that designing unit provides first Table utilizes SCD(Whole station system configuration file Substation Configuration Description)Configuration file is to institute There is the configuration of the intervals 110kV combining unit and secondary device to modify, deletes all intervals 110kV combining unit and wall Secondary device links all intervals 110kV and merges list to the II section busbar voltage SMV lines of I sections of busbar combining units of 110kV Member and wall secondary device configure SMV lines to the II section busbar voltage SMV lines of II sections of busbar combining units of 110kV When, for recipient, it is necessary to first add external signal, then add internal signal.It is as follows to add external signal configuration sequence:1) Select the physical address of SMV recipient;2)Selection SMV recipient corresponds to LD(SVLD);3)The LN where SMV lines is selected,(One As be fixed in LLNO);4)Select Inputs options(Virtual terminator line);5)Select external signal;6)By the SMV of sending device The FCDA that transmission data under accessing points is concentrated is dragged to middle window, and discharges in order.Select internal signal configuration sequence: In reception device, the LD-- under SMV accessing points》LN--》FC--》Under DO, corresponding DA is selected, is dragged in middle window Row where corresponding external signal completes the connection of external signal and internal signal, namely completes a SMV line, i.e., The modification for completing SCD file configuration generates.
After modification generates above-mentioned SCD file, then all intervals 110kV combining unit and wall secondary device producer CID files are generated after being extracted with this IED relevant informations in SCD file with the configuration tool of IED devices, and work is configured by device It is attached to specific IED equipment under tool, that is, completes virtual terminator configuration.
It completes after being filled under above-mentioned configuration virtual terminator configuration and CID files, finally by II sections of busbar combining unit grades of 110kV The spare optical port for joining or being connected to all intervals 110kV combining unit and wall secondary device opens, that is, completes all empty ends Son configuration and optical port configuration output.The intervals 110kV combining unit cascade voltage and directly drawing for wall secondary device take voltage Configuration differs only in the difference of voltage transport protocol, and the agreement of cascade voltage transmission is IEC60044-8, directly draws the electricity taken Pressure transport protocol is IEC61850-9-2, and classification configurations are needed in configuration process.
The not described part of the present embodiment is same as the prior art.

Claims (2)

1. a kind of 110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can back brake maintenance voltage configuration Scheme, all intervals 110kV combining unit and wall secondary device are cascaded or are connected directly to 110kVI by optical cable circuit Section busbar combining unit, it is characterised in that:Further include increasing all intervals 110kV combining unit and wall secondary device extremely The optical cable circuit of 110kVII sections of busbar combining units, and all intervals 110kV combining unit and wall secondary device are passed through Newly-increased optical cable circuit access II sections of busbar combining units of 110kV export optical port;I sections of busbar combining units of 110kV and strange Protection, observing and controlling, control and the intelligent assembly of number number line segregation are articulated in I sections of DC power supplies, and II sections of busbares of 110kV close And protection, observing and controlling, control and the intelligent assembly of unit and even-numbered line segregation are articulated in II sections of DC power supplies, own The voltage of the intervals 110kV combining unit and wall secondary device cascades or the virtual terminator of directly-attached loop is configured to own The intervals 110kV combining unit and wall secondary device mother I, which input cascade or draw, takes I sections of busbar combining units, mother's II input stage Join or draw and take II sections of busbar combining units, each interval combining unit is received and cascades different I sections of busbares or II sections of busbares merging lists Metamessage carries out software and differentiates upgrading processing, judges to distinguish mounting busbar by being spaced disconnecting link location status information, when to hang Connect busbar cascaded loop occur the chain rupture of SV links, error code, invalid bit these it is abnormal when, protect measuring and controlling equipment to receive merging at this time single Member is judged as that PT breaks after sending interval disconnecting link location status information, breaks according to PT and carries out logic discrimination and processing, if non- When exception information occurs in the cascaded loop of mounting busbar, protection interval layer equipment is not handled exception information at this time, is passed through The intervals 110kV combining unit is sent out non-and mounts busbar cascade SV exception information alarm prompts, and regulation and control O&M operator on duty passes through Monitoring system notifies repair and maintenance personnel to be handled to site inspection in time after obtaining alarm prompt;For directly being closed from busbar And unit draws the wall secondary device for taking voltage, also requires that and carries out software upgrading to control source testing mechanism, to two sections Busbar voltage input is detected and judges respectively, including SV links, error code and invalid bit these exception informations, certain section of busbar electricity Then secondary device carries out logic discrimination and processing, concurrent correspondent section busbar according to this section of busbar PT broken string after the existing above-mentioned exception of extrusion Voltage SV alarm signals.
2. 110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode according to claim 1 can fall The voltage allocation plan of lock maintenance, it is characterised in that:The virtual terminator concrete configuration is that system integrator is according to design first The modification virtual terminator that unit provides designs table, using SCD configuration files to all intervals 110kV combining unit and secondary device Configuration is modified, and deletes all intervals 110kV combining unit and wall secondary device to I sections of busbar combining units of 110kV II section busbar voltage SMV lines, it is female to II sections of 110kV to link all intervals 110kV combining unit and wall secondary device The II section busbar voltage SMV lines of line combining unit, when configuring SMV lines, for recipient, it is necessary to external signal is first added, Then internal signal is added, addition external signal configuration sequence is as follows:1)Select the physical address of SMV recipient;2)Select SMV Recipient corresponds to LD;3)Select the LN where SMV lines;4)Select virtual terminator line Inputs options;5)Select external signal; 6)The FCDA that transmission data under the SMV accessing points of sending device is concentrated is dragged to middle window, and is discharged in order;In selection Portion's signal configuration sequence:In reception device, the LD-- under SMV accessing points》LN--》FC--》Under DO, corresponding DA is selected, It is dragged to the row where corresponding external signal in middle window, that is, completes the connection of external signal and internal signal, namely A SMV line is completed, that is, the modification for completing SCD file configuration generates;
After modification generates above-mentioned SCD file, then all intervals 110kV combining unit and wall secondary device producer use The configuration tool of IED devices generates CID files after being extracted with this IED relevant informations in SCD file, and passes through device configuration tool Under be attached to specific IED equipment, that is, complete virtual terminator configuration;
It completes after being filled under above-mentioned virtual terminator configuration and CID files, finally by II sections of busbar combining unit cascades of 110kV or connection To the spare optical port of all intervals 110kV combining unit and wall secondary device, that is, complete all virtual terminator configurations and optical port Directly drawing for configuration output, the intervals 110kV combining unit cascade voltage and wall secondary device takes voltage configuration difference only to exist It is IEC60044-8 in the agreement of the difference of voltage transport protocol, cascade voltage transmission, directly drawing the voltage transport protocol taken is IEC61850-9-2 needs classification configurations in configuration process.
CN201610032836.9A 2016-01-19 2016-01-19 110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can back brake maintenance voltage allocation plan Active CN105515166B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610032836.9A CN105515166B (en) 2016-01-19 2016-01-19 110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can back brake maintenance voltage allocation plan

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610032836.9A CN105515166B (en) 2016-01-19 2016-01-19 110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can back brake maintenance voltage allocation plan

Publications (2)

Publication Number Publication Date
CN105515166A CN105515166A (en) 2016-04-20
CN105515166B true CN105515166B (en) 2018-07-24

Family

ID=55722923

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610032836.9A Active CN105515166B (en) 2016-01-19 2016-01-19 110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can back brake maintenance voltage allocation plan

Country Status (1)

Country Link
CN (1) CN105515166B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107015332B (en) * 2017-05-26 2023-09-15 国家电网有限公司 Optical cable connecting device between high-voltage side process layer and spacer layer of intelligent substation
CN110736609B (en) * 2019-10-24 2021-07-30 云南电网有限责任公司昆明供电局 Optical port power testing method based on automatic matching

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101599661A (en) * 2009-04-02 2009-12-09 杭州中实四方电力自动化有限公司 Full high-frequency does not have the railway signal intelligent power supply panel of two-way contact
CN103680238A (en) * 2013-11-04 2014-03-26 国家电网公司 Intelligent transformer station mixing simulation training system
CN204928123U (en) * 2015-08-07 2015-12-30 国家电网公司 Intelligent substation merging cells voltage automatic switch -over control circuit

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010068594A (en) * 2008-09-09 2010-03-25 Mitsubishi Electric Corp Protection and control system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101599661A (en) * 2009-04-02 2009-12-09 杭州中实四方电力自动化有限公司 Full high-frequency does not have the railway signal intelligent power supply panel of two-way contact
CN103680238A (en) * 2013-11-04 2014-03-26 国家电网公司 Intelligent transformer station mixing simulation training system
CN204928123U (en) * 2015-08-07 2015-12-30 国家电网公司 Intelligent substation merging cells voltage automatic switch -over control circuit

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
智能变电站合并单元的运行注意事项;陈瑞章;《通讯世界》;20151130(第22期);第160页 *

Also Published As

Publication number Publication date
CN105515166A (en) 2016-04-20

Similar Documents

Publication Publication Date Title
KR102218268B1 (en) Substation Automation Operating Device Equipped with Automatic Generation of Failure Judgment and Failure Recovery Scenarios
CN105891680B (en) 10kV distribution line multiphase disconnection fault determination method based on three-phase voltage current
CN105655879B (en) The voltage arrangement of 110 kilovolts of system busbar combining unit duplicate system retrofits of intelligent substation double bus scheme mode
CN105375635B (en) Power distribution network cascades switching station's intelligent management and system
WO2017166735A1 (en) Power-grid self-healing system and self-healing logic thereof in 110kv chain power-supply mode
KR102145266B1 (en) System and method for monitoring power system
CN107433883B (en) Railway traction power supply arm integrated monitoring system
EP3001535A1 (en) Protection control system for process bus, merging unit, and computation device
CN103412239B (en) Detecting and positioning method of bus coupler flashover fault in subway alternating current power system
KR101514999B1 (en) Method and system for self-checking and self-separating of fault section by using smart protection devices in a power distribution system
CN108134378A (en) A kind of DC protection system and direct current protecting implementation method
CN105305365A (en) Power grid relay protection emergency management system
CN105743072A (en) High-voltage electric circuit protection system for electric motor train unit
CN109444661A (en) A kind of mixed power transmission line shorted to earth On-line Fault monitoring system and localization method
CN103543384A (en) Method for determining bus ground faults
CN103560585B (en) Digitized line protection measurement and control system suitable for metro industry
CN101860002B (en) Computing method of preventive control measure for short-circuit current in electric power system
CN105515166B (en) 110 kilovolts of system busbar combining units of intelligent substation double bus scheme mode can back brake maintenance voltage allocation plan
CN201789272U (en) Relay protection circuit preventing transformer differential protection malfunction
CN104101813B (en) A kind of centralized fault zone method of discrimination
JP2009225534A (en) Distribution system operation device
CN109240265A (en) A kind of railway signal system and intelligent failure diagnosis method
CN106207999A (en) The guard method of a kind of photovoltaic plant DC side circuit and device
CN106774068B (en) The anti-error implementation method of intelligent substation and realization system
CN108493906B (en) Decentralized bus protection handset repair method and decentralized bus protection system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant