CN105511951A - Task scheduling method and task scheduling system for automatic WIFI performance test platform - Google Patents

Task scheduling method and task scheduling system for automatic WIFI performance test platform Download PDF

Info

Publication number
CN105511951A
CN105511951A CN201610007820.2A CN201610007820A CN105511951A CN 105511951 A CN105511951 A CN 105511951A CN 201610007820 A CN201610007820 A CN 201610007820A CN 105511951 A CN105511951 A CN 105511951A
Authority
CN
China
Prior art keywords
test
concurrent testing
testing set
test event
described concurrent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610007820.2A
Other languages
Chinese (zh)
Other versions
CN105511951B (en
Inventor
吕阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Jiji Intellectual Property Operation Co ltd
Original Assignee
Shanghai Feixun Data Communication Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Feixun Data Communication Technology Co Ltd filed Critical Shanghai Feixun Data Communication Technology Co Ltd
Priority to CN201610007820.2A priority Critical patent/CN105511951B/en
Publication of CN105511951A publication Critical patent/CN105511951A/en
Application granted granted Critical
Publication of CN105511951B publication Critical patent/CN105511951B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F9/00Arrangements for program control, e.g. control units
    • G06F9/06Arrangements for program control, e.g. control units using stored programs, i.e. using an internal store of processing equipment to receive or retain programs
    • G06F9/46Multiprogramming arrangements
    • G06F9/48Program initiating; Program switching, e.g. by interrupt
    • G06F9/4806Task transfer initiation or dispatching
    • G06F9/4843Task transfer initiation or dispatching by program, e.g. task dispatcher, supervisor, operating system
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F9/00Arrangements for program control, e.g. control units
    • G06F9/06Arrangements for program control, e.g. control units using stored programs, i.e. using an internal store of processing equipment to receive or retain programs
    • G06F9/46Multiprogramming arrangements
    • G06F9/48Program initiating; Program switching, e.g. by interrupt
    • G06F9/4806Task transfer initiation or dispatching
    • G06F9/4843Task transfer initiation or dispatching by program, e.g. task dispatcher, supervisor, operating system
    • G06F9/4881Scheduling strategies for dispatcher, e.g. round robin, multi-level priority queues
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W24/00Supervisory, monitoring or testing arrangements
    • H04W24/02Arrangements for optimising operational condition

Landscapes

  • Engineering & Computer Science (AREA)
  • Software Systems (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Debugging And Monitoring (AREA)

Abstract

The invention provides a task scheduling method and a task scheduling system for an automatic WIFI performance test platform. The task scheduling method comprises the steps of acquiring the current required WIFI performance test projects; acquiring the correlation attributes and the weight information of all test projects and test cases in the test projects; performing first sequencing on all the test projects according to the weight information of all the test projects; calculating all parallel test sets according to the resource conflict determination conditions and all test projects sequenced firstly, wherein the parallel test set is composed of test projects which can be tested in parallel; performing second sequencing on all the parallel test sets according to the priority judgment principle and taking the parallel test sets sequenced secondly as a testing sequence; and outputting the testing sequence. According to the task scheduling method and the task scheduling system for the WIFI performance automatic test platform, the execution efficiency of the automatic WIFI performance test platform and the utilization rate of the equipment are greatly improved.

Description

A kind of method for scheduling task of WIFI performance automation test platform and system
Technical field
The present invention relates to wireless communication field, particularly relate to a kind of method for scheduling task and system of WIFI performance automation test platform.
Background technology
Along with the universal of WIFI and popularization, increasing communication facilities starts to be equipped with WIFI communication module, the mobile terminal such as smart mobile phone and panel computer is as the important component part of mobile communications network, and the popularity rate of WIFI on the mobile terminal such as smart mobile phone and panel computer is very high.Every platform equipment all will carrying out quality testing and performance test, for ensureing the performance of the WIFI communication module of every platform equipment, just needing to carry out WIFI performance test to it after being produced before list marketing.
Performance test for WIFI is divided into manually and automatic two kinds.For the performance test of the Physical layer of WIFI, because the test item of WIFI Physical layer performance test is very many, generally adopt manual test.The WIFI module of such as mobile phone, each test item needs to arrange mobile phone and testing tool simultaneously, the efficiency comparison of manual test is low, the mobile phone update cycle was long in the past, require so not high to testing efficiency, the low defect of manual test mode testing efficiency does not impact the research and development of mobile phone and production efficiency.The cycle of the update of now mobile phone is shorter and shorter, proposes more and more higher requirement to research and development and production efficiency, and the WIFI Physical layer performance of mode to mobile phone of employing manual test tests the research and development and production efficiency that are unfavorable for improving mobile phone.Therefore, for WIFI performance automatic test more and more use by lots of manufacturers.
At present, automatic test many employings WIFI performance automation test platform of WIFI performance has come.But WIFI performance test project is mixed and disorderly, and content measurement is of a great variety, in different project testings, the WIFI performance automation test platform general project performing Test Engineer in order successively and submit to is generally serial between project and project.When no conflict occurred for resource, also can consider once in a while to walk abreast.But such testing sequence is far from reaching the object that the maximum load of WIFI performance automation test platform and shortest time test maximum projects.This certainly will result in the waste of some resources, has had a strong impact on the execution efficiency that entry is parallel.
Therefore, be directed to the WIFI performance test that kind is numerous, different projects often but exists many identical test cases needs test.How to spend the shortest time, utilize minimum resource to complete the WIFI performance test of these projects, become the problem of those skilled in the art institute growing interest.
Summary of the invention
The shortcoming of prior art in view of the above, the object of the present invention is to provide a kind of method for scheduling task and system of WIFI performance automation test platform, efficiency for solving when WIFI performance automation test platform in prior art carries out performance test is too low, easily causes the problem of the wasting of resources.
For achieving the above object and other relevant objects, the invention provides a kind of method for scheduling task of WIFI performance automation test platform, comprising: step S10, obtain the test event that all current need carry out WIFI performance test; Step S20, obtains the test case that the association attributes of all test events, weight information and test event comprise; Step S30, according to the described weight information of all test events, carries out first time sequence; Step S40, according to all test events after resource contention decision condition and first time sequence, calculates all concurrent testing set; Wherein, described concurrent testing set is by can the set that forms of test event tested of executed in parallel; Step S50, according to preferential decision principle, carries out second time sequence to all described concurrent testing set, and using the described concurrent testing set after second time sequence as cycle tests; Step S60, exports described cycle tests.
In one embodiment of the invention, described association attributes comprises the priority that test event has.
In one embodiment of the invention, described step S50 also comprises: after second time sequence, judge whether the test event that preferential execution priority is the highest: as the test event wanting preferential execution priority the highest, then test event the highest for priority be ranked first, after described concurrent testing set through second time sequence is come the highest test event of priority, in the lump as described cycle tests; The all described concurrent testing set performed as not preferential, then the described concurrent testing set will sorted through second time is as described cycle tests.
In one embodiment of the invention, in described step S40, described resource contention decision condition is whether there is identical test case in different test event: in this way, then resource contention; As no, then resource is not conflicted.
In one embodiment of the invention, between all test events in described concurrent testing set, resource is not conflicted mutually.
In one embodiment of the invention, in described step S50, according to preferential decision principle, to all described concurrent testing set carry out second time sequence comprise: the quantity calculating the test event comprised in described concurrent testing set: the described concurrent testing set that test event quantity is many front, after the described concurrent testing that test event quantity is few is integrated into; If the quantity of the test event comprised in described concurrent testing set is identical, then calculate the test event required time performed in described concurrent testing set: before the short described concurrent testing of required time is integrated into, after the short described concurrent testing of required time is integrated into.
The invention also discloses a kind of task scheduling system of WIFI performance automation test platform, comprising: test event acquisition module, carrying out all test events of WIFI performance test for obtaining current need; Relevant information acquisition module, user obtains the relevant information of all test events, and described relevant information comprises the test case that association attributes, weight information and test event comprise; An order module, for the weight information obtained according to described relevant information acquisition module, carries out the first time sequence of all test events; Concurrent testing set calculation module, for calculating all concurrent testing set according to all test events after resource contention decision condition and first time sequence; Wherein, described concurrent testing set be all can executed in parallel test test item destination aggregation (mda); Secondary order module, for according to preferential decision principle, carries out second time sequence to all described concurrent testing set, and using the described concurrent testing set after second time sequence as cycle tests; Cycle tests output module, for exporting described cycle tests.
In one embodiment of the invention, described secondary order module is according to carrying out two minor sorts as follows: the quantity calculating the test event comprised in described concurrent testing set: the described concurrent testing set that test event quantity is many front, after the described concurrent testing that test event quantity is few is integrated into; If the quantity of the test event comprised in described concurrent testing set is identical, then calculate the test event required time performed in described concurrent testing set: before the short described concurrent testing of required time is integrated into, after the short described concurrent testing of required time is integrated into.
In one embodiment of the invention, described association attributes comprises the priority that test event has.
In one embodiment of the invention, described secondary order module is after second time sequence, also to judge whether the test event that preferential execution priority is the highest: as the test event wanting preferential execution priority the highest, then test event the highest for priority be ranked first, after described concurrent testing set through second time sequence is come the highest test event of priority, in the lump as described cycle tests; The all described concurrent testing set performed as not preferential, then the described concurrent testing set will sorted through second time is as described cycle tests.
As mentioned above, the method for scheduling task of a kind of WIFI performance automation test platform of the present invention and system, can the possibility of concurrent testing by judging whether time point has, and find parallel Projects as much as possible by algorithm, and optimized sequence is carried out to parallel Projects, thus substantially increase the execution efficiency of WIFI performance automation test platform and the utilization factor of equipment.
Accompanying drawing explanation
Fig. 1 is shown as the schematic flow sheet of the method for scheduling task of a kind of WIFI performance automation test platform disclosed in the embodiment of the present invention.
Fig. 2 is shown as the concrete implementing procedure schematic diagram of step S30-S50 in the method for scheduling task of a kind of WIFI performance automation test platform disclosed in the embodiment of the present invention.
Fig. 3 is shown as the structural representation of the task scheduling system of a kind of WIFI performance automation test platform disclosed in the embodiment of the present invention.
Element numbers explanation
S10 ~ S60 step
310 test event acquisition modules
320 relevant information acquisition modules
330 order module
340 concurrent testing set calculation module
350 2 order module
360 cycle tests output modules
Embodiment
Below by way of specific instantiation, embodiments of the present invention are described, those skilled in the art the content disclosed by this instructions can understand other advantages of the present invention and effect easily.The present invention can also be implemented or be applied by embodiments different in addition, and the every details in this instructions also can based on different viewpoints and application, carries out various modification or change not deviating under spirit of the present invention.It should be noted that, when not conflicting, the feature in following examples and embodiment can combine mutually.
Refer to accompanying drawing.It should be noted that, the diagram provided in following examples only illustrates basic conception of the present invention in a schematic way, then only the assembly relevant with the present invention is shown in graphic but not component count, shape and size when implementing according to reality is drawn, it is actual when implementing, and the kenel of each assembly, quantity and ratio can be a kind of change arbitrarily, and its assembly layout kenel also may be more complicated.
Embodiment 1
Present embodiment discloses a kind of method for scheduling task of WIFI performance automation test platform, it is by obtaining test event relevant information (comprising the priority of test event itself), can the possibility of concurrent testing by judging whether time point has, and find parallel Projects as much as possible by algorithm, and optimized sequence is carried out to parallel Projects, reach the object improving WIFI performance test efficiency.
As shown in Figure 1, the method for scheduling task of the WIFI performance automation test platform of the present embodiment comprises:
Step S10, obtains the test event that all current need carry out WIFI performance test;
WIFI performance automation test platform both can carry out WIFI performance test to a test event, also can carry out WIFI performance test to multiple test event.
Step S20, obtains the test case that the association attributes of all test events, weight information and test event comprise:
Wherein, association attributes comprises the priority that test event has, and user can need to set according to self.
The kind of WIFI performance test is very many, therefore, just includes a lot of test case in test event, in order to carry out the judgement of executed in parallel test, so need to understand the test case in each test event.
Step S30, according to the described weight information of all test events, carries out first time sequence:
According to the priority level of weight information, carry out first time sequence.
Step S40, according to all test events after resource contention decision condition and first time sequence, calculates all concurrent testing set; Wherein, described concurrent testing set is by can the set that forms of test event tested of executed in parallel:
Wherein, resource contention decision condition is whether there is identical test case in different test event, if having identical test case, then and resource contention; If do not have identical test case, then resource is not conflicted.
Whether resource contention to be, be test event could executed in parallel test condition precedent.
By all concurrent testing set that resource contention decision condition calculates, the test resource belonged between all test events in same concurrent testing set does not conflict mutually.
Further, concurrent testing set also comprises the situation only having a test event, and the test event only comprised in the concurrent testing set expression set of a test event can only be tested separately.
Step S50, according to preferential decision principle, carries out second time sequence to all described concurrent testing set, and using all described concurrent testing set after second time sequence as cycle tests.
Wherein, second time sequence is according to carrying out as follows:
Calculate the quantity of the test event comprised in described concurrent testing set: the described concurrent testing set that test event quantity is many front, after the described concurrent testing that test event quantity is few is integrated into;
If the quantity of the test event comprised in described concurrent testing set is identical, then calculate the test event required time performed in described concurrent testing set: before the short described concurrent testing of required time is integrated into, after the short described concurrent testing of required time is integrated into.
Further, in order to meet the demand of user, now also need the test event judging whether that preferential execution priority is the highest:
As the test event wanting preferential execution priority the highest, then test event the highest for priority be ranked first, after the concurrent testing set through second time sequence is come the highest test event of priority, in the lump as described cycle tests;
The all described concurrent testing set performed as not preferential, then all described concurrent testing set will sorted through second time is as described cycle tests.
Step S60, exports through described cycle tests:
The cycle tests obtained after above-mentioned steps process, be several can executed in parallel test concurrent testing set, WIFI performance automation test platform according to this cycle tests perform WIFI test, can greatly save the test duration and improve testing efficiency.
Method step S40 in the method for scheduling task of the WIFI performance automation test platform of the present embodiment being calculated to concurrent testing set has a variety of when concrete realization; only enumerate one to be herein described in detail; certainly, the scope protected of the present invention be only limitted to this kind of implementation method.
As shown in Figure 2, wherein, X represents the label of concurrent testing set, and N represents the label order of test event after first time sequence; A represents the number of entry in concurrent testing set.In addition, B represents that current need carry out the number of entry of WIFI performance test; A represents the quantity of the residue test event after variation.The calculating of concurrent testing set is the order of the test event after sorting according to first time, from first test event, test event is contrasted between two, judge whether the conflict that there is test case, circulation is carried out, thus calculating gets all concurrent testing set.
The step of various method divides above, just in order to be described clearly, can merge into a step or splitting some step, being decomposed into multiple step, when realizing as long as comprise identical logical relation, all in the protection domain of this patent; To adding inessential amendment in algorithm or in flow process or introducing inessential design, but the core design not changing its algorithm and flow process is all in the protection domain of this patent.
Embodiment 2
Present embodiment discloses a kind of task scheduling system of WIFI performance automation test platform, it obtains test event relevant information (comprising the priority of project itself), whether the test resource first according to project conflicts, judging to calculate can the concurrent testing set (comprise projects that those can not walk abreast produce only have an item destination aggregation (mda)) of parallel Projects, according to the quantity order from more to less of the project in concurrent testing set, serial performs these set, if there is the situation that the number of entry in concurrent testing set is identical, then carry out order according to the length performing the time that the concurrent testing set of these identical items quantity spends to perform, the preferential execution that time is short, the project executed in parallel of concurrent testing set inside.The priority of test event itself has the highest authority, can do final adjustment above to the project implementation sequence automatically generated.
As shown in Figure 3, the task scheduling system of the WIFI performance automation test platform of the present embodiment comprises:
Test event acquisition module 310, carries out all test events of WIFI performance test for obtaining current need;
Relevant information acquisition module 320, user obtains the relevant information of all test events, and described relevant information includes but not limited to the test case that association attributes, weight information and test event comprise; Association attributes includes but not limited to the priority of test event.
An order module 330, for the weight information obtained according to described relevant information acquisition module, carries out the first time sequence of all test events; First time sequence is specifically dependent on the priority level of weight information.
Concurrent testing set calculation module 340, for calculating all concurrent testing set according to all test events after resource contention decision condition and first time sequence; Wherein, described concurrent testing set be all can executed in parallel test test item destination aggregation (mda):
Whether resource contention to be, be test event could executed in parallel test condition precedent, therefore, this module is the core calculations module of the task scheduling system of WIFI performance automation test platform.
Wherein, resource contention decision condition is whether there is identical test case in different test event, if having identical test case, then and resource contention; If do not have identical test case, then resource is not conflicted.
By all concurrent testing set that resource contention decision condition calculates, the test resource belonged between all test events in same concurrent testing set does not conflict mutually.
Further, concurrent testing set also comprises the situation only having a test event, and the test event only comprised in the concurrent testing set expression set of a test event can only be tested separately.
Secondary order module 350, for according to preferential decision principle, carries out second time sequence to all described concurrent testing set, and using the described concurrent testing set after second time sequence as cycle tests;
Wherein, second time sequence is according to carrying out as follows:
Calculate the quantity of the test event comprised in described concurrent testing set: the described concurrent testing set that test event quantity is many front, after the described concurrent testing that test event quantity is few is integrated into;
If the quantity of the test event comprised in described concurrent testing set is identical, then calculate the test event required time performed in described concurrent testing set: before the short described concurrent testing of required time is integrated into, after the short described concurrent testing of required time is integrated into.
Cycle tests output module 360, for exporting described cycle tests.
In addition, in order to outstanding innovative part of the present invention, the module not too close with solving technical matters relation proposed by the invention is not introduced in the present embodiment, but this does not show the module that there is not other in the present embodiment.
Be not difficult to find, the present embodiment is system embodiment corresponding to those in the first embodiment, and the present embodiment can be worked in coordination with the first embodiment and be implemented.The relevant technical details mentioned in first embodiment is still effective in the present embodiment, in order to reduce repetition, repeats no more here.Correspondingly, the relevant technical details mentioned in the present embodiment also can be applicable in the first embodiment.
In sum, the method for scheduling task of a kind of WIFI performance automation test platform of the present invention and system, can the possibility of concurrent testing by judging whether time point has, and find parallel Projects as much as possible by algorithm, and optimized sequence is carried out to parallel Projects, thus substantially increase the execution efficiency of WIFI performance automation test platform and the utilization factor of equipment.So the present invention effectively overcomes various shortcoming of the prior art and tool high industrial utilization.
Above-described embodiment is illustrative principle of the present invention and effect thereof only, but not for limiting the present invention.Any person skilled in the art scholar all without prejudice under spirit of the present invention and category, can modify above-described embodiment or changes.Therefore, such as have in art usually know the knowledgeable do not depart from complete under disclosed spirit and technological thought all equivalence modify or change, must be contained by claim of the present invention.

Claims (10)

1. a method for scheduling task for WIFI performance automation test platform, is characterized in that, comprising:
Step S10, obtains the test event that all current need carry out WIFI performance test;
Step S20, obtains the test case that the association attributes of all test events, weight information and test event comprise;
Step S30, according to the described weight information of all test events, carries out first time sequence;
Step S40, according to all test events after resource contention decision condition and first time sequence, calculates all concurrent testing set; Wherein, described concurrent testing set is by can the set that forms of test event tested of executed in parallel;
Step S50, according to preferential decision principle, carries out second time sequence to all described concurrent testing set, and using the described concurrent testing set after second time sequence as cycle tests;
Step S60, exports described cycle tests.
2. the method for scheduling task of WIFI performance automation test platform according to claim 1, is characterized in that: described association attributes comprises the priority that test event has.
3. the method for scheduling task of WIFI performance automation test platform according to claim 2, is characterized in that: described step S50 also comprises: after second time sequence, judge whether the test event that preferential execution priority is the highest:
As the test event wanting preferential execution priority the highest, then test event the highest for priority be ranked first, after the described concurrent testing set through second time sequence is come the highest test event of priority, in the lump as described cycle tests;
The all described concurrent testing set performed as not preferential, then the described concurrent testing set will sorted through second time is as described cycle tests.
4. the method for scheduling task of WIFI performance automation test platform according to claim 1, it is characterized in that: in described step S40, described resource contention decision condition is whether there is identical test case in different test event: in this way, then resource contention; As no, then resource is not conflicted.
5. the method for scheduling task of WIFI performance automation test platform according to claim 4, is characterized in that: between all test events in described concurrent testing set, resource is not conflicted mutually.
6. the method for scheduling task of WIFI performance automation test platform according to claim 1, is characterized in that: in described step S50, according to preferential decision principle, carries out second time sequence comprise all described concurrent testing set:
Calculate the quantity of the test event comprised in described concurrent testing set: the described concurrent testing set that test event quantity is many front, after the described concurrent testing that test event quantity is few is integrated into;
If the quantity of the test event comprised in described concurrent testing set is identical, then calculate the test event required time performed in described concurrent testing set: before the short described concurrent testing of required time is integrated into, after the short described concurrent testing of required time is integrated into.
7. a task scheduling system for WIFI performance automation test platform, is characterized in that: comprising:
Test event acquisition module, carries out all test events of WIFI performance test for obtaining current need;
Relevant information acquisition module, user obtains the relevant information of all test events, and described relevant information comprises the test case that association attributes, weight information and test event comprise;
An order module, for the weight information obtained according to described relevant information acquisition module, carries out the first time sequence of all test events;
Concurrent testing set calculation module, for calculating all concurrent testing set according to all test events after resource contention decision condition and first time sequence; Wherein, described concurrent testing set be all can executed in parallel test test item destination aggregation (mda);
Secondary order module, for according to preferential decision principle, carries out second time sequence to all described concurrent testing set, and using the described concurrent testing set after second time sequence as cycle tests;
Cycle tests output module, for exporting described cycle tests.
8. the task scheduling system of WIFI performance automation test platform according to claim 7, is characterized in that: described secondary order module is according to carrying out two minor sorts as follows:
Calculate the quantity of the test event comprised in described concurrent testing set: the described concurrent testing set that test event quantity is many front, after the described concurrent testing that test event quantity is few is integrated into;
If the quantity of the test event comprised in described concurrent testing set is identical, then calculate the test event required time performed in described concurrent testing set: before the short described concurrent testing of required time is integrated into, after the short described concurrent testing of required time is integrated into.
9. the task scheduling system of WIFI performance automation test platform according to claim 7, is characterized in that: described association attributes comprises the priority that test event has.
10. the task scheduling system of WIFI performance automation test platform according to claim 9, is characterized in that: described secondary order module, after second time sequence, also will judge whether the test event that preferential execution priority is the highest:
As the test event wanting preferential execution priority the highest, then test event the highest for priority be ranked first, after the described concurrent testing set through second time sequence is come the highest test event of priority, in the lump as described cycle tests;
The all described concurrent testing set performed as not preferential, then the described concurrent testing set will sorted through second time is as described cycle tests.
CN201610007820.2A 2016-01-06 2016-01-06 A kind of method for scheduling task and system of WIFI performance automation test platform Active CN105511951B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610007820.2A CN105511951B (en) 2016-01-06 2016-01-06 A kind of method for scheduling task and system of WIFI performance automation test platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610007820.2A CN105511951B (en) 2016-01-06 2016-01-06 A kind of method for scheduling task and system of WIFI performance automation test platform

Publications (2)

Publication Number Publication Date
CN105511951A true CN105511951A (en) 2016-04-20
CN105511951B CN105511951B (en) 2019-07-05

Family

ID=55719957

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610007820.2A Active CN105511951B (en) 2016-01-06 2016-01-06 A kind of method for scheduling task and system of WIFI performance automation test platform

Country Status (1)

Country Link
CN (1) CN105511951B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106598857A (en) * 2016-12-14 2017-04-26 英业达(重庆)有限公司 Method and device for testing electronic equipment based on automatic testing tool
CN107462845A (en) * 2017-07-28 2017-12-12 华南理工大学 LED light product-derived electrical characteristic parameter single-station multi parameter intallingent test device and method
WO2017219851A1 (en) * 2016-06-24 2017-12-28 深圳市中兴微电子技术有限公司 Method and apparatus for executing test case, and computer readable medium
CN108763093A (en) * 2018-06-01 2018-11-06 政采云有限公司 A kind of automated testing method and system
CN109728975A (en) * 2018-12-29 2019-05-07 广东电网有限责任公司 A kind of network protocol attack testing method, device, equipment and readable storage medium storing program for executing
CN111159007A (en) * 2018-11-08 2020-05-15 比亚迪汽车工业有限公司 Test sequence generation method and device
CN112345776A (en) * 2019-08-06 2021-02-09 深圳迈瑞生物医疗电子股份有限公司 Sample analysis system, sample analysis device and sample testing method
CN112363913A (en) * 2020-10-22 2021-02-12 北京电子工程总体研究所 Parallel test task scheduling optimization method and device and computing equipment
CN112559265A (en) * 2020-12-07 2021-03-26 深圳市鼎峰智能技术有限公司 Testing method based on big data intelligent optimization
WO2021185113A1 (en) * 2020-03-17 2021-09-23 华为技术有限公司 Data analysis method based on multiple analysis tasks and electronic device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3763474A (en) * 1971-12-09 1973-10-02 Bell Telephone Labor Inc Program activated computer diagnostic system
US20070233629A1 (en) * 2006-04-04 2007-10-04 Gil Balog Methods and systems for semiconductor testing using a testing scenario language
CN102012845A (en) * 2010-12-16 2011-04-13 迈普通信技术股份有限公司 Method for improving utilization rate of automatic testing resources
CN102495804A (en) * 2011-12-27 2012-06-13 创新科存储技术(深圳)有限公司 Automatic software testing method
CN104484162A (en) * 2014-10-31 2015-04-01 国云科技股份有限公司 Software testing case designing and writing method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3763474A (en) * 1971-12-09 1973-10-02 Bell Telephone Labor Inc Program activated computer diagnostic system
US20070233629A1 (en) * 2006-04-04 2007-10-04 Gil Balog Methods and systems for semiconductor testing using a testing scenario language
CN102012845A (en) * 2010-12-16 2011-04-13 迈普通信技术股份有限公司 Method for improving utilization rate of automatic testing resources
CN102495804A (en) * 2011-12-27 2012-06-13 创新科存储技术(深圳)有限公司 Automatic software testing method
CN104484162A (en) * 2014-10-31 2015-04-01 国云科技股份有限公司 Software testing case designing and writing method

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107544899B (en) * 2016-06-24 2020-04-24 深圳市中兴微电子技术有限公司 Method and device for executing test case
WO2017219851A1 (en) * 2016-06-24 2017-12-28 深圳市中兴微电子技术有限公司 Method and apparatus for executing test case, and computer readable medium
CN107544899A (en) * 2016-06-24 2018-01-05 深圳市中兴微电子技术有限公司 A kind of method and device of implementation of test cases
CN106598857A (en) * 2016-12-14 2017-04-26 英业达(重庆)有限公司 Method and device for testing electronic equipment based on automatic testing tool
CN107462845A (en) * 2017-07-28 2017-12-12 华南理工大学 LED light product-derived electrical characteristic parameter single-station multi parameter intallingent test device and method
CN107462845B (en) * 2017-07-28 2019-12-24 华南理工大学 Single-station multi-parameter intelligent testing method for electrical characteristic parameters of LED light source product
CN108763093A (en) * 2018-06-01 2018-11-06 政采云有限公司 A kind of automated testing method and system
CN111159007A (en) * 2018-11-08 2020-05-15 比亚迪汽车工业有限公司 Test sequence generation method and device
CN111159007B (en) * 2018-11-08 2023-04-07 比亚迪汽车工业有限公司 Test sequence generation method and device
CN109728975A (en) * 2018-12-29 2019-05-07 广东电网有限责任公司 A kind of network protocol attack testing method, device, equipment and readable storage medium storing program for executing
CN109728975B (en) * 2018-12-29 2021-03-12 广东电网有限责任公司 Network protocol attack testing method, device, equipment and readable storage medium
CN112345776A (en) * 2019-08-06 2021-02-09 深圳迈瑞生物医疗电子股份有限公司 Sample analysis system, sample analysis device and sample testing method
CN112345776B (en) * 2019-08-06 2024-01-09 深圳迈瑞生物医疗电子股份有限公司 Sample analysis system, device and sample testing method
WO2021185113A1 (en) * 2020-03-17 2021-09-23 华为技术有限公司 Data analysis method based on multiple analysis tasks and electronic device
CN112363913A (en) * 2020-10-22 2021-02-12 北京电子工程总体研究所 Parallel test task scheduling optimization method and device and computing equipment
CN112363913B (en) * 2020-10-22 2024-01-26 北京电子工程总体研究所 Parallel test task scheduling optimizing method, device and computing equipment
CN112559265A (en) * 2020-12-07 2021-03-26 深圳市鼎峰智能技术有限公司 Testing method based on big data intelligent optimization

Also Published As

Publication number Publication date
CN105511951B (en) 2019-07-05

Similar Documents

Publication Publication Date Title
CN105511951A (en) Task scheduling method and task scheduling system for automatic WIFI performance test platform
CN101196844B (en) System and method of testing hardware module
CN105426309A (en) Test case automatic generation method and apparatus
CN102012845B (en) Method for improving utilization rate of automatic testing resources
Cota et al. Constraint-driven test scheduling for NoC-based systems
CN105491140A (en) Remote testing method and system for terminal
CN109960871B (en) Single-station testing modeling scheduling method for performance of precision speed reducer of industrial robot
CN112799966B (en) Method, system, equipment and medium for generating test data in batches by extensible plug-in
CN106250317A (en) Electronic equipment and the method for testing of application thereof and system
CN104133172A (en) Novel test development method for improving simultaneous test number
CN116577639A (en) CIS chip testing method and testing system
CN105279061A (en) Server interface concurrent testing method and apparatus
CN112306004A (en) Semiconductor process recipe management method and system
CN108063101B (en) Sampling method for wafer defect test
CN111782507B (en) Data testing method and device, storage medium and electronic equipment
CN105955814A (en) Event priority scheduling-based complex event detection method
US9671779B2 (en) Method and system for filtering lot schedules using a previous schedule
Cevikcan et al. Integrating parts design characteristics and scheduling on parallel machines
Mirzapourrezaei et al. Simulation of a manufacturing assembly line based on witness
CN114300391B (en) Wafer test method and device, electronic equipment and storage medium
CN105022864A (en) System test point selecting method based on extended dependence matrix
CN113836032A (en) Android interface concurrent testing method, device, equipment and storage medium
CN105337769A (en) System and method for alarming processing flow
CN104217970A (en) Sampling method and system
CN111400221A (en) Adapter plate control method and system based on automatic production line

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20201116

Address after: Room 10242, No. 260, Jiangshu Road, Xixing street, Binjiang District, Hangzhou City, Zhejiang Province

Patentee after: Hangzhou Jiji Intellectual Property Operation Co.,Ltd.

Address before: 201616 Shanghai city Songjiang District Sixian Road No. 3666

Patentee before: Phicomm (Shanghai) Co.,Ltd.

TR01 Transfer of patent right
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20160420

Assignee: ZHEJIANG XINZAILING TECHNOLOGY Co.,Ltd.

Assignor: Hangzhou Jiji Intellectual Property Operation Co.,Ltd.

Contract record no.: X2024330000010

Denomination of invention: A Task Scheduling Method and System for WIFI Performance Automation Testing Platform

Granted publication date: 20190705

License type: Common License

Record date: 20240123

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20160420

Assignee: HANGZHOU DUNCHONG SCIENCE & TECHNOLOGY CO.,LTD.

Assignor: Hangzhou Jiji Intellectual Property Operation Co.,Ltd.

Contract record no.: X2024330000013

Denomination of invention: A Task Scheduling Method and System for WIFI Performance Automation Testing Platform

Granted publication date: 20190705

License type: Common License

Record date: 20240227

EE01 Entry into force of recordation of patent licensing contract