CN105488657B - A kind of electric power industry expansion project data processing method and processing device - Google Patents

A kind of electric power industry expansion project data processing method and processing device Download PDF

Info

Publication number
CN105488657B
CN105488657B CN201510816561.3A CN201510816561A CN105488657B CN 105488657 B CN105488657 B CN 105488657B CN 201510816561 A CN201510816561 A CN 201510816561A CN 105488657 B CN105488657 B CN 105488657B
Authority
CN
China
Prior art keywords
electric power
project data
power industry
expands
industry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510816561.3A
Other languages
Chinese (zh)
Other versions
CN105488657A (en
Inventor
谢枫
方茂益
傅军
张艳丽
牛逸宁
王鹏伍
周国鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
North China Electric Power Research Institute Co Ltd
Electric Power Research Institute of State Grid Jibei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
North China Electric Power Research Institute Co Ltd
Electric Power Research Institute of State Grid Jibei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, North China Electric Power Research Institute Co Ltd, Electric Power Research Institute of State Grid Jibei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510816561.3A priority Critical patent/CN105488657B/en
Publication of CN105488657A publication Critical patent/CN105488657A/en
Application granted granted Critical
Publication of CN105488657B publication Critical patent/CN105488657B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Water Supply & Treatment (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of electric power industry expansion project data processing method and processing device, wherein this method comprises: the electric power industry for receiving the first user input expands project data;Project data is expanded to the electric power industry of the first user input and carries out preliminary hearing;When preliminary hearing does not pass through, terminate the processing for expanding electric power industry project data;When preliminary hearing passes through, creation electric power industry expands project data and handles task;Expand the project data processing corresponding second user of task selection according to electric power industry to handle electric power industry expansion project data;Receive corresponding second user input expands the processing result that project data is handled to electric power industry;The processing result that corresponding second user inputs is summarized, the processing result after summarizing is sent to the first user.Electric power industry is carried out using the method for the present invention and device and expands project data processing, is not entirely dependent on manual type and electric power industry expansion project data is handled;Shorten and examines the period;It does not need to print a large amount of paper material, not will cause paper waste.

Description

A kind of electric power industry expansion project data processing method and processing device
Technical field
The present invention relates to electric power project engineering field, in particular to a kind of electric power industry expands project data processing method and dress It sets.
Background technique
Currently, the demand of large user's Business Process System is more and more, needs to establish an engineering during Business Process System, is The safety for ensuring engineering, needs just to set document to engineering and examines.Entire power consumer industry expands engineering and just sets document examination Operating mode is as shown in Figure 1, it is necessary first to apply to install user and submit industry to expand engineering Preliminary design document, client service center to client service center Integrality, completeness inspection are carried out to the documents data that user submits, inspection accepts user's request after passing through.Its Secondary, data is submitted according to user by power supply company, invites relevant speciality reviewer (expert) to carry out with conferencing form and sets text to first The in-process review of shelves papery data eventually forms Review conclusion and suggestion feedback to applying to install user.
Current power consumer industry sets document and examines that mode has the following problems at the beginning of expanding engineering:
(1) it is completely dependent on manual type and carries out the processing (examination) that electric power industry expands project data (industry expands engineering and just sets data) Work;
(2) since electric power industry expands, project data is various, and the data that client prepares if it exists are not complete or different design closes specially The problems such as industry standard, leads to design once examination and does not pass through, will cause and examine that link (data processing) period is long;
(3) it needs to print a large amount of paper material, causes paper waste.
Summary of the invention
The embodiment of the invention provides a kind of electric power industry to expand project data processing method, is not entirely dependent on manual type pair Electric power industry expands project data and is handled;Shorten and examines the period;It does not need to print a large amount of paper material, not will cause paper wave Take.The electric power industry expands project data processing method
The electric power industry for receiving the first user input expands project data;
Project data is expanded to the electric power industry of the first user input and carries out preliminary hearing;When preliminary hearing does not pass through, terminate to electric power industry Expand the processing of project data;When preliminary hearing passes through, creation electric power industry expands project data and handles task;
Expand project data processing task according to electric power industry and chooses corresponding second user to the expansion project data progress of electric power industry Processing;
Receive corresponding second user input expands the processing result that project data is handled to electric power industry;
The processing result that corresponding second user inputs is summarized, the processing result after summarizing is sent to the first use Family.
In one embodiment, specifically expand project data to the electric power industry of the first user input as follows to carry out in advance It examines:
The electric power industry of first user input is expanded project data to match with electric power industry expansion project data template;
When it fails to match, terminate the processing for expanding electric power industry project data;
When successful match, creation electric power industry expands project data and handles task.
In one embodiment, further includes:
When it fails to match, determines that the electric power industry of missing expands project data, project data phase is expanded according to the electric power industry of missing Information is closed, the electric power industry for notifying the first user to input missing expands project data.
In one embodiment, described to receive handling electric power industry expansion project data for corresponding second user input Processing result, specifically include:
According to preset electric power industry expand project data processing rule, corresponding second user to electric power industry expand project data into Row processing, obtains processing result;
Receive the processing result of corresponding second user input.
The embodiment of the invention also provides a kind of electric power industry to expand project data processing unit, is not entirely dependent on manual type Expand project data to electric power industry to handle;Shorten and examines the period;It does not need to print a large amount of paper material, not will cause paper Waste.The device includes:
Receiving module, the electric power industry for receiving the first user input expand project data;
Preliminary hearing module, the electric power industry for inputting to the first user expand project data and carry out preliminary hearing;When preliminary hearing does not pass through, Terminate the processing for expanding electric power industry project data;When preliminary hearing passes through, creation electric power industry expands project data and handles task;
Module is chosen, electric power industry is expanded for expanding project data processing task selection corresponding second user according to electric power industry Project data is handled;
The receiving module is also used to receive handling electric power industry expansion project data for corresponding second user input Processing result;
Summarizing module, the processing result for inputting corresponding second user summarize;
Sending module, for the processing result after summarizing to be sent to the first user.
In one embodiment, the preliminary hearing module is specifically used for:
The electric power industry of first user input is expanded project data to match with electric power industry expansion project data template;
When it fails to match, terminate the processing for expanding electric power industry project data;
When successful match, creation electric power industry expands project data and handles task.
In one embodiment, the preliminary hearing module is also used to:
When it fails to match, determines that the electric power industry of missing expands project data, project data phase is expanded according to the electric power industry of missing Information is closed, the electric power industry for notifying the first user to input missing expands project data.
In one embodiment, the receiving module also particularly useful for:
According to preset electric power industry expand project data processing rule, corresponding second user to electric power industry expand project data into Row processing, obtains processing result;
Receive the processing result of corresponding second user input.
In embodiments of the present invention, to electric power industry expand the reception of project data, preliminary hearing and processing be all in a computer into Capable, do not completely depend on manual type progress;Expand electric power industry the processing of project data, it is only necessary to carry out a preliminary hearing and primary Processing by second user can be completed, and shorten and examine link (data processing) period;Electric power industry expands project data, right Electric power industry expand project data preliminary hearing as a result, and to electric power industry expand project data processing processing result be stored entirely in computer In, it does not need to print a large amount of paper material, not will cause paper waste.
Detailed description of the invention
The drawings described herein are used to provide a further understanding of the present invention, constitutes part of this application, not Constitute limitation of the invention.In the accompanying drawings:
Fig. 1 is to set document at the beginning of a kind of existing industry provided in an embodiment of the present invention expands engineering to examine flow chart;
Fig. 2 is that a kind of electric power industry provided in an embodiment of the present invention expands project data processing method flow chart;
Fig. 3 is that a kind of specific electric power industry provided in an embodiment of the present invention expands project data examination process;
Fig. 4 is that a kind of electric power industry provided in an embodiment of the present invention expands project data processing unit structural block diagram.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, right below with reference to embodiment and attached drawing The present invention is described in further details.Here, exemplary embodiment and its explanation of the invention is used to explain the present invention, but simultaneously It is not as a limitation of the invention.
It is existing to expand power consumer industry the examination that engineering just sets document, it is completely dependent on manual type development;Power consumer Industry expands engineering, and just to set document numerous, may once examine and not pass through, and standard, specification being related to by evaluation course etc. is more, and Evaluation expert profile is different from experience level, there is the case where primary evaluation is not by needing secondary evaluation, will cause careful It is long to look into link (data processing) period;It needs to print a large amount of paper material, causes paper waste.If can be using examining It unites (computer process), as soon as time preliminary hearing and single treatment (examination) are carried out by expanding project data to power consumer industry, it can be complete Pairs of power consumer industry expands the examination that engineering just sets document, then just can solve above-mentioned problems of the prior art.Based on this, The present invention proposes that a kind of electric power industry expands project data processing method.
Fig. 2 is a kind of electric power industry expansion project data processing method flow chart provided in an embodiment of the present invention, as shown in Fig. 2, This method comprises:
Step 201: the electric power industry for receiving the first user input expands project data;
Step 202: project data being expanded to the electric power industry of the first user input and carries out preliminary hearing;When preliminary hearing does not pass through, terminate Expand electric power industry the processing of project data;When preliminary hearing passes through, creation electric power industry expands project data and handles task;
Step 203: project data processing task being expanded according to electric power industry and chooses corresponding second user to electric power industry expansion engineering Data are handled;
Step 204: receive corresponding second user input expands the processing result that project data is handled to electric power industry;
Step 205: the processing result that corresponding second user inputs being summarized, the processing result after summarizing is sent To the first user.
When it is implemented, described electric power industry expands project data, it may include that industry expands engineering process data, Preliminary design text Shelves data and design drawing three parts, document number nearly 20, document format covers Word, Excel, CAD, PDF etc..
Wherein, industry expansion engineering process data includes:
1) access system plan and review comment;
2) power supply plan and review comment.
Preliminary design document information includes:
It 1) is foundation by electrical engineering design and specification using the power supply plan after formally giving an written reply;
2) load composition and distribution map and design-calculated peak load data;
3) load composition, property and protective load;
4) the electrical equipment inventory for influencing power quality, the electricity quality evaluation report provided with corresponding qualification unit;
5) a power receiving equipment important technological parameters detail list;
6) main production equipments, production technology power consumption and permission interruption of power supply time;
7) calculating of electric power factor and Reactive Compensation Mode and capacity;
8) mode of overvoltage protection, relay protection and electric energy metering device;
9) technical measures and data with harmonic carcellation are generated;
10) the power autonomous and mode of connection;
11) power supply enterprise thinks the other data that must be provided.
Industry expands drawing of engineering design
1) floor plan of first and second wiring diagram of high powered device and the electric room of change (matching);
2) concealed work design data and earthing or grounding means figure;
3) the rod-type figure and geographical diagram of line facility.
When it is implemented, Fig. 3, which show a kind of specific power consumer industry, expands the intelligent mould that engineering just sets document examination Formula:
(1) document upload and automatic preliminary hearing
Power consumer is submitted by internet just sets document (above-mentioned described electric power industry expands project data), and evaluation is required It is cured as system function, system does not pass through according to the verification rule of setting to the automatic preliminary hearing of document progress, preliminary hearing is just set, end pair The processing of electric power industry expansion project data;Preliminary hearing, which accepts to apply to install user and evaluate after passing through, to be applied.User self-help completes entire industry and expands work The uploading operation of Cheng Chushe document, after application is accepted, client submits the paper material of major design document as evaluation reference.
It may include the verification rule of preliminary hearing that described evaluation, which requires, evaluation task creation requirement, set document (electric power to first Industry expands project data) processing requirement etc..
Wherein, verification rule, which can be, expands project data and electric power industry for the electric power industry of the first user (power consumer) input Expand project data template to be matched;When it fails to match, terminate the processing for expanding electric power industry project data;Work as successful match When, creation electric power industry expands project data and handles task.
It when matching unsuccessful, can also determine that the electric power industry of missing expands project data, according to the electric power industry of missing Expand project data relevant information, the electric power industry for notifying the first user to input missing expands project data.
(2) task is generated and is distributed
After preliminary hearing passes through, system can establish industry automatically and expand the evaluation (engineering of electric power industry expansion in other words that engineering just sets document Data processing) task.Because what electric power industry expansion project data was related to has multiple profession aspects, when establishing examination task, It is that electric power industry expansion project data is divided into multiple groups according to different professions, then by systems specialists management, according to being related to not Multiple groups electric power industry with profession expands project data, when selecting expert (second user) to examine, selects different special The suitable expert of industry examines corresponding data.After task is assigned, by way of Email or short message Notify the relevant unexamined mission bit stream of expert.
(3) expert evaluates online
The expert of evaluation is participated in by mobile terminal or PC machine login system, carries out online evaluation, evaluates content packet It includes and just sets file and two kinds of design drawing examinations.Evaluation reference frame (can be described as preset electric power industry and expand project data processing Rule) or case be managed by knowledge base, expert's (second user) according to examine reference frame (can be described as preset electric power Industry expand project data processing rule) or case come to electric power industry expand project data handle, the input processing result into system. Expert's (second user) can check the design data for applying to install user's submission online in checking process, and can be with retrieval knowledge library Knowledge assistance censorship.
(4) summarize generation review comment automatically
After each expert's (second user) expands project data evaluation to electric power industry, system can be to each expert (second user) Review comment summarized, by the way that pre-set algorithm or rule is arranged, automatically generate final review comment.If commented Fruit of concluding is not pass through, then establishes secondary evaluation task according to this evaluation task auto-associating.
(5) user's examination reports are replied
After examination, user's examination reports are replied by short message or E-mail mode, are posted under isochrone to user Written examination reports.
On stated can when preliminary hearing is unacceptable, notify the first user (power consumer) upload missing electric power industry Expand project data, can also finally examine after (processing), rectified and improved if necessary to client, internet is passed through again by client Submit secondary evaluation rectification material.
(6) online Data storage
After evaluation, system is to information such as assessment material involved in this checking process, evaluation course, review comments File storage after classification, and can be to the suggestion and this Project evaluation that expert in this evaluation course fills in after manual examination and verification It is included into knowledge base, realizes the dynamic optimization of knowledge base knowledge.
In conclusion invention achieves power consumer industry is expanded the mesh that engineering just sets document censorship intelligent processing , in entire checking process, reply from document upload, automatic preliminary hearing, task generation, experts' evaluation, opinion to Data storage, It is all made of on line intelligent operating mode, is effectively reduced to paper material, artificial experience, profile, working attitude etc. Dependence, improve power consumer industry and expand engineering and just set document censorship standardization of process, greatly shorten entire industry and expand engineering Document checking process just is set, improves the working efficiency and quality of staff, reduces the cost of serving and pipe of power grid enterprises Reason cost shortens the customer service response time.
Meanwhile the current standard needed to refer to during inspection of documents, expert are just set by the way that power consumer industry is expanded engineering Experience, classical case establish knowledge base, can search for knowledge base in specialist examination with real-time online and carry out assisted review, improve The science of specialist examination, that reduces electronic document when expert searches with reference to knowledge browses repetitive rate and blindness, while may be used also To realize that examination experience is transmitted, promote just to set being constantly progressive for document examination level.
By on line, work in conjunction mode under line, realize the full intelligent management of checking process, improve client's participation The perception of censorship forms client's demand closed loop management, can not only improve customer satisfaction with services, even more can be to entire work Make process and realizes fine-grained management.
In addition, by electronic chemical operation mode, it is convenient to bring for staff and specialist examination, instead of papery material Material, has saved a large amount of paper, provides convenience for the archive and protection of data.
The achievement that intelligent file censorship model study is set at the beginning of expanding engineering to electric power industry can be widely applied to SG186 battalion Pin Business Process System engineering documents accept in censorship.
Based on the same inventive concept, a kind of electric power industry expansion project data processing unit is additionally provided in the embodiment of the present invention, As described in the following examples.Since electric power industry expands the principle that project data processing unit solves the problems, such as and electric power industry expansion engineering number It is similar according to processing method, therefore the implementation of electric power industry expansion project data processing unit may refer to electric power industry and expand project data processing The implementation of method, overlaps will not be repeated.Used below, predetermined function may be implemented in term " unit " or " module " Software and/or hardware combination.Although device described in following embodiment is preferably realized with software, hardware, Or the realization of the combination of software and hardware is also that may and be contemplated.
Fig. 4 is a kind of structural block diagram of electric power industry expansion project data processing unit of the embodiment of the present invention, as shown in figure 4, The device includes:
Receiving module 401, the electric power industry for receiving the first user input expand project data;
Preliminary hearing module 402, the electric power industry for inputting to the first user expand project data and carry out preliminary hearing;When preliminary hearing does not pass through When, terminate the processing for expanding electric power industry project data;When preliminary hearing passes through, creation electric power industry expands project data and handles task;
Module 403 is chosen, chooses corresponding second user to electric power for expanding project data processing task according to electric power industry Industry expands project data and is handled;
The receiving module 401 is also used to receive expanding at project data electric power industry for corresponding second user input The processing result of reason;
Summarizing module 404, the processing result for inputting corresponding second user summarize;
Sending module 405, for the processing result after summarizing to be sent to the first user.
The structure is illustrated below.
When it is implemented, the preliminary hearing module 402 is specifically used for:
The electric power industry of first user input is expanded project data to match with electric power industry expansion project data template;
When it fails to match, terminate the processing for expanding electric power industry project data;
When successful match, creation electric power industry expands project data and handles task.
When it is implemented, the preliminary hearing module 402 is also used to:
When it fails to match, determines that the electric power industry of missing expands project data, project data phase is expanded according to the electric power industry of missing Information is closed, the electric power industry for notifying the first user to input missing expands project data.
When it is implemented, the receiving module 401 also particularly useful for:
According to preset electric power industry expand project data processing rule, corresponding second user to electric power industry expand project data into Row processing, obtains processing result;
Receive the processing result of corresponding second user input.
Obviously, those skilled in the art should be understood that each module of the above-mentioned embodiment of the present invention or each step can be with It is realized with general computing device, they can be concentrated on a single computing device, or be distributed in multiple computing devices On composed network, optionally, they can be realized with the program code that computing device can perform, it is thus possible to by it Store and be performed by computing device in the storage device, and in some cases, can be held with the sequence for being different from herein The shown or described step of row, perhaps they are fabricated to each integrated circuit modules or will be multiple in them Module or step are fabricated to single integrated circuit module to realize.In this way, the embodiment of the present invention be not limited to it is any specific hard Part and software combine.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the embodiment of the present invention can have various modifications and variations.All within the spirits and principles of the present invention, made Any modification, equivalent substitution, improvement and etc. should all be included in the protection scope of the present invention.

Claims (4)

1. a kind of electric power industry expands project data processing method characterized by comprising
The electric power industry for receiving the first user input expands project data, wherein it includes that industry expands engineering that the electric power industry, which expands project data, Process data, industry expand engineering Preliminary design document information and industry expands drawing of engineering design;
Project data is expanded to the electric power industry of the first user input and carries out preliminary hearing, comprising: the electric power industry of the first user input is expanded into work Number of passes is matched according to electric power industry expansion project data template, when it fails to match, terminates the place for expanding electric power industry project data Reason expands project data relevant information according to the electric power industry of missing, notifies first or, determining that the electric power industry of missing expands project data The electric power industry that user inputs missing expands project data;When successful match, creation electric power industry expands project data and handles task, described Electric power industry expand project data processing task be according to the industry expand engineering process data, industry expand engineering Preliminary design document information with And industry expands the different processing tasks of drawing of engineering design creation;
Expand the project data processing corresponding second user of task selection according to electric power industry to handle electric power industry expansion project data;
Receive corresponding second user input expands the processing result that project data is handled to electric power industry;
The processing result that corresponding second user inputs is summarized, the processing result after summarizing is sent to the first user.
2. electric power industry as described in claim 1 expands project data processing method, which is characterized in that described to receive corresponding second User's input expands the processing result that project data is handled to electric power industry, specifically includes:
Expand project data processing rule according to preset electric power industry, corresponding second user expands at project data electric power industry Reason obtains processing result;
Receive the processing result of corresponding second user input.
3. a kind of electric power industry expands project data processing unit characterized by comprising
Receiving module, the electric power industry for receiving the first user input expand project data, wherein the electric power industry expands project data Expand engineering process data including industry, industry expands engineering Preliminary design document information and industry expands drawing of engineering design;
Preliminary hearing module, the electric power industry for inputting to the first user expand project data and carry out preliminary hearing, comprising: input the first user Electric power industry expand project data and electric power industry and expand project data template and matched, when it fails to match, terminate to the expansion of electric power industry The processing of project data expands project data correlation letter according to the electric power industry of missing or, determining that the electric power industry of missing expands project data Breath, the electric power industry for notifying the first user to input missing expand project data;When successful match, creation electric power industry expands at project data Reason task, it is to expand engineering according to industry expansion engineering process data, industry and tentatively set that the electric power industry, which expands project data processing task, It counts document information and industry expands the different processing tasks of drawing of engineering design creation;
Module is chosen, engineering is expanded to electric power industry for expanding project data processing task selection corresponding second user according to electric power industry Data are handled;
The receiving module is also used to receive the place of corresponding second user input handled electric power industry expansion project data Manage result;
Summarizing module, the processing result for inputting corresponding second user summarize;
Sending module, for the processing result after summarizing to be sent to the first user.
4. electric power industry as claimed in claim 3 expands project data processing unit, which is characterized in that the receiving module is also specific For:
Expand project data processing rule according to preset electric power industry, corresponding second user expands at project data electric power industry Reason obtains processing result;
Receive the processing result of corresponding second user input.
CN201510816561.3A 2015-11-23 2015-11-23 A kind of electric power industry expansion project data processing method and processing device Active CN105488657B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510816561.3A CN105488657B (en) 2015-11-23 2015-11-23 A kind of electric power industry expansion project data processing method and processing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510816561.3A CN105488657B (en) 2015-11-23 2015-11-23 A kind of electric power industry expansion project data processing method and processing device

Publications (2)

Publication Number Publication Date
CN105488657A CN105488657A (en) 2016-04-13
CN105488657B true CN105488657B (en) 2019-08-30

Family

ID=55675626

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510816561.3A Active CN105488657B (en) 2015-11-23 2015-11-23 A kind of electric power industry expansion project data processing method and processing device

Country Status (1)

Country Link
CN (1) CN105488657B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US12125054B2 (en) 2019-09-25 2024-10-22 Valideck International Corporation System, devices, and methods for acquiring and verifying online information

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113408940B (en) * 2021-07-12 2023-06-30 广东电网有限责任公司 Electronic handover management and control system for industrial expansion engineering

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104267291A (en) * 2014-10-10 2015-01-07 长城电器集团乐山宁格朗电气有限责任公司 Remote power monitoring system
CN104715420A (en) * 2013-12-17 2015-06-17 国家电网公司 Method and device for processing electric power engineering data

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013155490A1 (en) * 2012-04-12 2013-10-17 Huawei Technologies Co., Ltd. System and method for quality of experience aware media search and recommendation with unified portal
CN103413190A (en) * 2013-04-30 2013-11-27 长园共创电力安全技术股份有限公司 Real-time auditing system of operation ticket and method
US20150149380A1 (en) * 2013-11-23 2015-05-28 Saagar Sunil Kulkarni Method and System for College Matching
CN103854137A (en) * 2014-03-14 2014-06-11 国家电网公司 Method for evaluating economic and technical indexes of engineering project

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104715420A (en) * 2013-12-17 2015-06-17 国家电网公司 Method and device for processing electric power engineering data
CN104267291A (en) * 2014-10-10 2015-01-07 长城电器集团乐山宁格朗电气有限责任公司 Remote power monitoring system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US12125054B2 (en) 2019-09-25 2024-10-22 Valideck International Corporation System, devices, and methods for acquiring and verifying online information

Also Published As

Publication number Publication date
CN105488657A (en) 2016-04-13

Similar Documents

Publication Publication Date Title
JP5973733B2 (en) System, method and apparatus for accelerating volt / VAR tidal optimization
CN109523225A (en) A kind of measure of managing contract, system and terminal device
CN106403188B (en) Air conditioner maintenance method and maintenance device thereof
CN110910089A (en) Intelligent community work order processing method and device, server and system
CN110969327B (en) Work order dispatching method, device, system and data processing method
CN104270787A (en) Full-automatic closed-loop control method of wireless network work order
CN105184501A (en) Efficient asynchronous order processing method
Shahnaghi et al. A robust modelling and optimisation framework for a batch processing flow shop production system in the presence of uncertainties
CN101211434A (en) Electronic order sign-off system and method
CN105488657B (en) A kind of electric power industry expansion project data processing method and processing device
CN105469319A (en) Data processing management terminal, data processing user terminal and data processing system for electric power service expansion engineering
CN109447656B (en) Enterprise group service method, device and system based on cloud technology and storage medium
WO2024120257A1 (en) Intelligent review and approval service system based on big data archive management
CN105260924A (en) Mobile terminal, order processing method thereof and Internet ticketing system and method
CN102799820B (en) A kind of restoration methods of user cipher
Liu et al. Modelling complex systems for project planning: a semiotics motivated method
CN105373897A (en) Graded examination and approval method and system
CN115130911A (en) Method and device for processing delivery tasks failed to execute by robot
WO2020031228A1 (en) Production scheduling device and production scheduling method
CN105069719A (en) Lawyer mandating system and method based on wireless network
CN115118631A (en) Link exception handling method and device, electronic equipment and storage medium
CN106294058A (en) The target strategy processing problems of operation document determines method and device
Bhardwaj et al. Stochastic model of a cold-stand by system with waiting for Arrival & Treatment of server
CN111898917B (en) Intelligent manufacturing management system based on big data
CN108197179A (en) Facility information querying method and terminal device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant