CN105469844A - Neutron absorbing material assembly for replaceable fuel storage grillwork - Google Patents

Neutron absorbing material assembly for replaceable fuel storage grillwork Download PDF

Info

Publication number
CN105469844A
CN105469844A CN201511017059.2A CN201511017059A CN105469844A CN 105469844 A CN105469844 A CN 105469844A CN 201511017059 A CN201511017059 A CN 201511017059A CN 105469844 A CN105469844 A CN 105469844A
Authority
CN
China
Prior art keywords
material assembly
neutron absorber
absorber material
screen work
changeable type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201511017059.2A
Other languages
Chinese (zh)
Inventor
朱自强
黄然
邵长磊
奚梅英
贺小明
刘建文
李雷
王志勇
高雷
贺湘炼
陶金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Nuclear Engineering Research and Design Institute Co Ltd
Original Assignee
Shanghai Nuclear Engineering Research and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Nuclear Engineering Research and Design Institute Co Ltd filed Critical Shanghai Nuclear Engineering Research and Design Institute Co Ltd
Priority to CN201511017059.2A priority Critical patent/CN105469844A/en
Publication of CN105469844A publication Critical patent/CN105469844A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21CNUCLEAR REACTORS
    • G21C19/00Arrangements for treating, for handling, or for facilitating the handling of, fuel or other materials which are used within the reactor, e.g. within its pressure vessel
    • G21C19/02Details of handling arrangements
    • G21C19/06Magazines for holding fuel elements or control elements
    • G21C19/07Storage racks; Storage pools
    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21CNUCLEAR REACTORS
    • G21C19/00Arrangements for treating, for handling, or for facilitating the handling of, fuel or other materials which are used within the reactor, e.g. within its pressure vessel
    • G21C19/19Reactor parts specifically adapted to facilitate handling, e.g. to facilitate charging or discharging of fuel elements
    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21CNUCLEAR REACTORS
    • G21C7/00Control of nuclear reaction
    • G21C7/06Control of nuclear reaction by application of neutron-absorbing material, i.e. material with absorption cross-section very much in excess of reflection cross-section
    • G21C7/08Control of nuclear reaction by application of neutron-absorbing material, i.e. material with absorption cross-section very much in excess of reflection cross-section by displacement of solid control elements, e.g. control rods
    • G21C7/10Construction of control elements
    • G21C7/11Deformable control elements, e.g. flexible, telescopic, articulated
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Abstract

The invention provides a neutron absorbing material assembly for a replaceable fuel storage grillwork. The neutron absorbing material assembly for the replaceable fuel storage grillwork comprises the replaceable fuel storage grillwork, neutron absorbing material assembly bodies and pressing parts; the replaceable fuel storage grillwork is provided with at least two storage cavities; each neutron absorbing material assembly body is detachably installed between every two adjacent storage cavities and placed on the tops of the adjacent cavity walls of the storage cavities; the pressing parts are used for fixing the neutron absorbing material assembly bodies on the replaceable fuel storage grillwork. According to the neutron absorbing material assembly for the replaceable fuel storage grillwork, the neutron absorbing material assembly bodies are independently installed on a structural body of the fuel storage grillwork and can be replaced.

Description

A kind of changeable type bunkering screen work neutron absorber material assembly
Technical field
The present invention relates to a kind of changeable type bunkering screen work neutron absorber material assembly.
Background technology
Spent fuel storage rack is mainly for the irradiated fuel assembly drawing off reactor core provides storage space, neutron absorber material in bunkering screen work is the key ensureing fuel assembly criticality safety, and fuel assembly can be made under various accident conditions can to meet criticality safety requirement.
The neutron absorber material that the design of existing bunkering screen work adopts mainly comprises aluminum boron composite, boron stainless steel and cadmium plate etc., and main mounting means has: 1) leave the cavity that storage chamber wall and outside stainless steel cladding are welded in; 2) storage chamber is formed as frame structure part; 3) be clipped between two-layer stainless steel square tube, sealed by seal weld.
Although a few class mounting means is safe and reliable above, but all cannot change neutron absorber material, because neutron absorber material must accept the irradiation of many decades and the immersion of boric acid water in Spent Fuel Pool, and face various accident conditions, therefore likely there is the various damages such as burn into swelling, bubbling, distortion, and then affect its neutron absorption capability, cannot ensure that fuel maintains subcritical safety, therefore likely need to change it.And in above-mentioned several screen work neutron absorber material design, screen work can only be scrapped, integral replacing, cost is high, have a big risk.
Summary of the invention
The present invention is directed to the deficiencies in the prior art, propose a kind of changeable type bunkering screen work neutron absorber material assembly.
Changeable type bunkering screen work neutron absorber material assembly comprises:
Changeable type bunkering screen work; Described changeable type bunkering screen work is provided with at least two storage chambers;
Neutron absorber material assembly; Described neutron absorber material assembly is removably mounted between two adjacent storage chambers, and is held on the top of the chamber wall of described storage chamber;
Compacting part; Described compacting part is for being fixed on described changeable type bunkering screen work by described neutron absorber material assembly.
Preferably, described compacting part comprises pressing plate, screw plate and straight pin; Described screw plate is welded on the top of described storage chamber; Described straight pin is arranged on described screw plate; Described pressing plate is arranged on described screw plate by bolt, and can around described screws; Described pressing plate offers 45 degree of deep-slotted chip breakers; Described straight pin can slide along described deep-slotted chip breaker; Described pressing plate, after described screws, is pushed down or unclamps described neutron absorber material assembly.
Preferably, described neutron absorber material assembly comprises neutron absorber plate, interior coaming plate, peripheral board, web joint and triangle orienting lug; Described neutron absorber plate is arranged in the cavity be welded by interior coaming plate and peripheral board; Described inside and outside coaming plate welds with described web joint; Described web joint welds with the triangle orienting lug at top; Described triangle orienting lug can be fixed on described changeable type bunkering screen work by described compacting part pressing.
Preferably, described triangle orienting lug two ends are welded with terminal block block, play lateral Displacement and the effect of structural strengthening.
Compared with prior art, the present invention has following beneficial effect:
1, changeable type bunkering screen work neutron absorber material assembly provided by the invention, neutron absorber material assembly is independently installed on bunkering frame structure body, can change.
2, changeable type bunkering screen work neutron absorber material assembly provided by the invention, is fixed on changeable type bunkering screen work by compacting part by neutron absorber material assembly, easy for installation, safe and reliable.
3, changeable type bunkering screen work neutron absorber material assembly provided by the invention, simultaneously as bunkering screen work targeting port, can be convenient to the charge and discharge operations of fuel assembly.
4, changeable type bunkering screen work neutron absorber material assembly provided by the invention, pressing plate has 45 degree of deep-slotted chip breakers, due to the stop effect of straight pin, makes pressing plate can rotate 45 degree, namely push down or unclamp the triangle orienting lug of neutron absorber material assembly.
Accompanying drawing explanation
Fig. 1 is the front elevation of the changeable type bunkering screen work neutron absorber material assembly meeting the preferred embodiment of the present invention.
The A-A cut-open view that Fig. 2 is structure shown in Fig. 1.
Fig. 3 is the schematic diagram of the compacting part meeting the preferred embodiment of the present invention.
Fig. 4 is the cut-open view of structure shown in Fig. 3.
Fig. 5 is the schematic diagram of the neutron absorber material assembly meeting the preferred embodiment of the present invention.
Fig. 6 is the partial sectional view of structure shown in Fig. 5.
Embodiment
For enabling above-mentioned purpose of the present invention, feature and advantage become apparent more, and below in conjunction with the drawings and specific embodiments, the present invention is further detailed explanation.
As shown in figures 1 to 6, changeable type bunkering screen work neutron absorber material assembly comprises:
Changeable type bunkering screen work 1; Described changeable type bunkering screen work 1 is provided with at least two storage chambers 11;
Neutron absorber material assembly 2; Described neutron absorber material assembly 2 is removably mounted between two adjacent storage chambers 11, and is held on the top of the chamber wall of described storage chamber;
Compacting part 3; Described compacting part 3 is for being fixed on described changeable type bunkering screen work 1 by described neutron absorber material assembly 2.
Preferably, described compacting part 3 comprises pressing plate 31, screw plate 32 and straight pin 33; Described screw plate 32 is welded on the top of described storage chamber 11; Described straight pin 33 is arranged on described screw plate 32; Described pressing plate 31 is arranged on described screw plate 32 by bolt 34, and can rotate around described bolt 34; Described pressing plate 31 offers 45 degree of deep-slotted chip breakers 35; Described straight pin 33 can slide along described deep-slotted chip breaker 35; Described pressing plate 31, after described bolt 34 rotates, is pushed down or unclamps described neutron absorber material assembly 2.
Preferably, described neutron absorber material assembly 2 comprises neutron absorber plate 25, interior coaming plate 24, peripheral board 26, web joint 23 and triangle orienting lug 21; Described neutron absorber plate 25 is arranged in the cavity be welded by interior coaming plate 24 and peripheral board 26; Described inside and outside coaming plate 24 welds with described web joint 23; Described web joint 23 welds with the triangle orienting lug 21 at top; Described triangle orienting lug 21 can be fixed on described changeable type bunkering screen work by described compacting part 3 pressing.
Preferably, described triangle orienting lug 21 two ends are welded with terminal block block 22, play lateral Displacement and the effect of structural strengthening.
Compared with prior art, the present invention has following beneficial effect:
1, changeable type bunkering screen work neutron absorber material assembly provided by the invention, neutron absorber material assembly is independently installed on bunkering frame structure body, can change.
2, changeable type bunkering screen work neutron absorber material assembly provided by the invention, is fixed on changeable type bunkering screen work by compacting part by neutron absorber material assembly, easy for installation, safe and reliable.
3, changeable type bunkering screen work neutron absorber material assembly provided by the invention, simultaneously as bunkering screen work targeting port, can be convenient to the charge and discharge operations of fuel assembly.
4, changeable type bunkering screen work neutron absorber material assembly provided by the invention, pressing plate has 45 degree of deep-slotted chip breakers, due to the stop effect of straight pin, makes pressing plate can rotate 45 degree, namely push down or unclamp the triangle orienting lug of neutron absorber material assembly.
In this instructions, each embodiment adopts the mode of going forward one by one to describe, and what each embodiment stressed is the difference with other embodiments, between each embodiment identical similar portion mutually see.For system disclosed in embodiment, owing to corresponding to the method disclosed in Example, so description is fairly simple, relevant part illustrates see method part.
Those skilled in the art can use distinct methods to realize described function to each specifically should being used for, but this realization should not thought and exceeds scope of the present invention.
Obviously, those skilled in the art can carry out various change and modification to invention and not depart from the spirit and scope of the present invention.Like this, if these amendments of the present invention and modification belong within the scope of the claims in the present invention and equivalent technologies thereof, then the present invention is also intended to comprise these change and modification.

Claims (4)

1. a changeable type bunkering screen work neutron absorber material assembly, is characterized in that, comprising:
Changeable type bunkering screen work; Described changeable type bunkering screen work is provided with at least two storage chambers;
Neutron absorber material assembly; Described neutron absorber material assembly is removably mounted between two adjacent storage chambers, and is held on the top of the chamber wall of described storage chamber;
Compacting part; Described compacting part is for being fixed on described changeable type bunkering screen work by described neutron absorber material assembly.
2. changeable type bunkering screen work neutron absorber material assembly as claimed in claim 1, it is characterized in that, described compacting part comprises pressing plate, screw plate and straight pin; Described screw plate is welded on the top of described storage chamber; Described straight pin is arranged on described screw plate; Described pressing plate is arranged on described screw plate by bolt, and can around described screws; Described pressing plate offers 45 degree of deep-slotted chip breakers; Described straight pin can slide along described deep-slotted chip breaker; Described pressing plate, after described screws, is pushed down or unclamps described neutron absorber material assembly.
3. changeable type bunkering screen work neutron absorber material assembly as claimed in claim 1, it is characterized in that, described neutron absorber material assembly comprises neutron absorber plate, interior coaming plate, peripheral board, web joint and triangle orienting lug; Described neutron absorber plate is arranged in the cavity be welded by interior coaming plate and peripheral board; Described inside and outside coaming plate welds with described web joint; Described web joint welds with the triangle orienting lug at top; Described triangle orienting lug can be fixed on described changeable type bunkering screen work by described compacting part pressing.
4. changeable type bunkering screen work neutron absorber material assembly as claimed in claim 3, it is characterized in that, described triangle orienting lug two ends are welded with terminal block block.
CN201511017059.2A 2015-12-29 2015-12-29 Neutron absorbing material assembly for replaceable fuel storage grillwork Pending CN105469844A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511017059.2A CN105469844A (en) 2015-12-29 2015-12-29 Neutron absorbing material assembly for replaceable fuel storage grillwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511017059.2A CN105469844A (en) 2015-12-29 2015-12-29 Neutron absorbing material assembly for replaceable fuel storage grillwork

Publications (1)

Publication Number Publication Date
CN105469844A true CN105469844A (en) 2016-04-06

Family

ID=55607459

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511017059.2A Pending CN105469844A (en) 2015-12-29 2015-12-29 Neutron absorbing material assembly for replaceable fuel storage grillwork

Country Status (1)

Country Link
CN (1) CN105469844A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107068221A (en) * 2017-02-28 2017-08-18 上海核工程研究设计院 A kind of standby neutron-absorbing component of spent fuel storage rack
CN108735318A (en) * 2018-06-04 2018-11-02 江苏核电有限公司 A kind of the stainless steel boron aluminum composite plate and manufacturing method of PWR fuel assemblies storage lattice cell

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4948553A (en) * 1983-03-01 1990-08-14 Westinghouse Electric Corp. Method of making a rack for the storage of spent nuclear fuel
US5245641A (en) * 1981-12-22 1993-09-14 Westinghouse Electric Corp. Spent fuel storage rack
CN102737741A (en) * 2012-07-12 2012-10-17 中广核工程有限公司 Spent fuel storage framework of nuclear power plant
CN204301712U (en) * 2014-12-29 2015-04-29 中核核电运行管理有限公司 A kind of measurement mechanism storing screen work gap for detecting spentnuclear fuel
CN205334975U (en) * 2015-12-29 2016-06-22 上海核工程研究设计院 Removable formula fuel storage screen work neutron absorbing material subassembly

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5245641A (en) * 1981-12-22 1993-09-14 Westinghouse Electric Corp. Spent fuel storage rack
US4948553A (en) * 1983-03-01 1990-08-14 Westinghouse Electric Corp. Method of making a rack for the storage of spent nuclear fuel
CN102737741A (en) * 2012-07-12 2012-10-17 中广核工程有限公司 Spent fuel storage framework of nuclear power plant
CN204301712U (en) * 2014-12-29 2015-04-29 中核核电运行管理有限公司 A kind of measurement mechanism storing screen work gap for detecting spentnuclear fuel
CN205334975U (en) * 2015-12-29 2016-06-22 上海核工程研究设计院 Removable formula fuel storage screen work neutron absorbing material subassembly

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107068221A (en) * 2017-02-28 2017-08-18 上海核工程研究设计院 A kind of standby neutron-absorbing component of spent fuel storage rack
CN107068221B (en) * 2017-02-28 2024-04-09 上海核工程研究设计院股份有限公司 Neutron absorption assembly for spent fuel storage grillwork
CN108735318A (en) * 2018-06-04 2018-11-02 江苏核电有限公司 A kind of the stainless steel boron aluminum composite plate and manufacturing method of PWR fuel assemblies storage lattice cell
CN108735318B (en) * 2018-06-04 2024-02-09 江苏核电有限公司 Stainless steel boron aluminum composite board for PWR fuel assembly storage cell and manufacturing method

Similar Documents

Publication Publication Date Title
CN210798987U (en) Prefabricated reinforced concrete segment
CN105469844A (en) Neutron absorbing material assembly for replaceable fuel storage grillwork
CN205334975U (en) Removable formula fuel storage screen work neutron absorbing material subassembly
CN211915944U (en) Automobile panel welding tool clamp
CN209989942U (en) Building steel structure combination beam convenient to equipment
CN201711728U (en) Welding mold used in processing of high-accuracy square zirconium alloy element box
CN202031342U (en) Edge protective railing
CN208507210U (en) A kind of PWR irradiated fuel assembly storage lattice cell
CN103557008B (en) The erosion control supporting and protection structure of walled metallic structure and the coupling of tunnel anchoring country rock
CN203245555U (en) Fixing device for transposition build-up welding of vapor generator tube plate on position changing machine
CN108735317B (en) PWR spent fuel assembly storage cell and manufacturing method
CN202307174U (en) Detachable movable fuel basket
CN208400510U (en) A kind of VVER irradiated fuel assembly storage lattice cell
CN210254876U (en) Assembly welding tool for engineering machinery crawler longitudinal beam
CN216370897U (en) A mould for being up to safe cage steel pipe
CN204845948U (en) Tubular metal resonator - honeycomb core combined type anticreeper that honeycomb in -core was put
CN214941008U (en) Lateral force resistant light steel structure member
CN212719012U (en) Building engineering environment monitoring device
CN214091001U (en) Strutting arrangement for housing construction
CN210529957U (en) Assembly type building node connection structure
CN209880170U (en) Nuclear reactor grid supporting plate device convenient to assemble
CN105405482A (en) Fuel storage grid with replaceable neutron absorption materials
CN207587395U (en) PWR nuclear power plant bilayer curved plate concrete structure module forming frock
CN112482653B (en) Composite refractory material wall prefabricated part
CN203329438U (en) Container-type oil cylinder seat of filter press

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160406