CN105466034B - The control method and device of the water tank of Teat pump boiler - Google Patents

The control method and device of the water tank of Teat pump boiler Download PDF

Info

Publication number
CN105466034B
CN105466034B CN201510996759.4A CN201510996759A CN105466034B CN 105466034 B CN105466034 B CN 105466034B CN 201510996759 A CN201510996759 A CN 201510996759A CN 105466034 B CN105466034 B CN 105466034B
Authority
CN
China
Prior art keywords
water
temperature
water tank
control
pump boiler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510996759.4A
Other languages
Chinese (zh)
Other versions
CN105466034A (en
Inventor
安建克
林海佳
赵鹏
黄昌成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gree Electric Appliances Inc of Zhuhai
Original Assignee
Gree Electric Appliances Inc of Zhuhai
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gree Electric Appliances Inc of Zhuhai filed Critical Gree Electric Appliances Inc of Zhuhai
Priority to CN201510996759.4A priority Critical patent/CN105466034B/en
Publication of CN105466034A publication Critical patent/CN105466034A/en
Application granted granted Critical
Publication of CN105466034B publication Critical patent/CN105466034B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24HFLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
    • F24H9/00Details
    • F24H9/20Arrangement or mounting of control or safety devices
    • F24H9/2007Arrangement or mounting of control or safety devices for water heaters

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Heat-Pump Type And Storage Water Heaters (AREA)

Abstract

The invention discloses a kind of control method and device of the water tank of Teat pump boiler.Wherein, this method comprises: receiving being instructed with water for user;In the case where being high temperature water with water instruction, the first water tank of control is connected to third water tank, and closes the second water tank;In the case where being medium temperature water with water instruction, the first water tank of control is connected to the second water tank, and closes third water tank.The technical issues of tank function that the present invention solves existing Teat pump boiler is simple, and thermal water resource is caused to waste.

Description

The control method and device of the water tank of Teat pump boiler
Technical field
The present invention relates to control fields, in particular to a kind of control method and device of the water tank of Teat pump boiler.
Background technique
The demand used with user's heat water increasingly improves, and various direct-heating-type heat pumps occur in succession, uses user in time Water becomes simple and easy, and common direct-heating-type heat pump has: carbon dioxide direct-heating-type air source heat pump, R32 direct-heating-type air-source heat Pump etc..Direct-heating-type heat pump has the features such as plug and play, high-efficient, complies fully with property and the uncertainty at any time of hot water for life, But if to fully meet the requirement of user's larger hot water usage amount once in a while, alleviate water consumption peak using heat accumulation type water tank Heat pump capacity pressure be necessary, and accord with the demands of the market.
It should be noted that the heat storage water tank function of existing Teat pump boiler is simpler, often single function water tank can be taken High-temperature water does low temperature use, greatly waste occurs, moreover, single function water tank will cause heat pump frequent start-stop and control it is complicated The problems such as.
For the problem that the tank function of above-mentioned existing Teat pump boiler is simple, thermal water resource is caused to waste, at present still It does not put forward effective solutions.
Summary of the invention
The embodiment of the invention provides a kind of control method and device of the water tank of Teat pump boiler, existing at least to solve Teat pump boiler tank function it is simple, the technical issues of causing thermal water resource to waste.
According to an aspect of an embodiment of the present invention, a kind of control method of the water tank of Teat pump boiler is provided, comprising: Receive being instructed with water for user;In the case where being high temperature water with water instruction, the first water tank of control is connected to third water tank, and Close the second water tank;In the case where being medium temperature water with water instruction, the first water tank of control is connected to the second water tank, and closing the Three-tank.
According to another aspect of an embodiment of the present invention, a kind of control device of the water tank of Teat pump boiler is additionally provided, is wrapped It includes: receiving unit, for receiving being instructed with water for user;First control unit, for being the feelings of high temperature water with water instruction Under condition, the first water tank of control is connected to third water tank, and closes the second water tank;Second control unit, for being with water instruction In the case where medium temperature water, the first water tank of control is connected to the second water tank, and closes third water tank.
In embodiments of the present invention, being instructed with water using reception user;In the case where being high temperature water with water instruction, It controls the first water tank to be connected to third water tank, and closes the second water tank;In the case where being medium temperature water with water instruction, control the One water tank is connected to the second water tank, and closes third water tank, and the tank function for solving existing Teat pump boiler is simple, is caused The technical issues of thermal water resource wastes.
Detailed description of the invention
The drawings described herein are used to provide a further understanding of the present invention, constitutes part of this application, this hair Bright illustrative embodiments and their description are used to explain the present invention, and are not constituted improper limitations of the present invention.In the accompanying drawings:
Fig. 1 is a kind of flow chart of the control method of the water tank of Teat pump boiler according to an embodiment of the present invention;
Fig. 2 is a kind of schematic diagram of the control method of the water tank of Teat pump boiler according to an embodiment of the present invention;And
Fig. 3 is a kind of schematic diagram of the control device of the water tank of Teat pump boiler according to an embodiment of the present invention.
Specific embodiment
In order to enable those skilled in the art to better understand the solution of the present invention, below in conjunction in the embodiment of the present invention Attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is only The embodiment of a part of the invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill people The model that the present invention protects all should belong in member's every other embodiment obtained without making creative work It encloses.
It should be noted that description and claims of this specification and term " first " in above-mentioned attached drawing, " Two " etc. be to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that using in this way Data be interchangeable under appropriate circumstances, so as to the embodiment of the present invention described herein can in addition to illustrating herein or Sequence other than those of description is implemented.In addition, term " includes " and " having " and their any deformation, it is intended that cover Cover it is non-exclusive include, for example, the process, method, system, product or equipment for containing a series of steps or units are not necessarily limited to Step or unit those of is clearly listed, but may include be not clearly listed or for these process, methods, product Or other step or units that equipment is intrinsic.
Embodiment 1
According to embodiments of the present invention, a kind of embodiment of the control method of the water tank of Teat pump boiler is provided, is needed Bright, step shown in the flowchart of the accompanying drawings can be held in a computer system such as a set of computer executable instructions Row, although also, logical order is shown in flow charts, and it in some cases, can be to be different from sequence herein Execute shown or described step.
Teat pump boiler in the present embodiment can include at least: the first water tank, the second water tank and third water tank, and first Water temperature in water tank, the second water tank and third water tank sorts from high to low, such as Fig. 1, the controlling party of the water tank of Teat pump boiler Method may include:
Step S12 receives being instructed with water for user.
Specifically, in the present solution, user can be high temperature water and medium temperature water with water instruction.
For example, high temperature can be sent to Teat pump boiler in the case where user needs with high-temperature water (such as bathing) and used Water instruction can be to Teat pump boiler in the case where user needs warm water in use (warm water heats to radiator in use) Warm water in transmission.
Step S14, in the case where being high temperature water with water instruction, the first water tank of control is connected to third water tank, and is closed Close the second water tank.
Step S16, in the case where being medium temperature water with water instruction, the first water tank of control is connected to the second water tank, and is closed Close third water tank.
Specifically, in above-mentioned steps S14 into step S16, the first water tank can be for for storing (such as 60 DEG C of high-temperature water More than) high-temperature water tank, above-mentioned second water tank can be middle warm water for warm water in storing (such as 40 DEG C to 60 ° or more) Case, above-mentioned third water tank can be the low temperature water tank for storing water at low temperature (such as 40 DEG C or less).As shown in Fig. 2, three not Synthermal water tank can be divided into three layers, respectively heat zone, medium temperature layer and cryosphere, with two A1, A2 threeways between three layers Reversal valve connection, this programme can be according to user's water needs, and determine two triple valves opens mode.Specific control mode can With are as follows: A1 is closed when user only uses high-temperature water, and A2 is opened, and is connected to heat zone with cryosphere, separates medium temperature layer;When with Family only use in warm water when, A1 open, A2 close, be connected to heat zone with medium temperature layer, partition cryosphere, need to illustrate It is that if user does not have particular/special requirement, A1 is opened, and A2 is also opened, and heat zone, medium temperature layer, cryosphere form series connection.
The present embodiment is by receiving being instructed with water for user;In the case where being high temperature water with water instruction, control first Water tank is connected to third water tank, and closes the second water tank;With water instruction be medium temperature water in the case where, control the first water tank with The connection of second water tank, and third water tank is closed, it is easily noted that, this programme can need to adjust three layers of water for the difference of user The connected state of case, can on the water demand for meet user to greatest extent energy conservation, therefore this programme solve it is existing The technical issues of tank function of Teat pump boiler is simple, and thermal water resource is caused to waste.
Optionally, step S12, after receiving being instructed with water of user, method provided in this embodiment can also include:
Step S18 acquires the temperature parameter set of pump water heater, wherein temperature parameter set includes at least: user's setting Water temperature t1, the temperature t2 of the second water outlet of water tank, temperature t3 in the first water tank, temperature t4 in the second water tank.
Specifically, in conjunction with Fig. 2, this programme can acquire user's set water temperature t1 using thermometer B1, using thermometer B2 The leaving water temperature t2 (supply water temperature of the medium temperature water tank to radiator) for acquiring medium temperature water tank acquires high-temperature water tank using thermometer B3 Interior temperature (water temperature inside high-temperature water tank), using thermometer B4 acquisition medium temperature water tank inside water temperature t4.
Step S20 controls the operating status of Teat pump boiler according to temperature parameter set.
Specifically, this programme can be according to above-mentioned user's set water temperature t1, the temperature t2 of the second water outlet of water tank, the first water Temperature t3 in case, temperature t4 controls the operating statuses of Teat pump boiler all parts in the second water tank, for example, the switching on and shutting down of special pump, The switching on and shutting down of electric heater unit, the open and close of water pump and opening size of water mixing valve etc..
Optionally, step S20 can wrap according to the step of operating status of temperature parameter set control Teat pump boiler It includes:
Step S201, in user's set water temperature t1 less than the feelings that the water mixing valve of the first preset temperature, Teat pump boiler is closed Under condition, Teat pump boiler is opened in control.
Specifically, this programme can judge the parameters in temperature parameter set, if thermometer B1 is surveyed User's set water temperature t1 less than the first preset temperature (such as high temperature water temperature ta0 of user demand), and water mixing valve is closed (i.e. The mixed volume of tap water at normal temperature is that 0), this programme controls Teat pump boiler and opens.
Step S202 is less than in the temperature t2 of the second water outlet of water tank less than temperature t3 in the second preset temperature, the first water tank In second water tank in the case where the difference of temperature t4 and third preset temperature, Teat pump boiler is opened in control.
Specifically, if the outlet temperature t2 for the medium temperature water tank that thermometer B2 is surveyed less than the second preset temperature (such as Middle warm water water temperature ta1 needed for user and △ t1's and, △ t1 is the optimal temperature difference set according to fitting experimental data), moreover, warm The interior temperature t3 of high-temperature water tank that degree meter B3 is surveyed is less than the t4 that thermometer B4 is surveyed and third preset temperature (such as t4 and △ t2 Difference, △ t2 are the optimal temperature difference set according to fitting experimental data) difference in the case where, this programme control open Heat Pump Hydrophone.
Step S203, in the case that temperature t3 is greater than the 4th preset temperature t in the first water tank, heat-pump hot-water is closed in control Device.
Specifically, in the present solution, if the temperature t3 that measures of B3 is that (such as fortune is stablized in heat pump booting to the 4th preset temperature Leaving water temperature when row) in the case where, control Teat pump boiler shutdown.
It should be noted that the execution sequence of above-mentioned steps S201 to step S203 can carry out simultaneously, it can also be successive It carries out.
Optionally, in the present solution, Teat pump boiler can also include: electric heater unit, wherein opened in Teat pump boiler After opening, method provided in this embodiment further include:
Step S204, user's set water temperature t1 less than the first preset temperature ta0, Teat pump boiler water mixing valve close, In the case that the runing time of the compressor of Teat pump boiler is greater than the predetermined time, electric heater unit is opened in control.
Specifically, in the present solution, if B1 measured temperature t1 is less than user demand high-temperature water water temperature ta0, and water mixing valve A4 is closed, i.e. tap water at normal temperature mixed volume V=0, and the runing time of the compressor of Teat pump boiler is greater than the predetermined time In the case of, electric heater unit is opened in this programme control.
Step S205, in compression of the temperature t2 of the second water outlet of water tank less than the 5th preset temperature ta1, Teat pump boiler In the case that machine is greater than the predetermined time, electric heater unit is opened in control.
Specifically, in the present solution, if B2 measured temperature t2 is less than the 5th preset temperature (such as middle warm water needed for user Water temperature ta1), and the runing time of the compressor of Teat pump boiler, greater than in the case where the predetermined time, this programme control is opened Electric heater unit.
Step S206, temperature t3 is greater than the 4th preset temperature t in the first water tank, the compressor of Teat pump boiler is greater than first In the case where scheduled duration, electric heater unit is closed in control.
Specifically, in the present solution, if when the collected temperature t3 of B3 be greater than heat pump booting stable operation when water outlet Temperature, and the compressor of Teat pump boiler, greater than in the case where the first scheduled duration, electric heater unit is closed in this programme control.
It should be noted that the execution sequence of above-mentioned steps S204 to step S206 can carry out simultaneously, it can also be successive It carries out.
Optionally, Teat pump boiler further include: water pump, wherein provided in this embodiment after Teat pump boiler unlatching Method further include:
Step S207 is closed in user's set water temperature t1 less than the water mixing valve of the first preset temperature ta0, Teat pump boiler In the case of, the water pump of Teat pump boiler is opened in control.
Step S208, in the case where the temperature t2 of the second water outlet of water tank is less than the 5th preset temperature ta1, control is opened The water pump of Teat pump boiler.
Step S209 receives the instruction of cutting off the water of user, in the case that Teat pump boiler runs the second scheduled duration, control Close the water pump of Teat pump boiler.
Specifically, in above-mentioned steps S207 into step S209, when meeting one of the following conditions, then the water in Fig. 2 is opened Pump D1: condition 1:B1 measured temperature t1 is less than user demand high-temperature water water temperature ta0, and water mixing valve A4 is closed, i.e. tap water at normal temperature Mixed volume V=0.Middle warm water water temperature ta1, that is, above-mentioned 5th preset temperature needed for condition 2:B2 measured temperature t2 is less than user.It needs Illustrate, client stop claim to hot water, and heat pump the time out of service be greater than the second scheduled duration in the case where, This programme control switches off the pump.
It should also be noted that, this programme then opens the water circulating pump D2 in Fig. 2 when client's centering warm water claims, It claims when client stops centering warm water water, this programme then closes the water circulating pump D2 in Fig. 2.
It should be noted that the execution sequence of above-mentioned steps S207 to step S209 can be it is also possible to be successive.
Optionally, after Teat pump boiler unlatching, method provided in this embodiment can also include:
Step S210 controls the mixed of Teat pump boiler in the case where user's set water temperature t1 is less than the first preset temperature The aperture of water valve is the first aperture.
Step S211, in the case where user's set water temperature t1 is greater than the sum of the first preset temperature and third preset temperature, The aperture for controlling the water mixing valve of Teat pump boiler is the second aperture.
Step S212 controls the mixed of Teat pump boiler in the case where user's set water temperature t1 is greater than six preset temperatures The aperture of water valve is third aperture.
Specifically, in above-mentioned steps S210 into step S212, this programme can with it is T1 seconds every (T1 be set according to experimental fit Fixed gained optimal values) primary above-mentioned temperature parameter set is detected, B1 measured temperature t1 is less than user demand high-temperature water water temperature When ta0, the aperture of 2 step of water mixing valve is closed, when B1 measured temperature t1 is greater than user demand high-temperature water water temperature ta0 and △ t2 (△ t2 According to experimental fit set gained optimal values) the sum of when, open 2 steps, when B1 measured temperature t1 be greater than the 6th preset temperature (user The sum of demand high-temperature water water temperature ta0 and 5 DEG C) when, open 10 steps.
It to sum up, in the present embodiment, can firstly, the heat zone of water tank, medium temperature layer and cryosphere pass through three-way diverter valve To realize that different form combines, high-temperature water can be prevented to be used as requirement of low temperature, cause to waste.Then, can be led to by this programme User demand can be met with the heat pump of small ability, reduce user's initial cost cost, and have very to the randomness of user demand Good adaptability avoids the frequent start-stop of heat pump, improves heat pump service life.Finally, the present embodiment is tested using user's water temperature It is tested with water tank each section water temperature, controls each three-way diverter valve, the closing of the components such as water pump and heat pump, control method is simple, It is easily achieved, and precision is high, control is with clearly defined objective, can save control cost.
Embodiment 2
This implementation can also provide a kind of control device of the water tank of Teat pump boiler, it should be noted that Teat pump boiler It includes at least: the first water tank, the second water tank and third water tank, the water temperature in the first water tank, the second water tank and third water tank It sorts from high to low, as shown in figure 3, the apparatus may include: receiving unit 30, for receiving being instructed with water for user;First Control unit 32, in the case where being high temperature water with water instruction, the first water tank of control to be connected to third water tank, and is closed Second water tank;Second control unit 34, for controlling the first water tank and the second water in the case where being medium temperature water with water instruction Case connection, and close third water tank.
The present embodiment is by receiving being instructed with water for user;In the case where being high temperature water with water instruction, control first Water tank is connected to third water tank, and closes the second water tank;With water instruction be medium temperature water in the case where, control the first water tank with The connection of second water tank, and third water tank is closed, it is easily noted that, this programme can need to adjust three layers of water for the difference of user The connected state of case, can on the water demand for meet user to greatest extent energy conservation, therefore this programme solve it is existing The technical issues of tank function of Teat pump boiler is simple, and thermal water resource is caused to waste.
Optionally, which can also include: acquisition unit, for acquiring the temperature parameter set of pump water heater, wherein Temperature parameter set includes at least: user's set water temperature t1, the temperature t2 of the second water outlet of water tank, in the first water tank temperature t3 and Temperature t4 in second water tank;Third control unit, for controlling the operating status of Teat pump boiler according to temperature parameter set.
Optionally, third control unit may include: the first control module, be used in user's set water temperature t1 less than first Preset temperature, Teat pump boiler water mixing valve close in the case where, control open Teat pump boiler;Second control module, The temperature t2 of two water outlet of water tank is pre- less than temperature t4 and third in the second water tank less than temperature t3 in the second preset temperature, the first water tank If in the case where the difference of temperature, Teat pump boiler is opened in control;Third control module, temperature t3 is greater than the 4th in the first water tank In the case where preset temperature, Teat pump boiler is closed in control.
Optionally, which can also include: the 4th control unit, in user's set water temperature t1 less than the first default temperature Degree, Teat pump boiler water mixing valve close, the case where runing time of the compressor of Teat pump boiler is greater than the first scheduled duration Under, electric heater unit is opened in control;5th control unit, the second water outlet of water tank temperature t2 less than the 5th preset temperature, In the case that the runing time of the compressor of Teat pump boiler is greater than the first scheduled duration, electric heater unit is opened in control;6th Control unit, temperature t3 is greater than the 4th preset temperature t in the first water tank, the runing time of compressor of Teat pump boiler is greater than the In the case where one scheduled duration, electric heater unit is closed in control.
Optionally, which can also include: the 7th control unit, in user's set water temperature t1 less than the first default temperature It spends, in the case where the closing of the water mixing valve of Teat pump boiler, water pump is opened in control;8th control unit, in the second water outlet of water tank Temperature t2 less than the 5th preset temperature in the case where, control open water pump;9th control unit receives the finger of cutting off the water of user It enables, in the case where Teat pump boiler the second scheduled duration of operation, control switches off the pump.
Optionally, which can also include: the tenth control unit, in user's set water temperature t1 less than the first preset temperature In the case where, the aperture for controlling the water mixing valve of Teat pump boiler is the first aperture;11st control unit, in user's set water temperature In the case that t1 is greater than the sum of the first preset temperature and third preset temperature, controlling the aperture of the water mixing valve of Teat pump boiler is the Two apertures;12nd control unit controls Teat pump boiler in the case where user's set water temperature t1 is greater than six preset temperatures Water mixing valve aperture be third aperture.
The serial number of the above embodiments of the invention is only for description, does not represent the advantages or disadvantages of the embodiments.
In the above embodiment of the invention, it all emphasizes particularly on different fields to the description of each embodiment, does not have in some embodiment The part of detailed description, reference can be made to the related descriptions of other embodiments.
In several embodiments provided herein, it should be understood that disclosed technology contents can pass through others Mode is realized.Wherein, the apparatus embodiments described above are merely exemplary, such as the division of the unit, Ke Yiwei A kind of logical function partition, there may be another division manner in actual implementation, for example, multiple units or components can combine or Person is desirably integrated into another system, or some features can be ignored or not executed.Another point, shown or discussed is mutual Between coupling, direct-coupling or communication connection can be through some interfaces, the INDIRECT COUPLING or communication link of unit or module It connects, can be electrical or other forms.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple On unit.It can some or all of the units may be selected to achieve the purpose of the solution of this embodiment according to the actual needs.
It, can also be in addition, the functional units in various embodiments of the present invention may be integrated into one processing unit It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list Member both can take the form of hardware realization, can also realize in the form of software functional units.
If the integrated unit is realized in the form of SFU software functional unit and sells or use as independent product When, it can store in a computer readable storage medium.Based on this understanding, technical solution of the present invention is substantially The all or part of the part that contributes to existing technology or the technical solution can be in the form of software products in other words It embodies, which is stored in a storage medium, including some instructions are used so that a computer Equipment (can for personal computer, server or network equipment etc.) execute each embodiment the method for the present invention whole or Part steps.And storage medium above-mentioned includes: that USB flash disk, read-only memory (ROM, Read-Only Memory), arbitrary access are deposited Reservoir (RAM, Random Access Memory), mobile hard disk, magnetic or disk etc. be various to can store program code Medium.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (12)

1. a kind of control method of the water tank of Teat pump boiler, which is characterized in that the Teat pump boiler includes at least: the first water Case, the second water tank and third water tank, the water temperature in first water tank, the second water tank and third water tank are arranged from high to low Sequence, wherein the described method includes:
Receive being instructed with water for user;
It is described with water instruction be high temperature water in the case where, control first water tank and be connected to the third water tank, and close Close second water tank;
It is described with water instruction be medium temperature water in the case where, control first water tank and be connected to second water tank, and close The third water tank is closed,
Wherein, water is adjusted by the heat exchanger tube being placed in first water tank, second water tank and the third water tank Temperature;
Wherein, the high temperature water is the water of heat exchanger tube in first water tank and second water tank;The medium temperature is with water The water of heat exchanger tube in second water tank.
2. the method according to claim 1, wherein the method is also after receiving being instructed with water of user Include:
Acquire the temperature parameter set of the Teat pump boiler, wherein the temperature parameter set includes at least: the user sets Determine water temperature t1, the temperature t2 of second water outlet of water tank, temperature t4 in temperature t3 and second water tank in first water tank;
The operating status of the Teat pump boiler is controlled according to the temperature parameter set.
3. according to the method described in claim 2, it is characterized in that, controlling the heat-pump hot-water according to the temperature parameter set The step of operating status of device includes:
The case where user's set water temperature t1 is closed less than the water mixing valve of the first preset temperature and the Teat pump boiler Under, the Teat pump boiler is opened in control;Or
It is less than in the temperature t2 of second water outlet of water tank less than temperature t3 in the second preset temperature and first water tank described In second water tank in the case where the difference of temperature t4 and third preset temperature, the Teat pump boiler is opened in control;Or
In the case that temperature t3 is greater than four preset temperatures in first water tank, the Teat pump boiler is closed in control.
4. according to the method described in claim 3, it is characterized in that, the Teat pump boiler further include: electric heater unit, In, after Teat pump boiler unlatching, the method also includes:
User's set water temperature t1 be less than first preset temperature, the Teat pump boiler water mixing valve close and it is described In the case that the runing time of the compressor of Teat pump boiler is greater than the first scheduled duration, the electric heater unit is opened in control; Or
Second water outlet of water tank temperature t2 less than the 5th preset temperature and the compressor of the Teat pump boiler fortune In the case that the row time is greater than first scheduled duration, the electric heater unit is opened in control;Or
When temperature t3 is greater than the 4th preset temperature and the operation of the compressor of the Teat pump boiler in first water tank Between be greater than first scheduled duration in the case where, the electric heater unit is closed in control.
5. according to the method described in claim 3, it is characterized in that, the Teat pump boiler further include: water pump, wherein in institute After stating Teat pump boiler unlatching, the method also includes:
It is less than the feelings of the water mixing valve closing of first preset temperature and the Teat pump boiler in user's set water temperature t1 Under condition, the water pump is opened in control;Or
In the case where the temperature t2 of second water outlet of water tank is less than five preset temperatures, and controls and open the water pump; Or
In the case where cut off the water instruction and the Teat pump boiler the second scheduled duration of operation that receive user, institute is closed in control State water pump.
6. according to the method described in claim 3, it is characterized in that, the method is also after Teat pump boiler unlatching Include:
In the case where user's set water temperature t1 is less than first preset temperature, the mixed water of the Teat pump boiler is controlled The aperture of valve is the first aperture;
In the case where user's set water temperature t1 is greater than the sum of first preset temperature and the third preset temperature, control The aperture for making the water mixing valve of the Teat pump boiler is the second aperture;
In the case where user's set water temperature t1 is greater than six preset temperatures, the water mixing valve of the Teat pump boiler is controlled Aperture is third aperture.
7. a kind of control device of the water tank of Teat pump boiler, which is characterized in that the Teat pump boiler includes at least: the first water Case, the second water tank and third water tank, the water temperature in first water tank, the second water tank and third water tank are arranged from high to low Sequence, wherein described device includes:
Receiving unit, for receiving being instructed with water for user;
First control unit, for it is described with water instruction be high temperature water in the case where, control first water tank with it is described The connection of third water tank, and close second water tank;
Second control unit, for it is described with water instruction be medium temperature water in the case where, control first water tank with it is described The connection of second water tank, and close the third water tank, wherein by being placed in first water tank, second water tank and institute The heat exchanger tube in third water tank is stated to adjust water temperature;
Wherein, the high temperature water is the water of heat exchanger tube in first water tank and second water tank;The medium temperature is with water The water of heat exchanger tube in second water tank.
8. device according to claim 7, which is characterized in that described device further include:
Acquisition unit, for acquiring the temperature parameter set of the Teat pump boiler, wherein the temperature parameter set is at least wrapped It includes: user's set water temperature t1, the temperature t2 of second water outlet of water tank, temperature t3 and described in first water tank Temperature t4 in two water tanks;
Third control unit, for controlling the operating status of the Teat pump boiler according to the temperature parameter set.
9. device according to claim 8, which is characterized in that the third control unit includes:
First control module, in user's set water temperature t1 less than the first preset temperature and the Teat pump boiler In the case that water mixing valve is closed, the Teat pump boiler is opened in control;
Second control module, second water outlet of water tank temperature t2 less than the second preset temperature and first water tank Interior temperature t3 is less than in second water tank in the case where the difference of temperature t4 and third preset temperature, and the heat-pump hot-water is opened in control Device;
Third control module, in the case that temperature t3 is greater than four preset temperatures in first water tank, the heat is closed in control Pump water heater.
10. device according to claim 9, which is characterized in that described device further include:
4th control unit, user's set water temperature t1 be less than first preset temperature, the Teat pump boiler it is mixed In the case that water valve is closed and the runing time of the compressor of the Teat pump boiler is greater than the first scheduled duration, electricity is opened in control Heating device;
5th control unit, second water outlet of water tank temperature t2 less than the 5th preset temperature and the heat-pump hot-water In the case that the runing time of the compressor of device is greater than first scheduled duration, the electric heater unit is opened in control;
6th control unit, temperature t3 is greater than the 4th preset temperature and the Teat pump boiler in first water tank In the case that the runing time of compressor is greater than first scheduled duration, the electric heater unit is closed in control.
11. device according to claim 9, which is characterized in that described device further include:
7th control unit is less than first preset temperature and the Teat pump boiler in user's set water temperature t1 In the case that water mixing valve is closed, water pump is opened in control;
8th control unit, in the case where the temperature t2 of second water outlet of water tank is less than five preset temperatures, control is opened Open the water pump;
9th control unit, receive user cut off the water instruction and the Teat pump boiler run the second scheduled duration the case where Under, the water pump is closed in control.
12. device according to claim 9, which is characterized in that described device further include:
Tenth control unit controls the heat in the case where user's set water temperature t1 is less than first preset temperature The aperture of the water mixing valve of pump water heater is the first aperture;
11st control unit is greater than first preset temperature and the third preset temperature in user's set water temperature t1 The sum of in the case where, control the water mixing valve of the Teat pump boiler aperture be the second aperture;
12nd control unit controls the heat pump in the case where user's set water temperature t1 is greater than six preset temperatures The aperture of the water mixing valve of water heater is third aperture.
CN201510996759.4A 2015-12-24 2015-12-24 The control method and device of the water tank of Teat pump boiler Active CN105466034B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510996759.4A CN105466034B (en) 2015-12-24 2015-12-24 The control method and device of the water tank of Teat pump boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510996759.4A CN105466034B (en) 2015-12-24 2015-12-24 The control method and device of the water tank of Teat pump boiler

Publications (2)

Publication Number Publication Date
CN105466034A CN105466034A (en) 2016-04-06
CN105466034B true CN105466034B (en) 2019-04-26

Family

ID=55604009

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510996759.4A Active CN105466034B (en) 2015-12-24 2015-12-24 The control method and device of the water tank of Teat pump boiler

Country Status (1)

Country Link
CN (1) CN105466034B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106016438B (en) * 2016-05-24 2020-01-03 江苏理想空间装饰工程股份有限公司 Household water system with separate control
CN111609552A (en) * 2020-04-23 2020-09-01 青岛海尔空调电子有限公司 Hot water unit
CN111609561B (en) * 2020-04-23 2022-10-28 青岛海尔空调电子有限公司 Control method of hot water unit

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102084190A (en) * 2009-04-21 2011-06-01 松下电器产业株式会社 Hot water storage-type hot water supply device, hot water supply and heating device, operation control device, operation control method, and program
CN104792066A (en) * 2015-04-24 2015-07-22 广东美的暖通设备有限公司 Transcritical CO2 heat pump multifunctional system and control method
CN204494793U (en) * 2015-02-05 2015-07-22 浙江正理生能科技有限公司 A kind of air energy running gear and automation air energy operational system
CN104819569A (en) * 2015-05-12 2015-08-05 广东今泉节能设备有限公司 Air source heat pump heating type water heater device
CN104879925A (en) * 2015-06-10 2015-09-02 江苏天舒电器有限公司 Control device for direct-heating heat pump water heater and control method of control device

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014142112A (en) * 2013-01-23 2014-08-07 Mitsubishi Electric Corp Hot water storage type water heater
JP2015092125A (en) * 2013-11-08 2015-05-14 サンデン株式会社 Storage water heater

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102084190A (en) * 2009-04-21 2011-06-01 松下电器产业株式会社 Hot water storage-type hot water supply device, hot water supply and heating device, operation control device, operation control method, and program
CN204494793U (en) * 2015-02-05 2015-07-22 浙江正理生能科技有限公司 A kind of air energy running gear and automation air energy operational system
CN104792066A (en) * 2015-04-24 2015-07-22 广东美的暖通设备有限公司 Transcritical CO2 heat pump multifunctional system and control method
CN104819569A (en) * 2015-05-12 2015-08-05 广东今泉节能设备有限公司 Air source heat pump heating type water heater device
CN104879925A (en) * 2015-06-10 2015-09-02 江苏天舒电器有限公司 Control device for direct-heating heat pump water heater and control method of control device

Also Published As

Publication number Publication date
CN105466034A (en) 2016-04-06

Similar Documents

Publication Publication Date Title
CN105466034B (en) The control method and device of the water tank of Teat pump boiler
CN105004063B (en) The method, apparatus and hot water machine of moisturizing control
US9405304B2 (en) Water heater and method of operating a water heater
CN108006988B (en) Water heater control method, device and computer readable storage medium
CN104633925A (en) Heat pump hot water machine system and control method thereof
CN104596117B (en) Zero cold water control method and device of gas heater
CN104422137A (en) Water heater appointment heating control method and system
CN108988467B (en) Power utilization strategy generation method and device
CN105299905B (en) The control method of air source water heater and air source water heater, control device
CN104019557B (en) Teat pump boiler and its method for heating and controlling and device
CN104110836A (en) Water heater and control method thereof
CN114183928A (en) Water heater, control method of water heater and related equipment
CN108332382A (en) Air conditioning control method and device, system, storage medium and processor
US9896347B2 (en) Dynamic fluid pasteurization
CN105423570B (en) Heating equipment control method and device
CN109520761A (en) Detect the method and device of inlet and outlet state
CN207815563U (en) Air-conditioner control system and controller
CN203949356U (en) Water heater
CN113654141B (en) Method and device for controlling electrochemical refrigeration system and electrochemical refrigeration system
CN110274360A (en) A kind of air conditioning control method, device, storage medium and air-conditioning
CN106765564B (en) Control method for electronic expansion valve, device and the air-conditioner set with the device in parallel
CN205261940U (en) Control system and heat pump water heater of heat pump water heater's water tank
CN109990477A (en) Electric heater and its control method, system and server
CN113339994A (en) Gas water heater, control method and control device thereof
CN112747441A (en) Method and device for controlling intelligent humidifier and intelligent humidifier

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant