CN105425694B - A kind of construction water intelligent central control system - Google Patents

A kind of construction water intelligent central control system Download PDF

Info

Publication number
CN105425694B
CN105425694B CN201510731762.3A CN201510731762A CN105425694B CN 105425694 B CN105425694 B CN 105425694B CN 201510731762 A CN201510731762 A CN 201510731762A CN 105425694 B CN105425694 B CN 105425694B
Authority
CN
China
Prior art keywords
water
construction
control
switch board
standpipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510731762.3A
Other languages
Chinese (zh)
Other versions
CN105425694A (en
Inventor
王进军
程剑
张欣
孙磊
曹世勇
罗意
李聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Third Engineering Division
Original Assignee
First Construction Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Third Engineering Division filed Critical First Construction Co Ltd of China Construction Third Engineering Division
Priority to CN201510731762.3A priority Critical patent/CN105425694B/en
Publication of CN105425694A publication Critical patent/CN105425694A/en
Application granted granted Critical
Publication of CN105425694B publication Critical patent/CN105425694B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/048Monitoring; Safety

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Automation & Control Theory (AREA)
  • Domestic Plumbing Installations (AREA)
  • Pipeline Systems (AREA)

Abstract

The invention discloses a kind of construction water intelligent central control system, the system includes switch board, water intaking terminal automatic valve control device and construction water supply system, and the water intaking terminal automatic valve control device is connected by cable and control line with switch board;Wherein switch board includes solenoid valve control loop, current instruction control loop and controlling alarm loop;Water supply system of constructing includes storage tank, ball-cock assembly, water pump, coating steel pipe, upper water standpipe, water supply master control valve;Water intaking terminal automatic valve control device includes the flow divider being arranged on water standpipe, and is arranged on water flow indicator and magnetic valve by flow divider.Present system realizes that construction is cut off the water and supplied water with water intelligence centralized Control temporarily, saves construction water amount, simple to operate, reduces engineering cost.

Description

A kind of construction water intelligent central control system
Technical field
The present invention relates to technical field of building construction, particularly a kind of construction water intelligent central control system.
Background technology
At present, construction site construction water relies on substantially traditional " pure duct type " way of supplying water, and dry point is all adopted With machinery valve, the hand switch of people is completely dependent on, not only operates not convenient, and whole water system is in without management and control shape State, easily there is the water leakage that water valve forgets the artificial waste and piping failure closed.
The technological difficulties to solve the above problems are:1st, the remote centralized control to each water intaking terminal how is realized, it is real When grasp the use regimen condition of each water intaking terminal;2nd, how to be realized by a centralized Control platform long-distance to each water intaking eventually The on/off operation at end;3rd, the phenomenon very first time intelligently realizes and automatic alarm for " run, drip, leakage " how occurred to water supply line; 4th, how Added Management personnel " home-confined " can complete to it is each water intaking terminal positive closing, realize to regional With water pipe control.5th, how to ensure that monitoring system self-operating is normal, terminal control valve breaks down or destroyed, system energy intelligence Can display.6th, the computer that the water consumption automatic gauge of each terminal can be achieved and data are sent to control cabinet-type air conditioner in real time is united Meter.
The content of the invention
The defects of the technical problem to be solved in the present invention is to be directed in the prior art, there is provided a kind of construction water intelligently collects Middle control system.
The technical solution adopted for the present invention to solve the technical problems is:A kind of construction water intelligent central control system, Including switch board, water intaking terminal automatic valve control device, construction water supply system and water metering system, the water intaking terminal is certainly Movable valve control device is connected by cable and control line with switch board;
Wherein switch board includes solenoid valve control loop, current instruction control loop and controlling alarm loop;
Water supply system of constructing includes storage tank, ball-cock assembly, water pump, vibration means for main pipe for supplying water, upper water standpipe, water supply master control valve;Institute It is coating steel pipe to state vibration means for main pipe for supplying water;
The storage tank is fixedly mounted on bottom of the building platform, and the water storage upper box part installs ball-cock assembly, and lower bottom part passes through zinc-plated Steel pipe is connected with water pump, and installation settings has a water supply master control valve on the coating steel pipe on storage tank one side, the upper water standpipe with Coating steel pipe connects;
Water intaking terminal automatic valve control device includes the flow divider being arranged on water standpipe, and is arranged on flow divider Other water flow indicator and magnetic valve;
The water metering system is used for the statistics of water consumption, and the water metering system is included installed in vibration means for main pipe for supplying water Water meter and the inductive flowmeter on upper water standpipe.
By such scheme, the upper water standpipe is arranged on each floor of construction building.
By such scheme, the switch board is metal cabinet.
By such scheme, the solenoid valve control loop is the on-off circuit for controlling magnetic valve start and stop, and current indicate Control loop is that the on-off circuit of total water current and each layer current is controlled for water flow indicator information, controlling alarm loop be for The ON-OFF control circuit of buzzer siren.
The device work principle be:By using present system, terminal automatic valve control dress of fetching water can be passed through Put and use switch board centralized Control construction water, remotely realize ON/OFF water supply branch pipe, realize that construction intelligently concentrates control with water temporarily Stop water and water supply.
The beneficial effect comprise that:It can realize that construction water is respectively fetched water terminal by switch board centralized management Supply water and cut off the water, carry out the application of each operation section construction water in construction site, and it is existing by water flow indicator light monitoring in 24 hours Regimen condition is used in field, so as to realize the control of scene water, avoids water waste.Reach using water wisely, reduce the purpose of construction cost. And there is advantages below:
1. be arranged on the electronic installation of water Intellectualized monitoring and control is attached on feedwater piping, control terminal can management and control arrive Each dry point, also can flexible arrangement to needing management and control water supply branch pipe.
2. switch board is integrated control circuit casing, internal control circuit can voluntarily be changed by water supply system management and control demand Dress, intelligent integrated degree is high, and repacking is simple.
3 pass through the on-off circuits of solenoid valve control circuit controls magnetic valve start and stop;Current instruction control loop, which is shown, respectively to be taken Water spot regimen condition, realize monitoring in real time;Controlling alarm loop is used for the ON-OFF control circuit of buzzer siren, and feed pipe is said Existing damaged leak can automatic alarm.
Brief description of the drawings
Below in conjunction with drawings and Examples, the invention will be further described, in accompanying drawing:
Fig. 1 is the structural representation of the device of one embodiment of the invention;
Fig. 2 is switch board current of the present invention instruction and one loop assembling schematic diagram of solenoid valve control;
Fig. 3 is solenoid valve control loop of the present invention assembling schematic diagram;
Fig. 4 is switch board controlling alarm loop assembling schematic diagram of the present invention.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that specific embodiment described herein is not used to limit only to explain the present invention The fixed present invention.
As shown in figure 1, a kind of construction water intelligent central control system, by one set of construction water supply network and intelligent with water The electronic installation of monitoring and control forms, specific as follows:Including switch board 1, water intaking terminal automatic valve control device 12, construction Water supply system and water metering system, wherein switch board are used for the centralized Control of construction water, including solenoid valve control loop, water Stream instruction control loop, controlling alarm loop;Terminal automatic valve control device includes water flow indicator 7, magnetic valve 8, shunting Valve 9, power line and control line 5, construction water supply system include storage tank 11, ball-cock assembly 10, water pump 4, coating steel pipe(It is total to supply water Pipe)2nd, upper water standpipe 6, water supply main valve 3;In water supply system of constructing, storage tank 11 is positioned over fixed position, by special feedwater Manage and be connected for cistern water supply, water tank upper installation ball-cock assembly 10, lower bottom part by coating steel pipe 2 with water pump 4, in storage tank on one side Water supply master control valve 3 is installed, coating steel pipe 2 is connected with upper water standpipe 6, and water metering system is used for water consumption on coating steel pipe 2 Statistics, the water metering system include installed in vibration means for main pipe for supplying water water meter and the induction type stream on upper water standpipe Gauge.The upper water standpipe 6 of each floor forms the branch water pipe of the floor, and water flow indicator is provided with every layer of branch water pipe 7 and magnetic valve 8;A Ge Zong roads water flow switch and water meter are set on total feed pipe.
Water flow indicator 7 in the present embodiment(Water flow switch):When have current by when, switch i.e. can act;Model: FB31-025FM1 blocked flake types, specification:DN25, parameter:4MPa, sensitivity 2L/min;Magnetic valve:For closed type, it is powered and opens Valve supplies water;Model PU5404-06, specification:DN25, parameter:5MPa, DC24V.
Fetch water in terminal automatic valve control device, flow divider 9 is installed on the upper water standpipe of every layer of construction building, and Flow divider 9 is while installation water flow indicator 7 and magnetic valve 8.Water flow indicator 7 and magnetic valve 8 by cable and control line 5 with Switch board 1 connects.In the present embodiment, construction building is 52 layers, and switch board 1 is metal cabinet, as shown in Fig. 2 electric in switch board 1 The assembling of magnet valve control loop includes start button SA1 ~ SA52, stop button TA1 ~ TA52, indicator lamp HG1 ~ HG52, for controlling Magnetic valve start and stop;
Fig. 2 is the first control loop control figure, amounts to n control loop, miniature circuit breaker QF1, controls power switch; In current instruction loop, switch K1 control branch pipe flowing water switches, auxiliary reclay KA1-1, KA1-2, corresponding indicator lamp HG1, HY1;In magnetic valve manual control circuit, stop button TA1, start button SA1, indicator lamp HR1.This is that a unit control is former Reason is schemed, and element number scheme is that corresponding digital coding is increased in remaining element, such as:The stop button of second unit is “TA2”。
Fig. 2 control loop operation principles:
1st, supply water:When pressing Water supply switch valve SA, relay KA2 obtains electric, one group normally open contact closure, for magnetic valve confession Electricity, magnetic valve are opened, and floor possesses water supply capacity, as long as now opening floor manually-operated gate, you can there are flowing out;Meanwhile after Electrical equipment KA2 another sets normally open contact closes, and is powered for red led HR, and red led is bright, supplies water and refers to as the floor Show;2nd, current:When floor manually-operated gate is opened, water flow switch K actions, control relay KA1 obtains electric, and KA1 normally open contacts close Close, powered for green indicating lamp HG, green indicating lamp is bright, is indicated as the floor current;3rd, alarm:One group of relay KA1 Normally open contact is connected with relay KA2 one group of normally closed interlock, is powered for yellow indicator lamp HY, as the floor police instruction. I.e.:Not to the floor solenoid valve, i.e., ordered without supplying water, if still having current by, triggering water flow switch K actions, will make after Electrical equipment KA1 obtains electric;Now electric current is turned on by KA2 normally closed interlock and KA1 normally open contact, is powered for yellow indicator lamp HY, Yellow indicator lamp is bright, shows the floor water supply failure.(During normal water supply, because relay KA2 obtains electric, its normally closed interlock disconnection, It will be unable to power for yellow indicator lamp, yellow indicator lamp will not light alarm.)
Component in Fig. 2:Indicating lamp type buzzer F, indicator lamp HY, HY1 ~ HY52, indicator lamp HR, HR1 ~ HR52 are micro- Type circuit breaker Q F, QF1 ~ QF52, auxiliary reclay KA1-1 ~ KA52-1, Switching Power Supply T, miniature circuit breaker QA, QA1 ~ QA52, water Stream switch K1 ~ K52, auxiliary reclay KA, KA1-12 ~ KA52-2, current master switch K.
Entered after the completion of switch board assembling by power line and control line 5 and the water flow indicator 7 and magnetic valve 8 of terminal of fetching water Row connection.
Fig. 3 is solenoid valve control loop of the present invention assembling schematic diagram, the component in Fig. 2:Miniature circuit breaker QA control electricity Source master switch, Switching Power Supply T, miniature circuit breaker QA1 ~ QA52 in each control loop, each ring current is controlled to switch respectively, it is middle Relay KA1-2 ~ KA52-2, the magnetic valve of each branch pipe is controlled respectively.
Fig. 4 is switch board controlling alarm loop assembling schematic diagram of the present invention, the component in Fig. 4:Miniature circuit breaker QF, control Power switch processed, indicator HR, HY, house steward water flow switch K, auxiliary reclay KA, KA1-2 ~ KA52-2, buzzing indicator F.
Fig. 4 control loop operation principles(That is pipeline alarm principle):It is identical with branch road alarm principle.I.e. all magnetic valves are equal When being closed, if now still having current in pipeline by being expressed as malfunction.Now main pipe rail water route switch is dynamic Make, its corresponding relay obtains electric, one group of normally open contact closure, electric current by with its all floor water supply relay KA2 to connect Normally closed interlock conducting, be that total road alarm lamp and alarm buzzer are powered, form total road alarm.When any floor is in water supply shape During state, due to there is relay KA2 actions, Ze Zong roads alarm system circuit disconnects, and will not form total road alarm.
The present invention establishes a set of intelligent managing and control system for being attached to water supply line, has broken traditional water supply system to water Without management and control, the unmonitored quagmire of flowing water, construction water intelligence management and control is realized, the whole intervention of personnel is cut off the water and supplied water, and science is united Ji Ge branches water consumption, limit use, and save construction water.Intelligence concentration water control system realizes administrative staff station and existed well Before centralized Control sales counter, it is possible to complete to tens of up to a hundred water intaking real-time monitoring of terminal and cutting off the water/supplying water to each branch pipe Control.It is realized by the electronic inductor of each branch road of master control cabinet collection control.
It should be appreciated that for those of ordinary skills, can according to the above description be improved or converted, And all these modifications and variations should all belong to the protection domain of appended claims of the present invention.

Claims (4)

1. a kind of construction water intelligent central control system, including switch board, it is characterised in that also include water intaking terminal automatic valve Controlling device for doors, construction water supply system and water metering system, the water intaking terminal automatic valve control device pass through cable It is connected with control line with switch board;
Wherein switch board includes solenoid valve control loop, current instruction control loop and controlling alarm loop;
Water supply system of constructing includes storage tank, ball-cock assembly, water pump, vibration means for main pipe for supplying water, upper water standpipe, water supply master control valve;The confession Water supervisor is coating steel pipe;
The storage tank is fixedly mounted on bottom of the building platform, and the water storage upper box part installs ball-cock assembly, and lower bottom part passes through coating steel pipe Be connected with water pump, installation settings has a water supply master control valve on the coating steel pipe on storage tank one side, the upper water standpipe with it is zinc-plated Fastener for connection;
Water intaking terminal automatic valve control device includes the flow divider being arranged on water standpipe, and is arranged on by flow divider Water flow indicator and magnetic valve;
The water metering system is used for the statistics of water consumption, and the water metering system includes the water installed in vibration means for main pipe for supplying water Table and the inductive flowmeter on upper water standpipe.
2. construction water intelligent central control system according to claim 1, it is characterised in that the upper water standpipe is set In each floor of construction building.
3. construction water intelligent central control system according to claim 1, it is characterised in that the switch board is metal Casing.
4. construction water intelligent central control system according to claim 1, it is characterised in that the solenoid valve control is returned Road is the on-off circuit for controlling magnetic valve start and stop, and current instruction control loop is for being controlled according to water flow indicator information The on-off circuit of total water current and each layer current, controlling alarm loop are the ON-OFF control circuit for buzzer siren.
CN201510731762.3A 2015-10-30 2015-10-30 A kind of construction water intelligent central control system Active CN105425694B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510731762.3A CN105425694B (en) 2015-10-30 2015-10-30 A kind of construction water intelligent central control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510731762.3A CN105425694B (en) 2015-10-30 2015-10-30 A kind of construction water intelligent central control system

Publications (2)

Publication Number Publication Date
CN105425694A CN105425694A (en) 2016-03-23
CN105425694B true CN105425694B (en) 2018-02-27

Family

ID=55503968

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510731762.3A Active CN105425694B (en) 2015-10-30 2015-10-30 A kind of construction water intelligent central control system

Country Status (1)

Country Link
CN (1) CN105425694B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112814082A (en) * 2021-02-03 2021-05-18 江苏省华建建设股份有限公司 Construction site permanent and temporary combined near-water supply device with pressure stabilization function and use method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201062974Y (en) * 2007-06-20 2008-05-21 高彦军 Automatic flow controller
CN201250418Y (en) * 2008-05-28 2009-06-03 龙腾 Automatic water supply device for high building construction
CN201778363U (en) * 2010-09-24 2011-03-30 甘肃省第三建筑工程公司 Automatic water supply system used for high-rise building construction water
CN102296670A (en) * 2011-06-14 2011-12-28 中建三局建设工程股份有限公司 Automatic supply system of water for high-rise building construction and fire control

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205263590U (en) * 2015-10-30 2016-05-25 中建三局第一建设工程有限责任公司 Construction water intelligence centralized control system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201062974Y (en) * 2007-06-20 2008-05-21 高彦军 Automatic flow controller
CN201250418Y (en) * 2008-05-28 2009-06-03 龙腾 Automatic water supply device for high building construction
CN201778363U (en) * 2010-09-24 2011-03-30 甘肃省第三建筑工程公司 Automatic water supply system used for high-rise building construction water
CN102296670A (en) * 2011-06-14 2011-12-28 中建三局建设工程股份有限公司 Automatic supply system of water for high-rise building construction and fire control

Also Published As

Publication number Publication date
CN105425694A (en) 2016-03-23

Similar Documents

Publication Publication Date Title
CN110374853A (en) A kind of substation's sump draining pump intelligence control system
CN108803510A (en) Pumping station automatization monitoring system
CN203405698U (en) Fixed winch type hoist intelligent control system
CN106097155B (en) A kind of car plumbing intelligent monitoring and management system based on mobile Internet
CN111305897A (en) Automatic drainage control system of mine
CN203008116U (en) Water discharge system
CN105425694B (en) A kind of construction water intelligent central control system
CN209083536U (en) A kind of Accident of Transformer oil storage well drainage arrangement
CN108803739A (en) A kind of wisdom building site spraying linkage management system
CN206110247U (en) Fire control cistern automatic water supply monitoring device
CN205263590U (en) Construction water intelligence centralized control system
CN206457881U (en) Full factory water supply pumping plant robot control system(RCS)
WO2022116238A1 (en) Underground deep automated spiral drainage apparatus
CN101749468A (en) Communication equipment room waterproof system
CN203445507U (en) Brush generator set integrated intelligent control screen
CN202834781U (en) Water leakage automatic protection device
CN205644256U (en) Property equipment is concentrated and distribution control management system
CN202004527U (en) Automatic double-power supply fan control box
CN205530592U (en) Cable tunnel automatic water discharging device
CN111210687B (en) Operation and maintenance training platform for electromechanical equipment system of urban rail transit
CN203518122U (en) Water leakage alarm system of air conditioner special for machine room
CN205248685U (en) Box switching station in all -weather underground
CN103557903A (en) Cable trench water level detection and alarm device for power transformer substation
CN203535019U (en) Automatic controller for gas pipeline
CN205540190U (en) Device is surely controlled in electrical equipment's energy -conservation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant