CN105382434A - Equipment for producing bridge guardrail and machining method of equipment - Google Patents

Equipment for producing bridge guardrail and machining method of equipment Download PDF

Info

Publication number
CN105382434A
CN105382434A CN201510830490.2A CN201510830490A CN105382434A CN 105382434 A CN105382434 A CN 105382434A CN 201510830490 A CN201510830490 A CN 201510830490A CN 105382434 A CN105382434 A CN 105382434A
Authority
CN
China
Prior art keywords
fixed bar
plate
horizontal fixed
equipment
location
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510830490.2A
Other languages
Chinese (zh)
Inventor
王华生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Wangdefu Metal Structure Co Ltd
Original Assignee
Chongqing Wangdefu Metal Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Wangdefu Metal Structure Co Ltd filed Critical Chongqing Wangdefu Metal Structure Co Ltd
Priority to CN201510830490.2A priority Critical patent/CN105382434A/en
Publication of CN105382434A publication Critical patent/CN105382434A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K31/00Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
    • B23K31/02Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
    • B23K37/04Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Optics & Photonics (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The invention discloses equipment for producing a bridge guardrail and a machining method of the equipment. The equipment comprises mounting bolts, a transverse fixed rod, vertical fixed rods, adjusting bolts, a locating plate, steel rulers, fixed screws, a bottom plate, an adjusting plate and a screw. The equipment has the beneficial effects that the adjusting plate can be driven to vertically move by rotating the adjusting bolts, and therefore the adjusting plate can clamp a pipe to be machined, the pipe is prevented from moving, and therefore welding and machining of the pipe are facilitated; a layer of rubber is attached to the bottom end of a fixed plate, so when the fixed plate clamps the pipe to be machined, no trace is left on the pipe, the steel rulers can conveniently measure the pipe to be machined so that the pipe with the unqualified size can be found in time, and finished product scraping caused by the size problem is avoided; the transverse fixed rod and the vertical fixed rods are all square hollow alloy pipes, and the hollow alloy pipes are low in mass and easy to machine; and on one hand, the weight of the whole equipment can be reduced so that equipment movement can be facilitated, and on the other hand, the machining difficulty of the equipment can be lowered.

Description

A kind of equipment and processing method thereof of producing Bridge guardrail
Technical field
The present invention relates to a kind of equipment producing Bridge guardrail, be specially a kind of equipment and processing method thereof of producing Bridge guardrail, belong to science of bridge building field.
Background technology
Bridge guardrail refers to the guardrail be arranged on bridge, its objective is to prevent errant vehicle from running off outside bridge, have and vehicle can not be broken through, under wear, cross bridge and beautify the function of bridge construction, metal post and beam guardrail is easy for installation because of it, cost is low, the advantage such as effective is used widely on medium and small bridges, present metal post and beam guardrail is use tubulose steel pipe to be welded mostly, welding method is be well placed by each assembly by guardrail shape on the table mostly, then carry out successively welding until become as a whole, this method is easy to cause each assembly to move when welding, and cannot the Assurance component position of putting, angle meets the requirements, the finished product welded often is caused not meet the requirements, the steel pipe assembly do not meeted the requirements for some length cannot Timeliness coverage, thus make the operating efficiency of this method very low.
Summary of the invention
Object of the present invention is just to provide a kind of equipment and processing method thereof of producing Bridge guardrail to solve the problem.
The present invention is achieved through the following technical solutions above-mentioned purpose: a kind of equipment producing Bridge guardrail, comprise construction bolt, horizontal fixed bar, vertical fixed bar, adjusting bolt, location-plate, steel ruler, fixed screw, base plate, adjustable plate and screw, it is characterized in that: described construction bolt runs through horizontal fixed bar and is laterally fixed on base plate by horizontal fixed bar, described horizontal fixed bar two ends are provided with a construction bolt, described horizontal fixed bar side is provided with two adjusting bolts, adjusting bolt on described horizontal fixed bar runs through horizontal fixed bar and adjustable plate welds together, described vertical fixed bar is evenly vertically welded on base plate, location-plate is welded with between described two adjacent vertical fixed bars, described location-plate is provided with adjusting bolt, adjusting bolt on described location-plate runs through location-plate and adjustable plate welds together, vertical fixed bar and the horizontal fixed bar side of described base plate both sides are provided with steel ruler, described steel ruler is fixed on horizontal fixed bar and vertical fixed bar by two fixed screws, described horizontal fixed bar and the location-plate screw through part that is fixed is provided with screw.
Preferably, in order to tubing to be processed can be clamped, described horizontal fixed bar and location-plate is welded with screw and adjusting bolt is linked together by internal and external threads.
Preferably, in order to protect tubing to be processed, described fixed head bottom is pasted with one deck rubber.
Preferably, in order to prevent off-dimension, the steel ruler on described horizontal fixed bar can transversely be twitched and steel ruler on vertical fixed bar can vertically be twitched.
Preferably, conveniently mobile and easy to process, described horizontal fixed bar and vertical fixed bar are square hollow compo pipe.
Produce a processing method for Bridge guardrail equipment, the processing method of described production Bridge guardrail equipment is made up of following step:
1) a square hollow compo pipe, is chosen respectively in upper surface with side end face is each beats holes and holes is symmetrical, the centre distance of the pitch-row clutch gold hollow pipe of both ends of the surface is different, tighten up a screw in the holes place welding of side, then on screw, adjusting bolt is installed, and adjustable plate on welding after adjusting bolt runs through hollow compo pipe, form horizontal fixed bar;
2), choose square sheet metal that size conforms to above-mentioned alloy hollow length of tube as base plate, and punch on the position that bottom edge is corresponding with the holes of horizontal fixed bar upper surface;
3), the two is connected and fixed through the hole on horizontal fixed bar upper surface and base plate by construction bolt;
4), choose that multistage alloy hollow pipe is equally spaced to be welded on as vertical fixed bar on base plate, during welding and horizontal fixed bar is perpendicular and port and horizontal fixed bar keep certain distance;
5), choose multiple identical square iron plate and have openning hole as location-plate on top, then on hole, having welded screw, adjusting bolt being run through after this location-plate adjustable plate on adjusting bolt welding edges;
6), on all adjustable plates, last layer TR thin rubber is attached;
7), location-plate is welded between two vertical fixed bars.
The invention has the beneficial effects as follows: the equipment de-sign of this production Bridge guardrail is reasonable, horizontal fixed bar and location-plate is welded with screw and adjusting bolt is linked together by internal and external threads, such rotation adjusting bolt can drive adjustable plate to move up and down, thus adjustable plate can be made to clamp tubing to be processed, prevent it from moving, thus facilitate its welding and processing, fixed head bottom is pasted with one deck rubber, such fixed head can not be left a trace when clamping pipe fitting to be processed on pipe fitting, ensure pipe fitting complete appearance and attractive in appearance, steel ruler on horizontal fixed bar can transversely be twitched and steel ruler on vertical fixed bar can vertically be twitched, processing pipe fitting can be treated very easily measure, so that Timeliness coverage off-dimension pipe fitting, prevent because dimensional problem causes finished product to scrap, horizontal fixed bar and vertical fixed bar are square hollow compo pipe, hollow compo pipe quality is light, process, the weight of whole device can be alleviated on the one hand, thus facilitate device to move, the opposing party lessens the difficulty of processing of this device.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is adjusting bolt of the present invention and adjustable plate structural representation;
Fig. 3 is horizontal fixed rod structure schematic diagram of the present invention;
Fig. 4 is vertical fixed rod structure schematic diagram of the present invention;
In figure: 1, construction bolt, 2, horizontal fixed bar, 3, vertical fixed bar, 4, adjusting bolt, 5, location-plate, 6, steel ruler, 7, fixed screw, 8, base plate, 9, adjustable plate and 10, screw.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, be clearly and completely described the technical scheme in the embodiment of the present invention, obviously, described embodiment is only the present invention's part embodiment, instead of whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art, not making the every other embodiment obtained under creative work prerequisite, belong to the scope of protection of the invention.
Below in conjunction with the accompanying drawing in the embodiment of the present invention, be clearly and completely described the technical scheme in the embodiment of the present invention, obviously, described embodiment is only the present invention's part embodiment, instead of whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art, not making the every other embodiment obtained under creative work prerequisite, belong to the scope of protection of the invention.
Refer to Fig. 1 ~ 4, a kind of equipment producing Bridge guardrail, comprise construction bolt 1, horizontal fixed bar 2, vertical fixed bar 3, adjusting bolt 4, location-plate 5, steel ruler 6, fixed screw 7, base plate 8, adjustable plate 9 and screw 10, described construction bolt 1 runs through horizontal fixed bar 2 and is laterally fixed on base plate 8 by horizontal fixed bar 2, described horizontal fixed bar two ends 2 are provided with a construction bolt 1, described horizontal fixed bar 2 side is provided with two adjusting bolts 4, adjusting bolt 4 on described horizontal fixed bar 2 runs through horizontal fixed bar 2 and adjustable plate 9 welds together, described vertical fixed bar 3 is evenly vertically welded on base plate 8, described horizontal fixed bar 2 and vertical fixed bar 3 are square hollow compo pipe, hollow compo pipe quality is light, process, the weight of whole device can be alleviated on the one hand, thus facilitate device to move, the opposing party lessens the difficulty of processing of this device, location-plate 5 is welded with between described two adjacent vertical fixed bars 3, described location-plate 5 is provided with adjusting bolt 4, adjusting bolt 4 on described location-plate 5 runs through location-plate 5 and adjustable plate 9 welds together, described fixed head 9 bottom is pasted with one deck rubber, such fixed head 9 can not be left a trace when clamping pipe fitting to be processed on pipe fitting, ensure pipe fitting complete appearance and attractive in appearance, vertical fixed bar 3 and horizontal fixed bar 2 side of described base plate 8 both sides are provided with steel ruler 6, described steel ruler 6 is fixed on horizontal fixed bar 2 and vertical fixed bar 3 by two fixed screws 7, steel ruler 6 on described horizontal fixed bar 2 can transversely be twitched and steel ruler 6 on vertical fixed bar 3 can vertically be twitched, processing pipe fitting can be treated very easily measure, so that Timeliness coverage off-dimension pipe fitting, prevent because dimensional problem causes finished product to scrap, described horizontal fixed bar 2 and location-plate 5 screw 7 through part that is fixed is provided with screw 10, described horizontal fixed bar 2 and location-plate 5 are welded with screw 10 and adjusting bolt 4 is linked together by internal and external threads, such rotation adjusting bolt 4 can drive adjustable plate 9 to move up and down, thus adjustable plate 9 can be made to clamp tubing to be processed, prevent it from moving, thus facilitate its welding and processing.
The processing method of described production Bridge guardrail equipment is made up of following step:
1) a square hollow compo pipe, is chosen respectively in upper surface with side end face is each beats holes and holes is symmetrical, the centre distance of the pitch-row clutch gold hollow pipe of both ends of the surface is different, 10 are tightened up a screw in the holes place welding of side, then on screw 10, adjusting bolt 4 is installed, and adjustable plate 10 on welding after adjusting bolt 4 runs through hollow compo pipe, form horizontal fixed bar 2;
3), choose square sheet metal that size conforms to above-mentioned alloy hollow length of tube as base plate 8, and punch on the position that base plate 8 edge is corresponding with the holes of horizontal fixed bar 2 upper surface;
3), the two is connected and fixed through the hole on horizontal fixed bar 2 upper surface and base plate 8 by construction bolt 1;
4), choose that multistage alloy hollow pipe is equally spaced to be welded on as vertical fixed bar 3 on base plate 8, during welding and horizontal fixed bar 2 is perpendicular and port and horizontal fixed bar 2 keep certain distance;
5), choose multiple identical square iron plate and have openning hole on top as location-plate 5, then on hole, having welded screw 10, adjusting bolt 4 being run through after this location-plate 5 adjustable plate 9 on adjusting bolt 4 welding edges;
6), on all adjustable plates 9, last layer TR thin rubber is attached;
7), location-plate 5 is welded between two vertical fixed bars 3.
The course of work: when using the equipment of described production Bridge guardrail, first, device is moved on workbench, a pipe fitting to be processed is inserted in the gap between horizontal fixed bar and vertical fixed bar again, then multiple pipe fitting is inserted in the space between vertical fixed bar, steel ruler can be twitched measure tubing, then turn adjusting bolt, adjustable plate is made to clamp pipe fitting, now can weld, after having welded, turn construction bolt, horizontal fixed bar can be taken off, then the finished product welded be extracted out and install horizontal fixed bar again.
To those skilled in the art, obviously the invention is not restricted to the details of above-mentioned one exemplary embodiment, and when not deviating from spirit of the present invention or essential characteristic, the present invention can be realized in other specific forms.Therefore, no matter from which point, all should embodiment be regarded as exemplary, and be nonrestrictive, scope of the present invention is limited by claims instead of above-mentioned explanation, and all changes be therefore intended in the implication of the equivalency by dropping on claim and scope are included in the present invention.Any Reference numeral in claim should be considered as the claim involved by limiting.
In addition, be to be understood that, although this description is described according to embodiment, but not each embodiment only comprises an independently technical scheme, this narrating mode of description is only for clarity sake, those skilled in the art should by description integrally, and the technical scheme in each embodiment also through appropriately combined, can form other embodiments that it will be appreciated by those skilled in the art that.

Claims (6)

1. produce the equipment of Bridge guardrail for one kind, comprise construction bolt (1), horizontal fixed bar (2), vertical fixed bar (3), adjusting bolt (4), location-plate (5), steel ruler (6), fixed screw (7), base plate (8), adjustable plate (9) and screw (10), it is characterized in that: described construction bolt (1) runs through horizontal fixed bar (2) and is laterally fixed on base plate (8) by horizontal fixed bar (2), described horizontal fixed bar two ends (2) are provided with a construction bolt (1), described horizontal fixed bar (2) side is provided with two adjusting bolts (4), adjusting bolt (4) on described horizontal fixed bar (2) runs through horizontal fixed bar (2) and adjustable plate (9) welds together, described vertical fixed bar (3) is evenly vertically welded on base plate (8), location-plate (5) is welded with between described two adjacent vertical fixed bars (3), described location-plate (5) is provided with adjusting bolt (4), adjusting bolt (4) on described location-plate (5) runs through location-plate (5) and adjustable plate (9) welds together, vertical fixed bar (3) and horizontal fixed bar (2) side of described base plate (8) both sides are provided with steel ruler (6), described steel ruler (6) is fixed on horizontal fixed bar (2) and vertical fixed bar (3) by two fixed screws (7), described horizontal fixed bar (2) and location-plate (5) screw (7) through part that is fixed is provided with screw (10).
2. a kind of equipment producing Bridge guardrail according to claim 1, is characterized in that: described horizontal fixed bar (2) and location-plate (5) are welded with screw (10) and adjusting bolt (4) is linked together by internal and external threads.
3. a kind of equipment producing Bridge guardrail according to claim 1 and 2, is characterized in that: described fixed head (9) bottom is pasted with one deck sheet rubber.
4. a kind of equipment producing Bridge guardrail according to claim 3, is characterized in that: the steel ruler (6) on described horizontal fixed bar (2) can transversely be twitched and steel ruler (6) on vertical fixed bar (3) can vertically be twitched.
5. a kind of equipment producing Bridge guardrail according to claim 1 or 4, is characterized in that: described horizontal fixed bar (2) and vertical fixed bar (3) are square hollow compo pipe.
6. produce a processing method for Bridge guardrail equipment, it is characterized in that: the processing method of described production Bridge guardrail equipment is made up of following step:
1) a square hollow compo pipe, is chosen respectively in upper surface with side end face is each beats holes and holes is symmetrical, the centre distance of the pitch-row clutch gold hollow pipe of both ends of the surface is different, (10) are tightened up a screw in the holes place welding of side, then on screw (10), adjusting bolt (4) is installed, and after adjusting bolt (4) runs through hollow compo pipe, weld upper adjustable plate (10), form horizontal fixed bar (2);
2), choose square sheet metal that size conforms to above-mentioned alloy hollow length of tube as base plate (8), and punch on the position that base plate (8) edge is corresponding with the holes of horizontal fixed bar (2) upper surface;
3), the two is connected and fixed through the hole on horizontal fixed bar (2) upper surface and base plate (8) by construction bolt (1);
4), choose that multistage alloy hollow pipe is equally spaced to be welded on as vertical fixed bar (3) on base plate (8), during welding and horizontal fixed bar (2) is perpendicular and port and horizontal fixed bar (2) keep certain distance;
5), choose multiple identical square iron plate and have openning hole on top as location-plate (5), then on hole, weld screw (10), adjusting bolt (4) to be run through after this location-plate (5) adjustable plate (9) on adjusting bolt (4) welding edges;
6), at all adjustable plates (9) upper attaching last layer TR thin rubber;
7), location-plate (5) is welded between two vertical fixed bars (3).
CN201510830490.2A 2015-11-25 2015-11-25 Equipment for producing bridge guardrail and machining method of equipment Pending CN105382434A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510830490.2A CN105382434A (en) 2015-11-25 2015-11-25 Equipment for producing bridge guardrail and machining method of equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510830490.2A CN105382434A (en) 2015-11-25 2015-11-25 Equipment for producing bridge guardrail and machining method of equipment

Publications (1)

Publication Number Publication Date
CN105382434A true CN105382434A (en) 2016-03-09

Family

ID=55415560

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510830490.2A Pending CN105382434A (en) 2015-11-25 2015-11-25 Equipment for producing bridge guardrail and machining method of equipment

Country Status (1)

Country Link
CN (1) CN105382434A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105773031A (en) * 2016-03-30 2016-07-20 西安聚能装备技术有限公司 Welding fixture for titanium, zirconium and titanium zirconium alloy electrode blocks
CN109202348A (en) * 2018-09-21 2019-01-15 中船澄西船舶修造有限公司 A kind of fence group of large ship vertical group mounted welder and assembly welding method in batches
CN110744252A (en) * 2019-10-24 2020-02-04 安徽鑫泰亿达装饰建材有限公司 Steel pipe auxiliary positioning mechanism for producing and processing protective guard in cell

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105773031A (en) * 2016-03-30 2016-07-20 西安聚能装备技术有限公司 Welding fixture for titanium, zirconium and titanium zirconium alloy electrode blocks
CN105773031B (en) * 2016-03-30 2017-10-20 西安聚能装备技术有限公司 It is a kind of to be used for the weld jig of titanium and zirconium and its alloy electrode block
CN109202348A (en) * 2018-09-21 2019-01-15 中船澄西船舶修造有限公司 A kind of fence group of large ship vertical group mounted welder and assembly welding method in batches
CN109202348B (en) * 2018-09-21 2020-12-04 中船澄西船舶修造有限公司 Fence small-assemblage batch assembling and welding tool and method for large ship
CN110744252A (en) * 2019-10-24 2020-02-04 安徽鑫泰亿达装饰建材有限公司 Steel pipe auxiliary positioning mechanism for producing and processing protective guard in cell

Similar Documents

Publication Publication Date Title
CN202411715U (en) Welding positioning fixture for mobile arm spider of crane
CN202752784U (en) Tool fixture for nuclear-power submerged-arc welding examination
CN205201063U (en) Novel bevel connection anchor clamps for sawing machine
CN105382434A (en) Equipment for producing bridge guardrail and machining method of equipment
CN207087238U (en) Automobile skeleton clamping and positioning device
CN201664830U (en) Tool clamp for welding production of H-type crossbeam of truck
CN104384807A (en) Rectangular frame welding device
CN203944924U (en) The removable deck of sawing machine workpiece
CN206373528U (en) Well word keel positioning tool
CN206216112U (en) Move freely clamped-in style friction welding frock
CN208358168U (en) A kind of vertical ladder bracket welding processing tooling
CN104325399B (en) A kind of simple positioning clamping device of saddle
CN102704696B (en) Space locator for high, big and heavy steel upright column
CN202292497U (en) Positioning jig
CN205915081U (en) Section bar adds clamping apparatus
CN205394071U (en) Adjustable multipurpose clamping
CN201863035U (en) Mechanical processing clamp for minor-caliber bend
CN204108665U (en) The Work fixing device of four axle lathes
CN203843411U (en) Production mold for instrument pillars
CN205520130U (en) Production bridge railing's equipment
CN217667988U (en) Tubular column shaft inclined hole drilling clamp
CN104827319A (en) Clamp for machining hexahedron out of round bar material and method for machining hexahedron
CN204657802U (en) A kind of underframe of coach frame welding fixture
CN210614803U (en) High-efficient perforating device of aluminum alloy ex-trusions
CN203738286U (en) Novel welding fixture

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160309