CN105331760B - The processing method that wall between a kind of air channel and gas pipe is damaged - Google Patents

The processing method that wall between a kind of air channel and gas pipe is damaged Download PDF

Info

Publication number
CN105331760B
CN105331760B CN201510766228.6A CN201510766228A CN105331760B CN 105331760 B CN105331760 B CN 105331760B CN 201510766228 A CN201510766228 A CN 201510766228A CN 105331760 B CN105331760 B CN 105331760B
Authority
CN
China
Prior art keywords
wall
gas pipe
oblique section
coal gas
air channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510766228.6A
Other languages
Chinese (zh)
Other versions
CN105331760A (en
Inventor
郑敬先
曹勇
芦文凯
万雷
常醒民
蔡景春
杨晓婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Shougang Co Ltd
Original Assignee
Beijing Shougang Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Shougang Co Ltd filed Critical Beijing Shougang Co Ltd
Priority to CN201510766228.6A priority Critical patent/CN105331760B/en
Publication of CN105331760A publication Critical patent/CN105331760A/en
Application granted granted Critical
Publication of CN105331760B publication Critical patent/CN105331760B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Chimneys And Flues (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses the processing method that the wall between a kind of air channel and gas pipe is damaged, belong to blast funnace hot blast stove maintenance technology field.The processing method that wall between the air channel and gas pipe is damaged comprises the following steps:The wall position do not collapsed between air channel and gas pipe is targetedly reinforced according to the principle for being convenient for constructing and protecting;The oblique section wall of coal gas pipe protection wall is repaired by way of one-piece casting;Top surface after the oblique section wall solidification of coal gas pipe protection wall builds supporting brick post by laying bricks or stones;Gas pipe wall above the oblique section wall of coal gas pipe protection wall with air channel insertion is repaired in integrated poured mode.Air channel of the present invention quickly can have been constructed with the processing method that the wall between gas pipe is damaged between air channel and gas pipe together with closely knit integral wall, enhance the structural stability of new reparation wall, it is ensured that keep the safety in production.

Description

The processing method that wall between a kind of air channel and gas pipe is damaged
Technical field
The present invention relates to blast funnace hot blast stove maintenance technology field, the wall between more particularly to a kind of air channel and gas pipe The processing method of damage.
Background technology
Burner is a key position in blast funnace hot blast stove.Its key built by laying bricks or stones be gas pipe can not with air channel it Between produce and gas leakage or collaborate.In the prior art, building by laying bricks or stones for hot-blast stove gas burner requires strict, the appearance and size requirement to brick Height, and pre-assembled numbering need to be generally carried out, built by laying bricks or stones by number when building by laying bricks or stones.In existing hot-blast stove gas pipe damage repair technology, one Denier burner gas pipe wall occurs damaging or caved in, no both quickly to repair gas pipe wall, it is ensured that the knot of wall Structure stability, can effectively prevent from collaborating between air channel and gas pipe, it is ensured that the scheme of safety in production again.
The content of the invention
The present invention provides the processing method that the wall between a kind of air channel and gas pipe is damaged, and solves or part is solved Burner gas pipe wall occurs damaging or caved in the prior art, and no scheme both can quickly repair gas pipe wall Body, it is ensured that the structural stability of wall, can effectively prevent the technical problem collaborated between air channel and gas pipe again.
In order to solve the above technical problems, the invention provides the processing that the wall between a kind of air channel and gas pipe is damaged Method, the wall body structure includes:The oblique section wall of coal gas pipe protection wall and the former cast bed of material, the coal gas pipe protection wall are oblique Section wall is connected with the gas pipe, and the former cast bed of material connects with the oblique section wall of the coal gas pipe protection wall and gas pipe Connect;It the treating method comprises following steps:To the wall position do not collapsed between air channel and gas pipe according to be easy into The principle of row construction and protection is targetedly reinforced;The oblique section of coal gas pipe protection wall is repaired by way of one-piece casting Wall;Top surface after the oblique section wall solidification of the coal gas pipe protection wall builds supporting brick post by laying bricks or stones;By the coal gas pipe protection wall Gas pipe wall above the oblique section wall of body with air channel insertion is repaired in integrated poured mode.
Further, the oblique section wall of coal gas pipe protection wall of being repaired by way of one-piece casting includes the coal gas The oblique section wall of pipe protection wall and its damaged location wall of the above take segmentation to use the integrated poured mode of gravity flow pouring material Repaired.
Further, the final stage of the oblique section wall pouring of the coal gas pipe protection wall, in the coal gas pipe protection wall The top surface of the oblique section wall of body reserves groove.
Further, before the oblique section wall of coal gas pipe protection wall is poured into a mould, in the oblique section of coal gas pipe protection wall Expansion bolt is installed at interval on the former cast bed of material of wall behind.
Further, it is fixed with anchoring hook on the expansion bolt.
Further, the top surface after the oblique section wall solidification of the coal gas pipe protection wall, which builds supporting brick post by laying bricks or stones, includes The supporting brick post is stayed in integrated poured wall as anchored brick or " reinforcement ".
Further, the gas pipe wall by above the oblique section wall of the coal gas pipe protection wall with air channel insertion Repaired in integrated poured mode including the gas pipe above the oblique section wall of the coal gas pipe protection wall with air channel insertion Wall is repaired in the way of integrated poured gravity flow pouring material.
Further, the one-piece casting mode is completed using pumping casting construction method.
The processing method that wall between air channel and gas pipe that the present invention is provided is damaged is first to air channel and coal gas The wall position do not collapsed between road is targetedly reinforced according to the principle for being convenient for constructing and protecting, by whole The mode that body is poured repairs the oblique section wall of coal gas pipe protection wall, and the top surface after the oblique section wall solidification of coal gas pipe protection wall is built by laying bricks or stones Supporting brick post, the gas pipe wall above the oblique section wall of coal gas pipe protection wall with air channel insertion is added in integrated poured mode To repair, quickly can have been constructed between air channel and gas pipe together with closely knit integral wall, enhance the knot of newly reparation wall Structure stability, it is ensured that safety in production.
Brief description of the drawings
Fig. 1 is the wall encapsulating method schematic flow sheet between air channel provided in an embodiment of the present invention and gas pipe;
Fig. 2 is the structural representation of the wall between air channel provided in an embodiment of the present invention and gas pipe.
Embodiment
Referring to Fig. 1-2, the processing side that the wall between a kind of air channel and gas pipe provided in an embodiment of the present invention is damaged Method, based on the wall body structure between air channel and gas pipe, the wall body structure includes:The oblique section wall 3 of coal gas pipe protection wall And the former cast bed of material 2, the oblique section wall 3 of coal gas pipe protection wall is connected with the gas pipe 1, the former cast bed of material 2 and The oblique section wall 3 of coal gas pipe protection wall and gas pipe 1 are connected;It the treating method comprises following steps:This method is Based on the wall body structure between the air channel and gas pipe in Fig. 2, so either specification or claims, is all needed First to introduce the structure of wall.
Step 1, to the wall position do not collapsed between air channel 8 and gas pipe 1 according to being convenient for constructing and protect Principle targetedly reinforced.
Step 2, the oblique section wall 3 of coal gas pipe protection wall is repaired by way of one-piece casting.
Step 3, the top surface after the oblique section wall 3 of the coal gas pipe protection wall solidifies builds supporting brick post 6 by laying bricks or stones.
Step 4, by the wall of gas pipe 1 above the oblique section wall 3 of the coal gas pipe protection wall with the insertion of air channel 8 with whole Body pouring type is repaired.
Step 2 is discussed in detail.
The oblique section wall 3 of coal gas pipe protection wall of being repaired by way of one-piece casting includes:The coal gas pipe protection The oblique section wall 3 of wall and its damaged location wall of the above take segmentation to give using the integrated poured mode of gravity flow pouring material 7 Repair.The final stage that the oblique section wall 3 of coal gas pipe protection wall is poured into a mould, in the oblique section wall 3 of the coal gas pipe protection wall Top surface reserve groove 5, the cast for lower step plays fixation, and tortuous reciprocal labyrinth-like is formd in wall seam crossing Seam, makes sealing effectiveness more preferably, can effectively prevent from collaborating between air channel 8 and gas pipe 1.Pouring into a mould the coal gas pipe protection wall Before the oblique section wall 3 of body, expanding screw is installed at interval on the former cast bed of material 2 of the oblique behind of section wall 3 of the coal gas pipe protection wall Bolt.Anchoring hook 4 is fixed with the expansion bolt, the globality of castable is kept, the connection of the bed of material and old wall is poured into a mould in enhancing, Because old wall is castable, so needing first to beat expansion bolt to weld anchoring hook 4.
Step 3 is discussed in detail.
The top surface after the oblique section wall 3 of the coal gas pipe protection wall solidifies, which builds supporting brick post 6 by laying bricks or stones, to be included:The branch Support brick post 6 is stayed in integrated poured wall as anchored brick or " reinforcement ", to strengthen the structural stability of repaired wall.
Step 4 is discussed in detail.
The wall of gas pipe 1 by the oblique top of section wall 3 of the coal gas pipe protection wall and air channel insertion is with entirety Pouring type, which is subject to reparation, to be included:The oblique top of section wall 3 of coal gas pipe protection wall and the wall of gas pipe 1 of the insertion of air channel 8 Body is repaired in the way of integrated poured gravity flow pouring material, constructed between air channel 8 and gas pipe 1 together with it is closely knit whole Body wall.
The one-piece casting mode is completed using pumping casting construction method so that the intensity and efficiency of construction are obtained for It is effective to improve.
In order to become apparent from introducing the embodiment of the present invention, introduced below from the application method of the embodiment of the present invention.
Before reparation, to the wall position do not collapsed between air channel 8 and gas pipe 1 according to being convenient for constructing and prevent The principle of shield is targetedly reinforced, and prevents furnace wall is secondary from collapsing, and uses the instruments such as channel-section steel, angle bar with the position that will not cave in Support.Segmentation is taken to be poured using gravity flow the damaged location wall of the oblique section wall 3 of burner coal gas pipe protection wall and its above The integrated poured mode of material feeding 7 is repaired, the construction method of the pumping perfusion self-flowing material of use so that the intensity and effect of construction Rate is obtained for effective improvement.Pour into a mould before the oblique section wall 3 of burner coal gas pipe protection wall, in the oblique section of coal gas pipe protection wall 200mm is spaced on the former cast bed of material 2 of the behind of wall 3, expansion bolt is installed, and the anchoring for the length 150mm that burn-ons on bolt Hook 4, keeps the globality of castable, the connection of the enhancing cast bed of material and old wall, because old wall is castable, so needing Expansion bolt is first beaten to be used for welding anchoring hook.The final stage that the oblique section wall 3 of coal gas pipe protection wall is poured into a mould, in coal gas pipe protection The oblique top surface of section wall 3 of wall reserves 50mm × 50mm groove 5, and fixation is played in the cast for lower step, in wall seam crossing Tortuous reciprocal labyrinth-like seam is formd, makes sealing effectiveness more preferably, can effectively prevent from collaborating between air channel 8 and gas pipe 1. Build the reinforcing done before the replacement repairing construction of supporting brick post 6 by laying bricks or stones in the top surface for the oblique section wall 3 of coal gas pipe protection wall being cured Support, meanwhile, these supporting brick posts as anchored brick or " reinforcement " stay in then with gravity flow pouring material 7 done it is integrated poured In wall, to strengthen the structural stability of repaired wall.By the oblique top of section wall 3 of coal gas pipe protection wall and air channel 8 The wall of gas pipe 1 of insertion is repaired in integrated poured mode, the construction method of the pumping perfusion self-flowing material of use so that apply The intensity and efficiency of work are obtained for effective improvement.
It should be noted last that, above embodiment is merely illustrative of the technical solution of the present invention and unrestricted, Although the present invention is described in detail with reference to example, it will be understood by those within the art that, can be to the present invention Technical scheme modify or equivalent substitution, without departing from the spirit and scope of technical solution of the present invention, it all should cover Among scope of the presently claimed invention.

Claims (8)

1. the processing method that the wall between a kind of air channel and gas pipe is damaged, the wall body structure includes:Coal gas pipe protection The oblique section wall (3) of wall and the former cast bed of material (2), the oblique section wall (3) of coal gas pipe protection wall connect with the gas pipe (1) Connect, the former cast bed of material (2) is connected with the oblique section wall of the coal gas pipe protection wall (3) and gas pipe (1);Its feature exists In the treating method comprises following steps:
To the wall position do not collapsed between air channel (8) and gas pipe (1) according to the principle for being convenient for constructing and protecting Targetedly reinforced;
The oblique section wall (3) of coal gas pipe protection wall is repaired by way of one-piece casting;
Top surface after oblique section wall (3) solidification of the coal gas pipe protection wall builds supporting brick post (6) by laying bricks or stones;
Gas pipe (1) wall above the oblique section wall (3) of the coal gas pipe protection wall with air channel (8) insertion is poured with overall Note mode is repaired.
2. processing method according to claim 1, it is characterised in that described that gas pipe is repaired by way of one-piece casting The oblique section wall (3) of wall is protected, including:
The damaged location wall of the oblique section wall (3) of coal gas pipe protection wall and its above takes segmentation to use gravity flow pouring material (7) integrated poured mode is repaired.
3. processing method according to claim 2, it is characterised in that
The final stage of oblique section wall (3) cast of coal gas pipe protection wall, in the oblique section wall of the coal gas pipe protection wall (3) top surface reserves groove (5).
4. processing method according to claim 2, it is characterised in that methods described also includes:
Before the oblique section wall (3) of coal gas pipe protection wall is poured into a mould, in the oblique section wall (3) of the coal gas pipe protection wall behind The former cast bed of material (2) on interval expansion bolt is installed.
5. processing method according to claim 4, it is characterised in that
Anchoring hook (4) is fixed with the expansion bolt.
6. processing method according to claim 1, it is characterised in that described in the oblique section wall of the coal gas pipe protection wall (3) top surface after solidifying builds supporting brick post (6) by laying bricks or stones, including:
The supporting brick post (6) is stayed in integrated poured wall as anchored brick or " reinforcement ".
7. processing method according to claim 1, it is characterised in that described by the oblique section wall of the coal gas pipe protection wall (3) top and gas pipe (1) wall of air channel insertion are repaired in integrated poured mode, including:
Gas pipe (1) wall above the oblique section wall (3) of coal gas pipe protection wall with air channel (8) insertion is with integrated poured The mode of gravity flow pouring material is repaired.
8. processing method according to claim 1, it is characterised in that:
The one-piece casting mode is completed using pumping casting construction method.
CN201510766228.6A 2015-11-11 2015-11-11 The processing method that wall between a kind of air channel and gas pipe is damaged Active CN105331760B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510766228.6A CN105331760B (en) 2015-11-11 2015-11-11 The processing method that wall between a kind of air channel and gas pipe is damaged

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510766228.6A CN105331760B (en) 2015-11-11 2015-11-11 The processing method that wall between a kind of air channel and gas pipe is damaged

Publications (2)

Publication Number Publication Date
CN105331760A CN105331760A (en) 2016-02-17
CN105331760B true CN105331760B (en) 2017-08-29

Family

ID=55282520

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510766228.6A Active CN105331760B (en) 2015-11-11 2015-11-11 The processing method that wall between a kind of air channel and gas pipe is damaged

Country Status (1)

Country Link
CN (1) CN105331760B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109825658B (en) * 2019-02-28 2020-10-16 中国十九冶集团有限公司 Method for treating air leakage of hot blast stove bottom plate

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104894320A (en) * 2015-05-08 2015-09-09 北京首钢股份有限公司 Gas channel of hot-blast stove

Also Published As

Publication number Publication date
CN105331760A (en) 2016-02-17

Similar Documents

Publication Publication Date Title
WO2020244676A1 (en) Steel reinforcement cage for use in ventilation shaft diaphragm wall, and usage method
CN108547643B (en) A kind of construction method encircleed for handling tunnel top large size cavity solution cavity shield
CN105545342B (en) The smoke shaft and its construction method of existing trimmed tunnel internal arch part
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
CN103276130B (en) Maintenance method for air leakage from pipeline of hot-air system of blast furnace
CN204174222U (en) The repair structure of iron-making heat wind furnace hot air duct and repairing mould thereof
CN108789815A (en) A kind of manufacturing method of shield prefabricated reinforced concrete section of jurisdiction
CN104790302A (en) Hanging-basket and bent-cap-support matched integral construction method for side span linear segment of high-pier continuous rigid frame bridge
CN106498844A (en) A kind of high speed railway box beam bridge floor pre-fabricated electric cables groove
CN108360380A (en) A kind of bridge pier column construction operation platform and its construction method
CN106958313A (en) Floor closed system and its construction method are poured after a kind of pipe well
CN109457551A (en) Group frame type connection reinforcing structure and construction method between sleeper block and railway roadbed
CN105973082B (en) The bore distribution method of reinforced concrete brace demolition blasting in a kind of foundation ditch
CN105331760B (en) The processing method that wall between a kind of air channel and gas pipe is damaged
CN103161474B (en) Construction method of down hole interchange roadway
CN108843346A (en) Lining construction method of the large section shallow-depth-excavation tunnel in water-rich sand layer
CN105862912B (en) A kind of agent on crack resistance of concrete sliding pile panelling construction method
CN105951891A (en) Concrete engineering deformation seam perpendicular water stopping cavity die with protrusions and reinforced fibers
CN109825658A (en) The method that processing hot wind drop-bottom leaks out
JP2007063895A (en) Construction method for side wall of underground tank
CN105804448A (en) Vertical prefabricating construction method of cooling tower herringbone column
CN104674796B (en) The template system and its construction method of a kind of buried shelter bored concrete pile
CN205576199U (en) Exhaust -heat boiler cast iron type feed opening water cooling plant
CN102134621A (en) Blast furnace iron notch patching method
CN109372522B (en) Construction method of complex overlapping tunnel for urban rail transit

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant