CN105305504B - Transmission cross-section limit method for solving based on equal and opposite quantities in pairs adjusting method - Google Patents

Transmission cross-section limit method for solving based on equal and opposite quantities in pairs adjusting method Download PDF

Info

Publication number
CN105305504B
CN105305504B CN201510856649.8A CN201510856649A CN105305504B CN 105305504 B CN105305504 B CN 105305504B CN 201510856649 A CN201510856649 A CN 201510856649A CN 105305504 B CN105305504 B CN 105305504B
Authority
CN
China
Prior art keywords
branch road
unit
branch
mrow
power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510856649.8A
Other languages
Chinese (zh)
Other versions
CN105305504A (en
Inventor
毛安家
裴子霞
王婷婷
宋颖巍
沈方
刘岩
吴卓航
侯玉琤
商文颖
李华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
North China Electric Power University
Economic and Technological Research Institute of State Grid Liaoning Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
North China Electric Power University
Economic and Technological Research Institute of State Grid Liaoning Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, North China Electric Power University, Economic and Technological Research Institute of State Grid Liaoning Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510856649.8A priority Critical patent/CN105305504B/en
Publication of CN105305504A publication Critical patent/CN105305504A/en
Application granted granted Critical
Publication of CN105305504B publication Critical patent/CN105305504B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention belongs to Power System and its Automation technical field, and in particular to a kind of transmission cross-section limit method for solving based on equal and opposite quantities in pairs adjusting method.Characterized in that, first under normal operating mode, a kind of typical load pattern is taken, forms ground state trend initial data;The maximum operation branch road of active power is found out, disconnects its power flow transfer of the branch road to other branch roads;The most easily out-of-limit branch road found out in other branch roads;Calculating is sent by sensitivity of each unit to most easily out-of-limit branch road in end regions, is calculated adjustment amount and is reversely adjusted to branch road l after most easily out-of-limit branch road overload, overloadeNonoverload;Calculate now all Branch Power Flow summations, as maximum transfer power.All controllable units are ranked up by the present invention according to level of sensitivity, select sensitivity maximum during each pairing adjustment and minimum unit is matched, as a result more rationally reliable independent of balancing machine during adjustment.

Description

Transmission cross-section limit method for solving based on equal and opposite quantities in pairs adjusting method
Technical field
The invention belongs to Power System and its Automation technical field, and in particular to one kind is adjusted based on equal and opposite quantities in pairs The transmission cross-section limit method for solving of method.
Background technology
Modern interconnected network is in large scale and complicated, and strong and weak different, the conveying energy of part circuit is contacted between net Power is inevitably restricted by the hot steady limit or the dynamic steady limit, is calculated for convenience of analysis and operational management, operations staff are led to The contact section often power network being divided between some subsystems and system.The transmission of electricity limit of each contact section is grasped exactly, can On the premise of safe operation of power system is ensured, farthest to meet the workload demand of all subregion.
The analysis of power transmitting capability and calculate all be all the time power system research important subject, existing meter Calculation method is broadly divided into two classes:Deterministic Methods and probabilistic approach.Deterministic Methods mainly have direct solving method, repeated power flow Method, Continuation Method, optimal load flow method, wherein, direct solving method causes circuit overload directly to increase interregional power, Cut down survey region by half again and exchange power, its algorithm is simple but precision is not high, it is difficult to meets practical application request, rear several sides Although method improves accuracy, but needed because solution procedure includes equation parameter, nonlinear equation processing and calculating process Iteration etc. is wanted, causes calculating speed excessively slow, it is actual engineering can not to be applied to;Probabilistic approach mainly has stochastic programming, enumerated Method and Monte Carlo Analogue Method etc., although these methods effectively meter and various uncertain factors, because it is dependent on a large amount of Stochastic production sample, the calculating of large-scale power grid can not be adapted to.
The content of the invention
To solve the above problems, the invention discloses a kind of transmission cross-section Solving Limit based on equal and opposite quantities in pairs adjusting method Solution method, is concretely comprised the following steps:
Step 1 takes a kind of typical load pattern under normal operating mode, forms ground state trend initial data:J-th strip branch Road ljActive power be Pj, ljMaximum allowable power beJ=1,2 ...;
Step 2 finds out the maximum operation branch road of active power, is set to lk, disconnected branches lkThen equivalent to generation most serious event Barrier, its power flow transfer is to other branch roads, in lkBranch road l in the state of disconnectionjActive power beNow all branch roads are not Overload;
The most easily out-of-limit branch road that step 3 is found out in other branch roads, i.e. disconnected branches lkOther front and rear each branch roads have The difference of work(powerMinimum branch road, is set to branch road le, then branch road leRequired adjustment amount is Δ Pe
Step 4 is calculated and sent by each unit in end regions to branch road leSensitivity, and by sensitivity descending arrangement form join Adjustment form is examined, sensitivity identical is matched somebody with somebody the first unit and last position unit according to the variable capacity descending sort of unit Pair and adjustment, ith pairing adjustment amount be Δ Pi,
In formula, Se1For the sensitivity of the first unit, SemFor the sensitivity of last position unit,For the maximum of the first unit Output limit value,For the EIAJ limit value of last position unit;
Step 5 judges present branch leAdjustment amountWhether Δ P is exceedede, wherein n is that present branch has matched The logarithm of unit, if the branch road l not less than ifeDo not overload, the first unit reaches with the power that there must be a unit in last position unit Limit value, it is removed from sequencing table, and continue again to be matched new the first unit and last position unit, return to step 4; If the branch road l more than ifeIt has been overloaded that, present branch leAdjustment amount Δ P will reduce Δ PiTo branch road leNonoverload;
Step 6 calculates now all Branch Power Flow summations, as maximum transfer power.
Beneficial effect:
The present invention proposes that a kind of improved equal and opposite quantities in pairs adjusting method applies to solve maximum transfer power.According to sensitive All controllable units are ranked up by degree size, and each pairing selects sensitivity maximum when adjusting and minimum unit is matched, It is as a result more rationally reliable independent of balancing machine during adjustment.
Brief description of the drawings
Fig. 1 is the flow chart of the method for the invention;
Fig. 2 is the reference adjustment sequence list in the present invention;
Fig. 3 is IEEE39 nodes modular system wiring diagram in the embodiment of the present invention;
In figure:M is all units sum.
Embodiment
With reference to Figure of description and one group of specific embodiment, the present invention will be further described.
Fig. 1 is the flow chart of the method for the invention.The present invention's concretely comprises the following steps:
Step 1 takes a kind of typical load pattern under normal operating mode, forms ground state trend initial data:J-th strip branch Road ljActive power be Pj, ljMaximum allowable power beJ=1,2 ...;
Step 2 finds out the maximum operation branch road of active power, is set to lk, disconnected branches lkThen equivalent to generation most serious event Barrier, its power flow transfer is to other branch roads, in lkBranch road l in the state of disconnectionjActive power beNow all branch roads are not Overload;
The most easily out-of-limit branch road that step 3 is found out in other branch roads, i.e. disconnected branches lkOther front and rear each branch roads have The difference of work(powerMinimum branch road, is set to branch road le, then branch road leRequired adjustment amount is Δ Pe
Step 4 is calculated and sent by each unit in end regions to branch road leSensitivity, and by sensitivity descending arrangement form join Adjustment form is examined, sensitivity identical is matched somebody with somebody the first unit and last position unit according to the variable capacity descending sort of unit Pair and adjustment, ith pairing adjustment amount be Δ Pi,
In formula, Se1For the sensitivity of the first unit, SemFor the sensitivity of last position unit,For the maximum of the first unit Output limit value,For the EIAJ limit value of last position unit;
Step 5 judges present branch leAdjustment amountWhether Δ P is exceedede, wherein n is that present branch has matched The logarithm of unit, if the branch road l not less than ifeDo not overload, the first unit reaches with the power that there must be a unit in last position unit Limit value, it is removed from sequencing table, and continue again to be matched new the first unit and last position unit, return to step 4; If the branch road l more than ifeIt has been overloaded that, present branch leAdjustment amount Δ P will reduce Δ PiTo branch road leNonoverload;
Step 6 calculates now all Branch Power Flow summations, as maximum transfer power.
Equal and opposite quantities in pairs method is a kind of method based on sensitivity, and its implication is:When adjusting system active power, it is The node that the node that each increase is contributed finds a reduction output is paired, and vice versa;The node of pairing is active The plus-minus amount of power is equal.In this way, the unbalanced power brought during conventional sensitivity class method adjustment unit output can be avoided All undertaken by balancing machine, cause to balance the out-of-limit situation of acc power.Meanwhile in engineering in practice in the absence of the general of balancing machine Read, be only concerned the plus-minus output situation of specific unit during adjustment during scheduling, and system power balances after ensureing adjustment, therefore reversely Equivalent matched pair technique meets the scheduling rule of engineering in practice, and once adjusts a pair of nodes, can improve the efficiency of algorithm.
All controllable units are ranked up according to level of sensitivity, each pairing selects sensitivity maximum when adjusting and minimum Unit matched, it is as a result more rationally reliable independent of balancing machine during adjustment.Detailed process is as follows:
If the active power that branch road l need to be adjusted is Δ Pl, active controllable unit number is m, according to its spirit to branch road road l Sensitivity carries out descending order arrangement, forms reference adjustment sequence list as shown in Figure 2, and the big one end of sensitivity is head end, The other end is end, is ranked up when sensitivity is identical according to the variable capacity of unit.
It is one group that the first unit and last position unit are selected during pairing.The first unit sensitivity is Sl1, increase output, last position machine Group sensitivity is Slm, reduce and contribute, two units plus-minus power generating value is equal, then the first unit is to branch road l sensibility in practice:
S′l1=Sl1-Slm (1)
S′l1> 0, above formula can be seen that S 'l1Size and balancing machine selection it is not related.
The adjustment amount of unit is:
And in real system, the minimax output limit value of unit is once considered as during pairing adjustment process adjusting, therefore, Actual adjustment amount is the minimum value in following three:
Obtain Δ PiAfterwards, the active power that need to be adjusted is corrected, if once pairing adjustment fails to meet to require, the first unit Or must there is a power of the assembling unit to reach limit value in last position unit, it is removed from sequencing table, and continues new the first machine Group with last position unit match and adjust again, until branch road l adjustment amount meet demand.
Using IEEE39 nodes modular system as research example, model and computational methods above are verified and analyzed. The system includes 39 nodes, 10 generators, 12 transformers, and 34 circuits can be divided into 3 regions, and balance nodes are Bus31.Reference voltage is 100kV, reference power 100MVA.System wiring figure and region division such as Fig. 3.
Region 1 is that region 3 is feeding section, region 1 and area by electric region it can be seen from ground state trend operation result The discontinuity surface of domain 3 includes 3 transmission lines of electricity, respectively Bus16-19, Bus21-22, Bus16-24, zoning 1 to region 3 Maximum transfer power.Power flow simulation adjustment is carried out using BPA.
The branch road Bus21-22 that trend is maximum under the basic method of operation is disconnected, its active power is transferred to other two branch Road.Ground state trend and section tidal current after disconnected branches Bus21-22 are as shown in table 1 below:
Table 1
As can be seen from Table 1, branch road Bus16-19 is most easily out-of-limit branch road, Δ P16-19=45.4MW.Calculate adjustable machine Sensitivity of the group to Bus16-19 and by descending arrangement form with reference to adjustment table, it is as shown in table 2 below.
Table 2
The maximum B of Unit us34 of sensitivity it can be seen from upper table 2, the minimum unit of sensitivity is Bus38, therefore the The unit for once carrying out reversely pairing adjustment is Bus34 and Bus38.Increase node Bus34 output, its variable capacity is 102MW, node Bus38 output being reduced, its variable capacity is 830MW, and the adjustment amount calculated according to formula (7) is 48.5561MW, It is 48.5561MW that formula (8), which obtains final adjustment amount,.After adjusting for the first time, branch road Bus16-19 active is 501.7MW, out-of-limit.Machine Group equal and opposite quantities in pairs adjustment result is as shown in table 3 below.
Table 3
According to above-mentioned calculating process, Δ P=2MW is set, continues equal and opposite quantities in pairs adjustment, but purpose is so that branch Road Bus16-19 is not again out-of-limit, and now the active sum of branch road is maximum transfer power.The active tide of branch road after second of adjustment Stream is as shown in below table 4.
Table 4
As can be seen from Table 4, the maximum transfer power in region 1 to region 3 is 1189.3MW.Regional internet has become electricity The inexorable trend of Force system development, turns into that to influence bulk power grid development important between Power System Interconnection rear region the problem of electrical grid transmission ability Factor.Can be rapidly and accurately to maximum transfer power under N-1 Static Security Constraints with equal and opposite quantities in pairs adjusting method is improved The problem of solved, the fast and accurately feature of this method can apply to engineering in practice.

Claims (1)

1. a kind of transmission cross-section limit method for solving based on equal and opposite quantities in pairs adjusting method, it is characterised in that concretely comprise the following steps:
Step 1 takes a kind of typical load pattern under normal operating mode, forms ground state trend initial data:J-th strip branch road lj Active power be Pj, ljMaximum allowable power beJ=1,2 ...;
Step 2 finds out the maximum operation branch road of active power, is set to lk, disconnected branches lkThen equivalent to occur most serious failure, its Power flow transfer is to other branch roads, in lkBranch road l in the state of disconnectionjActive power beThe now equal nonoverload of all branch roads;
The most easily out-of-limit branch road that step 3 is found out in other branch roads, i.e. disconnected branches lkThe active power of other front and rear each branch roads DifferenceMinimum branch road, is set to branch road le, then branch road leRequired adjustment amount is Δ Pe
Step 4 is calculated and sent by each unit in end regions to branch road leSensitivity, and by sensitivity descending arrangement form with reference to adjustment The first unit and last position unit are matched and adjusted according to the variable capacity descending sort of unit by form, sensitivity identical Whole, the adjustment amount of ith pairing is Δ Pi,
<mrow> <msub> <mi>&amp;Delta;P</mi> <mi>i</mi> </msub> <mo>=</mo> <mi>min</mi> <mo>{</mo> <mfrac> <mrow> <msub> <mi>&amp;Delta;P</mi> <mi>e</mi> </msub> </mrow> <mrow> <msub> <mi>S</mi> <mrow> <mi>e</mi> <mn>1</mn> </mrow> </msub> <mo>-</mo> <msub> <mi>S</mi> <mrow> <mi>e</mi> <mi>m</mi> </mrow> </msub> </mrow> </mfrac> <mo>,</mo> <msubsup> <mi>&amp;Delta;P</mi> <mn>1</mn> <mi>max</mi> </msubsup> <mo>,</mo> <msubsup> <mi>&amp;Delta;P</mi> <mi>m</mi> <mrow> <mi>m</mi> <mi>a</mi> <mi>x</mi> </mrow> </msubsup> <mo>}</mo> <mo>,</mo> </mrow>
In formula, Se1For the sensitivity of the first unit, SemFor the sensitivity of last position unit, Δ P1 maxFor the EIAJ of the first unit Limit value,For the EIAJ limit value of last position unit;
Step 5 judges present branch leAdjustment amountWhether Δ P is exceedede, wherein n is that present branch has matched unit Logarithm, if the branch road l not less than ifeNot overloading, the first unit reaches limit value with the power that must have a unit in last position unit, It is removed from sequencing table, and continues again to be matched new the first unit and last position unit, return to step 4;It is if super Cross then branch road leIt has been overloaded that, present branch leAdjustment amount Δ P will reduce Δ PiTo branch road leNonoverload so that branch road leTrend weight It is new not out-of-limit;
Step 6 calculates now all Branch Power Flow summations, as maximum transfer power.
CN201510856649.8A 2015-11-30 2015-11-30 Transmission cross-section limit method for solving based on equal and opposite quantities in pairs adjusting method Expired - Fee Related CN105305504B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510856649.8A CN105305504B (en) 2015-11-30 2015-11-30 Transmission cross-section limit method for solving based on equal and opposite quantities in pairs adjusting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510856649.8A CN105305504B (en) 2015-11-30 2015-11-30 Transmission cross-section limit method for solving based on equal and opposite quantities in pairs adjusting method

Publications (2)

Publication Number Publication Date
CN105305504A CN105305504A (en) 2016-02-03
CN105305504B true CN105305504B (en) 2018-01-23

Family

ID=55202431

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510856649.8A Expired - Fee Related CN105305504B (en) 2015-11-30 2015-11-30 Transmission cross-section limit method for solving based on equal and opposite quantities in pairs adjusting method

Country Status (1)

Country Link
CN (1) CN105305504B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107294103B (en) * 2017-07-24 2020-01-14 广东工业大学 Section flow control method and device

Also Published As

Publication number Publication date
CN105305504A (en) 2016-02-03

Similar Documents

Publication Publication Date Title
CN103311926B (en) Power system cascading failure simulation method based on unified power flow controller
CN106655177B (en) Distributed generation resource maximum access capability calculation method based on extension Second-order cone programming
CN108023364B (en) Power distribution network distributed generation resource maximum access capability calculation method based on convex difference planning
CN101882167A (en) Wind power station equivalent modeling method of large-scale wind power concentration access power grid
CN107221945A (en) A kind of UHVDC Transmission Lines forecast failure aid decision-making method and device
CN102403716A (en) Dynamic equalizing method for multi-infeed alternating/direct-current power grid
Tanti et al. Optimal placement of custom power devices in power system network to mitigate voltage sag under faults
Beigvand et al. Voltage stability analysis in radial smart distribution grids
Xia et al. Enhanced particle swarm optimisation applied for transient angle and voltage constrained discrete optimal power flow with flexible AC transmission system
Dixit et al. Optimal placement of SVC for minimizing power loss and improving voltage profile using GA
CN107425527A (en) A kind of THE UPFC static security prevention and control method
Vural Interior point‐based slack‐bus free‐power flow solution for balanced islanded microgrids
CN105305504B (en) Transmission cross-section limit method for solving based on equal and opposite quantities in pairs adjusting method
CN103280797A (en) Day-ahead static security correction method
Zhang et al. Impact of dynamic load models on transient stability-constrained optimal power flow
Venkatesh et al. Investigations on hybrid line stability ranking index with polynomial load modeling for power system security
Hussein et al. Employment of PSO algorithm to improve the neural network technique for radial distribution system state estimation
Avudayappan et al. Congestion management in deregulated power system using hybrid cat-firefly algorithm with TCSC and SVC FACTS devices
CN115940157A (en) Method, device and equipment for automatically generating load flow scene of stability control strategy checking task
Yang et al. Optimal usage of transmission capacity with FACTS devices in the presence of wind generation: A two-stage approach
Adebayo et al. Static voltage stability enhancement using FACTS controller
CN102420426B (en) Power grid partial loss reduction method based on injection power sensitivity
Muthulakshmi et al. The proper location and sizing of multiple distributed generators for maximizing voltage stability using PSO
CN111211581B (en) Method and device for determining new energy acceptance capacity in power system
CN103280841A (en) On-grid point confirmation method for intermittent energy sources

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180123

Termination date: 20201130