CN105271017A - Walking board connecting mechanism of tower crane - Google Patents

Walking board connecting mechanism of tower crane Download PDF

Info

Publication number
CN105271017A
CN105271017A CN201510639545.1A CN201510639545A CN105271017A CN 105271017 A CN105271017 A CN 105271017A CN 201510639545 A CN201510639545 A CN 201510639545A CN 105271017 A CN105271017 A CN 105271017A
Authority
CN
China
Prior art keywords
stage
walking
walking board
tower crane
connecting mechanism
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510639545.1A
Other languages
Chinese (zh)
Inventor
王建军
米成宏
申凤梅
朱斌
刘振
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou Construction Machinery Group Co Ltd XCMG
Original Assignee
Xuzhou Construction Machinery Group Co Ltd XCMG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuzhou Construction Machinery Group Co Ltd XCMG filed Critical Xuzhou Construction Machinery Group Co Ltd XCMG
Priority to CN201510639545.1A priority Critical patent/CN105271017A/en
Publication of CN105271017A publication Critical patent/CN105271017A/en
Pending legal-status Critical Current

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

The invention discloses a walking board connecting mechanism of a tower crane. The walking board connecting mechanism comprises a pair of lugs (1) welded to a crane upper support main structure (4), and installing shafts (2) welded to the two sides of a walking board stand column (3). The walking board stand column (3) is fixed into the lugs (1) on the crane upper support main structure (4) through the installing shafts (2). According to the walking board connecting mechanism of the tower crane, the lugs are welded to the upper support main structure, and the walking board stand column is hung in a connecting mechanism in clamping grooves of the lugs. The walking board connecting mechanism is simple in structure, low in cost, convenient to install, firm and stable. Usage of pin shafts is avoided, the coaxial precision of the pin shafts does not need to be guaranteed, the installing difficulty is lowered, and the installing efficiency is improved.

Description

A kind of tower crane is walked on stage bindiny mechanism
Technical field
The present invention relates to a kind of tower crane to walk on stage, specifically a kind of tower crane is walked on stage bindiny mechanism.
Background technology
Along with increasing of flat-top tower tower machine type, the scantling of structure of each parts of tower machine also increases thereupon, causes each parts of tower machine difficulty in the process of dismounting to increase.In existing structure, the upper bracket of tower crane adopts double-pin shaft type mostly with walking on stage to be connected, and this version is widely used in the swing type mechanism of tower machine, in, application in large tower machine is also more common.But for superhuge tower machine, this structure can bring very large difficulty to installation: 1, because ultra-large type tower machine block construction size is comparatively large, need squeeze into bearing pin at upper bracket and junction of walking on stage during installation, assembly difficulty is large, efficiency is low, higher to the requirement on machining accuracy of bearing pin; 2, in the actual course of processing, the right alignment of pin shaft hole is often difficult to ensure, because bearing pin and pin-and-hole exist Mismachining tolerance during installation, causes bearing pin to be installed very difficult, affects efficiency of installing software to a great extent.
Summary of the invention
For above-mentioned prior art Problems existing, the invention provides a kind of tower crane and to walk on stage bindiny mechanism, structure is simple, with low cost, it is convenient to install, and firm stable avoids the use of bearing pin, without the need to ensureing the coaxial precision of bearing pin, reducing installation difficulty, improving installation effectiveness.
To achieve these goals, this tower crane bindiny mechanism that walks on stage comprises the secondary hangers be welded in hoisting crane upper bracket main structure;
And be welded in the installation shaft of column both sides of walking on stage;
Described column of walking on stage is fixed in the hangers in described upper bracket main structure by installation shaft.
Further, column of walking on stage described in is mounted by installation shaft in the draw-in groove being fixed on and described hangers is offered.
Further, column lower end of walking on stage described in is fixedly connected with by jacking block one is corresponding with the jacking block two of described upper bracket main structure lower end.
Further, the installation shaft be linked in described draw-in groove is fixed by latch.
Compared with prior art, this tower crane walks on stage bindiny mechanism's employing at upper bracket main structure welding otic placode, column of walking on stage is mounted on the bindiny mechanism in otic placode draw-in groove, makes bindiny mechanism's structure of walking on stage simple, with low cost, it is convenient to install, firm stable, avoids the use of bearing pin, without the need to ensureing the coaxial precision of bearing pin, reduce installation difficulty, improve installation effectiveness.
Accompanying drawing explanation
Fig. 1 is front view of the present invention;
Fig. 2 is the birds-eye view of Fig. 1;
Fig. 3 is hanger structure schematic diagram of the present invention;
In figure: 1, hangers, 2, installation shaft, 3, column of walking on stage, 4, upper bracket main structure, 5, jacking block one, 6, latch, 7, jacking block two, 8, draw-in groove.
Detailed description of the invention
Below in conjunction with accompanying drawing, the present invention will be further described.
As depicted in figs. 1 and 2, this tower crane bindiny mechanism that walks on stage comprises the secondary hangers 1 be welded in hoisting crane upper bracket main structure 4;
And be welded in the installation shaft 2 of column 3 both sides of walking on stage;
Described column 3 of walking on stage is fixed in the hangers 1 in described upper bracket main structure 4 by installation shaft 2.
Further, column 3 of walking on stage described in is mounted by installation shaft 2 in the draw-in groove 8 being fixed on and described hangers 1 is offered.By the effect of draw-in groove 8, when mounted, due to Action of Gravity Field, it is interior and automatically sagging that installation shaft 2 can slip into draw-in groove 8 automatically, make use of the effect of gravity dexterously, and save manpower, cost of installation is low.
Further, column 3 lower end of walking on stage described in is fixedly connected with by jacking block 1 is corresponding with the jacking block 27 of described upper bracket main structure 4 lower end.The column 3 that makes to walk on stage well fits together with upper bracket main structure 4, avoiding walks on stage install after there is the phenomenon of inclination.
Further, the installation shaft 2 be linked in described draw-in groove 8 is fixed by latch 6.Effectively can prevent due to the work strenuous vibration platform that causes the up phenomenon that comes off of play.
This tower crane walks on stage bindiny mechanism when mounted, the installation shaft 2 of column 3 of walking on stage is put into the draw-in groove 8 of otic placode 1, due to Action of Gravity Field, it is interior and automatically sagging that installation shaft 2 can slip into draw-in groove 8 automatically, the tilt phenomenon occurred after installing in order to avoid walking on stage, be bolted on jacking block 27 corresponding to upper bracket main structure 4 lower end by the jacking block 1 of column 3 lower end of walking on stage, the column 3 that makes to walk on stage well fits together with upper bracket main structure 4, avoiding walks on stage install after there is the phenomenon of inclination.
After installation, the installation shaft 2 be linked in draw-in groove 8 loads latch 6, realizes fixation by latch 6, prevent because work strenuous vibration causes the platform up phenomenon that comes off of play.
When tearing machine open, upper end latch 6 and lower bolt are taken down, will walk on stage up to lift with car hosit and pull down.Not at use bearing pin in this structure installment process, installation aspect, make use of the effect of gravity dexterously, and install and save manpower, cost of installation is low.
In sum, this tower crane walks on stage bindiny mechanism's employing at upper bracket main structure welding otic placode, column of walking on stage is mounted on the bindiny mechanism in otic placode draw-in groove, makes bindiny mechanism's structure of walking on stage simple, with low cost, it is convenient to install, firm stable, avoids the use of bearing pin, without the need to ensureing the coaxial precision of bearing pin, reduce installation difficulty, improve installation effectiveness.

Claims (4)

1. tower crane is walked on stage a bindiny mechanism, it is characterized in that,
Comprise the secondary hangers (1) be welded in hoisting crane upper bracket main structure (4);
And be welded in the installation shaft (2) of column of walking on stage (3) both sides;
Described column of walking on stage (3) is fixed in the hangers (1) on described upper bracket main structure (4) by installation shaft (2).
2. a kind of tower crane according to claim 1 is walked on stage bindiny mechanism, it is characterized in that,
Described column of walking on stage (3) is mounted by installation shaft (2) in the draw-in groove (8) being fixed on and described hangers (1) is offered.
3. a kind of tower crane according to claim 1 and 2 is walked on stage bindiny mechanism, it is characterized in that,
Described column of walking on stage (3) lower end is fixedly connected with by jacking block one (5) is corresponding with the jacking block two (7) of described upper bracket main structure (4) lower end.
4. a kind of tower crane according to claim 2 is walked on stage bindiny mechanism, it is characterized in that,
The installation shaft (2) be linked in described draw-in groove (8) is fixed by latch (6).
CN201510639545.1A 2015-09-30 2015-09-30 Walking board connecting mechanism of tower crane Pending CN105271017A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510639545.1A CN105271017A (en) 2015-09-30 2015-09-30 Walking board connecting mechanism of tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510639545.1A CN105271017A (en) 2015-09-30 2015-09-30 Walking board connecting mechanism of tower crane

Publications (1)

Publication Number Publication Date
CN105271017A true CN105271017A (en) 2016-01-27

Family

ID=55140969

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510639545.1A Pending CN105271017A (en) 2015-09-30 2015-09-30 Walking board connecting mechanism of tower crane

Country Status (1)

Country Link
CN (1) CN105271017A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112279118A (en) * 2020-10-29 2021-01-29 江麓机电集团有限公司 Tower crane fast mounting and dismounting platform connecting device

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1643427A1 (en) * 1988-12-22 1991-04-23 Специальное Конструкторско-Технологическое Бюро По Механизации Монтажно-Строительных Работ И Запасным Частям "Стройдормаш" Detachable connection of tower crane sections
CN101428738A (en) * 2008-12-05 2009-05-13 沈阳建筑大学 Stacker crane body node-pin shaft connection mode and connection pin shaft
CN201325825Y (en) * 2008-12-12 2009-10-14 上海三一科技有限公司 Connecting structure of crane operating cab and main platform
CN203222434U (en) * 2013-04-18 2013-10-02 云南冶金昆明重工有限公司 Articulation device of flat-top tower crane
CN203582327U (en) * 2013-11-21 2014-05-07 中联重科股份有限公司 Connecting structure of cab platform and upper support and tower crane
CN204237469U (en) * 2014-10-31 2015-04-01 徐州建机工程机械有限公司 The connection structure of tower machine driver's cab platform and upper bracket
CN205151588U (en) * 2015-09-30 2016-04-13 徐州建机工程机械有限公司 Tower crane coupling mechanism that walks on stage

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1643427A1 (en) * 1988-12-22 1991-04-23 Специальное Конструкторско-Технологическое Бюро По Механизации Монтажно-Строительных Работ И Запасным Частям "Стройдормаш" Detachable connection of tower crane sections
CN101428738A (en) * 2008-12-05 2009-05-13 沈阳建筑大学 Stacker crane body node-pin shaft connection mode and connection pin shaft
CN201325825Y (en) * 2008-12-12 2009-10-14 上海三一科技有限公司 Connecting structure of crane operating cab and main platform
CN203222434U (en) * 2013-04-18 2013-10-02 云南冶金昆明重工有限公司 Articulation device of flat-top tower crane
CN203582327U (en) * 2013-11-21 2014-05-07 中联重科股份有限公司 Connecting structure of cab platform and upper support and tower crane
CN204237469U (en) * 2014-10-31 2015-04-01 徐州建机工程机械有限公司 The connection structure of tower machine driver's cab platform and upper bracket
CN205151588U (en) * 2015-09-30 2016-04-13 徐州建机工程机械有限公司 Tower crane coupling mechanism that walks on stage

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112279118A (en) * 2020-10-29 2021-01-29 江麓机电集团有限公司 Tower crane fast mounting and dismounting platform connecting device

Similar Documents

Publication Publication Date Title
CN102790481B (en) Dismounting device for rotor of water supply pump motor
CN201778663U (en) Rotary drilling dig and guide pulley yoke thereof
CN205377227U (en) A device of pegging graft fast for bus duct
CN205151588U (en) Tower crane coupling mechanism that walks on stage
CN105271017A (en) Walking board connecting mechanism of tower crane
CN104836161A (en) Hanger frame of fixed-steering pulley
CN204675726U (en) Purlin lifting auxiliary device
CN205132943U (en) Ready -package cab platform structure
CN204237469U (en) The connection structure of tower machine driver's cab platform and upper bracket
CN105006924A (en) Motor core-through device and core-through method thereof
CN201230165Y (en) Live operation conductive wire amending sliding flat stair
CN106284960A (en) Simple attachment type raise scaffold
CN203143945U (en) Crane trolley
CN202202557U (en) Novel horizontal truss attached to lifting scaffold
CN205046848U (en) Gate -type steel sheet mould holder
CN205178966U (en) Solar cell panel frame joint structure
CN202016804U (en) Hinge for installation of crane
CN207293997U (en) A kind of chassis suitable for ultra-large type derrick crane
CN203081313U (en) Drill floor widening footboard
CN201300912Y (en) Limiting device for assembling and disassembling crawler frame
CN205739892U (en) A kind of lower beam assembly of elevator
CN107780644B (en) Operation platform for elevator shaft construction and use method thereof
CN205367538U (en) Swing crane and A cabinet frame thereof
CN205591540U (en) Bayonet socket support
CN210286556U (en) Crane underframe with rear lying leg

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160127