CN105257288A - Method for determining tight reservoir original reservoir pressure based on injection pressure decline well testing technology - Google Patents

Method for determining tight reservoir original reservoir pressure based on injection pressure decline well testing technology Download PDF

Info

Publication number
CN105257288A
CN105257288A CN201510784512.6A CN201510784512A CN105257288A CN 105257288 A CN105257288 A CN 105257288A CN 201510784512 A CN201510784512 A CN 201510784512A CN 105257288 A CN105257288 A CN 105257288A
Authority
CN
China
Prior art keywords
pressure
reservoir
compact reservoir
original formation
injection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510784512.6A
Other languages
Chinese (zh)
Inventor
袁发勇
吉玉林
杨加祥
张国锋
张寅�
程建明
邹顺良
胡中桂
倪方杰
樊佳莉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Oilfield Service Corp
Sinopec Jianghan Petroleum Engineering Co Ltd
Original Assignee
Sinopec Oilfield Service Corp
Sinopec Jianghan Petroleum Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinopec Oilfield Service Corp, Sinopec Jianghan Petroleum Engineering Co Ltd filed Critical Sinopec Oilfield Service Corp
Priority to CN201510784512.6A priority Critical patent/CN105257288A/en
Publication of CN105257288A publication Critical patent/CN105257288A/en
Pending legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention provides a method for determining tight reservoir original reservoir pressure based on the injection pressure decline well testing technology. The method comprises the steps that liquid is injected into a reservoir according to the designed displacement before pressure cracking modification; downhole shut-in is performed, and shaft bottom data are recorded; the data are processed to obtain tight reservoir original reservoir pressure. The tight reservoir original reservoir pressure is determined in a downhole shut-in pressure measuring mode, the traditional well testing technology connotation is expanded, and tight reservoir original pressure features can be better reflected, and the better scientific bases are provided for knowing reservoir features, predicating single-well real capacity and guiding reasonable production allocation.

Description

Based on the method for injection pressure drop Well Test Technology determination compact reservoir original formation pressure
Technical field
The present invention relates to exploration of oil and gas field field, be specifically related to a kind of method based on injection pressure drop Well testing determination compact reservoir original formation pressure.
Background technology
Poor by reservoir permeability, yield poorly, the impact of the factor such as recovery time is long, conventional well-logging method is difficult to determine compact reservoir original formation pressure.Domestic large scale investment exploitation shale, Sandstone Gas Reservoir in recent years, the data that the strata pressure of its compact reservoir mainly obtains by carrying out wellhead shut-in after massive hydraulic fracture at present calculate.The strata pressure of compact reservoir can not represent reset pressure characteristic, and existing initial production capacity all adopts this pressure to predict, cannot reflect the true production capacity of reservoir.
Although industry is generally used by the method for injection pressure drop Well testing determination bed gas reservoir original formation pressure, test technology and analytical method are all ripe, and adopt wellhead shut-in pressure measurement mode, data quality is not high.
Summary of the invention
The object of the invention is to the deficiency overcoming the existence of above-mentioned technology, provide a kind of method based on injection pressure drop Well testing determination compact reservoir original formation pressure, the method comprises:
(1) liquid is injected to compact reservoir;
(2) downhole closing is carried out, admission shaft bottom data;
(3) injection and closing well data information are processed, obtain compact reservoir original formation pressure.
Do not carry out fracturing reform before the described compact reservoir of step (1) injects liquid, described liquid is smooth liquid.
Step (1) described injection is fluid operated to be carried out continuously with the described closing well operation of step (2).
The described data process of step (3) is mainly G-function drawdown analysis method, the straight line being specially initial point offsets downward along G-function differential of pressure curve, and original formation pressure is determined in the position overlapped with G-function differential of pressure curve, G-function pressure semilog derivative curve intersection point.
The present invention adopts injection pressure drop Well testing, by downhole closing pressure measurement mode determination compact reservoir original formation pressure, expand the intension of traditional Well Test Technology, compact reservoir reset pressure characteristic can be reflected preferably, for understanding reservoir characteristic, the prediction true production capacity of individual well and instructing rational proration to provide good scientific basis.
Accompanying drawing explanation
Fig. 1 is injection pressure drop Well testing ground of the present invention injection device operating diagram;
Fig. 2 is injection pressure drop Well testing downhole closing equipment schematic diagram of the present invention;
Fig. 3 is shale gas X well on-the-spot test pressure temperature curve of the present invention;
Fig. 4 is data process G-function drawdown analysis curve of the present invention.
Detailed description of the invention
Describe the present invention below in conjunction with drawings and the specific embodiments.
Injection pressure drop well testing test ground injection device of the present invention and downhole closing equipment schematic diagram are respectively as depicted in figs. 1 and 2, above ground portion comprises water tank, injection pump, high pressure pipe joint, flow meter, pressure meter etc., and underground part comprises packer, underground switching valve, down-hole pressure recorder etc.
The principle of determination compact reservoir original formation pressure of the present invention is as follows:
p w s = p i + 2.12 × 10 - 3 q B μ k h lg ( t p + Δ t Δ t ) - - - ( 1 )
In formula, q is that fluid injects discharge capacity, m 3/ d;
P wsfor bottom hole flowing pressure, MPa;
P ifor original formation pressure, MPa;
μ is for injecting fluid viscosity, mPas;
B is fluid volume coefficient, dimensionless;
K is reservoir permeability, mD;
H is reservoir thickness, m;
T pfor injection length, h;
△ t is the closed-in time, h.
Wherein, p wewith relation be straight line, its slope is
The present invention has carried out on-the-spot test for certain block shale gas well domestic.On September 5th, 2013,22:30-22:40 was to shale gas X well Lower Silurian Series Longma small stream group--upper Ordovician series five peak group, well section 2815.00-2818.00m (thickness 3m) cable transmission perforation.September 6,1:00-3:31 carried out squeezing test, operation pressure 23.4-26.8MPa, fracture pressure 24.3MPa, operational discharge capacity 1.04m 3/ min, termination of pumping pressure 18.7MPa, clamp-ons slippery water 7.2m 3, be down to 12.6MPa to 8:20 monitoring pressure on September 10 by 18.7MPa.Test period, injection process and closing well process are carried out continuously, and continuous monitor well bottom pressure.
The X well on-the-spot test pressure temperature curve that monitoring obtains as shown in Figure 3.
By carrying out G-function differentiate to underground monitoring flowing pressure, G-function semilog differentiate process obtains Fig. 4.Offset downward along G-function differential of pressure curve according to from initial point straight line out, the position overlapped with G-function differential of pressure curve, both G-function pressure semilog derivative curves intersection point to determine bottom pressure during closing up of cracks, thus obtains original formation pressure.
According to construction parameter: formation fracture pressure 24.3MPa, inject discharge capacity 1.04m 3/ min, fluid viscosity μ=0.95mPas, fluid volume coefficient B=1m 3/ m 3, injection length t p=2.52h, closed-in time △ t=100.82h, formation porosity K=0.05, wellbore radius r w=0.057m, compression coefficient Ct=0.00435, reservoir thickness h=3.0m, obtaining compact reservoir original formation pressure by G-function drawdown analysis is 18.35MPa.

Claims (4)

1., based on the method for injection pressure drop Well testing determination compact reservoir original formation pressure, it is characterized in that comprising the following steps:
(1) liquid is injected to compact reservoir;
(2) downhole closing is carried out, admission shaft bottom data;
(3) injection and closing well data information are processed, obtain compact reservoir original formation pressure.
2. the method determining compact reservoir original formation pressure according to claim 1, is characterized in that: do not carry out fracturing reform before the described compact reservoir of step (1) injects liquid, described liquid is smooth liquid.
3. the method determining compact reservoir original formation pressure according to claim 1, is characterized in that: step (1) described injection is fluid operated to be carried out continuously with the described closing well operation of step (2).
4. the method determining compact reservoir original formation pressure according to claim 1, it is characterized in that: the data process described in step (3) comprises G-function drawdown analysis method, the straight line being specially initial point offsets downward along G-function differential of pressure curve, and original formation pressure is determined in the position overlapped with G-function differential of pressure curve, G-function pressure semilog derivative curve intersection point.
CN201510784512.6A 2015-11-16 2015-11-16 Method for determining tight reservoir original reservoir pressure based on injection pressure decline well testing technology Pending CN105257288A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510784512.6A CN105257288A (en) 2015-11-16 2015-11-16 Method for determining tight reservoir original reservoir pressure based on injection pressure decline well testing technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510784512.6A CN105257288A (en) 2015-11-16 2015-11-16 Method for determining tight reservoir original reservoir pressure based on injection pressure decline well testing technology

Publications (1)

Publication Number Publication Date
CN105257288A true CN105257288A (en) 2016-01-20

Family

ID=55097178

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510784512.6A Pending CN105257288A (en) 2015-11-16 2015-11-16 Method for determining tight reservoir original reservoir pressure based on injection pressure decline well testing technology

Country Status (1)

Country Link
CN (1) CN105257288A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105781504A (en) * 2016-03-07 2016-07-20 中国石油天然气股份有限公司 Pressure testing method for segmented oil pool and segmented trial-squeezing tubing string
CN106321076A (en) * 2016-10-19 2017-01-11 中国石油化工股份有限公司 Method for testing starting pressure of water injection well
CN113417632A (en) * 2021-08-02 2021-09-21 中国石油大学(北京) Method and device for determining coal reservoir original formation pressure based on post-fracturing pressure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102418511A (en) * 2011-07-25 2012-04-18 中国石油天然气股份有限公司 Draw-down test analysis method for underground shut-in water well with low-permeability storage layer

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102418511A (en) * 2011-07-25 2012-04-18 中国石油天然气股份有限公司 Draw-down test analysis method for underground shut-in water well with low-permeability storage layer

Non-Patent Citations (12)

* Cited by examiner, † Cited by third party
Title
冯旭东: "哈拉哈塘碳酸盐岩缝洞型油藏酸压效果评价研究", 《中国优秀硕士学位论文全文数据库 工程科技I辑》 *
刘洪涛等: "滑溜水压裂液降阻剂的研制与应用", 《石油地质与工程》 *
刘远志等: "煤层气井注入/压降测试技术及应用", 《油气井测试》 *
刘通义等: "新型滑溜水压裂液的性能研究", 《钻井液与完井液》 *
张军涛等: "一种新型滑溜水压裂液减阻剂及其应用", 《长江大学学报(自科版)》 *
张文龙等: "水溶性减阻剂在页岩气滑溜水压裂中的应用进展", 《石油化工》 *
景兴鹏: "沁水盆地南部煤层气储层压力分布规律的研究", 《中国优秀硕士学位论文全文数据库 基础科学辑》 *
杜凯等: "页岩气滑溜水压裂用降阻剂研究与应用进展", 《中国科学》 *
王兴文: "裂缝性油藏压裂压力递减分析研究与应用", 《中国优秀博硕士学位论文全文数据库(硕) 工程科技I辑》 *
王金龙: "油气井压裂时井下压力与温度监测及分析研究", 《中国优秀硕士学位论文全文数据库 工程科技I辑》 *
辛莹娟: "低渗透储层压裂压力分析方法研究", 《中国优秀硕士学位论文全文数据库 工程科技I辑》 *
邵立民等: "非常规油气藏滑溜水压裂液的研究与应用", 《吐哈油气》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105781504A (en) * 2016-03-07 2016-07-20 中国石油天然气股份有限公司 Pressure testing method for segmented oil pool and segmented trial-squeezing tubing string
CN105781504B (en) * 2016-03-07 2019-06-11 中国石油天然气股份有限公司 A kind of segmentation reservoir pressure test method
CN106321076A (en) * 2016-10-19 2017-01-11 中国石油化工股份有限公司 Method for testing starting pressure of water injection well
CN106321076B (en) * 2016-10-19 2021-05-04 中国石油化工股份有限公司 Water injection well starting pressure testing method
CN113417632A (en) * 2021-08-02 2021-09-21 中国石油大学(北京) Method and device for determining coal reservoir original formation pressure based on post-fracturing pressure

Similar Documents

Publication Publication Date Title
US11634977B2 (en) Well injection and production method and system
CN100408806C (en) Method and apparatus for determining an optimal pumping rate based on a downhole dew point pressure determination
CN106522928B (en) Well testing method for unstable pressure drop of well logging head by stopping pump after acidizing and fracturing
CN105114061B (en) A kind of horizontal well fixed tubular column Multi-parameter Combined Tool tests quick searching pipe column and method
US10815761B2 (en) Process for producing hydrocarbons from a subterranean hydrocarbon-bearing reservoir
US20100242586A1 (en) In-situ fluid compatibility testing using a wireline formation tester
CN111119826B (en) Coiled tubing staged fracturing string and string fracturing method
Tian et al. Best practices for the determination of low-pressure/permeability coalbed methane reservoirs, Yuwu Coal Mine, Luan mining area, China
US20090250207A1 (en) Method and apparatus for sampling and/or testing downhole formations
CN102418511A (en) Draw-down test analysis method for underground shut-in water well with low-permeability storage layer
CN104594889B (en) A kind of Accurate Determining oil well remaining oil preserves the devices and methods therefor of position
CN111577257B (en) Horizontal well subsection setting type flow metering water exploration pipe column and water exploration method thereof
CN105443093A (en) Combined well mouth testing device for polymer injection well and method thereof
CN105257288A (en) Method for determining tight reservoir original reservoir pressure based on injection pressure decline well testing technology
CN105678082B (en) Double-pressure drop method for identifying type of oil-gas well acid fracturing communication reservoir
CN103048090A (en) Method for evaluating plugging action of plugging agent on crack
CN104234709A (en) Device for obtaining stratum real fluid samples of cased well
RU2598256C1 (en) Method for hydrodynamic tests of exploitation well formation (versions)
CA2209306A1 (en) Method for determining closure of a hydraulically induced in-situ fracture
RU2743478C1 (en) Difficult turonian gas production method
CN210798950U (en) Multi-parameter online monitoring device for deep well casing external annular thin guide pipe
CN205025412U (en) Many parameter combination of motionless tubular column of horizontal well test quick water detection tubular column
CN108180006B (en) Horizontal well productivity prediction method based on formation energy uplift after volume fracturing
CN113530511A (en) Method for developing natural gas reservoir
Neog Sensitivity analysis for enhancing crude oil recovery with continuous flow gas lift: A study in reference to the porous media of the upper Assam basin, India

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160120

RJ01 Rejection of invention patent application after publication