CN105256684B - A kind of embankment transverse drainage construction method - Google Patents

A kind of embankment transverse drainage construction method Download PDF

Info

Publication number
CN105256684B
CN105256684B CN201510565242.XA CN201510565242A CN105256684B CN 105256684 B CN105256684 B CN 105256684B CN 201510565242 A CN201510565242 A CN 201510565242A CN 105256684 B CN105256684 B CN 105256684B
Authority
CN
China
Prior art keywords
moisture content
soakaway trench
embankment
construction
rig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510565242.XA
Other languages
Chinese (zh)
Other versions
CN105256684A (en
Inventor
马玉伟
苗双全
徐春广
喻慧
贾长海
秦敬敏
汪志彬
党小红
李丽
任亚军
王光涛
姜帅
温丽娜
夏青
李红旗
赵路遥
陈锐
张彩丽
魏娟
周小飞
盛云超
吴强
刘长红
陈伟
李冶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Wanli Transportation Technology Group Co., Ltd.
Original Assignee
Henan Wanli Road&bridge Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Wanli Road&bridge Group Co Ltd filed Critical Henan Wanli Road&bridge Group Co Ltd
Priority to CN201510565242.XA priority Critical patent/CN105256684B/en
Publication of CN105256684A publication Critical patent/CN105256684A/en
Application granted granted Critical
Publication of CN105256684B publication Critical patent/CN105256684B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention relates to embankment drainage system field, specifically related to there is pit in highway pavement, cracking, differential settlement, rainwater in fracture and embankment, during the phenomenons such as the rainwater that capillary water and median strip can not be drained completely, a kind of embankment transverse drainage construction method without excavating and can be recycled, according to embankment moisture content and degree of disease, determine soakaway trench position, soakaway trench is installed in drilling, three-dimensional porous resin filter element is set in soakaway trench, hole mouthful is sealed, site clearing after construction, embankment moisture content is monitored after a period of time again, method of the present invention easy construction, cycle is short, engineering cost is low.

Description

A kind of embankment transverse drainage construction method
Technical field
The present invention relates to embankment drainage system field, and in particular to highway pavement occur pit, cracking, differential settlement, It is a kind of without excavating during the phenomenons such as the rainwater that fracture and the rainwater in embankment, capillary water and median strip can not be drained completely And the embankment transverse drainage construction method that can be recycled.
Background technology
With the fast development continued to develop with traffic science technology of communication, the quality and quantity of highway is all being carried Height, while also increasingly pay attention to the drainage works of highway, the also more and more higher of the requirement to it.And traditional roadbed transverse drainage Facility, is the setting transverse drainage duct at roadbed top, to discharge the infiltration of median strip collected, this drainage pattern without Method solves to pass through the moisture that median strip, earth shoulder, side slope etc. have been seeped into inside embankment, can not also discharge wet soft section road Capillary water in dike;Also there is the push pipe mode using no-dig technique to construct now, draining effect duration after draining, but its construction Short, often the water after the time of 1 year or so in drainpipe just can not discharge the drainpipe, it is necessary to more renew, cost due to blocking It can therewith increase, also increase the workload of road maintenance workman.
The content of the invention
There is provided a kind of without excavating and recyclable making it is an object of the invention to overcome the deficiencies in the prior art Embankment transverse drainage construction method.
The technical proposal of the invention is realized in this way:
A kind of embankment transverse drainage construction method, it is characterised in that construction method is as follows:
Step one), construction material prepare:Construction machinery includes dry drilling machine, generating set, rig traveling branch frame rail Road, drill bit, auger stem, soakaway trench, three-dimensional porous resin filter element, mixing water, PC32.5 bagged cements, medium grained sand, according to Check evaluation criterion, is detected to construction material, carries out aperture record, is bored before PVC-U pipes move into job site thereon Go out the hole of " product " font or " rice " font, aperture is 2.5mm, and infiltration is played in whole work progress;Wherein, described inspection The qualified examining report and ocular estimate that the third party for testing evaluation criteria to be provided by manufacturer goes out evidence are examined, and described three-dimensional is more Hole resin filter element is made up of plastic core body outer wrap filter cloth and has filtering function;
Step 2), the inspection of the scene of a crime:The inspection of the scene of a crime is carried out before construction, embankment moisture content is detected, the moisture content of analysis embankment is The no optimum moisture content regional higher than detection and " disease " degree for observing road surface, described optimum moisture content represent soil in maximum Its corresponding moisture content during dry density, is the ratio of the weight with the weight of moisture in soil Yu dry ground particle, uses percentage table Show;Described road surface " disease " is seriously road surface long-term existence frost boiling phenomenon or 0.5cm~1cm crack, pit occurs;
Step 3), positioning:According to step one)The analysis of middle embankment moisture content and the observation of road surface " disease ", it is determined that construction Location, the position of soakaway trench, if embankment moisture content is higher than 60% -75% and the road surface " disease " of the optimum moisture content in detection area Seriously, then soakaway trench every setting horizontal 20m together;If embankment moisture content higher than the regional optimum moisture content of detection 60%- 75% and without road surface " disease ", then soakaway trench every setting horizontal 30m -50m together;
Step 4), it is in place:Construction machinery needed for construction is stopped in place, the mechanical car that will be loaded with hanging device stops The construction point determined is leaned against, mechanical kickstand is fixed, starts loop wheel machine, rig traveling bracket track is lifted to the road chosen Roadside Po Chu, and rigging up traveling bracket track, the horizontal fix bar of rig traveling bracket track are pinned with latch closure, in rig row The both sides for entering bracket track hit real upper silk with drill rod screw rod, prevent that rig traveling work progress medium-height trestle track from occurring tilting, shaking It is dynamic, finally with horizon rule to rig traveling bracket track it is horizontal, vertically carry out leveling;
Rig lays steady in place, and the drilling rod used by rig arranges placement, soakaway trench, three-dimensional porous resin filter element by number It is smooth to place, meanwhile, generating set, drill bit, the supporting placement of drilling rod of numbering, borehole trajectory are fixed;
Step 5), drilling:Drill bit is installed, drilling rod in order of numbers is installed, starter-generator group trial operation rig, Rig normal operation then starts in construction, work progress every 5min-10min cleanings once miscellaneous soil, and tight in work progress Taboo is added water, it is to avoid roadbed is soaked by water, and structure is destroyed, wherein described drill bit is D90mm drill bit;
Step 6), soakaway trench, three-dimensional porous resin filter element configuration:According to soakaway trench selected in advance from three-dimensional porous Resin filter element, internal diameter small 10mm-20mm of the diameter than soakaway trench of three-dimensional porous resin filter element, three-dimensional porous resin filter element is included In in soakaway trench, and length is identical with infiltration length of tube;
Step 7), install soakaway trench, three-dimensional porous resin filter element:Soakaway trench, three-dimensional are selected into hole length according to drilling rod Porous resin filter core, installs the soakaway trench of a caliber caliber bigger than soakaway trench at away from hole mouthful 0.5m, wherein, described infiltration The pipe for D90mm or D110mm is managed, the pipe of a corresponding big caliber is D100mm or D120mm pipe, the pipe work of a big caliber For the sealer between hole and soakaway trench, by soakaway trench jacking hole;
Step 8), closing:Hole is made into Seal treatment with mortar or C15 concretes;Wherein, the proportioning of every cube of mortar is Cement:Sand:Water=242:1655:270, the proportioning of every cube of C15 concretes is cement:Sand:Water:Stone=185:247:768: 1200;
Step 9), cleaning job site:After hole closing terminates, the construction rubbish of cleaning job site, dismounting machinery, Bracket track, is moved to next hole position and continues to construct;
Step 10), embankment moisture content is detected after two weeks to one month again, such as moisture content is less than the optimal of detection area and contained Water rate, then engineering terminate;Optimum moisture content such as moisture content higher than detection area, then according to step 2)Again continue with.
Step one)Described in medium grained sand for particle diameter be more than 0.25mm granular mass exceed gross mass 50% sand.
Step one)Described in mixing water be drinking water.
The positive effect of the present invention is:1st, have a wide range of application, filled out suitable for Expressway Embankment, median strip and height The national highway and provincial highway of side;
2nd, easy construction, the cycle is short;Traditional drainage construction, which sets up support with steel pipe, needs 2h, and bracket track integration is only Need 55min;Total engineering time shortens 1.5h than conventional construction method;
3rd, traffic will not be blocked, greenery patches vegetation is not destroyed;
4th, engineering cost is low, and three-dimensional porous resin filter element can filter the impurity in draining, reaches permanence operation, when Between longer cost advantage it is more obvious;And in traditional drainage and construction method, the steel pipe for setting up support weares and teares meeting constantly for a long time Reduce, the congestion of tubing all can be cost increase.
Brief description of the drawings
Fig. 1 is the process chart of the present invention.
Embodiment
As shown in figure 1, a kind of embankment transverse drainage construction method, it is characterised in that construction method is as follows:
Step one), construction material prepare:Construction machinery includes dry drilling machine, generating set, rig traveling branch frame rail Road, drill bit, auger stem, soakaway trench, three-dimensional porous resin filter element, mixing water, PC32.5 bagged cements, medium grained sand, mix It is drinking water with water, medium grained sand is 50% sand of the granular mass more than gross mass that particle diameter is more than 0.25mm, according to test evaluation Standard, is detected to construction material, carries out aperture record, and " product " word is got out thereon before PVC-U pipes move into job site The hole of type or " rice " font, aperture is 2.5mm, and infiltration is played in whole work progress;Wherein, described test evaluation mark Standard is examined for the qualified examining report and ocular estimate that the third party that is provided by manufacturer goes out evidence, and described three-dimensional porous resin is filtered Core is made up of plastic core body outer wrap filter cloth and has filtering function;
Step 2), the inspection of the scene of a crime:The inspection of the scene of a crime is carried out before construction, embankment moisture content is detected, the moisture content of analysis embankment is The no optimum moisture content regional higher than detection and " disease " degree for observing road surface, described optimum moisture content represent soil in maximum Its corresponding moisture content during dry density, is the ratio of the weight with the weight of moisture in soil Yu dry ground particle, uses percentage table Show;Described road surface " disease " is seriously road surface long-term existence frost boiling phenomenon or 0.5cm~1cm crack, pit occurs;
Step 3), positioning:According to step one)The analysis of middle embankment moisture content and the observation of road surface " disease ", it is determined that construction Location, the position of soakaway trench, if embankment moisture content is tight higher than 60% -75% and the road surface " disease " of the regional optimum moisture content of detection Weight, then soakaway trench is every one of setting horizontal 20m;If 60% -75% of embankment moisture content higher than the regional optimum moisture content of detection And without road surface " disease ", then soakaway trench is every one of setting horizontal 30m -50m;
Step 4), it is in place:Construction machinery needed for construction is stopped in place, the mechanical car that will be loaded with hanging device stops The construction point determined is leaned against, mechanical kickstand is fixed, starts loop wheel machine, rig traveling bracket track is lifted to the road chosen Roadside Po Chu, and rigging up traveling bracket track, the horizontal fix bar of rig traveling bracket track are pinned with latch closure, in rig row The both sides for entering bracket track hit real upper silk with drill rod screw rod, prevent that rig traveling work progress medium-height trestle track from occurring tilting, shaking It is dynamic, finally with horizon rule to rig traveling bracket track it is horizontal, vertically carry out leveling;
Rig lays steady in place, and the drilling rod used by rig arranges placement, soakaway trench, three-dimensional porous resin filter element by number It is smooth to place, meanwhile, generating set, drill bit, the supporting placement of drilling rod of numbering, borehole trajectory are fixed;
Step 5), drilling:Drill bit is installed, drilling rod in order of numbers is installed, starter-generator group trial operation rig, Rig normal operation then starts in construction, work progress every 5min-10min cleanings once miscellaneous soil, and tight in work progress Taboo is added water, it is to avoid roadbed is soaked by water, and structure is destroyed, wherein described drill bit is D90mm drill bit;
Step 6), soakaway trench, three-dimensional porous resin filter element configuration:According to soakaway trench selected in advance from three-dimensional porous Resin filter element, internal diameter small 10mm-20mm of the diameter than soakaway trench of three-dimensional porous resin filter element, three-dimensional porous resin filter element is included In in soakaway trench, and length is identical with infiltration length of tube;
Step 7), install soakaway trench, three-dimensional porous resin filter element:Soakaway trench, three-dimensional are selected into hole length according to drilling rod Porous resin filter core, installs the pipe of a caliber caliber bigger than soakaway trench at away from hole mouthful 0.5m, wherein, described soakaway trench is D90mm or D110mm pipe, the pipe of a corresponding big caliber is D100mm or D120mm pipe, and the pipe of a big caliber is used as hole Sealer between hole and soakaway trench, by soakaway trench jacking hole;
Step 8), closing:Hole is made into Seal treatment with mortar or C15 concretes;Wherein, the proportioning of every cube of mortar is Cement:Sand:Water=242:1655:270, the proportioning of every cube of C15 concretes is cement:Sand:Water:Stone=185:247:768: 1200;
Step 9), cleaning job site:After hole closing terminates, the construction rubbish of cleaning job site, dismounting machinery, Bracket track, is moved to next hole position and continues to construct;
Step 10), embankment moisture content is detected after two weeks to one month again, such as moisture content is less than the optimal of detection area and contained Water rate, then engineering terminate;Optimum moisture content such as moisture content higher than detection area, then according to step 2)Again continue with.

Claims (3)

1. a kind of embankment transverse drainage construction method, it is characterised in that construction method is as follows:
Step one), construction material prepare:Construction machinery includes dry drilling machine, generating set, rig traveling bracket track, brill Head, auger stem, soakaway trench, three-dimensional porous resin filter element, mixing water, PC32.5 bagged cements, medium grained sand, are commented according to inspection Calibration is accurate, and construction material is detected, carries out aperture record, is got out before PVC-U drainpipes move into job site thereon The hole of " product " font or " rice " font, aperture is 2.5mm, and infiltration is played in whole construction;Wherein, described test evaluation Standard is examined for the qualified examining report and ocular estimate that the third party that is provided by manufacturer goes out evidence, described three-dimensional porous resin Filter core is made up of plastic core body outer wrap filter cloth and has filtering function;
Step 2), the inspection of the scene of a crime:The inspection of the scene of a crime is carried out before construction, embankment moisture content is detected, whether the moisture content for analyzing embankment is high In detection area optimum moisture content and observe " disease " degree on road surface, described optimum moisture content represents that soil is close in maximum dry Its corresponding moisture content when spending, is the ratio of the weight with the weight of moisture in soil Yu dry ground particle, is expressed as a percentage;Institute It is seriously road that " disease " degree on the road surface stated, which includes road surface " disease " serious without road surface " disease " and road surface " disease ", described, There is 0.5cm~1cm crack, pit in face long-term existence frost boiling phenomenon;
Step 3), positioning:According to step 2)The analysis of middle embankment moisture content and the observation of road surface " disease ", determine construction ground Section, the position of soakaway trench, if embankment moisture content is tight higher than 60% -75% and the road surface " disease " of the optimum moisture content in detection area Weight, then soakaway trench is every one of setting horizontal 20m;If 60% -75% of embankment moisture content higher than the regional optimum moisture content of detection And without road surface " disease ", then soakaway trench is every one of setting horizontal 30m -50m;
Step 4), it is in place:Construction machinery needed for construction is stopped in place, the mechanical car that will be loaded with hanging device rests in The construction point determined, fixes mechanical kickstand, starts loop wheel machine, rig traveling bracket track is lifted to the road roadside chosen At slope, and rigging up traveling bracket track, the horizontal fix bar of rig traveling bracket track, rig traveling support are pinned with latch closure The both sides of track hit real upper silk with drill rod screw rod, prevent that rig traveling work progress medium-height trestle track from occurring tilting, rocking, finally With horizon rule to rig traveling bracket track it is horizontal, vertically carry out leveling;
Rig lays steady in place, and the drilling rod used by rig arranges placement by number, and soakaway trench, three-dimensional porous resin filter element are smooth Place, meanwhile, generating set, drill bit, the supporting placement of drilling rod of numbering, rig traveling track are fixed;
Step 5), drilling:Drill bit is installed, drilling rod in order of numbers is installed, starter-generator group trial operation rig, rig Normal operation then starts in construction, work progress every 5min-10min cleanings once miscellaneous soil, and forbid to add in work progress Water, it is to avoid roadbed is soaked by water, structure is destroyed, wherein described drill bit is D90mm drill bit;
Step 6), soakaway trench, three-dimensional porous resin filter element configuration:Three-dimensional porous resin is selected according to soakaway trench selected in advance Invest and ooze in filter core, the small 10mm-20mm of internal diameter of the diameter than soakaway trench of three-dimensional porous resin filter element, three-dimensional porous resin filter element In water pipe, and length is identical with infiltration length of tube;
Step 7), install soakaway trench, three-dimensional porous resin filter element:According to drilling rod into hole length selection soakaway trench, three-dimensional porous Resin filter element, installs the soakaway trench of a caliber caliber bigger than soakaway trench at away from hole mouthful 0.5m, wherein, described soakaway trench is D90mm or D110mm pipe, the pipe of a corresponding big caliber is managed for D100mm or D120mm PVC-U, the pipe of a big caliber As the sealer between hole and soakaway trench, by soakaway trench jacking hole;
Step 8), closing:Hole is made into Seal treatment with mortar or C15 concretes;Wherein, the proportioning of every cube of mortar is cement: Sand:Water=242:1655:270, the proportioning of every cube of C15 concretes is cement:Sand:Water:Stone=185:247:768:1200;
Step 9), cleaning job site:After hole closing terminates, the construction rubbish of job site is cleared up, machinery, support is removed Track, is moved to next hole position and continues to construct;
Step 10), embankment moisture content is detected after two weeks to one month again, such as moisture content is less than the optimal aqueous of detection area Rate, then engineering terminate;Optimum moisture content such as moisture content higher than detection area, then according to step 2)Again continue with.
2. embankment transverse drainage construction method according to claim 1, it is characterised in that:Step one)Described in middle grain Sand is 50% sand of the granular mass more than gross mass that particle diameter is more than 0.25mm.
3. embankment transverse drainage construction method according to claim 1, it is characterised in that:Step one)Described in mix It is drinking water with water.
CN201510565242.XA 2015-09-08 2015-09-08 A kind of embankment transverse drainage construction method Active CN105256684B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510565242.XA CN105256684B (en) 2015-09-08 2015-09-08 A kind of embankment transverse drainage construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510565242.XA CN105256684B (en) 2015-09-08 2015-09-08 A kind of embankment transverse drainage construction method

Publications (2)

Publication Number Publication Date
CN105256684A CN105256684A (en) 2016-01-20
CN105256684B true CN105256684B (en) 2017-07-11

Family

ID=55096600

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510565242.XA Active CN105256684B (en) 2015-09-08 2015-09-08 A kind of embankment transverse drainage construction method

Country Status (1)

Country Link
CN (1) CN105256684B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978502A (en) * 2018-08-13 2018-12-11 朱晓颖 A kind of induction type roadbed transverse drainage construction method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4313221C2 (en) * 1993-04-22 1995-08-17 Flowtex Service Ges Fuer Horiz Process for laying underground collecting pipes for liquids and gases, in particular for building horizontal filter wells and drainage pipes, and tools for carrying out the process
JP2001172951A (en) * 1999-12-21 2001-06-26 Nippon Concrete Ind Co Ltd Seepage water drainage structure and its construction method
JP2006194044A (en) * 2005-01-17 2006-07-27 Ohbayashi Corp Installation method for water drain pipe in toe of slope on back of levee body, water draining method for seepage water on back of levee body, and water drain structure for seepage water
CN101748734A (en) * 2008-12-04 2010-06-23 中国二十冶建设有限公司 Foundation pit side slope sandy soil drainage method
CN204510192U (en) * 2014-12-30 2015-07-29 重庆市永川区老科学技术工作者协会 Double-level Reticulated eye gutter
CN104727319B (en) * 2015-04-07 2016-05-11 兰州理工大学 A kind of side slope is from drainage anchor rod and construction method

Also Published As

Publication number Publication date
CN105256684A (en) 2016-01-20

Similar Documents

Publication Publication Date Title
Zhou et al. Engineering issues on karst
CN109881694A (en) A kind of constructing structure blocked for foundation pit substrate Sand and method
CN103147442B (en) Ultra-deep foundation pit press-grouting pile and prestressed anchor combined supporting construction method
CN107761495A (en) A kind of pre-buried expanding bag compensation subgrade settlement construction method
CN110469332B (en) Advanced support consolidation method for tunnel penetrating through debris flow accumulation body
CN110453678B (en) Method for treating loess highway subgrade settlement by high-pressure jet grouting pile double-pipe method
CN109236367A (en) A kind of tunnel structure and its frozen construction method with antiseepage drain function
Sandoval et al. Clogging phenomenon in Pervious Concrete (PC): A systematic literature review
CN208982109U (en) A kind of tunnel structure with antiseepage drain function
CN111424702A (en) Integrated water drainage pipe structure and construction method
CN110644461A (en) Foundation treatment method
CN105256684B (en) A kind of embankment transverse drainage construction method
CN210238157U (en) Plateau permafrost region high-speed railway roadbed structure
CN207484214U (en) A kind of water permeability and water storage ability terrace
CN110565452A (en) Railway roadbed body steel flower tube grouting reinforcement method and railway roadbed
Chopra et al. Construction and maintenance assessment of pervious concrete pavements
Chopra et al. Pervious pavement systems in Florida—Research results
Kropp et al. Field wetting tests on a collapsible soil fill
JP4060497B2 (en) Roadbed material and roadbed structure with excellent strength and water permeability
Yang et al. High fill embankment of collapsible loess settlement observation and research
CN209975535U (en) Supporting-free double-layer arc-shaped drilling and pouring deep foundation pit retaining structure
CN115233718B (en) Anti-seepage plugging structure of foundation pit dewatering well and plugging method of foundation pit dewatering well
Gracia et al. Restoration Project of vernacular architecture affected for ground subsidence. A case study in Juslibol Church (Zaragoza, Spain)
Ahmadkhani Investigation of movement of rain water in railway track ballast and subballast layers
Luo et al. Investigation on evolution mechanism and treatment of invert damage in operating railway tunnels under heavy rainfall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Ma Yuwei

Inventor after: Ren Yajun

Inventor after: Wang Guangtao

Inventor after: Jiang Shuai

Inventor after: Wen Lina

Inventor after: Xia Qing

Inventor after: Li Hongqi

Inventor after: Zhao Luyao

Inventor after: Chen Rui

Inventor after: Zhang Caili

Inventor after: Wei Juan

Inventor after: Miao Shuangquan

Inventor after: Zhou Xiaofei

Inventor after: Sheng Yunchao

Inventor after: Wu Qiang

Inventor after: Liu Changhong

Inventor after: Chen Wei

Inventor after: Li Ye

Inventor after: Xu Chunguang

Inventor after: Yu Hui

Inventor after: Jia Changhai

Inventor after: Qin Jingmin

Inventor after: Wang Zhibin

Inventor after: Dang Xiaohong

Inventor after: Li Li

Inventor before: Ma Yuwei

Inventor before: Li Li

Inventor before: Ren Yajun

Inventor before: Wang Guangtao

Inventor before: Jiang Shuai

Inventor before: Wen Lina

Inventor before: Xia Qing

Inventor before: Li Hongqi

Inventor before: Zhao Luyao

Inventor before: Chen Rui

Inventor before: Zhang Caili

Inventor before: Miao Shuangquan

Inventor before: Wei Juan

Inventor before: Zhou Xiaofei

Inventor before: Sheng Yunchao

Inventor before: Wu Qiang

Inventor before: Miao Zhijie

Inventor before: Xia Junjie

Inventor before: Xu Chunguang

Inventor before: Yu Hui

Inventor before: Jia Changhai

Inventor before: Qin Jingmin

Inventor before: Ding Yifei

Inventor before: Dang Xiaohong

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 461000 Yongchang West Road, Xuchang City, Henan Province

Patentee after: Henan Wanli Transportation Technology Group Co., Ltd.

Address before: 461000 Lunan, East Section of North Ring West Road, Xuchang City, Henan Province

Patentee before: HENAN WANLI ROAD&BRIDGE GROUP CO., LTD.

CP03 Change of name, title or address