CN105202107B - Using the earthquake isolation platform and its construction method of braiding prestressed cable - Google Patents

Using the earthquake isolation platform and its construction method of braiding prestressed cable Download PDF

Info

Publication number
CN105202107B
CN105202107B CN201510703663.4A CN201510703663A CN105202107B CN 105202107 B CN105202107 B CN 105202107B CN 201510703663 A CN201510703663 A CN 201510703663A CN 105202107 B CN105202107 B CN 105202107B
Authority
CN
China
Prior art keywords
mass
prestressed cable
cylinder
braiding
cylindrical core
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510703663.4A
Other languages
Chinese (zh)
Other versions
CN105202107A (en
Inventor
何铭华
马彦会
任革学
郭佳
石永久
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tsinghua University
Original Assignee
Tsinghua University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tsinghua University filed Critical Tsinghua University
Priority to CN201510703663.4A priority Critical patent/CN105202107B/en
Publication of CN105202107A publication Critical patent/CN105202107A/en
Application granted granted Critical
Publication of CN105202107B publication Critical patent/CN105202107B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

A kind of earthquake isolation platform and its construction method using braiding prestressed cable, the earthquake isolation platform includes pedestal, it is fixed on the hanging frame above pedestal, it is fixed on the core mass cylinder hoist cable on hanging frame, the mass-adjustable cylindrical core quality cylinder in the cylindrical space for being placed in base interior is hung up using core mass cylinder hoist cable, the netted braiding prestressed cable that many prestressed cables being fixed on base internal wall are formed, netted braiding prestressed cable forms encirclement shape and goes along with sb. to guard him to mass-adjustable cylindrical core quality cylinder;Horizontal impact is mainly used for isolating, the amplitude of passive control, suppression and reduction horizontal vibration reaches the effect of earthquake isolation;With simple structure, convenient material drawing, with low cost, the characteristics of the convenient, superior performance of constructing;The earthquake isolation platform stress system of the establishment prestressed cable for being formed rationally, overcomes the reliability and safety issue of traditional earthquake isolation platform, is a kind of advanced technology, implements easily earthquake isolation platform scheme.

Description

Using the earthquake isolation platform and its construction method of braiding prestressed cable
Technical field
The invention belongs to Structural Engineering and mechanical engineering technical field, and in particular to it is a kind of using braiding prestressed cable every Shake damped platform and its construction method.
Background technology
Precision instrument and equipment, high-grade scientific experimentation room, super high rise structure vibration suppression damping etc., all to earthquake isolation platform Performance requirement higher is proposed, in Structural Engineering and mechanical engineering field, all to look for performance more prominent, cost performance more has excellent The earthquake isolation platform of gesture.
The earthquake isolation platform formed using mechanism such as spring-damper, sliding frictions has all been emerged in multitude and obtained Extensive use, but the earthquake isolation platform realized using braiding prestressed cable has more advantage, the present invention in some environments The earthquake isolation platform using braiding prestressed cable of proposition is the newcomer in earthquake isolation family, with good economy And convenience for construction, can be generalized to every field.
The content of the invention
For the problem for overcoming above-mentioned prior art to exist, it is an object of the invention to provide one kind using braiding prestressing force The earthquake isolation platform and its construction method of rope, simple structure of the present invention, construction are flexible, materials facility, practical reliable, warp Ji performance is protruded.
To achieve the above objectives, the present invention is adopted the following technical scheme that:
A kind of earthquake isolation platform using braiding prestressed cable, the earthquake isolation platform using braiding prestressed cable 1 includes pedestal 6, is fixed on the hanging frame 5 of the top of pedestal 6, is fixed on the core mass cylinder hoist cable 4 on hanging frame 5, uses Core mass cylinder hoist cable 4 hangs up the mass-adjustable cylindrical core quality cylinder in the cylindrical space being placed in inside pedestal 6 2, the mass-adjustable cylindrical core quality cylinder 2 can in the horizontal direction to all directions free translation;Also include netted volume Prestressed cable 3 is knitted, the netted braiding prestressed cable 3 is formed by many prestressed cables being fixed on the inwall of pedestal 6, netted volume Knit prestressed cable 3 mass-adjustable cylindrical core quality cylinder 2 is formd and surround shape and go along with sb. to guard him with to mass-adjustable cylindrical core matter Graduated cylinder 2 enters row constraint and fixation;The horizontal force pass through mechanism that the netted braiding prestressed cable 3 is formed, it is initial for building zero The horizontal power transmission pattern of rigidity, under the feature of zero initial stiffness, with the relative displacement of mass-adjustable cylindrical core quality cylinder 2 Increase, the cylindrical space inside pedestal 6 is accommodated because of the mass-adjustable cylindrical core quality cylinder 2 that horizontal impact, vibrations trigger Horizontal relative motions, constitute the relative motion mechanism of the netted braiding prestressed cable 3 of extruding, effectively can draw horizontal displacement The interaction transmission of hair, forms power transmission mechanism.
Each in the netted braiding prestressed cable 3 is tangent with mass-adjustable cylindrical core quality cylinder 2.
The mass-adjustable cylindrical core quality cylinder 2 constitutes the mounting platform of sensitive instrument and equipment, or for resisting The mass of horizontal vibration;It is integral using steel, concreting, or the internal cavity that sets forms matter by priming petock mode Measure adjustable big rigidity entirety.
The construction method of the earthquake isolation platform using braiding prestressed cable described above, can give birth to as shaped article Produce or process, it is also possible to be built on-site according to design working drawing, but its production method or construction method are common, and it is special Levy and be, comprise the following steps that:
Step 1:Mass-adjustable cylindrical core quality cylinder 2 is made, its production method is generally prefabricated in the factory or scene is entered Row all round victory shuttering supporting makes or is lifted by crane after making;
Step 2:Hanging frame 5 is made, installation is lifted by crane with core mass cylinder hoist cable 4 or shuttering supporting is removed and installs adjustable Quality cylindrical core quality cylinder 2, the requirement on being connected is non-with mass-adjustable cylindrical core quality cylinder 2 for core mass cylinder hoist cable 4 Chang Yange, accomplishes perfectly safe;
Step 3:Make pedestal 6 and uniform netted braiding prestressed cable 3 is installed on its inwall, it is pre- for netted braiding Stress rope 3 should be noted effective applying of internal pretension.
The construction method of the netted braiding prestressed cable 3, comprises the following steps that:
Step 1:Scene is taken to be applied according to the mode that the dead hang position of mass-adjustable cylindrical core quality cylinder 2 is reference Work;Pedestal 6 is designed arrangement of reinforcement and construction according to specification, while the pre-buried anchoring piece that can fix netted braiding prestressed cable 3, Netted braiding prestressed cable 3 is that have default diameter in practice, and many prestressed cables can not possibly strictly be distributed in same In plane, it should take regulating measures so that netted braiding prestressed cable 3 can effectively to mass-adjustable cylindrical core quality Cylinder 2 is formed and gone along with sb. to guard him;
Step 2:A construction for prestressed cable is completed on the anchoring piece of pre-buried good pedestal 6;Prestressed cable with Mass-adjustable cylindrical core quality cylinder 2 is tangent or forms nature encirclement;
Step 3:Repeat step 2 completes the construction of all prestressed cables, eventually forms netted braiding prestressed cable 3.
Compared to the prior art compared with the present invention possesses following advantage:
(1) a kind of new earthquake isolation platform technology side is provided by the earthquake isolation platform using braiding prestressed cable Case and its construction method.Using braiding prestressed cable earthquake isolation platform employ braiding prestressed cable ensure that go along with sb. to guard him just Beginning zero stiffness, particularly in the horizontal direction, zero initial stiffness has very important effect for shock isolation, shock insulation;Core Heart quality cylinder hoist cable gets up the cylinder suspention of mass-adjustable cylindrical core quality, so that mass-adjustable cylindrical core quality cylinder exists Certain limit can be moved freely in the horizontal direction, to design and utilizing the mechanical property for weaving prestressed cable to provide possibility.
(2) braiding prestressed cable can be effectively formed horizontal power transmission mechanism, such that it is able to by mass-adjustable cylindrical core Quality cylinder is realized to ground or the suppression of structural vibration, plays a part of suppression and shake.
(3) it is that can accommodate braiding in advance should by the space built between mass-adjustable cylindrical core quality cylinder and pedestal Power rope plays the basis of effect.
(4) for the isolation and damping of vertical motion, suspended using mass-adjustable cylindrical core quality cylinder and combined upper and lower The mode that surface zero stiffness rope is gone along with sb. to guard him is achieved.
(5) using the convenient material drawing of the earthquake isolation platform for weaving prestressed cable, simple structure, the mode of production can be used Factory's customization processing, or process on demand at the construction field (site), very flexibly, financial cost is cheap.
(6) difficulty of construction of the present invention is low, and operation is less.
Brief description of the drawings
Fig. 1 is the overall structure diagram of earthquake isolation platform of the present invention.
Fig. 2 is the upward view of earthquake isolation platform of the present invention.
Specific embodiment
Below in conjunction with drawings and the specific embodiments, the present invention is described in further detail.
As depicted in figs. 1 and 2, a kind of earthquake isolation platform using braiding prestressed cable of the present invention is first using volume Knit prestressed cable and form the earthquake isolation platform that zero stiffness is surrounded.The earthquake isolation platform 1 using braiding prestressed cable is wrapped Pedestal 6 is included, the hanging frame 5 of the top of pedestal 6 is fixed on, the core mass cylinder hoist cable 4 on hanging frame 5 is fixed on, using core Heart quality cylinder hoist cable 4 hangs up the mass-adjustable cylindrical core quality cylinder 2 in the cylindrical space being placed in inside pedestal 6, The mass-adjustable cylindrical core quality cylinder 2 can in the horizontal direction to all directions free translation;Also include netted braiding Prestressed cable 3, the netted braiding prestressed cable 3 is formed by many prestressed cables being fixed on the inwall of pedestal 6, netted braiding Prestressed cable 3 forms to mass-adjustable cylindrical core quality cylinder 2 and surrounds shape and go along with sb. to guard him with to mass-adjustable cylindrical core quality Cylinder 2 enters row constraint and fixation;The horizontal force pass through mechanism that the netted braiding prestressed cable 3 is formed, it is initial firm for building zero The horizontal power transmission pattern of degree, under the feature of zero initial stiffness, the relative displacement with mass-adjustable cylindrical core quality cylinder 2 increases Greatly, the cylindrical space inside pedestal 6 is accommodated because of the water of the mass-adjustable cylindrical core quality cylinder 2 that horizontal impact, vibrations trigger Flat relative motion, constitutes the relative motion mechanism of the netted braiding prestressed cable 3 of extruding, effectively can trigger horizontal displacement Interaction transmission, formed power transmission mechanism.
Used as the preferred embodiment of the present invention, each in the netted braiding prestressed cable 3 is justified with mass-adjustable Post core mass cylinder 2 is tangent.
Used as the preferred embodiment of the present invention, the mass-adjustable cylindrical core quality cylinder 2 constitutes precision instrument and sets Standby mounting platform, or for resisting the mass of horizontal vibration;It is integral using steel, concreting, or inside sets It is empty chamber and the adjustable big rigidity entirety of quality is formed by priming petock mode.
The present invention using braiding prestressed cable earthquake isolation platform construction method, can as shaped article production or Person processes, it is also possible to be built on-site according to design working drawing, but its production method or construction method are common, and its feature exists In comprising the following steps that:
Step 1:Mass-adjustable cylindrical core quality cylinder 2 is made, the part typically comprises the installation of sensitive instrument and equipment Platform, or for resisting the mass of horizontal vibration, therefore can be integral using steel, concreting, it is also possible to it is interior Portion sets cavity and forms the adjustable big rigidity entirety of quality by modes such as priming petocks, and production method can generally be prefabricated in the factory Or scene carries out the making of all round victory shuttering supporting or is lifted by crane after making;
Step 2:Hanging frame 5 is made, installation is lifted by crane with core mass cylinder hoist cable 4 or shuttering supporting is removed and installs adjustable Quality cylindrical core quality cylinder 2, the requirement on being connected is non-with mass-adjustable cylindrical core quality cylinder 2 for core mass cylinder hoist cable 4 Chang Yange, accomplishes perfectly safe;
Step 3:Make pedestal 6 and uniform netted braiding prestressed cable 3 is installed on its inwall, it is pre- for netted braiding Stress rope 3 should be noted effective applying of internal pretension.
The construction method of the netted braiding prestressed cable 3, comprises the following steps that:
Step 1:Scene is taken to be applied according to the mode that the dead hang position of mass-adjustable cylindrical core quality cylinder 2 is reference Work;Pedestal 6 is designed arrangement of reinforcement and construction according to specification, while the pre-buried anchoring piece that can fix netted braiding prestressed cable 3, Netted braiding prestressed cable 3 is that have default diameter in practice, and many prestressed cables can not possibly strictly be distributed in same In plane, it should take regulating measures so that netted braiding prestressed cable 3 can effectively to mass-adjustable cylindrical core quality Cylinder 2 is formed and gone along with sb. to guard him;
Step 2:A construction for prestressed cable is completed on the anchoring piece of pre-buried good pedestal 6;Prestressed cable with Mass-adjustable cylindrical core quality cylinder 2 is tangent or forms nature encirclement;
Step 3:Repeat step 2 completes the construction of all prestressed cables, eventually forms netted braiding prestressed cable 3.
The invention discloses a kind of earthquake isolation platform using braiding prestressed cable, and typhoon is named as according to its feature Eye earthquake isolation platform, and disclose construction and use the typhoon eye earthquake isolation platform using braiding prestressed cable Construction method.It is newcomer in earthquake isolation device extended familys using the earthquake isolation platform of braiding prestressed cable, by can be quenched The compositions such as amount cylinder quality Core Walls Structure, pre- stretching rope net, cylindric pedestal, quality Core Walls Structure hoist cable and hanging frame, mainly For level of isolation impact, the amplitude of passive control, suppression and reduction horizontal vibration reaches the effect of earthquake isolation.The present invention The earthquake isolation platform of the braiding prestressed cable being related to has simple structure, convenient material drawing, with low cost, convenient, performance of constructing Superior the characteristics of;Formed establishment prestressing force earthquake isolation platform stress system it is clearly reasonable, overcome traditional shock insulation The reliability and safety issue of damped platform, are a kind of advanced technology, implement easily earthquake isolation platform scheme.

Claims (3)

1. a kind of using the earthquake isolation platform for weaving prestressed cable, it is characterised in that:It is described using braiding prestressed cable every Shake damped platform (1) includes pedestal (6), is fixed on the hanging frame (5) above pedestal (6), is fixed on hanging frame (5) Core mass cylinder hoist cable (4), is hung up using core mass cylinder hoist cable (4) and is placed in the internal cylindrical space of pedestal (6) Interior mass-adjustable cylindrical core quality cylinder (2), mass-adjustable cylindrical core quality cylinder (2) can in the horizontal direction to All directions free translation;Also include netted braiding prestressed cable (3), netted braiding prestressed cable (3) is by being fixed on base Many prestressed cables on seat (6) inwall are formed, and netted braiding prestressed cable (3) is to mass-adjustable cylindrical core quality cylinder (2) Form going along with sb. to guard him for encirclement shape and enter row constraint and fixation with to mass-adjustable cylindrical core quality cylinder (2);The netted braiding is pre- The horizontal force pass through mechanism that stress rope (3) is formed, the horizontal power transmission pattern for building zero initial stiffness, in zero initial stiffness Under feature, the relative displacement with mass-adjustable cylindrical core quality cylinder (2) increases, and the internal cylindrical space of pedestal (6) holds Receive because of the horizontal relative motions of mass-adjustable cylindrical core quality cylinder (2) that horizontal impact, vibrations trigger, constitute extruding netted The relative motion mechanism of braiding prestressed cable (3), the interaction transmission that effectively can trigger horizontal displacement, forms power transmission Mechanism;
Each in netted braiding prestressed cable (3) is tangent with mass-adjustable cylindrical core quality cylinder (2);
Mass-adjustable cylindrical core quality cylinder (2) constitutes the mounting platform of sensitive instrument and equipment, or for resisting water The mass of flat vibration;It is integral using steel, concreting, or the internal cavity that sets forms quality by priming petock mode Adjustable big rigidity entirety.
2. the use described in claim 1 weaves the construction method of the earthquake isolation platform of prestressed cable, it is characterised in that:Can Produced as shaped article or processed, it is also possible to be built on-site according to design working drawing, but its production method or construction party Method is common, it is characterised in that comprised the following steps that:
Step 1:Mass-adjustable cylindrical core quality cylinder (2) is made, its production method is generally prefabricated in the factory or scene is carried out All round victory shuttering supporting makes or is lifted by crane after making;
Step 2:Hanging frame (5) is made, installation is lifted by crane with core mass cylinder hoist cable (4) or shuttering supporting is removed and installs adjustable Quality cylindrical core quality cylinder (2), core mass cylinder hoist cable (4) will on being connected with mass-adjustable cylindrical core quality cylinder (2) Ask very strict, accomplish perfectly safe;
Step 3:Make pedestal (6) and uniform netted braiding prestressed cable (3) is installed on its inwall, it is pre- for netted braiding Stress rope (3) should be noted effective applying of internal pretension.
3. construction method according to claim 2, it is characterised in that:The construction party of netted braiding prestressed cable (3) Method, comprises the following steps that:
Step 1:Scene is taken to be applied according to the mode that the dead hang position of mass-adjustable cylindrical core quality cylinder (2) is reference Work;Pedestal (6) is designed arrangement of reinforcement and construction according to specification, while the pre-buried anchor that can fix netted braiding prestressed cable (3) Firmware, netted braiding prestressed cable (3) is that have default diameter in practice, and many prestressed cables can not possibly strictly be distributed in In approximately the same plane, it should take regulating measures so that netted braiding prestressed cable (3) can effectively to mass-adjustable cylinder Core mass cylinder (2) is formed and gone along with sb. to guard him;
Step 2:A construction for prestressed cable is completed on the anchoring piece of pre-buried good pedestal (6);Prestressed cable with can Quenched amount cylindrical core quality cylinder (2) is tangent or forms nature encirclement;
Step 3:Repeat step 2 completes the construction of all prestressed cables, eventually forms netted braiding prestressed cable (3).
CN201510703663.4A 2015-10-26 2015-10-26 Using the earthquake isolation platform and its construction method of braiding prestressed cable Expired - Fee Related CN105202107B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510703663.4A CN105202107B (en) 2015-10-26 2015-10-26 Using the earthquake isolation platform and its construction method of braiding prestressed cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510703663.4A CN105202107B (en) 2015-10-26 2015-10-26 Using the earthquake isolation platform and its construction method of braiding prestressed cable

Publications (2)

Publication Number Publication Date
CN105202107A CN105202107A (en) 2015-12-30
CN105202107B true CN105202107B (en) 2017-06-16

Family

ID=54949963

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510703663.4A Expired - Fee Related CN105202107B (en) 2015-10-26 2015-10-26 Using the earthquake isolation platform and its construction method of braiding prestressed cable

Country Status (1)

Country Link
CN (1) CN105202107B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113152260B (en) * 2021-05-18 2023-02-17 大连理工大学 Spring-flexible mesh cloth tuning device for inhibiting vortex-induced vibration of bridge
CN113431335B (en) * 2021-08-03 2023-03-14 宜春职业技术学院(宜春市技术工人学校) A ground treatment facility for interior decoration

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85104304A (en) * 1985-06-05 1986-12-03 新西兰发展财务公司 Friction energy absorption plant and energy-absorbing method
DE4103961A1 (en) * 1991-02-09 1992-08-13 Licentia Gmbh Device to limit imbalance deviations - in oscillating container systems in household washing machines, to limit mechanical damage when electronic imbalance control fails
DE102004020605A1 (en) * 2004-04-27 2005-11-24 Erwin W. Kötter Consulting Engineers e.K. Vibration absorbing or compensating device, designed as housing accommodating mass element attached to helical springs
CN102661055A (en) * 2012-03-12 2012-09-12 河海大学 Reinforcing device for reinforced concrete column using prestressing cable, and application method thereof
CN102979181A (en) * 2012-12-21 2013-03-20 徐州工程学院 Intelligent shock isolation and absorption nickel-titanium alloy supporting seat for large-span spatial structure (net rack)
CN103132628A (en) * 2013-03-13 2013-06-05 上海材料研究所 Pendulum eddy current tuning mass damper device
CN103306531A (en) * 2013-07-09 2013-09-18 东北石油大学 Reticulated shell-annular truss frame-irregular-shaped combination column combined support spherical tank system capable of slightly moving
CN205118110U (en) * 2015-10-26 2016-03-30 清华大学 Prestressed cable's shock insulation shock attenuation platform is woven in adoption

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85104304A (en) * 1985-06-05 1986-12-03 新西兰发展财务公司 Friction energy absorption plant and energy-absorbing method
DE4103961A1 (en) * 1991-02-09 1992-08-13 Licentia Gmbh Device to limit imbalance deviations - in oscillating container systems in household washing machines, to limit mechanical damage when electronic imbalance control fails
DE102004020605A1 (en) * 2004-04-27 2005-11-24 Erwin W. Kötter Consulting Engineers e.K. Vibration absorbing or compensating device, designed as housing accommodating mass element attached to helical springs
CN102661055A (en) * 2012-03-12 2012-09-12 河海大学 Reinforcing device for reinforced concrete column using prestressing cable, and application method thereof
CN102979181A (en) * 2012-12-21 2013-03-20 徐州工程学院 Intelligent shock isolation and absorption nickel-titanium alloy supporting seat for large-span spatial structure (net rack)
CN103132628A (en) * 2013-03-13 2013-06-05 上海材料研究所 Pendulum eddy current tuning mass damper device
CN103306531A (en) * 2013-07-09 2013-09-18 东北石油大学 Reticulated shell-annular truss frame-irregular-shaped combination column combined support spherical tank system capable of slightly moving
CN205118110U (en) * 2015-10-26 2016-03-30 清华大学 Prestressed cable's shock insulation shock attenuation platform is woven in adoption

Also Published As

Publication number Publication date
CN105202107A (en) 2015-12-30

Similar Documents

Publication Publication Date Title
CN102884251A (en) Wind power plant foundation and wind power plant
CN105202107B (en) Using the earthquake isolation platform and its construction method of braiding prestressed cable
CN205118110U (en) Prestressed cable's shock insulation shock attenuation platform is woven in adoption
CN102979220A (en) Hollow shear wall structure for cross diagonal reinforcing bar and construction method thereof
CN208633299U (en) A kind of plurality of pendulums-viscous liquid-multi link formula damper array
CN113565690A (en) Wind power generator base
CN111576631B (en) Liftable formula individual layer building
CN210106482U (en) Buffering shock isolation device based on suspension structure
CN204311721U (en) A kind of double bracket hanging basket is encorbelmented device
RU175705U1 (en) COMPOSITE RACK FOR SUPPORT OF BRIDGE STRUCTURES
CN207944491U (en) A kind of anchor ingot plate improved adjusting device for the isolator on architecture foundation pile
RU2014106918A (en) SYSTEM OF MONOLITHIC-ASSEMBLY CONSTRUCTION OF BUILDINGS
CN206072520U (en) A kind of concrete pump pipe damping device
RU193791U1 (en) Pipe-concrete seismic-insulating support on a monolithic reinforced concrete foundation
RU148123U1 (en) SEISMIC RESISTANT QUIET PRODUCTION BUILDING
CN105926662B (en) A kind of construction method of top plate type main transformer foundation
KR101358213B1 (en) Tower support structure and method for constructing the structure
CN210739246U (en) Anti-swing three-dimensional shock isolation device
CN215925946U (en) Buffering shock attenuation building foundation pile structure
CN204590367U (en) A kind of steel concrete sound-absorbing hollow floor cover plate
CN221119234U (en) Cloth machine construction platform
CN216130170U (en) Iron tower shock insulation base
SU947367A1 (en) Earthquake-proof building
CN215558530U (en) Tower crane landing leg fixing device
CN211548925U (en) Effectual wall body support column of antidetonation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170616

Termination date: 20171026