CN105181253A - 用于管片纵缝抗渗性能试验的管片试件及其制造方法 - Google Patents

用于管片纵缝抗渗性能试验的管片试件及其制造方法 Download PDF

Info

Publication number
CN105181253A
CN105181253A CN201510609224.7A CN201510609224A CN105181253A CN 105181253 A CN105181253 A CN 105181253A CN 201510609224 A CN201510609224 A CN 201510609224A CN 105181253 A CN105181253 A CN 105181253A
Authority
CN
China
Prior art keywords
jurisdiction
section
segment
duct
test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510609224.7A
Other languages
English (en)
Other versions
CN105181253B (zh
Inventor
龚琛杰
丁文其
朱合华
闫治国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CN201510609224.7A priority Critical patent/CN105181253B/zh
Publication of CN105181253A publication Critical patent/CN105181253A/zh
Application granted granted Critical
Publication of CN105181253B publication Critical patent/CN105181253B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本发明涉及一种用于管片纵缝抗渗性能试验的管片试件及其制造方法,管片试件包括第一管片与第二管片,第一管片与第二管片相对一端均为密封面,第一管片和第二管片中均设置有用于穿过连接螺栓的螺栓孔道,通过连接螺栓使第一管片与第二管片的密封面相互压紧,在第一管片和第二管片的密封面上均设置有框形沟槽,在框形沟槽内嵌有首尾封闭连接的弹性密封垫,在第一管片上还设置有一注水孔道,该注水孔道的一端位于第一管片的上圆弧表面,注水孔道的另一端位于第一管片上框形沟槽的内框所限定的区域内。与现有技术相比,本发明采用盾构隧道现有管片钢模进行试验构件的制作,保证了试验数据的准确性,缩短了试验时间,具有良好的经济效益。

Description

用于管片纵缝抗渗性能试验的管片试件及其制造方法
技术领域
本发明涉及盾构隧道管片纵缝抗渗性能试验用管片试件,尤其是涉及一种用于盾构隧道管片纵缝抗渗性能试验的管片试件及其制造方法。
背景技术
对于盾构隧道,渗漏水一直是困扰地铁结构安全和正常运营的突出难题。调查发现,绝大多数渗漏水均发生于管片接缝部位,而接缝的防水密封一般采用粘贴在靠近管片外弧面的弹性密封垫来实现。由此可见,隧道接缝的抗渗性能对于盾构隧道的可靠服役至关重要。盾构隧道的接缝可划分为纵向接缝(管片-管片)和环向接缝(衬砌环-衬砌环)。因此,为保证盾构隧道在横向和纵向两个维度上的防水密封,需要分别针对纵向接缝和环向接缝进行抗渗机理研究。鉴于管片纵缝的受力性态、防水密封性能的机制规律十分复杂,难以在理论分析上取得突破,因而需采用试验分析的方法来确定。
申请号为CN101929911A的中国发明专利公布了一种盾构隧道弹性密封垫“一字型”水密性检验装置,该装置包括相贴合的两块矩形盖板,盖板上设置有出气孔和进水孔,两块盖板贴合面中央位置开设有相对应的矩形槽;两块盖板由盖板周缘分布的螺栓紧固贴合,盖板侧向安装有限位板。采用该发明装置可精确验证弹性密封垫在不同管片张开量、不同错台的情况下的防水能力,使得防水能力的评价体系更加精准。公开号为CN104075854A的发明专利公布了一种盾构管片接头抗渗性能试验装置,包括:高压供水系统,用于提供压力水或液体;试验台,用于安装试件、提供压力水(液体)作用空间以及实现管片接头接触状态的模拟;量测系统,用于设置试验工况参数以及测量试验过程数据。所述高压供水系统和所述试验台采用耐高压软管连接;所述量测系统通过电缆将安装在所述试验台上的各类传感器与记录仪、计算机连接读数的方式进行。上述两篇对比专利均是基于小比例尺的室内模型试验,且采用钢模夹具模拟管片,不能反映弹性密封垫橡胶材料和混凝土沟槽的真实接触性态,因而试验结果与工程实际存在较大出入,结果的正确性有待进一步的验证。
综上所述,鉴于盾构隧道管片接缝复杂的受力状态和接触性态,小比例尺的室内模型试验难以准确反映其真实可靠的防水密封机理,因此研发一种可用于足尺管片纵缝抗渗性能试验的管片试件制造方法,对于推动盾构隧道防水技术领域的深入发展至关重要。
发明内容
本发明的目的就是为了克服上述现有技术存在的缺陷而提供一种用于管片纵缝抗渗性能试验的管片试件及其制造方法。
本发明的目的可以通过以下技术方案来实现:
一种用于管片纵缝抗渗性能试验的管片试件,包括弧形的第一管片与弧形的第二管片,所述的第一管片与第二管片相对一端均为密封面,所述的第一管片和第二管片中均设置有用于穿过连接螺栓的螺栓孔道,通过连接螺栓使第一管片与第二管片的密封面相互压紧,在第一管片和第二管片的密封面上均设置有框形沟槽,在框形沟槽内嵌有首尾封闭连接的弹性密封垫,在第一管片上还设置有一注水孔道,该注水孔道的一端位于第一管片的上圆弧表面,注水孔道的另一端位于第一管片上框形沟槽的内框所限定的区域内。
所述的弹性密封垫的内圈与第一管片、第二管片的密封面所限定的空间构成水压腔,压紧第一管片和第二管片的连接螺栓从水压腔中穿过。
所述的连接螺栓为弧形弯螺栓,其两个连接端设有螺栓密封垫圈。
所述的螺栓孔道为圆弧形状的管状通道,螺栓孔道的一端贯通至第一管片或第二管片内圆弧面,另一端位于框形沟槽的内框所限定的区域内,在第一管片和第二管片的密封面对接时,第一管片和第二管片的螺栓孔道连通。
所述的第一管片和第二管片中各有两个螺栓孔道,第一管片和第二管片的螺栓孔道配对设置。
用于管片纵缝抗渗性能试验的管片试件的制作方法,包括以下步骤:
制作第一管片和第二管片的钢筋笼,在钢筋笼纵缝接触面位置处预留框形沟槽预埋件的安装位,将框形沟槽预埋件安装在钢筋笼结构的纵缝接触面;在第一管片的外弧面和纵缝接触面之间的某区域内预留注水孔道的安装位,将注水孔道预埋件安装在钢筋笼结构的该区域内,注水孔道预埋件靠外弧面侧通过螺纹与水压加载系统连接;之后将钢筋笼结构、框形沟槽预埋件和注水孔道预埋件放入现有钢模中固定并进行试件的混凝土浇筑。
所述的第一管片和第二管片均由钢筋混凝土制成。
所述的第一管片和第二管片利用盾构隧道现有管片钢模进行制作。
与现有技术相比,本发明采用盾构隧道现有管片钢模进行试验构件的制作,充分利用了既有钢模的使用价值,保证了试验构件与实际管片制作精度的一致性,进而保证了试验数据的准确性,而且减少了试件的钢模加工成本和造价,缩短了试验时间,具有良好的经济效益。
附图说明
图1为第一管片和第二管片连接结构示意图;
图2为第一管片密封连接面结构示意图;
图3为第一管片A-A剖视图;
图4为第二管片密封连接面结构示意图;
图5为第二管片B-B剖视图。
具体实施方式
下面结合附图和具体实施例对本发明进行详细说明。
实施例
一种用于管片纵缝抗渗性能试验的管片试件,如图1~图5所示,包括弧形的第一管片1与弧形的第二管片2,第一管片1与第二管片2相对一端均为密封面,第一管片1和第二管片2中均设置有用于穿过连接螺栓6的螺栓孔道9,通过连接螺栓6使第一管片1与第二管片2的密封面相互压紧,在第一管片1和第二管片2的密封面上均设置有框形沟槽3,在框形沟槽3内嵌有首尾封闭连接的弹性密封垫4,在第一管片1上还设置有一注水孔道5,该注水孔道5的一端位于第一管片1的上圆弧表面,注水孔道5的另一端位于第一管片1上框形沟槽3的内框所限定的区域内。弹性密封垫4的内圈与第一管片1、第二管片2的密封面所限定的空间构成水压腔7,压紧第一管片1和第二管片2的连接螺栓6从水压腔7中穿过。连接螺栓6为弧形弯螺栓,其两个连接端设有螺栓密封垫圈8。第一管片1和第二管片2中各有两个螺栓孔道9,第一管片1和第二管片2的螺栓孔道9配对设置。螺栓孔道9为圆弧形状的管状通道,螺栓孔道9的一端贯通至第一管片1或第二管片2内圆弧面,另一端位于框形沟槽3的内框所限定的区域内,在第一管片1和第二管片2的密封面对接时,第一管片1和第二管片2的螺栓孔道9连通。
用于管片纵缝抗渗性能试验的管片试件的制作方法,包括以下步骤:
首先,制作第一管片1和第二管片2的钢筋笼。
对于第一管片:按照纵缝接触面位置在钢筋笼的相对应位置处预留框形沟槽预埋件的安装位,按照纵缝接触面和外弧面之间区域位置在钢筋笼的相对应位置处预留注水孔道预埋件的安装位;将框形沟槽预埋件拼接在钢筋笼的纵缝接触面位置,将注水孔道预埋件拼接在钢筋笼的纵缝接触面和外弧面之间位置;之后将钢筋笼、框形沟槽预埋件和注水孔道预埋件放入现有钢模中固定,并进行试件的混凝土浇筑,进行相应的养护工作。
对于第二管片:按照纵缝接触面位置在钢筋笼的相对应位置处预留框形沟槽预埋件的安装位;将框形沟槽预埋件拼接在钢筋笼的纵缝接触面位置;之后将钢筋笼和框形沟槽预埋件放入现有钢模中固定,并进行试件的混凝土浇筑,进行相应的养护工作。
制作第一管片和第二管片的钢筋笼的钢筋材料选用通用管片材料,试件钢筋笼的尺寸规格与通用管片的钢筋笼基本相同,区别在于对第一管片:钢筋笼的纵缝接触面上预留框形沟槽预埋件的安装位,为框形沟槽预埋件安装就位,钢筋笼的纵缝接触面和外弧面之间区域预留注水孔道预埋件的安装位,为注水孔道预埋件安装就位;对第二管片:钢筋笼的纵缝接触面上预留框形沟槽预埋件的安装位,为框形沟槽预埋件安装就位。
上述的对实施例的描述是为便于该技术领域的普通技术人员能理解和使用发明。熟悉本领域技术的人员显然可以容易地对这些实施例做出各种修改,并把在此说明的一般原理应用到其他实施例中而不必经过创造性的劳动。因此,本发明不限于上述实施例,本领域技术人员根据本发明的揭示,不脱离本发明范畴所做出的改进和修改都应该在本发明的保护范围之内。

Claims (8)

1.一种用于管片纵缝抗渗性能试验的管片试件,其特征在于,包括弧形的第一管片(1)与弧形的第二管片(2),所述的第一管片(1)与第二管片(2)相对一端均为密封面,所述的第一管片(1)和第二管片(2)中均设置有用于穿过连接螺栓(6)的螺栓孔道(9),通过连接螺栓(6)使第一管片(1)与第二管片(2)的密封面相互压紧,在第一管片(1)和第二管片(2)的密封面上均设置有框形沟槽(3),在框形沟槽(3)内嵌有首尾封闭连接的弹性密封垫(4),在第一管片(1)上还设置有一注水孔道(5),该注水孔道(5)的一端位于第一管片(1)的上圆弧表面,注水孔道(5)的另一端位于第一管片(1)上框形沟槽(3)的内框所限定的区域内。
2.根据权利要求1所述的一种用于管片纵缝抗渗性能试验的管片试件,其特征在于,所述的弹性密封垫(4)的内圈与第一管片(1)、第二管片(2)的密封面所限定的空间构成水压腔(7),压紧第一管片(1)和第二管片(2)的连接螺栓(6)从水压腔(7)中穿过。
3.根据权利要求1所述的一种用于管片纵缝抗渗性能试验的管片试件,其特征在于,所述的连接螺栓(6)为弧形弯螺栓,其两个连接端设有螺栓密封垫圈(8)。
4.根据权利要求1所述的一种用于管片纵缝抗渗性能试验的管片试件,其特征在于,所述的螺栓孔道(9)为圆弧形状的管状通道,螺栓孔道(9)的一端贯通至第一管片(1)或第二管片(2)内圆弧面,另一端位于框形沟槽(3)的内框所限定的区域内,在第一管片(1)和第二管片(2)的密封面对接时,第一管片(1)和第二管片(2)的螺栓孔道(9)连通。
5.根据权利要求1所述的一种用于管片纵缝抗渗性能试验的管片试件,其特征在于,所述的第一管片(1)和第二管片(2)中各有两个螺栓孔道(9),第一管片(1)和第二管片(2)的螺栓孔道(9)配对设置。
6.一种如权利要求1所述的用于管片纵缝抗渗性能试验的管片试件的制作方法,其特征在于,包括以下步骤:
制作第一管片(1)和第二管片(2)的钢筋笼,在钢筋笼纵缝接触面位置处预留框形沟槽预埋件的安装位,将框形沟槽预埋件安装在钢筋笼结构的纵缝接触面;在第一管片(1)的外弧面和纵缝接触面之间的某区域内预留注水孔道(5)的安装位,将注水孔道预埋件安装在钢筋笼结构的该区域内,注水孔道预埋件靠外弧面侧通过螺纹与水压加载系统连接;之后将钢筋笼结构、框形沟槽预埋件和注水孔道预埋件放入现有钢模中固定并进行试件的混凝土浇筑。
7.根据权利要求6所述的一种用于管片纵缝抗渗性能试验的管片试件的制作方法,其特征在于,所述的第一管片(1)和第二管片(2)均由钢筋混凝土制成。
8.根据权利要求6所述的一种用于管片纵缝抗渗性能试验的管片试件的制作方法,其特征在于,所述的第一管片(1)和第二管片(2)利用盾构隧道现有管片钢模进行制作。
CN201510609224.7A 2015-09-23 2015-09-23 用于管片纵缝抗渗性能试验的管片试件及其制造方法 Active CN105181253B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510609224.7A CN105181253B (zh) 2015-09-23 2015-09-23 用于管片纵缝抗渗性能试验的管片试件及其制造方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510609224.7A CN105181253B (zh) 2015-09-23 2015-09-23 用于管片纵缝抗渗性能试验的管片试件及其制造方法

Publications (2)

Publication Number Publication Date
CN105181253A true CN105181253A (zh) 2015-12-23
CN105181253B CN105181253B (zh) 2017-11-07

Family

ID=54903495

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510609224.7A Active CN105181253B (zh) 2015-09-23 2015-09-23 用于管片纵缝抗渗性能试验的管片试件及其制造方法

Country Status (1)

Country Link
CN (1) CN105181253B (zh)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105738220A (zh) * 2016-04-12 2016-07-06 天津大学 考虑土体影响的管片弹性密封垫水密性试验方法
CN106017961A (zh) * 2016-07-01 2016-10-12 上海交通大学 一种模拟盾构隧道管片接头的试验模型
CN106050275A (zh) * 2016-07-13 2016-10-26 同济大学 一种盾构隧道管片螺栓孔密封防水装置
CN106969884A (zh) * 2017-04-21 2017-07-21 中铁第四勘察设计院集团有限公司 一种隧道管片弹性密封垫的防水试验方法及装置
CN107036763A (zh) * 2017-03-09 2017-08-11 同济大学 盾构管片接头渗漏水的试验方法
CN108286448A (zh) * 2018-04-27 2018-07-17 西南石油大学 一种盾构隧道管片防水密封垫
CN108709694A (zh) * 2018-03-28 2018-10-26 中铁十二局集团有限公司 适用于隧道盾构弧形管片的水密性检验装置及试验方法
CN109209433A (zh) * 2018-10-31 2019-01-15 上海隧道工程有限公司 管片密封垫的预埋方法
CN109209434A (zh) * 2018-10-31 2019-01-15 上海隧道工程有限公司 预埋式管片密封垫及其预埋方法
CN109853855A (zh) * 2018-12-19 2019-06-07 苏州交通工程集团有限公司 管片弧面型钢筋高精度保护层施工工艺
CN110132503A (zh) * 2019-06-14 2019-08-16 国网上海市电力公司 一种透明式盾构隧道管片高压气密性模型试验箱
CN110174225A (zh) * 2019-06-14 2019-08-27 国网上海市电力公司 一种可调节张开角度的盾构隧道管片接头气密性模拟装置
CN111794768A (zh) * 2020-03-31 2020-10-20 中铁十六局集团北京轨道交通工程建设有限公司 推压紧固与弯螺栓组合的盾构管片接头及其使用方法
CN112171864A (zh) * 2020-09-11 2021-01-05 中国电建集团华东勘测设计研究院有限公司 一种分片预制装配式混凝土塔架管片预制模具及预制工艺
CN112761681A (zh) * 2021-02-04 2021-05-07 西南交通大学 一种高水头盾构隧道管片的螺栓孔防水结构

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006118307A (ja) * 2004-10-25 2006-05-11 Kumagai Gumi Co Ltd セグメント及びセグメントの製造方法
CN101338682A (zh) * 2008-08-08 2009-01-07 广州市建筑机械施工有限公司 地铁专用盾构管片预制施工工法
CN201606084U (zh) * 2009-06-09 2010-10-13 中铁第四勘察设计院集团有限公司 一种盾构隧道管片防水结构
WO2012168729A2 (en) * 2011-06-09 2012-12-13 Macrete Ireland Limited Lining segment
KR101256494B1 (ko) * 2013-02-14 2013-04-19 이시카와지마 겐자이 고교 가부시키가이샤 천정부 및 종방향 결합부 접합성능이 증진된 프리캐스트 터널구조물 시공방법
CN104612710A (zh) * 2015-02-02 2015-05-13 同济大学 一种盾构隧道管片纵缝接头
CN104865012A (zh) * 2015-05-08 2015-08-26 同济大学 隧道接缝防水性能试验装置及试验方法
CN205091091U (zh) * 2015-09-23 2016-03-16 同济大学 用于管片纵缝抗渗性能试验的管片试件

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006118307A (ja) * 2004-10-25 2006-05-11 Kumagai Gumi Co Ltd セグメント及びセグメントの製造方法
CN101338682A (zh) * 2008-08-08 2009-01-07 广州市建筑机械施工有限公司 地铁专用盾构管片预制施工工法
CN201606084U (zh) * 2009-06-09 2010-10-13 中铁第四勘察设计院集团有限公司 一种盾构隧道管片防水结构
WO2012168729A2 (en) * 2011-06-09 2012-12-13 Macrete Ireland Limited Lining segment
KR101256494B1 (ko) * 2013-02-14 2013-04-19 이시카와지마 겐자이 고교 가부시키가이샤 천정부 및 종방향 결합부 접합성능이 증진된 프리캐스트 터널구조물 시공방법
CN104612710A (zh) * 2015-02-02 2015-05-13 同济大学 一种盾构隧道管片纵缝接头
CN104865012A (zh) * 2015-05-08 2015-08-26 同济大学 隧道接缝防水性能试验装置及试验方法
CN205091091U (zh) * 2015-09-23 2016-03-16 同济大学 用于管片纵缝抗渗性能试验的管片试件

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
沈佳佳: "地铁盾构隧道管片接头抗渗与耐久性能演化研究", 《中国优秀硕士学位论文全文数据库 工程科技II辑》 *
罗云峰等: "地铁管片的力学性能及抗渗性试验方法的探讨", 《混凝土与水泥制品》 *
赵运臣等: "武汉长江隧道管片接缝防水密封垫设计与试验研究", 《现代隧道技术》 *

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105738220B (zh) * 2016-04-12 2018-11-09 天津大学 考虑土体影响的管片弹性密封垫水密性试验方法
CN105738220A (zh) * 2016-04-12 2016-07-06 天津大学 考虑土体影响的管片弹性密封垫水密性试验方法
CN106017961A (zh) * 2016-07-01 2016-10-12 上海交通大学 一种模拟盾构隧道管片接头的试验模型
CN106050275B (zh) * 2016-07-13 2018-10-26 同济大学 一种盾构隧道管片螺栓孔密封防水装置
CN106050275A (zh) * 2016-07-13 2016-10-26 同济大学 一种盾构隧道管片螺栓孔密封防水装置
CN107036763A (zh) * 2017-03-09 2017-08-11 同济大学 盾构管片接头渗漏水的试验方法
CN107036763B (zh) * 2017-03-09 2019-01-25 同济大学 盾构管片接头渗漏水的试验方法
CN106969884A (zh) * 2017-04-21 2017-07-21 中铁第四勘察设计院集团有限公司 一种隧道管片弹性密封垫的防水试验方法及装置
CN108709694A (zh) * 2018-03-28 2018-10-26 中铁十二局集团有限公司 适用于隧道盾构弧形管片的水密性检验装置及试验方法
CN108286448A (zh) * 2018-04-27 2018-07-17 西南石油大学 一种盾构隧道管片防水密封垫
CN109209433A (zh) * 2018-10-31 2019-01-15 上海隧道工程有限公司 管片密封垫的预埋方法
CN109209434A (zh) * 2018-10-31 2019-01-15 上海隧道工程有限公司 预埋式管片密封垫及其预埋方法
CN109853855A (zh) * 2018-12-19 2019-06-07 苏州交通工程集团有限公司 管片弧面型钢筋高精度保护层施工工艺
CN110132503A (zh) * 2019-06-14 2019-08-16 国网上海市电力公司 一种透明式盾构隧道管片高压气密性模型试验箱
CN110174225A (zh) * 2019-06-14 2019-08-27 国网上海市电力公司 一种可调节张开角度的盾构隧道管片接头气密性模拟装置
CN111794768A (zh) * 2020-03-31 2020-10-20 中铁十六局集团北京轨道交通工程建设有限公司 推压紧固与弯螺栓组合的盾构管片接头及其使用方法
CN112171864A (zh) * 2020-09-11 2021-01-05 中国电建集团华东勘测设计研究院有限公司 一种分片预制装配式混凝土塔架管片预制模具及预制工艺
CN112761681A (zh) * 2021-02-04 2021-05-07 西南交通大学 一种高水头盾构隧道管片的螺栓孔防水结构
CN112761681B (zh) * 2021-02-04 2022-04-22 西南交通大学 一种高水头盾构隧道管片的螺栓孔防水结构

Also Published As

Publication number Publication date
CN105181253B (zh) 2017-11-07

Similar Documents

Publication Publication Date Title
CN105181253A (zh) 用于管片纵缝抗渗性能试验的管片试件及其制造方法
CN101929911B (zh) 盾构隧道弹性密封垫“一字型”水密性检验装置
CN101929910B (zh) 盾构隧道弹性密封垫 “t字型”水密性检验装置
CN105403366A (zh) 盾构隧道管片环缝抗渗性能试验系统
CN104865012A (zh) 隧道接缝防水性能试验装置及试验方法
CN104075854A (zh) 盾构管片接头抗渗性能试验装置
CN105300601A (zh) 盾构隧道管片纵缝抗渗性能试验系统
CN204924568U (zh) 隧道接缝防水性能试验装置
CN103698218A (zh) 一种模拟不同应力条件下混凝土构件水力劈裂试验装置
EP3625437B1 (en) Pre-cast segment for tunnels and method for producing and monitoring said pre-cast segment
BRPI0611032A2 (pt) obtenção de informação sobre vazamentos em tubulações
CN208969089U (zh) 漏点位置、漏缝宽度可控的海底盾构隧道模型试验装置
Dinno et al. An experimental investigation into the plastic behaviour of flush nozzles in spherical pressure vessels
CN205091091U (zh) 用于管片纵缝抗渗性能试验的管片试件
CN205246284U (zh) 盾构隧道管片环缝抗渗性能试验系统
CN110700794A (zh) 一种多分支水平井煤层瓦斯抽采物理模拟实验系统
CN102207366A (zh) 应变传感器结构及安装方法
CN109738302B (zh) 一种用于岩石直剪-渗流的试验装置及方法
CN205091090U (zh) 一种盾构隧道管片环缝抗渗性能试验用试件
KR101097414B1 (ko) 배관진동 평가방법
KR101604306B1 (ko) 방사능 격납 건물의 방사능 유출 모니터링 시스템
CN203949766U (zh) 盾构管片接头抗渗性能试验装置
CN210221485U (zh) 一种气体流量测试气体排空装置
CN105651670B (zh) 二维加压通水机构及应用其的二维岩石试样渗流试验装置
KR20150114192A (ko) 고무확장조인트에 대한 내압성능 시험장치 및 그 제조방법

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20151223

Assignee: TONGJI ARCHITECTURAL DESIGN (Group) Co.,Ltd.

Assignor: TONGJI University

Contract record no.: X2021980004660

Denomination of invention: Segment specimen used for impermeability test of segment longitudinal seam and its manufacturing method

Granted publication date: 20171107

License type: Exclusive License

Record date: 20210611

EE01 Entry into force of recordation of patent licensing contract