CN105178248A - 软土河坡混凝土植绿护坡方法 - Google Patents

软土河坡混凝土植绿护坡方法 Download PDF

Info

Publication number
CN105178248A
CN105178248A CN201510458103.7A CN201510458103A CN105178248A CN 105178248 A CN105178248 A CN 105178248A CN 201510458103 A CN201510458103 A CN 201510458103A CN 105178248 A CN105178248 A CN 105178248A
Authority
CN
China
Prior art keywords
soil
slope
concrete
water
seedling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510458103.7A
Other languages
English (en)
Other versions
CN105178248B (zh
Inventor
葛加君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Xineng Environmental Protection Technology Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510458103.7A priority Critical patent/CN105178248B/zh
Publication of CN105178248A publication Critical patent/CN105178248A/zh
Application granted granted Critical
Publication of CN105178248B publication Critical patent/CN105178248B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Cultivation Of Plants (AREA)

Abstract

本发明公开了一种软土河坡混凝土植绿护坡方法,包括坡体修整、土壤固化剂灌入、混凝土护坡浇筑、串筋、开孔、灌入营养土、植物种植、维护等步骤。本发明施工方便、效果好。植物成活率达95%以上。

Description

软土河坡混凝土植绿护坡方法
技术领域
本发明涉及一种软土河坡混凝土植绿护坡方法。
背景技术
坡基体混凝土植绿护坡是充分利用坡体资源,提高绿化面积,改善生态环境的一种很好途径。对软土坡体,现有技术采用采用直接植绿法,务必使之劳而无功,遭受大雨侵袭植被冲毁,坡基体塌方,且夏季植绿一般成活率较低。
发明内容
本发明的目的在于提供一种方便、效果好的软土河坡混凝土植绿护坡方法。
本发明的技术解决方案是:
一种软土河坡混凝土植绿护坡方法,其特征是:包括下列步骤:
(一)坡体修整:按原坡体坡度进行修整;如塌方面积较大,塌方量较大可将坡度放缓,但坡比不大于1:2,修补方法:进行削高填低,并用蛙式打夯机强夯2遍以上,再进行坡体修整,用坡比测量器测量,允许偏差系数±0.1,用水平仪测量,平整度偏差±2mm;
(二)土壤固化剂灌入
1)土壤固化剂配置:采用石灰、水泥、砂土;将砂土磨细过筛,将石灰成扬灰,并过筛,剔除石块;再将三种物质按1:1:1质量比例用搅拌机搅拌;
2)土壤固化剂灌入量:对坡体土壤压实系数≥1.5,灌入土壤固化剂土体体积的5‰~10‰;
3)土壤固化剂灌入方法:按纵横间距1.5m,采用钢管法插入灌入;选用长3.5m,φ150mm空心钢管,并将钢管尾部设置成150mm尖头状,头部焊接吊环,然后采用人工纤插与锤击相结合方法,插入土中,插入前将钢管外侧涂一层润滑油;当固化剂流入后,采用人工或机械拨出钢管,再转入第二个灌入点,当土壤固化剂灌入48小时后,进行取土测试,采用环刀测试仪测试,测试结果土壤压实系数≤1,如达不到应加大灌入量,直至检验合格;
(三)混凝土护坡浇筑:
1)模袋制作:选用锦纶、纤维或丙纶材料,模袋厚度为混凝土浇筑厚度,宽度3-4m,长度8-10m,模袋叠缝≥50mm,针脚间距≤8mm;
2)模袋铺设:采用横向铺设,纵向排列,灌浆口设置在坡体上方;
3)混凝土配置、搅拌;
4)安装灌浆机械:采用混凝土喷射灌注机,安装在坡体上部平台面上,安装前设置围档、警示牌,安装基地用电夯反复夯实提高平台基地承载力;
5)灌浆:将混凝土喷射灌注机机射头,插入模袋进料口,并将进料口用钢绳扎紧,启动灌注机,当灌注机上的流量表读数达到模袋饱和度98%时立即关闭灌注机;
6)压浆:选用长度≥坡体宽度300mm,宽度1000mm,厚度100mm木质或钢质板,覆盖在模袋上面,用平板振动器反复振动,直至混凝土含水率≤20%;
(四)串筋
1)竹筋材料选择:选用三年以上生山竹、毛竹或青竹;
2)竹筋制作:用蔑刀削成竹片,竹片长度≥15000mm,宽度为80-100mm,厚度为3-5mm,将竹筋头削成100mm尖头状;
3)串筋间距:按照纵横间距2000mm串插;
4)串筋方法:在混凝土初凝前,采用人工从混凝土面上穿过混凝土层直至插入坡基体之中;
5)复浆:当竹筋插入混凝土面共坡基体后,再次用木板或钢板覆盖在混凝土模袋上面,用平板振动器反复振动,并使表面析出水份;
(五)开孔
按照设定的株距行距,用木线确定开孔位置,采用金刚石钻孔机,配置设置的孔径直径钻头进行钻孔,钻孔深度为混凝土厚度;
(六)灌入营养土
1)营养土材料配置:按田园土、腐叶土、有机畜禽粪肥重量比6:3:1进行配置;
2)灌入:采用人工将营养土灌入种植植物孔洞内,灌土量以灌入孔洞口面为宜;
(七)植物种植:采用种子种植或植物植载方法;
A)种子种植
1)种子处理:剔除瘪籽、破籽、蛀籽,并用多菌灵水液1:200倍,浸种24~48小时,然后捞出来冷干;
2)播种:采用人工播种法,每穴2-3粒,种子放入种穴中,采用营养土覆土,覆土厚度15mm;
B)移栽种植:
1)起苗:在起苗前一天晚上将苗木基地浇足水,第二天上午起苗;
2)栋苗:将所起苗木剔除断苗、死苗、病苗、小苗、过大苗、保持所栽苗大小一致;
3)剪苗:修剪过长主须根以及叉枝、枯枝;
4)浸苗:用多菌灵水液1:200倍浸苗根,浸苗时间为12~24小时;
5)栽植:将苗木直接垂直插入苗孔穴内,然后灌入营养土,并用木棒将苗木根基四周土捣实;
6)浇水:每株浇足清水1kg以上,确保200mm深度浇透;
(八)维护
A)对种子种植坡地覆盖保养覆
1)保养保温膜制作:
选用柔性0.5mm厚的塑料薄膜和φ1mm空心塑胶管及φ5mm空心塑胶管;其中φ1mm空心塑胶管作支流管,φ5mm塑胶管作主流管,将支流管侧面按0.5cm距离钻孔,孔径为0.1m;主流管按2cm距离钻眼孔,孔径为1mm;然后将塑料薄膜平铺在制作台上,刷粘合剂,按间距2cm横向铺贴φ1mm空心胶管,铺贴时眼孔朝上,然后纵向顶面铺贴2-3根φ5mm塑胶管,并将φ1mm空心塑胶管插入φ5mm孔眼,周边涂入粘合剂,然后再将预选准备的眼状膜覆盖上面,完成保养保温膜制作;
所述眼状膜制作:在商品膜上按横向2cm间距,纵向0.5cm间距,钻φ0.1孔径眼;
2)保养保温膜铺贴:将保温保养膜平铺在所需保养的坡面上,铺贴后,在保养保温膜上覆盖保护网;保护网由聚丙烯线编制成,网眼为10×10cm,并将网绷紧压入地面;
3)贮水箱制作与安装:选择塑胶桶或铁桶,在桶底安装控水阀门和水咀,水咀咀头直径≤5mm;桶可装水50kg以上;水箱制作后,在保养保温膜铺贴后,进行水箱安装,水箱高度高于所保养混体高度的2m以上,安装后,将主流管连接贮水箱水咀,然后将水箱灌满水,打开阀门,实施保养;
B)搭设遮阳棚:遮阳棚由构体,遮阳帘,保护网制成;遮阳架体选择金属管、木管或竹管制作,长高度1.5m-2.0m;遮阳帘用麦草编织;保护网用草纸或尼龙绳编织,网眼空为20cm×20cm,立管埋深度为300mm,然后绑扎横管,用麻丝或钢丝绑扎,形成架体,覆盖遮阳帘与保护网;
C)拆除维护设施:当种粒苗木出土后,掀去保养膜;当种植苗木或现栽苗木3月后,拆去遮阳设施;
D)间苗补苗:当种植苗木3月后进行间苗补苗,每穴保留2株;
E)施肥喷药:当苗木出土或现栽3个月后,采用水与人畜尿20:1稀释进行浇施,并喷施1:500液多菌灵液。
本发明施工方便、效果好。植物成活率达95%以上。
下面结合实施例对本发明作进一步说明。
具体实施方式
一种软土河坡混凝土植绿护坡方法,包括下列步骤:
(一)坡体修整:按原坡体坡度进行修整;如塌方面积较大,塌方量较大可将坡度放缓,但坡比不大于1:2,修补方法:进行削高填低,并用蛙式打夯机强夯2遍以上,再进行坡体修整,用坡比测量器测量,允许偏差系数±0.1,用水平仪测量,平整度偏差±2mm;
(二)土壤固化剂灌入
1)土壤固化剂配置:采用石灰、水泥、砂土;将砂土磨细过筛,将石灰成扬灰,并过筛,剔除石块;再将三种物质按1:1:1质量比例用搅拌机搅拌;
2)土壤固化剂灌入量:对坡体土壤压实系数≥1.5,灌入土壤固化剂土体体积的5‰~10‰;
3)土壤固化剂灌入方法:按纵横间距1.5m,采用钢管法插入灌入;选用长3.5m,φ150mm空心钢管,并将钢管尾部设置成150mm尖头状,头部焊接吊环,然后采用人工纤插与锤击相结合方法,插入土中,插入前将钢管外侧涂一层润滑油;当固化剂流入后,采用人工或机械拨出钢管,再转入第二个灌入点,当土壤固化剂灌入48小时后,进行取土测试,采用环刀测试仪测试,测试结果土壤压实系数≤1,如达不到应加大灌入量,直至检验合格;
(三)混凝土护坡浇筑:
1)模袋制作:选用锦纶、纤维或丙纶材料,模袋厚度为混凝土浇筑厚度,宽度3-4m,长度8-10m,模袋叠缝≥50mm,针脚间距≤8mm;
2)模袋铺设:采用横向铺设,纵向排列,灌浆口设置在坡体上方;
3)混凝土配置、搅拌;
4)安装灌浆机械:采用混凝土喷射灌注机,安装在坡体上部平台面上,安装前设置围档、警示牌,安装基地用电夯反复夯实提高平台基地承载力;
5)灌浆:将混凝土喷射灌注机机射头,插入模袋进料口,并将进料口用钢绳扎紧,启动灌注机,当灌注机上的流量表读数达到模袋饱和度98%时立即关闭灌注机;
6)压浆:选用长度≥坡体宽度300mm,宽度1000mm,厚度100mm木质或钢质板,覆盖在模袋上面,用平板振动器反复振动,直至混凝土含水率≤20%;
(四)串筋
1)竹筋材料选择:选用三年以上生山竹、毛竹或青竹;
2)竹筋制作:用蔑刀削成竹片,竹片长度≥15000mm,宽度为80-100mm,厚度为3-5mm,将竹筋头削成100mm尖头状;
3)串筋间距:按照纵横间距2000mm串插;
4)串筋方法:在混凝土初凝前,采用人工从混凝土面上穿过混凝土层直至插入坡基体之中;
5)复浆:当竹筋插入混凝土面共坡基体后,再次用木板或钢板覆盖在混凝土模袋上面,用平板振动器反复振动,并使表面析出水份;
(五)开孔
按照设定的株距行距,用木线确定开孔位置,采用金刚石钻孔机,配置设置的孔径直径钻头进行钻孔,钻孔深度为混凝土厚度;
(六)灌入营养土
1)营养土材料配置:按田园土、腐叶土、有机畜禽粪肥重量比6:3:1进行配置;
2)灌入:采用人工将营养土灌入种植植物孔洞内,灌土量以灌入孔洞口面为宜;
(七)植物种植:采用种子种植或植物植载方法;
A)种子种植
1)种子处理:剔除瘪籽、破籽、蛀籽,并用多菌灵水液1:200倍,浸种24~48小时,然后捞出来冷干;
2)播种:采用人工播种法,每穴2-3粒,种子放入种穴中,采用营养土覆土,覆土厚度15mm;
B)移栽种植:
1)起苗:在起苗前一天晚上将苗木基地浇足水,第二天上午起苗;
2)栋苗:将所起苗木剔除断苗、死苗、病苗、小苗、过大苗、保持所栽苗大小一致;
3)剪苗:修剪过长主须根以及叉枝、枯枝;
4)浸苗:用多菌灵水液1:200倍浸苗根,浸苗时间为12~24小时;
5)栽植:将苗木直接垂直插入苗孔穴内,然后灌入营养土,并用木棒将苗木根基四周土捣实;
6)浇水:每株浇足清水1kg以上,确保200mm深度浇透;
(八)维护
A)对种子种植坡地覆盖保养覆
1)保养保温膜制作:
选用柔性0.5mm厚的塑料薄膜和φ1mm空心塑胶管及φ5mm空心塑胶管;其中φ1mm空心塑胶管作支流管,φ5mm塑胶管作主流管,将支流管侧面按0.5cm距离钻孔,孔径为0.1m;主流管按2cm距离钻眼孔,孔径为1mm;然后将塑料薄膜平铺在制作台上,刷粘合剂,按间距2cm横向铺贴φ1mm空心胶管,铺贴时眼孔朝上,然后纵向顶面铺贴2-3根φ5mm塑胶管,并将φ1mm空心塑胶管插入φ5mm孔眼,周边涂入粘合剂,然后再将预选准备的眼状膜覆盖上面,完成保养保温膜制作;
所述眼状膜制作:在商品膜上按横向2cm间距,纵向0.5cm间距,钻φ0.1孔径眼;
2)保养保温膜铺贴:将保温保养膜平铺在所需保养的坡面上,铺贴后,在保养保温膜上覆盖保护网;保护网由聚丙烯线编制成,网眼为10×10cm,并将网绷紧压入地面;
3)贮水箱制作与安装:选择塑胶桶或铁桶,在桶底安装控水阀门和水咀,水咀咀头直径≤5mm;桶可装水50kg以上;水箱制作后,在保养保温膜铺贴后,进行水箱安装,水箱高度高于所保养混体高度的2m以上,安装后,将主流管连接贮水箱水咀,然后将水箱灌满水,打开阀门,实施保养;
B)搭设遮阳棚:遮阳棚由构体,遮阳帘,保护网制成;遮阳架体选择金属管、木管或竹管制作,长高度1.5m-2.0m;遮阳帘用麦草编织;保护网用草纸或尼龙绳编织,网眼空为20cm×20cm,立管埋深度为300mm,然后绑扎横管,用麻丝或钢丝绑扎,形成架体,覆盖遮阳帘与保护网;
C)拆除维护设施:当种粒苗木出土后,掀去保养膜;当种植苗木或现栽苗木3月后,拆去遮阳设施;
D)间苗补苗:当种植苗木3月后进行间苗补苗,每穴保留2株;
E)施肥喷药:当苗木出土或现栽3个月后,采用水与人畜尿20:1稀释进行浇施,并喷施1:500液多菌灵液。
然后进行正常维护即可。

Claims (1)

1.一种软土河坡混凝土植绿护坡方法,其特征是:包括下列步骤:
(一)坡体修整:按原坡体坡度进行修整;如塌方面积较大,塌方量较大可将坡度放缓,但坡比不大于1:2,修补方法:进行削高填低,并用蛙式打夯机强夯2遍以上,再进行坡体修整,用坡比测量器测量,允许偏差系数±0.1,用水平仪测量,平整度偏差±2mm;
(二)土壤固化剂灌入
1)土壤固化剂配置:采用石灰、水泥、砂土;将砂土磨细过筛,将石灰成扬灰,并过筛,剔除石块;再将三种物质按1:1:1质量比例用搅拌机搅拌;
2)土壤固化剂灌入量:对坡体土壤压实系数≥1.5,灌入土壤固化剂土体体积的5‰~10‰;
3)土壤固化剂灌入方法:按纵横间距1.5m,采用钢管法插入灌入;选用长3.5m,φ150mm空心钢管,并将钢管尾部设置成150mm尖头状,头部焊接吊环,然后采用人工纤插与锤击相结合方法,插入土中,插入前将钢管外侧涂一层润滑油;当固化剂流入后,采用人工或机械拨出钢管,再转入第二个灌入点,当土壤固化剂灌入48小时后,进行取土测试,采用环刀测试仪测试,测试结果土壤压实系数≤1,如达不到应加大灌入量,直至检验合格;
(三)混凝土护坡浇筑:
1)模袋制作:选用锦纶、纤维或丙纶材料,模袋厚度为混凝土浇筑厚度,宽度3-4m,长度8-10m,模袋叠缝≥50mm,针脚间距≤8mm;
2)模袋铺设:采用横向铺设,纵向排列,灌浆口设置在坡体上方;
3)混凝土配置、搅拌;
4)安装灌浆机械:采用混凝土喷射灌注机,安装在坡体上部平台面上,安装前设置围档、警示牌,安装基地用电夯反复夯实提高平台基地承载力;
5)灌浆:将混凝土喷射灌注机机射头,插入模袋进料口,并将进料口用钢绳扎紧,启动灌注机,当灌注机上的流量表读数达到模袋饱和度98%时立即关闭灌注机;
6)压浆:选用长度≥坡体宽度300mm,宽度1000mm,厚度100mm木质或钢质板,覆盖在模袋上面,用平板振动器反复振动,直至混凝土含水率≤20%;
(四)串筋
1)竹筋材料选择:选用三年以上生山竹、毛竹或青竹;
2)竹筋制作:用蔑刀削成竹片,竹片长度≥15000mm,宽度为80-100mm,厚度为3-5mm,将竹筋头削成100mm尖头状;
3)串筋间距:按照纵横间距2000mm串插;
4)串筋方法:在混凝土初凝前,采用人工从混凝土面上穿过混凝土层直至插入坡基体之中;
5)复浆:当竹筋插入混凝土面共坡基体后,再次用木板或钢板覆盖在混凝土模袋上面,用平板振动器反复振动,并使表面析出水份;
(五)开孔
按照设定的株距行距,用木线确定开孔位置,采用金刚石钻孔机,配置设置的孔径直径钻头进行钻孔,钻孔深度为混凝土厚度;
(六)灌入营养土
1)营养土材料配置:按田园土、腐叶土、有机畜禽粪肥重量比6:3:1进行配置;
2)灌入:采用人工将营养土灌入种植植物孔洞内,灌土量以灌入孔洞口面为宜;
(七)植物种植:采用种子种植或植物植载方法;
A)种子种植
1)种子处理:剔除瘪籽、破籽、蛀籽,并用多菌灵水液1:200倍,浸种24~48小时,然后捞出来冷干;
2)播种:采用人工播种法,每穴2-3粒,种子放入种穴中,采用营养土覆土,覆土厚度15mm;
B)移栽种植:
1)起苗:在起苗前一天晚上将苗木基地浇足水,第二天上午起苗;
2)栋苗:将所起苗木剔除断苗、死苗、病苗、小苗、过大苗、保持所栽苗大小一致;
3)剪苗:修剪过长主须根以及叉枝、枯枝;
4)浸苗:用多菌灵水液1:200倍浸苗根,浸苗时间为12~24小时;
5)栽植:将苗木直接垂直插入苗孔穴内,然后灌入营养土,并用木棒将苗木根基四周土捣实;
6)浇水:每株浇足清水1kg以上,确保200mm深度浇透;
(八)维护
A)对种子种植坡地覆盖保养覆
1)保养保温膜制作:
选用柔性0.5mm厚的塑料薄膜和φ1mm空心塑胶管及φ5mm空心塑胶管;其中φ1mm空心塑胶管作支流管,φ5mm塑胶管作主流管,将支流管侧面按0.5cm距离钻孔,孔径为0.1m;主流管按2cm距离钻眼孔,孔径为1mm;然后将塑料薄膜平铺在制作台上,刷粘合剂,按间距2cm横向铺贴φ1mm空心胶管,铺贴时眼孔朝上,然后纵向顶面铺贴2-3根φ5mm塑胶管,并将φ1mm空心塑胶管插入φ5mm孔眼,周边涂入粘合剂,然后再将预选准备的眼状膜覆盖上面,完成保养保温膜制作;
所述眼状膜制作:在商品膜上按横向2cm间距,纵向0.5cm间距,钻φ0.1孔径眼;
2)保养保温膜铺贴:将保温保养膜平铺在所需保养的坡面上,铺贴后,在保养保温膜上覆盖保护网;保护网由聚丙烯线编制成,网眼为10×10cm,并将网绷紧压入地面;
3)贮水箱制作与安装:选择塑胶桶或铁桶,在桶底安装控水阀门和水咀,水咀咀头直径≤5mm;桶可装水50kg以上;水箱制作后,在保养保温膜铺贴后,进行水箱安装,水箱高度高于所保养混体高度的2m以上,安装后,将主流管连接贮水箱水咀,然后将水箱灌满水,打开阀门,实施保养;
B)搭设遮阳棚:遮阳棚由构体,遮阳帘,保护网制成;遮阳架体选择金属管、木管或竹管制作,长高度1.5m-2.0m;遮阳帘用麦草编织;保护网用草纸或尼龙绳编织,网眼空为20cm×20cm,立管埋深度为300mm,然后绑扎横管,用麻丝或钢丝绑扎,形成架体,覆盖遮阳帘与保护网;
C)拆除维护设施:当种粒苗木出土后,掀去保养膜;当种植苗木或现栽苗木3月后,拆去遮阳设施;
D)间苗补苗:当种植苗木3月后进行间苗补苗,每穴保留2株;
E)施肥喷药:当苗木出土或现栽3个月后,采用水与人畜尿20:1稀释进行浇施,并喷施1:500液多菌灵液。
CN201510458103.7A 2015-07-30 2015-07-30 软土河坡混凝土植绿护坡方法 Active CN105178248B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510458103.7A CN105178248B (zh) 2015-07-30 2015-07-30 软土河坡混凝土植绿护坡方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510458103.7A CN105178248B (zh) 2015-07-30 2015-07-30 软土河坡混凝土植绿护坡方法

Publications (2)

Publication Number Publication Date
CN105178248A true CN105178248A (zh) 2015-12-23
CN105178248B CN105178248B (zh) 2017-01-04

Family

ID=54900638

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510458103.7A Active CN105178248B (zh) 2015-07-30 2015-07-30 软土河坡混凝土植绿护坡方法

Country Status (1)

Country Link
CN (1) CN105178248B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106212100A (zh) * 2016-07-26 2016-12-14 浙江大学宁波理工学院 含有种植基质的护坡植生型沥青混合料及其制备方法和应用
CN108570993A (zh) * 2018-04-26 2018-09-25 熊远 一种生态植被混凝土护坡结构及其施工方法
CN108612050A (zh) * 2018-06-14 2018-10-02 堡森(上海)环境工程有限公司 一种利用疏浚泥原位固化制备海绵土生态护坡的方法
CN110106830A (zh) * 2019-04-30 2019-08-09 湖北工业大学 一种有孔模袋混凝土生态护岸结构及施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110080281A (ko) * 2010-01-05 2011-07-13 이득근 녹생토에 수분공급이 가능한 사면의 녹화구조
CN103225309A (zh) * 2013-04-03 2013-07-31 葛加君 混凝土基体植绿护坡施工方法
KR20140074582A (ko) * 2012-12-10 2014-06-18 주식회사 에코피아 사면 녹화 구조 및 그 시공방법
CN204112342U (zh) * 2014-09-15 2015-01-21 武汉橄石代环境资源科技有限公司 一种护坡绿化带

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110080281A (ko) * 2010-01-05 2011-07-13 이득근 녹생토에 수분공급이 가능한 사면의 녹화구조
KR20140074582A (ko) * 2012-12-10 2014-06-18 주식회사 에코피아 사면 녹화 구조 및 그 시공방법
CN103225309A (zh) * 2013-04-03 2013-07-31 葛加君 混凝土基体植绿护坡施工方法
CN204112342U (zh) * 2014-09-15 2015-01-21 武汉橄石代环境资源科技有限公司 一种护坡绿化带

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106212100A (zh) * 2016-07-26 2016-12-14 浙江大学宁波理工学院 含有种植基质的护坡植生型沥青混合料及其制备方法和应用
CN108570993A (zh) * 2018-04-26 2018-09-25 熊远 一种生态植被混凝土护坡结构及其施工方法
CN108612050A (zh) * 2018-06-14 2018-10-02 堡森(上海)环境工程有限公司 一种利用疏浚泥原位固化制备海绵土生态护坡的方法
CN108612050B (zh) * 2018-06-14 2020-08-04 堡森(上海)环境工程有限公司 一种利用疏浚泥原位固化制备海绵土生态护坡的方法
CN110106830A (zh) * 2019-04-30 2019-08-09 湖北工业大学 一种有孔模袋混凝土生态护岸结构及施工方法
CN110106830B (zh) * 2019-04-30 2020-11-27 湖北工业大学 一种有孔模袋混凝土生态护岸结构及施工方法

Also Published As

Publication number Publication date
CN105178248B (zh) 2017-01-04

Similar Documents

Publication Publication Date Title
CN106900342B (zh) 一体化半岩质高边坡植被重建保护方法
CN104264692B (zh) 一种边坡生态修复方法
CN102498875B (zh) 一种在岩质边坡构建灌、草植物群落的方法
CN108432495B (zh) 一种岩质边坡绿化施工方法
CN101849454B (zh) 盐碱滩地的生物综合改良方法
KR100828167B1 (ko) 옥상 녹화용 식생기반재, 이를 포함하는 식생매트 및 그 제조 방법
CN209185138U (zh) 一种树木移植结构
CN105210494B (zh) 黄土陡坡混交绿化治理方法
CN111851531B (zh) 一种高陡岩石边坡生态修复系统和方法
CN114351733A (zh) 一种岩质边坡植被系统及植被种植施工方法
CN105178248B (zh) 软土河坡混凝土植绿护坡方法
CN109392582A (zh) 一种山体坡面种植方法
CN102146675A (zh) 一种岩质高边坡的组合式生态护坡方法
CN109723068A (zh) 利于边坡植被生长陡立混凝土框格梁护坡系统及营造方法
CN108951667A (zh) 一种绿色生态边坡一体化加固方法
CN110552356B (zh) 一种高原区道路下边坡挂渣综合治理系统及其施工方法
CN103392474A (zh) 紫色淮山、铁棍淮山药的种植新方法及其种植装置
CN110219310A (zh) 蓄排水管联合多功能汲水加筋带的框格式植被水泥土护坡方法及设施
CN111485565A (zh) 一种绿色生态边坡一体化加固方法
CN109339068A (zh) 一种用于混凝土和岩石高陡坡面的生态护坡植物措施方法
KR101043361B1 (ko) 식생용 망태기 및 이를 이용한 생태 호안 조성방법
CN108589746A (zh) 一种绿色喷锚和生态植被相结合的边坡防护方法
CN112673881A (zh) 一种植树方法及所用材料
CN209816870U (zh) 利于边坡植被生长陡立混凝土框格梁护坡系统
CN111576453A (zh) 坡面锚钉挂网及使用其的裸露岩体生态修复方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191111

Address after: 215400 group 2, Mijing village, Guizhuang District, Shaxi Town, Taicang City, Suzhou City, Jiangsu Province

Patentee after: Taicang Kaiqi Shoes Co., Ltd

Address before: 226400, Development Building, east side of Taishan Road, digging Town, Rudong County, Jiangsu, Nantong 1002

Patentee before: Ge Jiajun

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201020

Address after: 215400 room 01, building 13, No.1, Zhaoyan Road, Shaxi Town, Taicang City, Suzhou City, Jiangsu Province

Patentee after: Suzhou Xineng Environmental Protection Technology Co.,Ltd.

Address before: 215400 group 2, Mijing village, Guizhuang District, Shaxi Town, Taicang City, Suzhou City, Jiangsu Province

Patentee before: Taicang Kaiqi Shoes Co.,Ltd.

TR01 Transfer of patent right