CN105138024B - A kind of safety is again without water tower, the water level in water pool control device for waiting for power consumption - Google Patents

A kind of safety is again without water tower, the water level in water pool control device for waiting for power consumption Download PDF

Info

Publication number
CN105138024B
CN105138024B CN201510584232.0A CN201510584232A CN105138024B CN 105138024 B CN105138024 B CN 105138024B CN 201510584232 A CN201510584232 A CN 201510584232A CN 105138024 B CN105138024 B CN 105138024B
Authority
CN
China
Prior art keywords
resistance
electric capacity
water
rectifying tube
triggering pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510584232.0A
Other languages
Chinese (zh)
Other versions
CN105138024A (en
Inventor
钟兴明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510584232.0A priority Critical patent/CN105138024B/en
Publication of CN105138024A publication Critical patent/CN105138024A/en
Application granted granted Critical
Publication of CN105138024B publication Critical patent/CN105138024B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention discloses a kind of safety again without water tower, the water level in water pool control device for waiting for power consumption, includes excessively stream earth leakage circuit-breaker, contactor LJ, level sensor switch, multiple resistance, multiple rectifying tubes, voltage-stabiliser tube W, FET, multiple electric capacity, multiple triggers and relay DJ;The present apparatus is discharged using energy storage is integrated; the low current conversion high current of delay release is integrated again; there is the mode that more low current discharges again; triggering and conducting holding circuit is constituted using FET, multiple triggering pipes and electric capacity C2, resistance R7; voltage-stabiliser tube W protection grid source electrodes avoid overvoltage from damaging, and make resistance in opposite sets bigger, and the current value of the level sensor switch of the present apparatus is smaller; safety requirements is met, circuit needs are met again.The electric leakage monitoring to level sensor switch and wire is made up of resistance R9, resistance R10, electric capacity C5, relay DJ coils, triggering pipe B7, triggering pipe B6 and excessively stream earth leakage circuit-breaker tripping coil;It is intended to improve the reliability of the present apparatus.

Description

A kind of safety is again without water tower, the water level in water pool control device for waiting for power consumption
Technical field
The present invention relates to water-level control apparatus art, a kind of safety is referred in particular to again without water tower, the water for waiting for power consumption Pool level controller.
Background technology
There are many money water towers, water level in water pool control device on current market, there is with display water level and have the high-end production of prompt tone Product, also there is an ordinary electronic water gauge, also mechanical float ball, the water tower water level control device such as switch, now on the market again There is a kind of switch sensor of break-make form, this product great advantage is that there was only the two of on-off with the height change of water level The height change of water level, is fully replaced as the on off operating mode of electric switch by individual state, and the height change of water level is replaced as establishing by cable The through and off state of pass can be selected arbitrarily, if contact is met by high current requirement, it is possible to be assembled into nothing and wait for power consumption Automatic water-supply, drainage arrangement, in fact, the electricity due to needing to meet water supply installation current needs between water tower and water supply installation Line, cost is perhaps very high, supply water, draught engine starting current it is much larger compared with running current, and switch contact position is not true Qualitative, direct service life is very short, and because inner heat damages the personal safety as well as the property safety problem for triggering electric leakage to bring;Generally will Switch is protected plus leakage, and is added after isolating transformer decompression, automatic water supply device is installed by low voltage control contactor;This side Safely and effectively, but the unavoidable spending for waiting for power consumption, general more than 5W wait for power consumption such year and also spend hundred tons of the electricity of drawing water method Take expenditure, high-end product waits for that power consumption is just bigger, power consumption and security be difficult to the to get both ideal of the common people are waited in a word and double is required.
The content of the invention
In view of this, in view of the existing deficiencies of the prior art, its main purpose is to provide a kind of safety again without keeping to the present invention Water tower, the water level in water pool control device of power consumption are waited, it can effectively be solved, and existing water-level control apparatus cost is high, it is big to wait for power consumption And the problem of security is bad.
To achieve the above object, the present invention is using following technical scheme:
A kind of safety includes excessively stream earth leakage circuit-breaker, connect again without water tower, the water level in water pool control device for waiting for power consumption Tentaculum LJ, level sensor switch, resistance R1, resistance R2, resistance R3, resistance R4, resistance R5, resistance R6, resistance R7, resistance R8, Resistance R9, resistance R10, rectifying tube D1, rectifying tube D2, rectifying tube D3, rectifying tube D4, rectifying tube D5, voltage-stabiliser tube W, FET, Electric capacity C1, electric capacity C2, electric capacity C3, electric capacity C4, electric capacity C5, triggering pipe B1, triggering pipe B2, triggering pipe B3, triggering pipe B4, triggering pipe B5, triggering pipe B6, triggering pipe B7 and relay DJ;Contactor LJ is connected to excessively stream earth leakage circuit-breaker and water supply or draining Between equipment, level sensor switch is arranged in water supply or draining water receptacle;Resistance R1 one end connection excessively stream electric leakage is protected The N line output terminals of switch are protected, resistance R1 other end connection rectifying tube D1 input is connected with rectifying tube D2 output ends again, Rectifying tube D2 inputs are connected with D with equipotential line, and rectifying tube D1 output ends are connected with the drain electrode end of FET, resistance R2 One end connect the L line output terminals of excessively stream earth leakage circuit-breaker, resistance R2 other end connection contactor LJ one end and rectification Pipe D5 input, contactor LJ other end connection rectifying tube D3 inputs are connected with rectifying tube D4 output ends again, rectification Pipe D3 output ends connect the drain electrode end of FET, and rectifying tube D4 inputs are connected with D with equipotential line, rectifying tube D5 output ends Electric capacity C4 one end is connected, electric capacity C4 one end connection resistance R9 one end, electric capacity C5 one end and relay DJ anodes, electric capacity C4 are another End is connected with D with equipotential line, the resistance R9 other ends and the electric capacity C5 other ends connection resistance R3 one end, and relay DJ's is negative End connection triggering pipe B7 one end and the normally opened contact ends of connection relay DJ in itself, triggering pipe B7 other end connection triggering pipes B6's One end, the triggering pipe B6 other end connection electric capacity C5 other ends and connection resistance R3 one end, resistance R3 other end connection water The output end of position sensitive switch, relay DJ movable contact end is connected with the control input anode of excessively stream earth leakage circuit-breaker Connect, the control input negative terminal of excessively stream earth leakage circuit-breaker is connected with resistance R10 one end, resistance the R10 other end and the same electricity of D Bit line is connected;The input of resistance R4 one end connection level sensor switch, the one of resistance R4 other end connection electric capacity C3 End, the electric capacity C3 other end is connected with D with equipotential line, and the one end of the resistance R4 other ends also with resistance R5 is connected, resistance R5 The other end be connected with electric capacity C1 one end, the electric capacity C1 other ends are connected with D with equipotential line, and the resistance R5 other end is again and R6 One end is connected, and the resistance R6 other ends are connected with D with equipotential line, triggering pipe B1, triggering pipe B2, triggering pipe B3, triggering pipe B4 Be sequentially connected in series with triggering pipe B5, the resistance R5 other end is also connected with triggering pipe B1 one end, the triggering pipe B5 other end with Resistance R8 one end is connected, and the resistance R8 other end is connected with resistance R7 one end, resistance the R7 other end and the same current potentials of D Line is connected, and the resistance R8 other end is connected with electric capacity C2 one end again, and the electric capacity C2 other end is connected with D with equipotential line Connect, the one end of the resistance R8 other end also with voltage-stabiliser tube W is connected, and the voltage-stabiliser tube W other end is connected with D with equipotential line, resistance The R8 other end also has to be connected with the gate terminal of FET, and the drain electrode end of FET is connected with rectifying tube D1 output ends And be connected with rectifying tube D3 output ends, the source terminal of FET is connected with D with equipotential line.
As a kind of preferred scheme, the resistance R1 and resistance R2 are positive temperature coefficient resistance.
As a kind of preferred scheme, the resistance R3 and resistance R4 are that external sensing line drop voltage is rationed the power supply leakage resistance.
As a kind of preferred scheme, the resistance R6 is partial pressure and electric capacity C1 discharge resistances.
As a kind of preferred scheme, the resistance R7 is electric capacity C2 delay discharge resistances.
As a kind of preferred scheme, the resistance R8 is trigger current buffer resistance.
As a kind of preferred scheme, the FET drives electronic switch for the voltage that model is 4N90.
As a kind of preferred scheme, the resistance R9 is water level inductive switch and wire detection of electrical leakage resistance.
As a kind of preferred scheme, the resistance R10 is driving current limliting dropping resistor.
As a kind of preferred scheme, the electric capacity C5 is detection energy storage integrating capacitor.
The present invention has clear advantage and beneficial effect compared with prior art, specifically, by above-mentioned technical proposal Understand:
According to human body safe current 30mA, the condition for bearing safe voltage 36V is contracted to human body unaware scope, meter The current value for calculating the level sensor switch of the present apparatus is design considerations, is discharged using energy storage is integrated, then integrates the small of delay release Electric current changes high current, there is the mode that more low current discharges again, using FET and triggering pipe and electric capacity C2, resistance R7 groups Into triggering and conducting holding circuit, make resistance in opposite sets bigger, resistance senses lines to dispatch from foreign news agency as two in selection 2.2M Ω Resistance, voltage-stabiliser tube W avoids overvoltage from damaging for protection grid source electrode, and the current value for switching the level sensor of the present apparatus is smaller, i.e., full Foot safety requirements, meets circuit needs again.Using by excessively stream earth leakage circuit-breaker N line output terminals to resistance R1 to rectifying tube D1, rectifying tube D2, rectifying tube D3, rectifying tube D4, FET with by excessively stream earth leakage circuit-breaker L line output terminals to resistance R2 to Contactor LJ to rectifying tube D1, rectifying tube D2, rectifying tube D3, rectifying tube D4, FET composition exchange the function of turning direct current, full Sufficient Alternating Current Power Supply contactor LJ must operate at the characteristic of alternating current, and the spy that FET must operate at direct current supply is met again Property;Changed using the height of the existing on off operating mode for the height change of water level being replaced as electric switch on the market, and water level and put The through and off state for changing electric switch into can be with optional level sensor.This product is applied to unit, the water tower of family, water The water level control of the water receptacles such as well, basement collecting-tank.
More clearly to illustrate the architectural feature and effect of the present invention, come below in conjunction with the accompanying drawings with specific embodiment to this hair It is bright to be described in detail.
Brief description of the drawings
Fig. 1 is the structural representation of the preferred embodiments of the invention.
Embodiment
It refer to shown in Fig. 1, that show the concrete structure of the preferred embodiments of the invention, include excessively stream electric leakage super Press protection switch 10, contactor LJ, level sensor switch 20, resistance R1, resistance R2, resistance R3, resistance R4, resistance R5, resistance R6, resistance R7, resistance R8, resistance R9, resistance R10, rectifying tube D1, rectifying tube D2, rectifying tube D3, rectifying tube D4, rectifying tube D5, Voltage-stabiliser tube W, FET, electric capacity C1, electric capacity C2, electric capacity C3, electric capacity C4, electric capacity C5, triggering pipe B1, triggering pipe B2, triggering pipe B3, triggering pipe B4, triggering pipe B5, triggering pipe B6, triggering pipe B7 and relay DJ.
Contactor LJ is connected between excessively stream earth leakage circuit-breaker 10 and water supply or drainage equipment 30, and the level sensor is opened 20 are closed to be arranged in water supply or draining water receptacle 30;Resistance R1 one end connects the N line output terminals of excessively stream earth leakage circuit-breaker, Resistance R1 other end connection rectifying tube D1 input is connected with rectifying tube D2 output end again, rectifying tube D2 inputs with D is connected with equipotential line, and rectifying tube D1 output ends are connected with the drain electrode end of FET, resistance R2 one end connection excessively stream leakage The L line output terminals of electric protective circuit breaker, resistance R2 other end connection contactor LJ one end and rectifying tube D5 input, contact Device LJ other end connection rectifying tube D3 inputs are connected with rectifying tube D4 output ends again, rectifying tube D3 output ends connection field effect Should pipe drain electrode end, rectifying tube D4 inputs are connected with D with equipotential line, rectifying tube D5 output ends connection electric capacity C4 one end, electricity Hold the C4 other ends with D with equipotential line to be connected, electric capacity C4 one end connection resistance R9 one end, electric capacity C5 one end and relay DJ Anode, the resistance R9 other ends and the electric capacity C5 other ends connection resistance R3 one end, relay DJ negative terminals connection triggering pipe B7 One end and the normally opened contact ends of connection relay DJ in itself, triggering pipe B7 other end connection triggering pipes B6 one end, triggering pipe B6 The other end connection electric capacity C5 other ends and connection resistance R3 one end, resistance R3 other end connection level sensor switch it is defeated Go out end, relay DJ movable contact end is connected with the control input anode of excessively stream earth leakage circuit-breaker 10, excessively stream electric leakage is protected The control input negative terminal of shield switch 10 is connected with resistance R10 one end, and the resistance R10 other end is connected with D with equipotential line; The input of resistance R4 one end connection level sensor switch 10, resistance R4 other end connection electric capacity C3 one end, electric capacity C3 The other end be connected with D with equipotential line, the one end of the resistance R4 other ends also with resistance R5 is connected, the resistance R5 other ends with electricity Hold C1 one end to be connected, the electric capacity C1 other ends are connected with D with equipotential line, and the resistance R5 other ends are connected with R6 one end again, electricity The resistance R6 other ends are connected with D with equipotential line, and triggering pipe B1, triggering pipe B2, triggering pipe B3, triggering pipe B4 and triggering pipe B5 are successively Series connection, the resistance R5 other ends are connected with triggering pipe B1 one end, and the triggering pipe B5 other end is connected with resistance R8 one end, The resistance R8 other end is connected with resistance R7 one end, and the resistance R7 other end is connected with D with equipotential line, and resistance R8's is another One end is connected with electric capacity C2 one end again, and the electric capacity C2 other end is connected with D with equipotential line, the resistance R8 other end also with Voltage-stabiliser tube W one end is connected, and the voltage-stabiliser tube W other end is connected with D with equipotential line, and the resistance R8 other end also has and field-effect Pipe 4N90 gate terminals are connected, and FET 4N90 drain electrode end is connected with rectifying tube D1 output ends and exported with rectifying tube D3 End is connected, and the source terminal of FET is connected with D with equipotential line;There are electric capacity C3, electricity with the element that equipotential line is connected with D Hold C1, resistance R6, resistance R10, electric capacity C4, rectifying tube D2, arrangement pipe D4, the source terminal of FET, voltage-stabiliser tube W, electric capacity C2 With resistance R7.
In the present embodiment, the resistance R1 and resistance R2 are positive temperature coefficient resistance, and the resistance R3 and resistance R4 are equal Rationed the power supply leakage resistance for externally sensing line drop voltage, the resistance R5 and resistance R6 are partial pressure and electric capacity C1 discharge resistances, described Resistance R7 is electric capacity C2 delay discharge resistances, and the resistance R8 is trigger current buffer resistance, and the FET is for model 4N90 voltage driving electronic switch, the resistance R9 is water level inductive switch and wire detection of electrical leakage resistance, and electric capacity C5 is inspection Energy storage integrating capacitor is surveyed, the triggering pipe B6, triggering pipe B7 are water level inductive switch and lead leakage trigger thresholding and triggering Function, normal open switch itself is connected to become from locking driving function, the resistance R10 relay DJ coils with relay DJ For driving current limliting dropping resistor, the triggering pipe B1, triggering pipe B2, triggering pipe B3, triggering pipe B4, triggering pipe B5 are composed in series tactile The function of thresholding and triggering is sent out, the voltage-stabiliser tube W avoids overvoltage from damaging for protection grid source electrode.
By the N line output terminals of excessively stream earth leakage circuit-breaker 10 to resistance R1 to rectifying tube D1, rectifying tube D2, rectifying tube D3, Rectifying tube D4, FET are with the L line output terminals by excessively stream electric leakage overpressure protection switch 10 to resistance R2 to contactor LJ to whole Flow tube D1, rectifying tube D2, rectifying tube D3, rectifying tube D4, FET composition exchange the function of turning direct current, meet Alternating Current Power Supply and connect Tentaculum LJ must operate at the characteristic of alternating current, and the characteristic that FET must operate at direct current supply is met again.Leaked by excessively stream To resistance R2 to rectifying tube D5 to resistance R9 to resistance R3, the positive electricity formed is pressed onto water to the N phase output terminals of electric overpressure protection switch 10 Position sensitive switch 20, by level sensor switch 20 to resistance R4 to resistance R5 to resistance R6 to rectifying tube D2 to resistance R1 to excessively stream The N line output terminals of earth leakage circuit-breaker, form level sensor and switch 20 electric signal return lines.
When level sensor switch 20 is connected, the level sensor of formation switchs 20 signal circuit line currents, over resistor r 6 Form voltage and give electric capacity C1 chargings, until when electric capacity C1 both end voltages are raised to 160V, triggering pipe B1, triggering pipe B2, triggering pipe B3, Triggering pipe B4, triggering pipe B5 are triggered rapid conducting, the electric capacity C1 triggered pipe B1 of discharge loop, triggering pipe B2, trigger pipe B3, Trigger pipe B4, triggering pipe B5 to resistance R8 to charge to electric capacity C2, the 20V electricity on 20V, subsequent electric capacity C2 is limited in by voltage-stabiliser tube W Discharge loop can be formed by resistance R7, is about needed 3-5 seconds, the DC current and the electric capacity C1 that are conveyed due to level sensor signal wire and is touched It is 1-2 times/second to send out pipe B1, triggering pipe B2, triggering pipe B3, triggering pipe B4, the discharge and recharge triggering frequency of triggering pipe B5 compositions, continuously Electric capacity C2 chargings are given, electric capacity C2 two ends is maintained 20V or so voltages, unnecessary 20V current drain is carried out by voltage-stabiliser tube W;Electricity The grid g and source electrode s of road it can be seen from the figure that now FET are connected in parallel on electric capacity C2 two ends, therefore FET is turned on Condition and maintain conducting, FET conducting makes contactor LJ obtain AC power driving and work, contactor LJ switching points are closed Close, L to L1 electric currents passes through, supply water or drainage equipment 30 works;When level sensor switch 20 increases to the height of pass because of water level, water Contact disconnects in the sensitive switch 20 of position, and electric current is zero in resistance R3, resistance R4, and electric capacity C1 does not trigger residue by resistance R6 releases Electric energy, electric capacity C3 is discharged by resistance R5 to electric capacity C1, and electric capacity C2 storage electric energy is discharged by resistance R7, about needs put within 3 to 5 seconds It is complete, that is, contactor LJ level sensor switch 20 disconnect 3 seconds after cut-out supply water or drainage equipment 30 power supply, stop supply water Or draining, subsequently enter the phase of waiting for, resistance R4, electric capacity C3, resistance R5, resistance R6, electric capacity C1, triggering pipe B1, B2, B3, B4, B5 Anti-jamming circuit is constituted, the interference signal that the sensing of level sensor line is come in is resisted, it is ensured that stable to wait for, it is to avoid misoperation, full electricity Road is blocking state, and loss due to leakage is minimum, is approximately zero, and waiting water level drops back into water tower or going up to pond makes level sensor switch 20 again It is secondary to connect, worked next time.
Protected by resistance R9, resistance R10, electric capacity C5, relay DJ coils, triggering pipe B7, triggering pipe B6 and excessively stream electric leakage Electric leakage of the switch trip coil composition to level sensor switch and wire is protected to monitor;It is intended to improve the reliability of the present apparatus.
When level sensor switch or wire leak resistance are equal to or more than 800K Ω, triggering pipe B6 series connection triggering pipes B7 two Terminal voltage does not reach triggering pipe turn-on condition;When level sensor switch or wire leak resistance are less than 800K Ω, leakage current is in electricity Resistance R9 two ends cause boosting, electric capacity C5 chargings are given, when being charged to 66v(Trigger conducting voltage 33v+33v=66v of pipe)Trigger Guan Yin It is triggered and is mutated conducting, the electric energy on electric capacity C5 is discharged back by relay DJ coils to triggering pipe B7 to triggering pipe B6 formation Road, closes relay DJ normal open switch point, and at the same time L lines are to resistance R2 to rectifying tube D5 to relay DJ coils to relay Device normal open switch point is to excessively stream earth leakage circuit-breaker interior loop KJ to resistance R10 to rectifying tube D2 to the loop of resistance R1 to N lines Electric current passes through immediately, not only maintains relay DJ conducting, also drives the dropout of excessively stream earth leakage circuit-breaker, disconnects general supply.
The present apparatus is applied to well, the water level in pond, only another joint need to be selected on level sensor switch 20, water Two water level nodes that position sensitive switch 20 is put into debugging control in well, pond can be achieved to control well, water level in water pool; The present apparatus changes wiring and can be used to work in three-phase alternating current pipeline equipment accordingly.
The design focal point of the present invention is:According to human body safe current 30mA, safe voltage 36V condition contracting is born As low as human body unaware scope, the current value for calculating the level sensor switch of the present apparatus is design considerations, is released using energy storage is integrated Put, then integrate the low current conversion high current of delay release, have the mode that more low current discharges again, using FET and triggering Pipe DB3 and electric capacity C2, resistance R7 constitute triggering and conducting holding circuit, make resistance in opposite sets bigger, in selection 2.2M Ω Resistance is as two sensing lines to external resistance, and the current value for switching the level sensor of the present apparatus is smaller, that is, meeting safety will Ask, circuit needs are met again.Using by excessively stream earth leakage circuit-breaker N line output terminals to resistance R1 to rectifying tube D1, rectifying tube D2, Rectifying tube D3, rectifying tube D4, FET with by excessively stream earth leakage circuit-breaker L line output terminals to resistance R2 to contactor LJ to whole Flow tube D1, rectifying tube D2, rectifying tube D3, rectifying tube D4, FET composition exchange the function of turning direct current, meet Alternating Current Power Supply and connect Tentaculum LJ must operate at the characteristic of alternating current, and the characteristic that FET must operate at direct current supply is met again;Utilize market The upper existing on off operating mode for the height change of water level being replaced as electric switch, and the height change of water level is replaced as electric switch Through and off state can be switched with optional level sensor.This product is applied to unit, the water tower of family, well, basement The water level control of the water receptacles such as collecting-tank.
The above described is only a preferred embodiment of the present invention, be not intended to limit the scope of the present invention, Therefore any subtle modifications, equivalent variations and modifications that every technical spirit according to the present invention is made to above example, still Belong in the range of technical solution of the present invention.

Claims (10)

1. a kind of safety is again without water tower, the water level in water pool control device for waiting for power consumption, it is characterised in that:Include excessively stream electric leakage guarantor Protect switch, contactor LJ, level sensor switch, resistance R1, resistance R2, resistance R3, resistance R4, resistance R5, resistance R6, resistance R7, resistance R8, resistance R9, resistance R10, rectifying tube D1, rectifying tube D2, rectifying tube D3, rectifying tube D4, rectifying tube D5, voltage-stabiliser tube W, FET, electric capacity C1, electric capacity C2, electric capacity C3, electric capacity C4, electric capacity C5, triggering pipe B1, triggering pipe B2, triggering pipe B3, triggering Pipe B4, triggering pipe B5, triggering pipe B6, triggering pipe B7 and relay DJ;Contactor LJ is connected to excessively stream earth leakage circuit-breaker Between water supply or drainage equipment, level sensor switch is arranged in water supply or draining water receptacle;Resistance R1 one end connects Take over the N line output terminals of stream earth leakage circuit-breaker, resistance R1 other end connection rectifying tube D1 input again with rectifying tube D2 Output end is connected, and rectifying tube D2 inputs are connected with D with equipotential line, the drain electrode end of rectifying tube D1 output ends and FET It is connected, resistance R2 one end connects the L line output terminals of excessively stream earth leakage circuit-breaker, resistance R2 other end connection contactor LJ One end and rectifying tube D5 input, contactor LJ the other end connection rectifying tube D3 inputs again with rectifying tube D4 output ends It is connected, rectifying tube D3 output ends connect the drain electrode end of FET, and rectifying tube D4 inputs are connected with D with equipotential line, whole Flow tube D5 output ends connection electric capacity C4 one end, electric capacity C4 one end connection resistance R9 one end, electric capacity C5 one end and relay DJ are just End, the electric capacity C4 other ends are connected with D with equipotential line, and the resistance R9 other ends and the electric capacity C5 other ends connect the one of resistance R3 End, relay DJ negative terminal connection triggering pipe B7 one end and the normally opened contact ends of connection relay DJ in itself, triggering pipe B7 is another End connection triggering pipe B6 one end, the triggering pipe B6 other end connection electric capacity C5 other ends and connection resistance R3 one end, resistance The output end of R3 other end connection level sensor switch, relay DJ movable contact end and the control of excessively stream earth leakage circuit-breaker Input positive terminal processed is connected, and the control input negative terminal of excessively stream earth leakage circuit-breaker is connected with resistance R10 one end, resistance R10 The other end be connected with D with equipotential line;The input of resistance R4 one end connection level sensor switch, the resistance R4 other end Electric capacity C3 one end is connected, the electric capacity C3 other end is connected with D with equipotential line, the one end of the resistance R4 other ends also with resistance R5 It is connected, the resistance R5 other end is connected with electric capacity C1 one end, and the electric capacity C1 other ends are connected with D with equipotential line, resistance R5 The other end be connected again with R6 one end, the resistance R6 other ends are connected with D with equipotential line, triggering pipe B1, triggering pipe B2, trigger Pipe B3, triggering pipe B4 and triggering pipe B5 are sequentially connected in series, and the resistance R5 other end is also connected with triggering pipe B1 one end, triggering pipe The B5 other end is connected with resistance R8 one end, and the resistance R8 other end is connected with resistance R7 one end, and resistance R7's is another One end is connected with D with equipotential line, and the resistance R8 other end is connected with electric capacity C2 one end again, electric capacity the C2 other end and D It is connected with equipotential line, the one end of the resistance R8 other end also with voltage-stabiliser tube W is connected, voltage-stabiliser tube the W other end and the same equipotential lines of D It is connected, the resistance R8 other end also has to be connected with the gate terminal of FET, drain electrode end and the rectifying tube D1 of FET Output end is connected and is connected with rectifying tube D3 output ends, and the source terminal of FET is connected with D with equipotential line.
2. a kind of safety according to claim 1 is again without water tower, the water level in water pool control device for waiting for power consumption, its feature exists In:The resistance R1 and resistance R2 are positive temperature coefficient resistance.
3. a kind of safety according to claim 1 is again without water tower, the water level in water pool control device for waiting for power consumption, its feature exists In:The resistance R3 and resistance R4 are that external sensing line drop voltage is rationed the power supply leakage resistance.
4. a kind of safety according to claim 1 is again without water tower, the water level in water pool control device for waiting for power consumption, its feature exists In:The resistance R6 is partial pressure and electric capacity C1 discharge resistances.
5. a kind of safety according to claim 1 is again without water tower, the water level in water pool control device for waiting for power consumption, its feature exists In:The resistance R7 is electric capacity C2 delay discharge resistances.
6. a kind of safety according to claim 1 is again without water tower, the water level in water pool control device for waiting for power consumption, its feature exists In:The resistance R8 is trigger current buffer resistance.
7. a kind of safety according to claim 1 is again without water tower, the water level in water pool control device for waiting for power consumption, its feature exists In:The FET drives electronic switch for the voltage that model is 4N90.
8. a kind of safety according to claim 1 is again without water tower, the water level in water pool control device for waiting for power consumption, its feature exists In:The resistance R9 is water level inductive switch and wire detection of electrical leakage resistance.
9. a kind of safety according to claim 1 is again without water tower, the water level in water pool control device for waiting for power consumption, its feature exists In:The resistance R10 is driving current limliting dropping resistor.
10. a kind of safety according to claim 1 is again without water tower, the water level in water pool control device for waiting for power consumption, its feature It is:The electric capacity C5 is detection energy storage integrating capacitor.
CN201510584232.0A 2015-09-15 2015-09-15 A kind of safety is again without water tower, the water level in water pool control device for waiting for power consumption Active CN105138024B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510584232.0A CN105138024B (en) 2015-09-15 2015-09-15 A kind of safety is again without water tower, the water level in water pool control device for waiting for power consumption

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510584232.0A CN105138024B (en) 2015-09-15 2015-09-15 A kind of safety is again without water tower, the water level in water pool control device for waiting for power consumption

Publications (2)

Publication Number Publication Date
CN105138024A CN105138024A (en) 2015-12-09
CN105138024B true CN105138024B (en) 2017-10-03

Family

ID=54723398

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510584232.0A Active CN105138024B (en) 2015-09-15 2015-09-15 A kind of safety is again without water tower, the water level in water pool control device for waiting for power consumption

Country Status (1)

Country Link
CN (1) CN105138024B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106212311A (en) * 2016-10-13 2016-12-14 四川森迪科技发展股份有限公司 A kind of plant drinking trough electric current buffer protection type water level control system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0167257A1 (en) * 1984-06-01 1986-01-08 Honeywell Inc. Boiler water level monitoring
CN87208984U (en) * 1987-06-09 1988-04-13 田国华 Automaton for controlling liguid level
CN2575733Y (en) * 2002-09-29 2003-09-24 陈毅超 Turnover mechanism for external equipment of extracting computer
CN2773765Y (en) * 2005-02-05 2006-04-19 刘方泽 Pumping controller of automatic-protecting electric motor
CN201762763U (en) * 2010-06-28 2011-03-16 兰如根 Water level controller with over-voltage protection
CN204945821U (en) * 2015-09-15 2016-01-06 钟兴明 A kind of safety is again without water tower, the water level in water pool control device of waiting for power consumption

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100180811A1 (en) * 2009-01-21 2010-07-22 George Sotiriou Water level detector

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0167257A1 (en) * 1984-06-01 1986-01-08 Honeywell Inc. Boiler water level monitoring
CN87208984U (en) * 1987-06-09 1988-04-13 田国华 Automaton for controlling liguid level
CN2575733Y (en) * 2002-09-29 2003-09-24 陈毅超 Turnover mechanism for external equipment of extracting computer
CN2773765Y (en) * 2005-02-05 2006-04-19 刘方泽 Pumping controller of automatic-protecting electric motor
CN201762763U (en) * 2010-06-28 2011-03-16 兰如根 Water level controller with over-voltage protection
CN204945821U (en) * 2015-09-15 2016-01-06 钟兴明 A kind of safety is again without water tower, the water level in water pool control device of waiting for power consumption

Also Published As

Publication number Publication date
CN105138024A (en) 2015-12-09

Similar Documents

Publication Publication Date Title
US9203232B2 (en) Leakage detection protective circuit
CN102832591B (en) There is the leakage current detection protection circuit of lightning impulse resistant function
CN204945821U (en) A kind of safety is again without water tower, the water level in water pool control device of waiting for power consumption
CN105138024B (en) A kind of safety is again without water tower, the water level in water pool control device for waiting for power consumption
CN202210598U (en) Dual anti-creeping socket
CN206657049U (en) Power transformer iron core grounding current sample circuit
CN203659733U (en) Outdoor high-voltage demarcation vacuum circuit breaker
CN206180985U (en) Can change circuit breaker of intelligent control ware with electricity
CN205141289U (en) Convertible ground wire protected mode's leakage protection plug
CN206517038U (en) Leakage protection circuit with ground wire grounded resistance detection function
CN217282209U (en) Open circuit protection device for current transformer
CN105006708A (en) Protection-mode-convertible electric leakage protection plug
CN102255277A (en) Leakage detection protection circuit
CN205846688U (en) Small-sized electric leakage overvoltage/undervoltage protection control circuit
CN201966581U (en) Electric leakage detection and protection circuit
CN205029118U (en) Convertible protected mode's leakage protection plug
CN209150411U (en) Power off the leakage protecting plug of automatic trip
CN208299433U (en) Voltage-time type vacuum loading switch cabinet equipment
CN201985508U (en) Zero line break protector and connecting structure thereof
CN101944716A (en) Electricity leakage detection protective circuit
CN206517041U (en) The temperature over-range protection circuit of distribution box
CN206481036U (en) A kind of DC control cabinet power control
CN205122902U (en) Can change ground wire protected mode's leakage protection plug
CN2457729Y (en) Single phase leakage braker
CN205141288U (en) Convertible ground wire protected mode's leakage protection plug

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant