Prior art keywords
powder charge
pipe
charge pipe
vertical tube
powder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510392567.2A
Other languages
Chinese (zh)
Other versions
CN105129447B (en
Inventor
李佳
吕静
盛文奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jun Sheng Automotive Safety System Changxin Co ltd
Original Assignee
Gao Tian (changxin) Automotive Safety Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gao Tian (changxin) Automotive Safety Equipment Co Ltd filed Critical Gao Tian (changxin) Automotive Safety Equipment Co Ltd
Priority to CN201510392567.2A priority Critical patent/CN105129447B/en
Publication of CN105129447A publication Critical patent/CN105129447A/en
Application granted granted Critical
Publication of CN105129447B publication Critical patent/CN105129447B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a detection and control device and method for the powder adding height of a powder charging pipe of a gas generator and belongs to the technical field of detection and control of the powder adding height of the powder charging pipe of the gas generator. According to the device, the compaction degree between gas generating powder pieces in the powder charging pipe can be adjusted, the clearances between the gas generating powder pieces are uniform, and the powder adding height can be detected. The device comprises a support, a powder input unit, a first motor, a second motor, a tumbler, a lifting rope, a pull frame with an opening formed in the lower end, a vertical pipe and a controller. The vertical pipe shakes under rotation of the tumbler, the vertical pipe rolls under rotation of the second motor, and the vertical pipe sieves under sieving of a sieving generator; and the compaction degree between the gas generating powder pieces in the powder charging pipe is adjusted, the clearances between the gas generating powder pieces are uniform, and the powder adding height can be detected in a shaking manner, a rolling manner and a sieving manner. The detection and control device and method are mainly used for the gas generating powder piece adding technology of the powder charging pipe of the gas generator.

Description

Gas generator powder charge pipe dosing height detection control setup and detection control method
Technical field
The present invention relates to gas generator powder charge pipe dosing height detection control technology field, be specifically related to a kind of gas generator powder charge pipe dosing height detection control setup and detection control method.
Background technology
At present, to the chemical feeding quantity adding aerogenesis tablet in gas generator powder charge pipe completely by range estimation, not only cause chemical feeding quantity to be difficult to hold, and clearence degree between aerogenesis tablet is also restive.
The performance of chemical feeding quantity on gas generator adding aerogenesis tablet in gas generator powder charge pipe plays vital impact.If aerogenesis tablet chemical feeding quantity adds few, not only can affect the explosion property of gas generator, after mounting, also can allow between aerogenesis tablet and there is larger gap, even leave the space of aerogenesis tablet vibration, cause in use, because vehicle has vibration in the process of moving, make, between aerogenesis tablet, collision mutually occurs in powder charge pipe, between aerogenesis tablet, mutually collision may cause aerogenesis tablet to rub the spark being lighted, occur that accident free clashes into the phenomenon that gas generator blast just occurs.If aerogenesis tablet chemical feeding quantity adds many, follow-up assembling can be affected again.Because aerogenesis tablet chemical feeding quantity calculates by the clearence degree between dosing height and aerogenesis tablet.
Therefore, design a kind of dosing height of the aerogenesis tablet that can detect in powder charge pipe, the compaction degree in powder charge pipe between aerogenesis tablet can be made adjustable when filling aerogenesis tablet again, the uniform gas generator of the clearence degree after installing gas generant composition in accordance in powder charge pipe between aerogenesis tablet powder charge pipe dosing height detection control setup and detection control method seem very necessary.
Summary of the invention
The present invention be in order to solve add aerogenesis tablet in existing gas generator powder charge pipe chemical feeding quantity completely by range estimation, chemical feeding quantity is not only caused to be difficult to hold, and the deficiency that clearence degree between aerogenesis tablet is also restive, thering is provided a kind of can make the compaction degree in powder charge pipe between aerogenesis tablet adjustable when filling aerogenesis tablet, make the clearence degree between aerogenesis tablet even after installing gas generant composition in accordance in powder charge pipe again, the gas generator powder charge pipe dosing height detection control setup that after can also installing gas generant composition in accordance in powder charge pipe, aerogenesis tablet dosing height can detect and detection control method.
Above technical matters is solved by following technical proposal:
Gas generator powder charge pipe dosing height detection control setup, comprises support, medicine input unit, motor, No. two motors, pivoted arm, lifting rope, lower end is opening draws frame, VERTICAL TUBE and controller; A pedestal of a motor is fixedly mounted on support, and a motor rotating shaft is arranged straight down; One end level of described pivoted arm is fixedly connected on the lower end of a described rotating shaft, the other end of described pivoted arm is fixedly connected on the upper end of described lifting rope, the lower end of described lifting rope is fixedly connected on No. two pedestals of No. two motors, and No. two motors No. two rotating shafts are arranged straight down; Draw the upper end of frame to be fixedly connected on the lower end of described No. two rotating shafts, draw the opening of frame lower end to be fixedly connected on the outer wall upper end of VERTICAL TUBE; The outside face of VERTICAL TUBE is provided with can to VERTICAL TUBE produce sieve sieve producer, annulus base plate is fixedly connected with in the lower port of VERTICAL TUBE, the lower surface of annulus base plate is fixedly connected with magnetic metal ring, the support below magnetic metal ring is fixed with electromagnet; The upper surface of the annulus base plate surrounded at the tube chamber of VERTICAL TUBE is provided with a contact pickup; The vertical bar drawing frame is fixedly equipped with angular transducer; Drawing on frame vertically towards having the measurement expansion link driven by a cylinder expansion link directly over the opening of VERTICAL TUBE, the measurement annulus be arranged in parallel with the upper end mouth of pipe of VERTICAL TUBE is fixedly connected with in the lower end measuring expansion link, and the line of centers of the line of centers and VERTICAL TUBE of measuring annulus overlaps, the lower surface measuring annulus is laid with No. two equal contact pickups of several detection faces height; Storage medicine-chest is fixedly housed drawing on frame, what the medicine outlet storing medicine-chest was connected to medicine input unit by a drug feeding pipe docking is used as medicine on mouth; One end mouth of pipe being provided with the medicine input pipe of electromagnetic valve is fixedly connected on the medicine outlet of medicine input unit, the other end mouth of pipe of this root medicine input pipe is arranged in directly over the upper end mouth of pipe of VERTICAL TUBE down, and the line of centers of the other end mouth of pipe of this root medicine input pipe overlaps with the line of centers of VERTICAL TUBE; The control end of a described contact pickup, angular transducer, cylinder, several No. two contact pickups, electromagnetic valve, the control end of electromagnet, the control end of a motor, the control end of No. two motors, the control end of medicine input unit and the control end sieving producer are electrically connected with controller respectively.
Be applicable to a detection control method for gas generator powder charge pipe dosing height detection control setup, detection control method comprises the steps:
The powder charge pipe of gas generator is put in VERTICAL TUBE, and allows the air extractor duct connection end of powder charge pipe arrange down;
When a contact pickup is subject to the lower surface extruding of powder charge pipe, a contact pickup sends a signal to controller;
After controller receives a signal, controller sends the instruction of an expansion link elongation to immediately a cylinder, after an expansion link elongation of a cylinder, No. two contact pickups measured on expansion link is placed into the setting height place in powder charge pipe;
Then, controller sends the instruction of opening valve immediately to electromagnetic valve, electromagnetic valve opens valve immediately;
Then, controller sends dosing instruction to immediately medicine input unit, and medicine input unit is put into the aerogenesis tablet stored in medicine-chest in powder charge pipe through drug feeding pipe and medicine input pipe successively;
Simultaneously, controller sends sieve instruction to sieving producer, what sieve producer generation sieves wave loops on the aerogenesis tablet in powder charge pipe, aerogenesis tablet sieves in powder charge pipe, for realize making when filling aerogenesis tablet the compaction degree in powder charge pipe between aerogenesis tablet adjustable, in powder charge pipe, install gas generant composition in accordance after make to install gas generant composition in accordance in all even powder charge pipe of the clearence degree between aerogenesis tablet after aerogenesis tablet dosing height can detect and provide precondition;
Simultaneously, controller sends rotation command to a motor, pivoted arm is driven to rotate after an electric machine rotation, pivoted arm rotates and then drives lifting rope to be made with the circumference whipping of centripetal force, the circumference whipping that lifting rope is made with centripetal force then drives the powder charge pipe be placed in VERTICAL TUBE also to follow suit the circumference whipping of centripetal force, and then make the aerogenesis tablet in powder charge pipe also be made with the circumference whipping of centripetal force, aerogenesis tablet extrudes toward the bottom in powder charge pipe under centripetal force effect, compaction degree in centripetal force larger powder charge pipe between aerogenesis tablet is tighter, the compaction degree in controlled loading of explosive pipe between aerogenesis tablet is carried out by the rotating speed controlling a motor, thus realize making the compaction degree in powder charge pipe between aerogenesis tablet adjustable when filling aerogenesis tablet,
Simultaneously, controller sends rotation command to No. two motors, drive after No. two electric machine rotations and draw frame roll rotational, the powder charge pipe be placed in VERTICAL TUBE also follows roll rotational to draw frame roll rotational then to drive, powder charge pipe roll rotational can make the aerogenesis tablet in powder charge pipe also follow roll rotational, aerogenesis tablet makes the clearence degree between aerogenesis tablet even under roll rotational effect, thus makes the clearence degree between aerogenesis tablet even after realizing installing gas generant composition in accordance in powder charge pipe;
When measuring each No. two contact pickups on annulus and being subject to the extruding of the aerogenesis tablet in powder charge pipe, each No. two contact pickups send No. two signals to controller respectively;
After controller receives No. two signals that each No. two contact pickups send, controller sends the instruction of valve-off immediately to electromagnetic valve, electromagnetic valve is valve-off immediately, thus after realizing installing gas generant composition in accordance in powder charge pipe, aerogenesis tablet dosing height can detect, and then realize chemical feeding quantity required in powder charge pipe;
Then, controller sends stopping dosing instruction to immediately medicine input unit, and medicine input unit stops dosing immediately;
Meanwhile, controller sends stopping sieve instruction to sieving producer, sieves producer and stops sieving;
Meanwhile, controller sends the instruction that stops operating, No. two motor stalls to No. two motors;
Meanwhile, controller sends the instruction that stops operating, a motor stalls to a motor;
Then, controller sends the instruction of an expansion link shortening to a cylinder, after an expansion link shortening of a cylinder, No. two contact pickups measured on expansion link is shifted out in powder charge pipe, terminates the charging to powder charge pipe.
As preferably, described measurement expansion link comprises vertical section and is connected to vertical section lower end and the some bending segments bent respectively outwardly, and described measurement annulus is fixed on bending segment.This structural stability is good, and install gas generant composition in accordance in detection powder charge pipe after, during aerogenesis tablet dosing height, accuracy is high.
As preferably, also comprise rubber liquid tyre bead, the inner tubal wall of VERTICAL TUBE is laterally provided with annular groove, and the line of centers of annular groove overlaps with the line of centers of VERTICAL TUBE, the one number service hole communicated with the outer tube wall of VERTICAL TUBE is provided with in annular groove, the collar wall of rubber liquid tyre bead is pasted and is connected in annular groove, and the liquid mouth pipe of rubber liquid tyre bead is arranged in one number service hole; Be fixed with No. two cylinders and liquid-adding tube respectively drawing on frame, seal cover cap is sealedly connected with in one end of liquid-adding tube, seal cover cap is provided with communication port, in liquid-adding tube, slipper seal is provided with sliding shoe, one end of a pipe link to enter in liquid-adding tube from the other end of liquid-adding tube and is fixedly connected on the outer wall of sliding shoe, the other end of described pipe link is fixedly connected on No. two expansion links of No. two cylinders, liquid-adding tube between seal cover cap and sliding shoe is built with liquid, and the two ends of a hydraulic pipe are docked respectively and are connected in described communication port with on described liquid mouth pipe; The control end of No. two cylinders is electrically connected with controller.
After controller receives a signal, controller sends the instruction of No. two expansion links elongations to immediately No. two cylinders, after No. two expansion links elongations of No. two cylinders, the liquid in liquid-adding tube is pressed in rubber liquid tyre bead, the inner ring wall of rubber liquid tyre bead will outwards expand.When placing in VERTICAL TUBE by powder charge pipe, the result that the inner ring wall of rubber liquid tyre bead outwards expands just makes powder charge pipe firmly be entangled by the inner ring wall of rubber liquid tyre bead, ensure that powder charge pipe is rigidly mounted in VERTICAL TUBE in powder charge process, thus provide precondition for follow-up shot elevation measurement.
As preferably, the outer wall of the inner ring of rubber liquid tyre bead is provided with pressure sensor, and pressure sensor is electrically connected with controller.When the pressure that pressure sensor is subject to reaches setting pressure, pressure sensor sends pressure signal to controller immediately, after controller receives the pressure signal that pressure sensor transmits, controller sends the instruction stopping continuing elongation to immediately No. two cylinders, and now No. two cylinders keep the extended length of No. two expansion links until terminate when a motor stops.
As preferably, the tube wall of VERTICAL TUBE is laterally provided with No. two through holes communicated with tube chamber, in No. two through holes, be provided with automatically controlled lock pin device, and the lock pin of described automatically controlled lock pin device is arranged towards the tube chamber of VERTICAL TUBE, the control end of described automatically controlled lock pin device is electrically connected with controller.After controller receives a signal, controller sends lock pin locking instruction to immediately automatically controlled lock pin device.Powder charge pipe is firmly locked in VERTICAL TUBE by lock pin, thus provides precondition for follow-up shot elevation measurement.
As preferably, also comprise stay cord, lower surface center that one end of stay cord is fixedly connected on magnetic metal ring, the other end of stay cord is fixedly connected on the upper surface center of electromagnetic valve.On a driven by motor lifting rope draw frame to be made with the circumference whipping of centripetal force time, stay cord then can control the maximum tilt angle of drawing frame, and stay cord can also allow and draw frame fast and pulsation-free stopping whipping, provide condition for the clearence degree in guarantee powder charge pipe between aerogenesis tablet is destroyed, reliability is high.
The present invention can reach following effect:
The present invention can make the compaction degree in powder charge pipe between aerogenesis tablet adjustable when filling aerogenesis tablet, make the clearence degree between aerogenesis tablet even after installing gas generant composition in accordance in powder charge pipe again, after can also installing gas generant composition in accordance in powder charge pipe, aerogenesis tablet dosing height can detect, intelligent automation degree is high, controllability is strong, safe and reliable, practicality is good.
Accompanying drawing explanation
Fig. 1 is a kind of using state connection structure schematic diagram when drawing frame also not have a whipping in the embodiment of the present invention.
Fig. 2 is a kind of using state connection structure schematic diagram after No. two expansion links of No. two cylinders in the embodiment of the present invention extend, the liquid in liquid-adding tube is pressed in rubber liquid tyre bead.
Fig. 3 is a kind of connection structure schematic diagram that the lock pin of automatically controlled lock pin device in the embodiment of the present invention is locked at powder charge pipe in VERTICAL TUBE.
Fig. 4 is a kind of circuit theory connection structure schematic block diagram of the embodiment of the present invention.
Fig. 5 draws frame by a kind of using state connection structure schematic diagram during whipping in the embodiment of the present invention.
Detailed description of the invention
Below in conjunction with accompanying drawing and embodiment, the present invention is further illustrated.
Embodiment: gas generator air extractor duct aluminium foil attaches device for detecting sealability, shown in Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5.Gas generator powder charge pipe dosing height detection control setup, comprises support 1, medicine input unit 2, motor 3, No. two motors 4, pivoted arm 5, lifting rope 6, lower end is opening draws frame 7, VERTICAL TUBE 8 and controller 9; A pedestal 10 of a motor is fixedly mounted on support, and a motor rotating shaft 11 is arranged straight down; One end level of described pivoted arm is fixedly connected on the lower end of a described rotating shaft, the other end of described pivoted arm is fixedly connected on the upper end of described lifting rope, the lower end of described lifting rope is fixedly connected on No. two pedestals 12 of No. two motors, and No. two motors No. two rotating shafts 13 are arranged straight down; Draw the upper end of frame to be fixedly connected on the lower end of described No. two rotating shafts, draw the opening of frame lower end to be fixedly connected on the outer wall upper end of VERTICAL TUBE; The outside face of VERTICAL TUBE is provided with can to VERTICAL TUBE produce sieve sieve producer 14, annulus base plate 15 is fixedly connected with in the lower port of VERTICAL TUBE, the lower surface of annulus base plate is fixedly connected with magnetic metal ring 16, the support below magnetic metal ring is fixed with electromagnet 26; The upper surface of the annulus base plate surrounded at the tube chamber of VERTICAL TUBE is provided with a contact pickup 17; The vertical bar drawing frame is fixedly equipped with angular transducer 18; Drawing on frame vertically towards having the measurement expansion link 20 driven by a cylinder 19 expansion link 30 directly over the opening of VERTICAL TUBE, the measurement annulus 27 be arranged in parallel with the upper end mouth of pipe of VERTICAL TUBE is fixedly connected with in the lower end measuring expansion link, and the line of centers of the line of centers and VERTICAL TUBE of measuring annulus overlaps, the lower surface measuring annulus is laid with No. two equal contact pickups 21 of several detection faces height; Store medicine-chest 22 drawing frame is fixedly equipped with, what the medicine outlet storing medicine-chest was connected to medicine input unit by drug feeding pipe 23 docking is used as medicine on mouth; One end mouth of pipe being provided with the medicine input pipe 24 of electromagnetic valve 25 is fixedly connected on the medicine outlet of medicine input unit, the other end mouth of pipe 26 of this root medicine input pipe is arranged in directly over the upper end mouth of pipe of VERTICAL TUBE down, and the line of centers of the other end mouth of pipe of this root medicine input pipe overlaps with the line of centers of VERTICAL TUBE; The control end of a described contact pickup, angular transducer, cylinder, several No. two contact pickups, electromagnetic valve, the control end of electromagnet, the control end of a motor, the control end of No. two motors, the control end of medicine input unit and the control end sieving producer are electrically connected with controller respectively.Described measurement expansion link 20 comprises vertical section 28 and is connected to vertical section lower end and the some bending segments 29 bent respectively outwardly, and described measurement annulus is fixed on bending segment.Also comprise rubber liquid tyre bead 31, the inner tubal wall of VERTICAL TUBE is laterally provided with annular groove, and the line of centers of annular groove overlaps with the line of centers of VERTICAL TUBE, the one number service hole communicated with the outer tube wall of VERTICAL TUBE is provided with in annular groove, the collar wall of rubber liquid tyre bead is pasted and is connected in annular groove, and the liquid mouth pipe 33 of rubber liquid tyre bead is arranged in one number service hole, be fixed with No. two cylinders 34 and liquid-adding tube 35 respectively drawing on frame, seal cover cap 36 is sealedly connected with in one end of liquid-adding tube, seal cover cap is provided with communication port 37, in liquid-adding tube, slipper seal is provided with sliding shoe 38, one end of a pipe link 39 to enter in liquid-adding tube from the other end of liquid-adding tube and is fixedly connected on the outer wall of sliding shoe, the other end of described pipe link is fixedly connected on No. two expansion links 40 of No. two cylinders, liquid-adding tube between seal cover cap and sliding shoe is built with liquid 41, the two ends of a hydraulic pipe 32 are docked respectively and are connected in described communication port with on described liquid mouth pipe, the control end of No. two cylinders is electrically connected with controller.The outer wall of the inner ring of rubber liquid tyre bead is provided with pressure sensor 46, and pressure sensor is electrically connected with controller.The tube wall of VERTICAL TUBE 8 is laterally provided with No. two through holes 42 communicated with tube chamber, automatically controlled lock pin device 43 is provided with in No. two through holes, and the lock pin 44 of described automatically controlled lock pin device is arranged towards the tube chamber of VERTICAL TUBE, the control end of described automatically controlled lock pin device is electrically connected with controller.Also comprise stay cord 45, lower surface center that one end of stay cord is fixedly connected on magnetic metal ring, the other end of stay cord is fixedly connected on the upper surface center of electromagnetic valve.
Be applicable to a detection control method for gas generator powder charge pipe dosing height detection control setup, detection control method comprises the steps:
The powder charge pipe 47 of gas generator is put in VERTICAL TUBE, and allows the air extractor duct connection end of powder charge pipe arrange down;
When a contact pickup is subject to the lower surface extruding of powder charge pipe, a contact pickup sends a signal to controller;
After controller receives a signal, controller sends the instruction of an expansion link elongation to immediately a cylinder, after an expansion link elongation of a cylinder, No. two contact pickups measured on expansion link is placed into the setting height place in powder charge pipe;
After controller receives a signal, controller sends the instruction of No. two expansion links elongations to immediately No. two cylinders, after No. two expansion links elongations of No. two cylinders, the liquid in liquid-adding tube is pressed in rubber liquid tyre bead, the inner ring wall of rubber liquid tyre bead will outwards expand, the result that the inner ring wall of rubber liquid tyre bead outwards expands just makes powder charge pipe firmly be entangled by the inner ring wall of rubber liquid tyre bead, ensure that powder charge pipe is rigidly mounted in VERTICAL TUBE in powder charge process; When the pressure that pressure sensor is subject to reaches setting pressure, pressure sensor sends pressure signal to controller immediately, after controller receives the pressure signal that pressure sensor transmits, controller sends the instruction stopping continuing elongation to immediately No. two cylinders, and now No. two cylinders keep the extended length of No. two expansion links until terminate when a motor stops.
After controller receives a signal, controller sends lock pin locking instruction to immediately automatically controlled lock pin device.Powder charge pipe is firmly locked in VERTICAL TUBE by lock pin.
Then, controller sends the instruction of opening valve immediately to electromagnetic valve, electromagnetic valve opens valve immediately;
Then, controller sends dosing instruction to immediately medicine input unit, and medicine input unit is put into the aerogenesis tablet 48 stored in medicine-chest in powder charge pipe through drug feeding pipe and medicine input pipe successively;
Simultaneously, controller sends sieve instruction to sieving producer, what sieve producer generation sieves wave loops on the aerogenesis tablet in powder charge pipe, aerogenesis tablet sieves in powder charge pipe, for realize making when filling aerogenesis tablet the compaction degree in powder charge pipe between aerogenesis tablet adjustable, in powder charge pipe, install gas generant composition in accordance after make to install gas generant composition in accordance in all even powder charge pipe of the clearence degree between aerogenesis tablet after aerogenesis tablet dosing height can detect and provide precondition;
Simultaneously, controller sends rotation command to a motor, pivoted arm is driven to rotate after an electric machine rotation, pivoted arm rotates and then drives lifting rope to be made with the circumference whipping of centripetal force, the circumference whipping that lifting rope is made with centripetal force then drives the powder charge pipe be placed in VERTICAL TUBE also to follow suit the circumference whipping of centripetal force, and then make the aerogenesis tablet in powder charge pipe also be made with the circumference whipping of centripetal force, aerogenesis tablet extrudes toward the bottom in powder charge pipe under centripetal force effect, compaction degree in centripetal force larger powder charge pipe between aerogenesis tablet is tighter, the compaction degree in controlled loading of explosive pipe between aerogenesis tablet is carried out by the rotating speed controlling a motor, thus realize making the compaction degree in powder charge pipe between aerogenesis tablet adjustable when filling aerogenesis tablet.On a driven by motor lifting rope draw frame to be made with the circumference whipping of centripetal force time, stay cord then can control the maximum tilt angle of drawing frame, and stay cord can also allow and draw frame fast and pulsation-free stopping whipping, provide condition for the clearence degree in guarantee powder charge pipe between aerogenesis tablet is destroyed, reliability is high.
Simultaneously, controller sends rotation command to No. two motors, drive after No. two electric machine rotations and draw frame roll rotational, the powder charge pipe be placed in VERTICAL TUBE also follows roll rotational to draw frame roll rotational then to drive, powder charge pipe roll rotational can make the aerogenesis tablet in powder charge pipe also follow roll rotational, aerogenesis tablet makes the clearence degree between aerogenesis tablet even under roll rotational effect, thus makes the clearence degree between aerogenesis tablet even after realizing installing gas generant composition in accordance in powder charge pipe;
When measuring each No. two contact pickups on annulus and being subject to the extruding of the aerogenesis tablet in powder charge pipe, each No. two contact pickups send No. two signals to controller respectively;
After controller receives No. two signals that each No. two contact pickups send, controller sends the instruction of valve-off immediately to electromagnetic valve, electromagnetic valve is valve-off immediately, thus after realizing installing gas generant composition in accordance in powder charge pipe, aerogenesis tablet dosing height can detect, and then realize chemical feeding quantity required in powder charge pipe;
Then, controller sends stopping dosing instruction to immediately medicine input unit, and medicine input unit stops dosing immediately;
Meanwhile, controller sends stopping sieve instruction to sieving producer, sieves producer and stops sieving;
Meanwhile, controller sends the instruction that stops operating, No. two motor stalls to No. two motors;
Meanwhile, controller sends the instruction that stops operating, a motor stalls to a motor;
Then, controller sends the instruction of an expansion link shortening to a cylinder, after an expansion link shortening of a cylinder, No. two contact pickups measured on expansion link is shifted out in powder charge pipe, terminates the charging to powder charge pipe.
The present embodiment can make the compaction degree in powder charge pipe between aerogenesis tablet adjustable when filling aerogenesis tablet, make the clearence degree between aerogenesis tablet even after installing gas generant composition in accordance in powder charge pipe again, after can also installing gas generant composition in accordance in powder charge pipe, aerogenesis tablet dosing height can detect, intelligent automation degree is high, controllability is strong, safe and reliable, practicality is good.
Describe embodiments of the present invention by reference to the accompanying drawings above, but do not limit by above-described embodiment when realizing, those of ordinary skill in the art can make a variety of changes within the scope of the appended claims or revise.

Claims (7)

1. a gas generator powder charge pipe dosing height detection control setup, it is characterized in that, comprise support (1), medicine input unit (2), motor (3), No. two motors (4), pivoted arm (5), lifting rope (6), lower end are opening draws frame (7), VERTICAL TUBE (8) and controller (9); A pedestal (10) of a motor is fixedly mounted on support, and a motor rotating shaft (11) is arranged straight down; One end level of described pivoted arm is fixedly connected on the lower end of a described rotating shaft, the other end of described pivoted arm is fixedly connected on the upper end of described lifting rope, the lower end of described lifting rope is fixedly connected on No. two pedestals (12) of No. two motors, and No. two motors No. two rotating shafts (13) are arranged straight down; Draw the upper end of frame to be fixedly connected on the lower end of described No. two rotating shafts, draw the opening of frame lower end to be fixedly connected on the outer wall upper end of VERTICAL TUBE; The outside face of VERTICAL TUBE is provided with can to VERTICAL TUBE produce sieve sieve producer (14), annulus base plate (15) is fixedly connected with in the lower port of VERTICAL TUBE, the lower surface of annulus base plate is fixedly connected with magnetic metal ring (16), the support below magnetic metal ring is fixed with electromagnet (26); The upper surface of the annulus base plate surrounded at the tube chamber of VERTICAL TUBE is provided with a contact pickup (17); The vertical bar drawing frame is fixedly equipped with angular transducer (18); Drawing on frame vertically towards having the measurement expansion link (20) driven by an expansion link (30) of a cylinder (19) directly over the opening of VERTICAL TUBE, the measurement annulus (27) be arranged in parallel with the upper end mouth of pipe of VERTICAL TUBE is fixedly connected with in the lower end measuring expansion link, and the line of centers of the line of centers and VERTICAL TUBE of measuring annulus overlaps, the lower surface measuring annulus is laid with No. two equal contact pickups (21) of several detection faces height; Store medicine-chest (22) drawing frame is fixedly equipped with, what the medicine outlet storing medicine-chest was connected to medicine input unit by drug feeding pipe (23) docking is used as medicine on mouth; One end mouth of pipe being provided with the medicine input pipe (24) of electromagnetic valve (25) is fixedly connected on the medicine outlet of medicine input unit, the other end mouth of pipe (26) of this root medicine input pipe is arranged in directly over the upper end mouth of pipe of VERTICAL TUBE down, and the line of centers of the other end mouth of pipe of this root medicine input pipe overlaps with the line of centers of VERTICAL TUBE; The control end of a described contact pickup, angular transducer, cylinder, several No. two contact pickups, electromagnetic valve, the control end of electromagnet, the control end of a motor, the control end of No. two motors, the control end of medicine input unit and the control end sieving producer are electrically connected with controller respectively.
2. gas generator powder charge pipe dosing height detection control setup according to claim 1, it is characterized in that, described measurement expansion link (20) comprises vertical section (28) and is connected to vertical section lower end and the some bending segments (29) bent respectively outwardly, and described measurement annulus is fixed on bending segment.
3. gas generator powder charge pipe dosing height detection control setup according to claim 1, it is characterized in that, also comprise rubber liquid tyre bead (31), the inner tubal wall of VERTICAL TUBE is laterally provided with annular groove, and the line of centers of annular groove overlaps with the line of centers of VERTICAL TUBE, the one number service hole communicated with the outer tube wall of VERTICAL TUBE is provided with in annular groove, the collar wall of rubber liquid tyre bead is pasted and is connected in annular groove, and the liquid mouth pipe (33) of rubber liquid tyre bead is arranged in one number service hole, be fixed with No. two cylinders (34) and liquid-adding tube (35) respectively drawing on frame, seal cover cap (36) is sealedly connected with in one end of liquid-adding tube, seal cover cap is provided with communication port (37), in liquid-adding tube, slipper seal is provided with sliding shoe (38), a pipe link 39) one end to enter in liquid-adding tube from the other end of liquid-adding tube and be fixedly connected on the outer wall of sliding shoe, the other end of described pipe link is fixedly connected on No. two expansion links (40) of No. two cylinders, liquid-adding tube between seal cover cap and sliding shoe is built with liquid (41), the two ends of a hydraulic pipe (32) are docked respectively and are connected in described communication port with on described liquid mouth pipe, the control end of No. two cylinders is electrically connected with controller.
4. gas generator powder charge pipe dosing height detection control setup according to claim 3, it is characterized in that, the outer wall of the inner ring of rubber liquid tyre bead is provided with pressure sensor (46), and pressure sensor is electrically connected with controller.
5. gas generator powder charge pipe dosing height detection control setup according to claim 1, it is characterized in that, the tube wall of VERTICAL TUBE (8) is laterally provided with No. two through holes (42) communicated with tube chamber, automatically controlled lock pin device (43) is provided with in No. two through holes, and the lock pin (44) of described automatically controlled lock pin device is arranged towards the tube chamber of VERTICAL TUBE, the control end of described automatically controlled lock pin device is electrically connected with controller.
6. gas generator powder charge pipe dosing height detection control setup according to claim 1, it is characterized in that, also comprise stay cord (45), lower surface center that one end of stay cord is fixedly connected on magnetic metal ring, the other end of stay cord is fixedly connected on the upper surface center of electromagnetic valve.
7. be applicable to a detection control method for gas generator powder charge pipe dosing height detection control setup according to claim 1, it is characterized in that, detection control method comprises the steps:
The powder charge pipe (47) of gas generator is put in VERTICAL TUBE, and allows the air extractor duct connection end of powder charge pipe arrange down;
When a contact pickup is subject to the lower surface extruding of powder charge pipe, a contact pickup sends a signal to controller;
After controller receives a signal, controller sends the instruction of an expansion link elongation to immediately a cylinder, after an expansion link elongation of a cylinder, No. two contact pickups measured on expansion link is placed into the setting height place in powder charge pipe;
Then, controller sends the instruction of opening valve immediately to electromagnetic valve, electromagnetic valve opens valve immediately;
Then, controller sends dosing instruction to immediately medicine input unit, and medicine input unit is put into the aerogenesis tablet (48) stored in medicine-chest in powder charge pipe through drug feeding pipe and medicine input pipe successively;
Simultaneously, controller sends sieve instruction to sieving producer, what sieve producer generation sieves wave loops on the aerogenesis tablet in powder charge pipe, aerogenesis tablet sieves in powder charge pipe, for realize making when filling aerogenesis tablet the compaction degree in powder charge pipe between aerogenesis tablet adjustable, in powder charge pipe, install gas generant composition in accordance after make to install gas generant composition in accordance in all even powder charge pipe of the clearence degree between aerogenesis tablet after aerogenesis tablet dosing height can detect and provide precondition;
Simultaneously, controller sends rotation command to a motor, pivoted arm is driven to rotate after an electric machine rotation, pivoted arm rotates and then drives lifting rope to be made with the circumference whipping of centripetal force, the circumference whipping that lifting rope is made with centripetal force then drives the powder charge pipe be placed in VERTICAL TUBE also to follow suit the circumference whipping of centripetal force, and then make the aerogenesis tablet in powder charge pipe also be made with the circumference whipping of centripetal force, aerogenesis tablet extrudes toward the bottom in powder charge pipe under centripetal force effect, compaction degree in centripetal force larger powder charge pipe between aerogenesis tablet is tighter, the compaction degree in controlled loading of explosive pipe between aerogenesis tablet is carried out by the rotating speed controlling a motor, thus realize making the compaction degree in powder charge pipe between aerogenesis tablet adjustable when filling aerogenesis tablet,
Simultaneously, controller sends rotation command to No. two motors, drive after No. two electric machine rotations and draw frame roll rotational, the powder charge pipe be placed in VERTICAL TUBE also follows roll rotational to draw frame roll rotational then to drive, powder charge pipe roll rotational can make the aerogenesis tablet in powder charge pipe also follow roll rotational, aerogenesis tablet makes the clearence degree between aerogenesis tablet even under roll rotational effect, thus makes the clearence degree between aerogenesis tablet even after realizing installing gas generant composition in accordance in powder charge pipe;
When measuring each No. two contact pickups on annulus and being subject to the extruding of the aerogenesis tablet in powder charge pipe, each No. two contact pickups send No. two signals to controller respectively;
After controller receives No. two signals that each No. two contact pickups send, controller sends the instruction of valve-off immediately to electromagnetic valve, electromagnetic valve is valve-off immediately, thus after realizing installing gas generant composition in accordance in powder charge pipe, aerogenesis tablet dosing height can detect, and then realize chemical feeding quantity required in powder charge pipe;
Then, controller sends stopping dosing instruction to immediately medicine input unit, and medicine input unit stops dosing immediately;
Meanwhile, controller sends stopping sieve instruction to sieving producer, sieves producer and stops sieving;
Meanwhile, controller sends the instruction that stops operating, No. two motor stalls to No. two motors;
Meanwhile, controller sends the instruction that stops operating, a motor stalls to a motor;
Then, controller sends the instruction of an expansion link shortening to a cylinder, after an expansion link shortening of a cylinder, No. two contact pickups measured on expansion link is shifted out in powder charge pipe, terminates the charging to powder charge pipe.
CN201510392567.2A 2015-07-02 2015-07-02 Gas generator powder charge pipe dosing height detection control device and detection control method Active CN105129447B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510392567.2A CN105129447B (en) 2015-07-02 2015-07-02 Gas generator powder charge pipe dosing height detection control device and detection control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510392567.2A CN105129447B (en) 2015-07-02 2015-07-02 Gas generator powder charge pipe dosing height detection control device and detection control method

Publications (2)

Publication Number Publication Date
CN105129447A true CN105129447A (en) 2015-12-09
CN105129447B CN105129447B (en) 2017-03-29

Family

ID=54715114

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510392567.2A Active CN105129447B (en) 2015-07-02 2015-07-02 Gas generator powder charge pipe dosing height detection control device and detection control method

Country Status (1)

Country Link
CN (1) CN105129447B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6845890B2 (en) * 2001-10-16 2005-01-25 Universal Aggregates, Llc Bulk granular solids gravity flow curing vessel
WO2012176950A1 (en) * 2011-06-20 2012-12-27 Na Gi-Oh Automatic powder bag opening device
CN103287868A (en) * 2012-03-02 2013-09-11 扬州龙锦涂装环保设备有限公司 Adding medicine chamber
CN203728225U (en) * 2014-02-19 2014-07-23 刘兆卫 Reverse-pulse dust-collection feeding device for trace material batcher

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6845890B2 (en) * 2001-10-16 2005-01-25 Universal Aggregates, Llc Bulk granular solids gravity flow curing vessel
WO2012176950A1 (en) * 2011-06-20 2012-12-27 Na Gi-Oh Automatic powder bag opening device
CN103287868A (en) * 2012-03-02 2013-09-11 扬州龙锦涂装环保设备有限公司 Adding medicine chamber
CN203728225U (en) * 2014-02-19 2014-07-23 刘兆卫 Reverse-pulse dust-collection feeding device for trace material batcher

Also Published As

Publication number Publication date
CN105129447B (en) 2017-03-29

Similar Documents

Publication Publication Date Title
CN108444665A (en) Rotating vane excitation system and apparatus for rotating vane vibration test system
US20140199157A1 (en) Method for barring a rotor of a turbomachine and barring apparatus for conducting such method
CN104807646B (en) Solid propellant rocket is centrifuged the erecting device of overload test
CN107765181A (en) Motor dynamics detecting and analysing system
CN207502127U (en) A kind of camshaft air-tightness and oilhole plug compressive property detection device
CN104792540A (en) Centrifugal overload test system of solid rocket engine
CN104729581B (en) Panoramic sunroof production line
CN109229421A (en) A kind of unmanned plane power performance test macro and method
CN206470048U (en) Large-scale impeller overspeed test bench
BR102016004249A2 (en) METHOD TO DISTINGUISH ENGINE BEAT FROM PISTON POPPING, SYSTEM AND COMPUTER-READable NON-TRANSITORY MEDIUM
CN204776106U (en) Gas generator powder charge pipe adds medicine height detection controlling means
CN109569900A (en) A kind of geotechnical centrifuge self balancing device
CN106312872A (en) Horizontal rotating device for electric water heater inner container
CN105129447A (en) Detection and control device and method for powder adding height of powder charging pipe of gas generator
CN107667278A (en) The piston rotation device of gravity pressure meter
CN107797062A (en) The online operating mode malfunction elimination system of motor
CN107816362A (en) A kind of tunnel air monitoring system for engineering design based on BIM
KR102069462B1 (en) Metal powders drying system for improved secondary cell battery manufacturing using negative pressure and drying method Thereof
JP4290892B2 (en) Ore charging equipment for shaft furnace
CN206145417U (en) Guide device and sealed gas chamber of rubber membrane that has guide device
CN206945107U (en) A kind of meausring apparatus of automatic discharging
CN206269972U (en) A kind of survey air tightness test and water injection unit that can be applied to full-automatic melting wiring body
CN105910890A (en) Method and device for synchronizing rotating disc station number recognition and steel seal number reading
CN206242318U (en) A kind of nano imvite phosphorus flame retardant powder blanking device
CN205713404U (en) Pneumoelectric elevation mast

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 313104 Changxing County Agricultural Institute, Changxing County City, Zhejiang

Patentee after: Jun Sheng automotive safety system (Changxin) Co.,Ltd.

Address before: 313104 Changxing County Agricultural Institute, Changxing County City, Zhejiang

Patentee before: GAOTIAN (CHANGXING) AUTOMOBILE SAFETY DEVICE CO.,LTD.

CP01 Change in the name or title of a patent holder
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Gas generator charging tube dosing height detection control device and detection control method

Effective date of registration: 20211206

Granted publication date: 20170329

Pledgee: Bank of China Limited by Share Ltd. Changxing County branch

Pledgor: Jun Sheng automotive safety system (Changxin) Co.,Ltd.

Registration number: Y2021330002453

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20230522

Granted publication date: 20170329

Pledgee: Bank of China Limited by Share Ltd. Changxing County branch

Pledgor: Jun Sheng automotive safety system (Changxin) Co.,Ltd.

Registration number: Y2021330002453