CN105113529B - Aid-sedimentation construction method for open caisson engineering in dense round gravel layer or gravel layer - Google Patents

Aid-sedimentation construction method for open caisson engineering in dense round gravel layer or gravel layer Download PDF

Info

Publication number
CN105113529B
CN105113529B CN201510481446.5A CN201510481446A CN105113529B CN 105113529 B CN105113529 B CN 105113529B CN 201510481446 A CN201510481446 A CN 201510481446A CN 105113529 B CN105113529 B CN 105113529B
Authority
CN
China
Prior art keywords
open caisson
gravel
gravel layer
formula
critical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510481446.5A
Other languages
Chinese (zh)
Other versions
CN105113529A (en
Inventor
姜源
陈红梅
肖琴
陈利军
赵龙
洪涛
吴庆林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Jing Hong Construction Co Ltd
Original Assignee
Yunnan Jing Hong Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Jing Hong Construction Co Ltd filed Critical Yunnan Jing Hong Construction Co Ltd
Priority to CN201510481446.5A priority Critical patent/CN105113529B/en
Publication of CN105113529A publication Critical patent/CN105113529A/en
Application granted granted Critical
Publication of CN105113529B publication Critical patent/CN105113529B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses an aid-sedimentation construction method for open caisson engineering in a dense round gravel layer or a gravel layer, which is mainly used for solving the construction problem encountered very easily in the prior art that an open caisson sinks slowly and even does not sink in open caisson construction under the geological condition of the dense round gravel layer or the gravel layer. The aid-sedimentation construction method comprises the following steps: rotationally cutting soil masses in the range of cutting edges by rotary spraying of high-pressure rotary spraying water so as to reduce the percentage of the hard round gravel layer and the frictional resistance of the soil masses and cause the open caisson to sink by own gravity, determining the depth, radius and spacing which are needed by rotary spraying according to L1 and X% after sequentially calculating the critical frictional resistance, the area of round gravels scattered by the rotary spraying water on the peripheral wall sides of the open caisson, the depth L1 of the soil piercing part of the open caisson above the cutting edges and the area proportion X% of the round gravel layer improved at the cutting edges, then selecting an appropriate high-pressure jet grouting pile machine for scattering the soil masses, and cutting earth in the open caisson so as to cause the open caisson to sink by own gravity. By adopting the technical scheme, the aid-sedimentation construction method achieves the purpose of causing the open caisson to easily sink.

Description

Sinking construction method is helped for sinking well engineering in closely knit gravel layer or sandy gravel stratum
Technical field
The present invention relates to sinking well engineering field, specifically, is to be related to one kind to be used to sink in closely knit gravel layer or sandy gravel stratum The construction method of well engineering.
Background technology
Open caisson is the works of pit shaft shape, and it is, to cut the earth in well, to overcome by self gravitation and sink after borehole wall frictional resistance To designed elevation, then through concrete sealing bottom and clog wellhole so as to become Bridge Pier (pump house, upper pipe working well) or The basis of other structures thing;Which has obtained applying in municipal works and other engineering constructions extremely widely, and this is applied Work technology has gradually tended to ripe.But, in open caisson construction under closely knit gravel layer or sandy gravel stratum geological conditions, it is heavy easily to run into The deep and slow slow even not heavy construction difficult problem in down-hole.
The content of the invention
The problem to be solved in the present invention is, in open caisson construction under closely knit gravel layer or sandy gravel stratum geological conditions, easily to run into The slowly even not heavy construction difficult problem of well sinking.
In order to solve the above problems, the present invention provides following technical scheme:
A kind of sinking construction method that helps for sinking well engineering in closely knit gravel layer or sandy gravel stratum comprises the following steps:
A () calculates caisson cutting edge above open caisson and buries the gravel layer area ratio improved by partial depth L1 and cutting shoe part X%;
B () determines churning desired depth, radius, churning desired spacing needed for churning according to L1, X%;According to following requirements Select jet grouting pile driving machine and the position of stake is set, churning desired depth=stake is long, radius needed for churning=stake footpath, needed for churning Spacing=pile spacing;
C the laggard horizontal high voltage injection water operation of rig drilling intubation in place of () jet grouting pile driving machine connection makes the soil body in aperture Form flowing, the soil body of bulk;
Cut the earth in (d) open caisson, make open caisson sink by soil compaction of conducting oneself with dignity.
Specifically, the process that implements of step (a) is:
(a1) open caisson is calculated by the critical frictional resistance f to be reached that sinks that conducts oneself with dignity according to formula (1)It is critical
fIt is critical=G/K (1)
In formula, fIt is critical- critical frictional resistance (KN/m2);
G-open caisson deadweight (KN);
K-and it is sinking safety coefficient, its span is 1.15~1.25;
(a2) the round gravel face that open caisson perisporium side is broken up by churning water is calculated according to formula (1) in formula (2) and step (a1) Product AImprove
fGravel layer.(As-AImprove)/As+fDissipate circle gravel.AImprove/As=fIt is critical (2)
In formula, fGravel layer- for hard gravel layer unit area frictional resistance, it is known that;
As-it is open caisson perisporium area, it is known that;
fDissipate circle gravel- justify the unit area frictional resistance after gravel is broken up for hard, it is known that;
fIt is critical- it is critical frictional resistance, can be calculated according to formula (1), it is known that;
AImprove--- it is for the round gravel area that open caisson perisporium side is broken up by churning, unknown;
(a3) calculate cutting shoe above open caisson to bury the gravel layer area ratio improved by partial depth L1 and cutting shoe part X%;Cutting shoe height h is known;
fh=fDissipate circle gravel.X%+fGravel layer. (1-X%) (3)
In formula, fh- it is the critical friction power that the soil body is corresponded in basil altitude range;
It is different soil layers up and down after improved, substitutes into soil layer average friction and pass through weighted average formula f=∑ qihi/ ∑hi, have
[fDissipate circle gravel.L1+fh.h]/(L1+h)=fIt is critical (4)
Formula (3) substitution (4) can be obtained:
fDissipate circle gravel.L1+[fDissipate circle gravel.X%+fGravel layer. (1-X%)] .h=fIt is critical.(L1+h) (5)
Churning to help heavy section cutting shoe bottom when, entirely improving has following relational expression between area and well sinking depth:
AImprove=L1.LGirth+ h.X%.LGirth (6)
In formula (6), LGirthFor open caisson girth, it was known that AImproveCalculate and learn;Formula (5), (6)
In h be caisson cutting edge height, it is known that;
Therefore the linear equation in two unknowns that solution formula (5) is constituted with (6), the value of L1, X% can be drawn;
Specifically, the process that implements of step (b) is:Long=the L1+h of stake, in the long certain situation of stake, selected stake footpath, Pile spacing, by trying whether this long, stake footpath of spray experimental verification, pile spacing can reach L1, X% for calculating, be, then this stake Length, stake footpath, pile spacing are correct selection, no, then reselect a footpath, pile spacing and can extremely reach L1, the X% for calculating.
Specifically, the process that implements of step (c) is:
(c1) rig laggard water-filling in place is flat, vertical correction, to ensure between hole heart position and open caisson inwall distance 20 In~30cm;
(c2) adjust the angle of the drilling cramp of rig so as to get perpendicularity deviation scope≤1.5% in hole;
(c3) drill to caisson cutting edge designed elevation, play pipe, high-pressure injection water filling;
(c4) drilling rod of rig is disturbed up and down, cuts the soil body;
(c5) repeat step (c3) and (c4) stop when being less than grouting amount 20% to the leakage amount for drilling, and now the soil body is obtained Fully cut.
Specifically, the rotation of the drilling rod of rig and lifting continuously must not interrupted, and keep rotating speed and lifting speed constant, tear open Drilling rod will be kept when unloading drilling rod there are more than the 0.1m laps of splice.
Compared with prior art, the invention has the advantages that:
(1) by the soil body in the range of high-pressure rotary-spray water churning rotary cutting cutting shoe in the present invention, reduce hard gravel layer Shared percentage, is reduced soil body frictional resistance, makes open caisson smoothly be sunk by self gravitation.
(2) present invention and traditional caisson sinking construction are compared, by the stake of control jet grouting pile driving machine it is long, between stake footpath, stake Away from, reduce frictional resistance of the soil body to the borehole wall, it is ensured that the smooth sinking of open caisson, what thoroughly solution well sinking did not slowly even sink asks Topic, and take other to help the risk of heavy measure, it is ensured that the quality of construction.
(3) spray water with high pressure and smash gravel layer, the soil body is stirred, produce certain swelling mud reach loosening soil layer, Lubrication borehole wall drag-reduction effect is formed, efficiency of construction is improved, is made open caisson smoothly sink, increase construction speed.
(4) present invention helps heavy technique to compare with thixotropic slurry, is not limited by place, without preloading, it is to avoid guide hole thixotropic slurry The hidden danger that the safety brought, quality, environmental protection bring;And process is simple, save construction cost.
Description of the drawings
Fig. 1 is the structured flowchart of the present invention.
Specific embodiment
The invention will be further described with reference to the accompanying drawings and examples, and embodiments of the present invention are included but is not limited to The following example.
Embodiment
As shown in figure 1, the sinking construction method that helps for sinking well engineering in closely knit gravel layer or sandy gravel stratum is revolved by high pressure The soil body in the range of water spray churning rotary cutting cutting shoe, reduces the percentage shared by hard gravel layer, reduces soil body frictional resistance, Open caisson is made to sink by self gravitation, which comprises the following steps:
1.1 calculate open caisson by the critical frictional resistance f to be reached that sinks that conducts oneself with dignity according to formula (1)It is critical
fIt is critical=G/K (1)
In formula, fIt is critical- critical frictional resistance (KN/m2);
G-open caisson deadweight (KN);
K-and it is sinking safety coefficient, its span is 1.15~1.25, and the present embodiment K values take 1.25;
1.2 calculate the round gravel area that open caisson perisporium side is broken up by churning water according to formula (1) in formula (2) and step (a) AImprove
fGravel layer.(As-AImprove)/As+fDissipate circle gravel.AImprove/As=fIt is critical (2)
In formula, fGravel layer- for hard gravel layer unit area frictional resistance, it is known that;
As-it is open caisson perisporium area, it is known that;
fDissipate circle gravel- justify the unit area frictional resistance after gravel is broken up for hard, rule of thumb (or experiment) can determine that, it is known that;
fIt is critical- it is critical frictional resistance, can be calculated according to formula (1), it is known that;
AImprove--- it is for the round gravel area that open caisson perisporium side is broken up by churning, unknown;
1.3 calculating cutting shoe above open caissons bury the gravel layer area ratio X% improved by partial depth L1 and cutting shoe part; Cutting shoe is known highly for h;
fh=fDissipate circle gravel.X%+fGravel layer. (1-X%) (3)
In formula, fh- it is the critical friction power that the soil body is corresponded in basil altitude range;
It is different soil layers up and down after improved, substitutes into soil layer average friction and pass through weighted average formula f=∑ qihi/ ∑hi, have
[fDissipate circle gravel.L1+fh.h]/(L1+h)=fIt is critical (4)
Formula (3) substitution (4) can be obtained:
fDissipate circle gravel.L1+[fDissipate circle gravel.X%+fGravel layer. (1-X%)] .h=fIt is critical.(L1+h) (5)
Churning to help heavy section cutting shoe bottom when, entirely improving has following relational expression between area and well sinking depth:
AImprove=L1.LGirth+ h.X%.LGirth (6)
In formula (6), LGirthFor open caisson girth, it was known that AImproveCalculate and learn;H in formula (5), (6) is caisson cutting edge Highly, it is known that;
Therefore the linear equation in two unknowns that solution formula (5) is constituted with (6), the value of L1, X% can be drawn;
1.7 according to L1, X%, determines churning desired depth, radius, churning desired spacing needed for churning;According to following requirements Select jet grouting pile driving machine and the position of stake is set, churning desired depth=stake is long, radius needed for churning=stake footpath, needed for churning Spacing=pile spacing;
1.8 long=L1+h, in the long certain situation of stake, select stake footpath, pile spacing, by this stake of examination spray experimental verification Whether length, stake footpath, pile spacing can reach L1, the X% for calculating, and be, then this long, stake footpath, pile spacing are correct selection, no, Then reselect a footpath, pile spacing and can extremely reach L1, the X% for calculating;
The laggard water-filling in place of 1.9 rigs is flat, vertical correction, with ensure between hole heart position and open caisson inwall distance 20~ In 30cm;The present embodiment takes 30cm;
The angle of the drilling cramp of 2.0 adjustment rigs so as to get perpendicularity deviation scope≤1.5% in hole;
2.1 drill to caisson cutting edge designed elevation, play pipe, high-pressure injection water filling;
The drilling rod of 2.2 rigs is disturbed up and down, cuts the soil body;
The leakage amount of 2.3 repeat steps 2.1 and 2.2 to drilling stops when being less than grouting amount 20%, and now the soil body is filled Cutting is cut;
Cut the earth in 2.3 open caissons, make open caisson sink by soil compaction of conducting oneself with dignity.
Complete the purpose that step 1.1~2.3 item complete in closely knit gravel layer or sandy gravel stratum, make open caisson smoothly sink.
Wherein, the rotation of the drilling rod of rig and lifting continuously must not interrupted, and keep rotating speed and lifting speed constant, dismounting Drilling rod will be kept during drilling rod there are more than the 0.1m laps of splice;More than 20% or completely not grout person, should ascertain the reason, take corresponding Measure, repeat drilling repeat high-pressure injection water filling, the soil body is fully cut (be typically repeated 3~5 times);Leakage amount mistake It is greatly that effective high pressure water injection spray regime is inadaptable with water injection rate caused, reduction injection pressure can be taken when leakage amount is larger; It is appropriate to reduce nozzle diameter;Accelerate the measures such as lifting and churning speed, reduce leakage amount, high pressure water injection amount is larger to be caused to avoid Spray regime larger damage is made to the borehole wall.
As a example by Sewage Disposal:The engineering is full underground type sewage disposal reason station, and long 26m, wide 11m, deep 10.35m are adopted Caisson sinking construction technique, has close shape gravel layer in 2.4~7.2m, and whole place between 1881.99~1885.81m It is distributed;Relevant parameter (the stake for helping heavy mode, spray determination being calculated and tried by the design principle for calculating above using the present invention Ф 500) clear distance 0.7m between stake, churning depth 6.5m are selected in footpath, can be effectively improved soil body area up to 80%, apply the open caisson Work is smoothly sunk;One row Φ, 500 jet grouting pile driving machines, stake outer wall are being set away from open caisson outer wall 30cm positions surrounding specially Between clear distance be 70cm, ejected from nozzle with 20~40MPa high-pressure sprays, the drilling rod carried using jet grouting pile driving machine is band The water injection pipe for having nozzle creeps into face absolute altitude heavy to cutting shoe design, and slowly rotates with 20r/min, is punched, disturbs, destroys the soil body, Drilling rod gradually lifts generally 15-30cm/min with certain speed simultaneously, makes the soil body in aperture be able to fully be cut into bulk, and one It is secondary the churning of all churning hole positions to be stirred deeply to 6.5m depths;Using method of cutting the earth in general well, conducted oneself with dignity outside soil compaction by open caisson, Open caisson is made smoothly to sink.
Performance analysis
For the benefit that society and environment bring
Floor space of the present invention is little, and the disturbance to surrounding soil is less, and without soil erosion, the sedimentation for causing is also less, disappears Except or effectively reduce impact to urban transportation and adjoining building, this is a kind of potential, invisible social benefit.
With clean water as raw material, obtain waste residue (roach), waste water (mud), dust and noise of construction generation etc. To effective control and process;During engineering construction, the resident of surrounding and enterprises and institutions can normally live and work, environmental benefit Substantially.
Economic benefit
The present invention helps heavy technics comparing with thixotropic slurry, except floor space is little, construction speed is fast, interference factor is few, favorably Outside civilized construction, various resources preferably can be utilized, and can ensure that the excellent of around existing facility, it is ensured that periphery is original to be built Build life, property safety of thing and resident etc.;In addition, having saved construction machinery, equipment, equipment, facility and artificial etc. a large amount of straight The expense for connecing and putting into indirectly, economic benefit are very notable.
By taking the Hospital Sewage Treatment station of Yan'an as an example, adopt high-pressure rotary-spray help be sink to designed elevation actually occur expense for 34720 yuan;It is 213164 yuan to help according to the outer tube method of thixotropic slurry and be sink to designed elevation budget expense, investment reduction cost 178444 Unit.
Present device is facilitated, and construction technology is simple, and efficiency of construction is high, can be compared with the reduction of erection time of limits.
According to above-described embodiment, the present invention just can be realized well.What deserves to be explained is, before said structure design Put, be to solve same technical problem, even if some made in the present invention are adopted without substantial change or polishing Technical scheme essence still as the present invention, therefore which should also be as within the scope of the present invention.

Claims (5)

1. it is a kind of to help sinking construction method for sinking well engineering in closely knit gravel layer or sandy gravel stratum, it is characterised in that under which includes Row step:
A () calculates caisson cutting edge above open caisson and buries the gravel layer area ratio X% improved by partial depth L1 and cutting shoe part;
B () determines churning desired depth, radius, churning desired spacing needed for churning according to L1, X%;Selected according to following requirements Jet grouting pile driving machine simultaneously arranges the position of stake, and churning desired depth=stake is long, radius needed for churning=stake footpath, churning desired spacing =pile spacing;
C the laggard horizontal high voltage injection water operation of rig drilling intubation in place of () jet grouting pile driving machine connection forms the soil body in aperture Flowing, the soil body of bulk;
Cut the earth in (d) open caisson, make open caisson sink by soil compaction of conducting oneself with dignity.
2. according to claim 1 to help sinking construction method for sinking well engineering in closely knit gravel layer or sandy gravel stratum, which is special Levy and be, the process that implements of step (a) is:
(a1) open caisson is calculated by the critical frictional resistance f to be reached that sinks that conducts oneself with dignity according to formula (1)It is critical
fIt is critical=G/K (1)
In formula, fIt is critical- critical frictional resistance (KN/m2);
G-open caisson deadweight (KN);
K-and it is sinking safety coefficient, its span is 1.15~1.25;
(a2) the round gravel area that open caisson perisporium side is broken up by churning water is calculated according to formula (1) in formula (2) and step (a1) AImprove
fGravel layer.(As-AImprove)/As+fDissipate circle gravel.AImprove/As=fIt is critical (2)
In formula, fGravel layer- for hard gravel layer unit area frictional resistance, it is known that;
As-it is open caisson perisporium area, it is known that;
fDissipate circle gravel- justify the unit area frictional resistance after gravel is broken up for hard, it is known that;
fIt is critical- it is critical frictional resistance, can be calculated according to formula (1), it is known that;
AImprove- round gravel the area broken up by churning for open caisson perisporium side, it is unknown;
(a3) calculate cutting shoe above open caisson to bury the gravel layer area ratio X% improved by partial depth L1 and cutting shoe part;Sword Foot height h is known;
fh=fDissipate circle gravel.X%+fGravel layer. (1-X%) (3)
In formula, fh- it is the critical friction power that the soil body is corresponded in basil altitude range;
It is different soil layers up and down after improved, substitutes into soil layer average friction and pass through weighted average formula f=∑ qihi/∑hi, Have
[fDissipate circle gravel.L1+fh.h]/(L1+h)=fIt is critical (4)
Formula (3) substitution (4) can be obtained:
fDissipate circle gravel.L1+[fDissipate circle gravel.X%+fGravel layer. (1-X%)] .h=fIt is critical.(L1+h) (5)
Churning to help heavy section cutting shoe bottom when, entirely improving has following relational expression between area and well sinking depth:
AImprove=L1.LGirth+ h.X%.LGirth (6)
In formula (6), LGirthFor open caisson girth, it was known that AImproveCalculate and learn;H in formula (5), (6) is that caisson cutting edge is high Degree, it is known that;
Therefore the linear equation in two unknowns that solution formula (5) is constituted with (6), the value of L1, X% can be drawn.
3. according to claim 2 to help sinking construction method for sinking well engineering in closely knit gravel layer or sandy gravel stratum, which is special Levy and be, the process that implements of step (b) is:Long=the L1+h of stake, in the long certain situation of stake, selectes stake footpath, pile spacing, leads to Cross whether this long, stake footpath of examination spray experimental verification, pile spacing can reach L1, the X% for calculating, be, then this long, stake footpath, stake Spacing is correct selection, no, then reselect a footpath, pile spacing and can extremely reach L1, the X% for calculating.
4. according to claim 3 to help sinking construction method for sinking well engineering in closely knit gravel layer or sandy gravel stratum, which is special Levy and be, the process that implements of step (c) is:
(c1) rig laggard water-filling in place is flat, vertical correction, with ensure between hole heart position and open caisson inwall distance 20~ In 30cm;
(c2) adjust the angle of the drilling cramp of rig so as to get perpendicularity deviation scope≤1.5% in hole;
(c3) drill to caisson cutting edge designed elevation, play pipe, high-pressure injection water filling;
(c4) drilling rod of rig is disturbed up and down, cuts the soil body;
(c5) repeat step (c3) and (c4) stop when being less than grouting amount 20% to the leakage amount for drilling, and now the soil body is obtained fully Cutting.
5. according to claim 4 to help sinking construction method for sinking well engineering in closely knit gravel layer or sandy gravel stratum, which is special Levy and be, the rotation and lifting of the drilling rod of rig continuously must not interrupted, keep rotating speed and lifting speed constant, during dismounting drilling rod Drilling rod to be kept has more than the 0.1m laps of splice.
CN201510481446.5A 2015-08-03 2015-08-03 Aid-sedimentation construction method for open caisson engineering in dense round gravel layer or gravel layer Active CN105113529B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510481446.5A CN105113529B (en) 2015-08-03 2015-08-03 Aid-sedimentation construction method for open caisson engineering in dense round gravel layer or gravel layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510481446.5A CN105113529B (en) 2015-08-03 2015-08-03 Aid-sedimentation construction method for open caisson engineering in dense round gravel layer or gravel layer

Publications (2)

Publication Number Publication Date
CN105113529A CN105113529A (en) 2015-12-02
CN105113529B true CN105113529B (en) 2017-04-12

Family

ID=54661621

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510481446.5A Active CN105113529B (en) 2015-08-03 2015-08-03 Aid-sedimentation construction method for open caisson engineering in dense round gravel layer or gravel layer

Country Status (1)

Country Link
CN (1) CN105113529B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088127A (en) * 2016-07-02 2016-11-09 天鸿建设集团有限公司 Open caisson construction method
CN106168033B (en) * 2016-08-09 2018-09-18 岩土科技股份有限公司 A kind of vertical mud and water balance constructing device
CN106245653B (en) * 2016-08-09 2018-03-09 岩土科技股份有限公司 A kind of vertical mud and water balance construction method
CN108677984A (en) * 2018-05-14 2018-10-19 广东省建筑工程机械施工有限公司 A kind of land sunk well helps heavy technique

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000087361A (en) * 1998-09-10 2000-03-28 Hazama Gumi Ltd Construction method of underground structure
JP2004225326A (en) * 2003-01-22 2004-08-12 Kato Construction Co Ltd Caisson cutting-edge, caisson method and paint composition for caisson cutting-edge
CN102155020A (en) * 2011-01-28 2011-08-17 福建工程学院 Open caisson construction method of reinforced concrete for soft soil layer
CN102505704A (en) * 2011-12-19 2012-06-20 中国水利水电第五工程局有限公司 Large open caisson construction method in soft geological shaft
CN102635124A (en) * 2012-04-23 2012-08-15 浙江省建工集团有限责任公司 Construction method aiming to large open caisson in weak soil area
CN103205978A (en) * 2013-04-18 2013-07-17 成军 High-permeability zone under-water-level elevator foundation pit open caisson moulding bed construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000087361A (en) * 1998-09-10 2000-03-28 Hazama Gumi Ltd Construction method of underground structure
JP2004225326A (en) * 2003-01-22 2004-08-12 Kato Construction Co Ltd Caisson cutting-edge, caisson method and paint composition for caisson cutting-edge
CN102155020A (en) * 2011-01-28 2011-08-17 福建工程学院 Open caisson construction method of reinforced concrete for soft soil layer
CN102505704A (en) * 2011-12-19 2012-06-20 中国水利水电第五工程局有限公司 Large open caisson construction method in soft geological shaft
CN102635124A (en) * 2012-04-23 2012-08-15 浙江省建工集团有限责任公司 Construction method aiming to large open caisson in weak soil area
CN103205978A (en) * 2013-04-18 2013-07-17 成军 High-permeability zone under-water-level elevator foundation pit open caisson moulding bed construction method

Also Published As

Publication number Publication date
CN105113529A (en) 2015-12-02

Similar Documents

Publication Publication Date Title
CN105113529B (en) Aid-sedimentation construction method for open caisson engineering in dense round gravel layer or gravel layer
CN103603342B (en) Major diameter assembled casing super-long filling pile construction method
CN102587401B (en) Sinking construction method for open caisson in geological sludge layer under saturated water condition
CN105735245B (en) The soil stabilization method of trenching construction in the hydraulic reclamation mud layer stratum of seashore
CN207143981U (en) 3rd is rich water half diagenesis Sandstone Section Metro station excavation discharge structure
Kohan et al. The effect of water jetting on spudcan extraction from deep embedment in soft clay
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
Fischer et al. Karst site remediation grouting
CN109487777A (en) A method of a reinforcing deep soft soil foundation of filling the span of a man's arms is formed using slip casing by pressure
Lande et al. Effects of drilling for tieback anchors on surrounding ground: Results from field tests
CN203821414U (en) Structure of protecting wall of hole-digging pile
CN107700508A (en) A kind of shaped steel stirs the construction method of water spray soil curtain support pile
CN105350544B (en) For water-stop curtain and its construction method containing block stone region
CN103806444A (en) Soft soil layer rotary excavating pile construction method
CN104831742B (en) The Method on Dewatering of Foundation Pit that adjacent two layers low pressure water layer is not cut off by water barrier
CN106836182A (en) A kind of compacted technique of vibroflotation water conservancy diversion
CN104727289A (en) Construction method for controlling multiple water-bearing strata to achieve leaking recharge and to protect ambient environment
CN104775444B (en) A kind of method for wet environment protection archeological site earthen ruins Yield rainfall relation
CN105951864A (en) Prevention method for soft soil foundation settlement caused by open caisson manufacturing
CN205742136U (en) Lava grows by force construction site filled type geological disposal structure
Charlton et al. Comprehensive Foundation Rehabilitation at Bear Creek Dam
Langford et al. Pore pressure reduction and settlements induced by deep supported excavations in soft clay
CN205875128U (en) Quincunx shaped steel cement stirring wall
CN107975056A (en) The excessive processing method for causing water-stop curtain stake to be difficult to pile of Bored Pile Filling Coefficient
Guatteri et al. Challenges in the execution of jet grouting curtains at the Estreito HPP

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant