CN105089655A - Rod tubular column for horizontal-well coiled tubing transportation dynamic logging process - Google Patents

Rod tubular column for horizontal-well coiled tubing transportation dynamic logging process Download PDF

Info

Publication number
CN105089655A
CN105089655A CN201510227830.2A CN201510227830A CN105089655A CN 105089655 A CN105089655 A CN 105089655A CN 201510227830 A CN201510227830 A CN 201510227830A CN 105089655 A CN105089655 A CN 105089655A
Authority
CN
China
Prior art keywords
coiled tubing
horizontal well
leading block
fixed pulley
gripper shoe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510227830.2A
Other languages
Chinese (zh)
Inventor
王凤清
张宝辉
杨永祥
章沙莉
李向齐
胡书宝
王一鸣
郭吉民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Natural Gas Co Ltd
Original Assignee
China Petroleum and Natural Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Natural Gas Co Ltd filed Critical China Petroleum and Natural Gas Co Ltd
Priority to CN201510227830.2A priority Critical patent/CN105089655A/en
Publication of CN105089655A publication Critical patent/CN105089655A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a rod tubular column for a horizontal-well coiled tubing transportation dynamic logging process, and belongs to the technical field of oilfield horizontal-well logging. The rod tubular column for the horizontal-well coiled tubing transportation dynamic logging process is composed of a rod tubular column body for the horizontal-well coiled tubing transportation dynamic logging process and a rod column for the horizontal-well coiled tubing transportation dynamic logging process; the tubular column consists of a horn moth, an oil tube, a horizontal-well test hollow pump, a packer, an anti-jacking machine, a disconnecting machine and an oil tube which are sequentially connected from bottom to top, wherein the oil tube I is directly connected with a well mouth; the rod column is as follows: the upper part of a downhole instrument is connected with a flexible short joint, a cable head and a continuous oil tube; and the two ends of the downhole instrument are connected with downhole instrument centralizers. The rod tubular column for the horizontal-well coiled tubing transportation dynamic logging process has the beneficial effects of realizing dynamic logging by adopting the rod tubular column to carry out horizontal-well logging, being removed by adopting the continuous oil tube, and being good in rigidity and toughness.

Description

Horizontal well coiled tubing conveying dynamic logging technique rod tube post
Technical field
The present invention relates to horizontal well coiled tubing conveying dynamic logging technique rod tube post, belong to oilfield horizontal well logging technique field.
Background technology
Production Logging in Horizontal Wells generally adopts three kinds of modes such as the conveying of oil pipe coiled tubing, tractor conveying, Hydraulic transportation both at home and abroad at present.Existing oil pipe conveying and Hydraulic transportation, pumping liquid, liquid enters stratum, directly affects test result, and tractor conveying and coiled tubing carry input cost higher.In the urgent need to finding a kind of testing method as straight well is logged well.
Chinese patent literature " continuous tube horizontal borehole process and device " publication number: CN101382069A, publication date: on March 11st, 2009, adopt continuous-tube as the means of delivery of downhole logging instrument, but horizontal well is adopted for numerous machine, also cannot carry out producing profile testing under normal production status at present.
Chinese patent literature " horizontal well gas lift method producing profile testing process adopted by machine " publication number: CN101403292A, publication date: on April 8th, 2009, adopt the gaslift mode of production, tester is driven, " mainly solving the problem that existing horizontal well cannot carry out producing profile testing under normal production status " with tractor.Shortcomings is that the gaslift mode of production not only needs special nitrogen to produce car and compression locomotive, and truly can not reflect that the normal production status of horizontal well adopted by machine.
Chinese patent literature " preset production fluid section plane test method of mechanical mining horizontal well and special shaft mouth test apparatus " publication number: CN101403291A, publication date: on April 8th, 2009, " method adopting prior preset tester and downhole tractor to combine coordinates special shaft mouth test apparatus to realize machine and adopts horizontal well presetting system producing profile testing." Shortcomings is that whole technique is more complicated.
Chinese patent literature " method for testing horizontal well oil conduit transportation under pumping state " publication number: CN101377127A, publication date: on March 4th, 2009, adopts conventional pumping tool wire rope swab to carry out pumping production, oil pipe conveying test.Shortcomings is because test cable is positioned at outside oil pipe, and not only whole to remove technique more complicated, and whether goes out the uncertainty of protective due to the leakage of pumping instrument and tester, can not reflect that the normal production status of horizontal well adopted by machine.
Summary of the invention
The object of the invention is: a kind of horizontal well coiled tubing conveying well measuring technique rod tube post and logging method are provided, realize horizontal continuity oil pipe conveying well measuring.
The present invention adopts horizontal well to test hollow pump lifting and produces, and coiled tubing crosses the conveying of pump instrument, realizes horizontal well coiled tubing conveying dynamic logging.
The invention provides a kind of coiled tubing well head guiding device; test for horizontal well; guarantee that coiled tubing and cable connector pass through well head smoothly; working rig travelling block can be avoided; reduce the friction of coiled tubing and cable and working rig travelling block, protection coiled tubing and cable prevent the wearing and tearing of coiled tubing and cable.
The technical solution used in the present invention is:
A kind of horizontal well coiled tubing conveying dynamic logging technique rod tube post,
Horizontal well coiled tubing conveying dynamic logging technique rod tube post, is tested dynamic lifting device formed by horizontal well coiled tubing conveying dynamic logging process pipe string, horizontal well coiled tubing conveying dynamic logging technique roofbolt, horizontal well,
Horizontal well coiled tubing conveying dynamic logging process pipe string, primarily of oil pipe, disjointed device, anti-apical organ, packer, horizontal well test hollow pump, horn mouth composition, syndeton is from bottom to top: horn mouth, oil pipe, horizontal well test hollow pump, packer, anti-apical organ, disjointed device are connected successively with oil pipe, and oil pipe receives well head always;
Horizontal well coiled tubing conveying dynamic logging technique roofbolt, primarily of compositions such as coiled tubing, cable head, flexible nipple, downhole instrument centralizers, downhole instrument top connects flexible nipple, cable head, coiled tubing, and downhole instrument two ends are connected to downhole instrument centralizer;
Horizontal well tests dynamic lifting device, and be made up of production rig, self-sealing blowout preventer, oil pipe, on-off connector, connecting rod, anti-apical organ, packer, horizontal well test hollow pump, horn mouth, oil pipe, through self-sealing blowout preventer, passes through 2 with on-off connector 7/ 8heavy wall tubing is threaded; On-off connector is by 2 7/ 8heavy wall tubing screw thread is connected with anti-apical organ; Anti-apical organ is by 2 7/ 8heavy wall tubing screw thread is connected with packer; Packer is by 2 7/ 8heavy wall tubing screw thread and horizontal well are tested hollow pump and are connected; Horizontal well test hollow pump is by 2 7/ 8heavy wall tubing screw thread is connected with oil pipe horn mouth; The length of connecting rod is 9.5m, external diameter 48.3mm, internal diameter 40mm, and its two ends are respectively with the pin thread of M48 × 2.5, and the hollow plunger testing hollow pump respectively with the male of on-off connector and horizontal well is connected;
Coiled tubing well head guiding device, forms primarily of casing coupling 1301, fixed pulley gripper shoe 1303 placed in the middle, fixed pulley 1304 placed in the middle, fixed pulley axis 1305, junction plate 1306, leading block 1307, leading block axle 1308, pivot pin 1309, leading block gripper shoe 1310, nut 1311, screw mandrel 1312 and bearing pin 1314 placed in the middle.Casing coupling 1301 is cylindrical shape, and the tubing coupling that casing coupling 1301 can be enclosed within well head during well logging is used for fixing guiding device.The outer wall of casing coupling 1301 is welded with two parallel fixed pulley gripper shoes 1303 rectangular placed in the middle, the centerline parallel of fixed pulley gripper shoe 1303 placed in the middle and casing coupling 1301; Be connected with a fixed pulley 1304 placed in the middle in the upper end of two fixed pulley gripper shoes 1303 placed in the middle by fixed pulley axis 1305 placed in the middle, fixed pulley 1304 placed in the middle is in the centre of two fixed pulley gripper shoes 1303 placed in the middle; A screw mandrel joint 1313 is connected with by bearing pin 1314 in the bottom of two fixed pulley gripper shoes 1303 placed in the middle, screw mandrel joint 1313 cross section is circular or square, pin shaft hole is had in one end of screw mandrel joint 1313, have pin hole in the bottom of two fixed pulley gripper shoes 1303 placed in the middle, bearing pin 1314 passes pin shaft hole and two fixed pulley gripper shoe 1303 pin holes placed in the middle of screw mandrel joint 1313; Screw mandrel joint 1313 can rotate along pivot pin 1314; Have center screw at the other end of screw mandrel joint 1313, screw mandrel joint 1313 other end center screw internal fixtion has screw mandrel 1312, and the center line of screw mandrel joint 1313 and the center line of screw mandrel 1312 are on same straight line; Screw mandrel 1312 there is nut 1311; Cover has a sliding sleeve in the bottom of nut 1311 and on screw mandrel 1312, sliding sleeve outer wall is symmetrically welded with two to ship and resell on another market, ship and resell on another market hole in the bottom of two leading block gripper shoes 1310, two ship and resell on another market insert two leading block gripper shoe 1310 bottoms respectively ship and resell on another market in hole;
Two leading block gripper shoes 1310 are rectangular flat board; There is pin hole the upper end of two leading block gripper shoes 1310 respectively, a leading block axle 1308 is had in the pin hole of two leading block gripper shoe 1310 upper ends, leading block axle 1308 is connected with leading block 1307, leading block 1307 is in the middle of two leading block gripper shoes 1310;
Pin hole is had at the middle part of two leading block gripper shoes 1310, pivot pin 1309 is had in pin hole in the middle part of two leading block gripper shoes 1310, pivot pin 1309 is through the pin hole of the pin hole in the middle part of two leading block gripper shoes 1310 and junction plate 1306 one end, and junction plate 1306 is connected to the middle part of two leading block gripper shoes 1310 by pivot pin 1309; Have pin shaft hole in the middle part of fixed pulley gripper shoe 1303 placed in the middle, be installed with bearing pin in the pin shaft hole of fixed pulley gripper shoe 1303 placed in the middle, the other end of junction plate 1306 is connected to the two ends of bearing pin;
Horizontal well coiled tubing conveying dynamic logging method,
First, former well casing post is tripped out, drifting, well-flushing;
Secondly, to enter in sleeve pipe under horizontal well coiled tubing conveying dynamic logging process pipe string: be: the test of horn mouth, oil pipe, horizontal well hollow pump, packer, anti-apical organ, disjointed device, oil pipe from bottom to top, oil pipe receives well head always, base sealed packer, the anti-apical organ of grappling, tubing string is thrown off from on-off connector, discharge opeing;
3rd, under enter horizontal well coiled tubing conveying dynamic logging technique roofbolt: downhole instrument top connects flexible nipple, cable head, coiled tubing, and downhole instrument two ends are connected to downhole instrument centralizer;
Then, adopt coiled tubing to remove to test;
Finally, coiled tubing, logger is tripped out;
Further comprising the steps of:
The leading block of coiled tubing well head guiding device is unloaded, the hole slot that coiled tubing has through leading block gripper shoe one end, install leading block and rotary screw rod, leading block is moved inward, after making to there is certain distance between coiled tubing and working rig travelling block, coiled tubing can be transferred; When the lower coiled tubing of needs, rotating nut, makes nut rotate to screw mandrel one end near screw mandrel joint; Due to fixed pulley gripper shoe placed in the middle, junction plate, between leading block gripper shoe and screw mandrel joint, form a quadrangle, make leading block gripper shoe parallel with fixed pulley gripper shoe placed in the middle, leading block gripper shoe drives leading block away from the top of casing coupling above well head; Now coiled tubing leaves above well head at the draught line of leading block; After under operation, coiled tubing starts, coiled tubing can avoid the friction that working rig travelling block avoids coiled tubing and working rig travelling block, prevents coiled tubing from wearing and tearing; Then, coiled tubing enters in well head through the guiding of fixed pulley placed in the middle, make coiled tubing can not with wellhead casing pipe or oil pipe friction, decrease the wearing and tearing of cable.
According to another aspect of the invention, provide a kind of horizontal well coiled tubing conveying dynamic logging technique rod tube post, be arranged in horizontal well, horizontal well has sleeve pipe, horizontal well coiled tubing conveying dynamic logging technique rod tube post comprises: horizontal well coiled tubing conveying dynamic logging process pipe string, is arranged in sleeve pipe; Horizontal well coiled tubing conveying dynamic logging technique roofbolt, horizontal well coiled tubing conveying dynamic logging technique roofbolt is arranged in sleeve pipe through horizontal well coiled tubing conveying dynamic logging process pipe string, horizontal well coiled tubing conveying dynamic logging technique roofbolt comprises downhole instrument, cable head and coiled tubing, coiled tubing is connected with downhole instrument, cable head is electrically connected with downhole instrument through coiled tubing, and cable head is used for being connected with the cable of horizontal well outside; Horizontal well for lifting tests dynamic lifting device, is arranged on horizontal well inside.
Further, horizontal well coiled tubing conveying dynamic logging process pipe string comprises: oil pipe, is arranged in sleeve pipe, and coiled tubing can pass from oil pipe.
Further, horizontal well coiled tubing conveying dynamic logging process pipe string also comprises: the anti-apical organ of disjointed device, packer and oil pipe, the anti-apical organ of disjointed device, oil pipe is connected in turn with packer, and packer is communicated with oil pipe.
Further, horizontal well rod tube conveying dynamic logging process pipe string also comprises: horizontal well test hollow pump, is arranged between packer and oil pipe.
Further, horizontal well is tested dynamic lifting device and is comprised: casing coupling, is arranged on the well head of horizontal well; For the pulley assembly of the coiled tubing that leads, be arranged on casing coupling.
Further, pulley assembly comprises: fixed pulley placed in the middle, is arranged on casing coupling; Leading block, is arranged on casing coupling rotationally, and coiled tubing coordinates to change coiled tubing moving direction by fixed pulley placed in the middle with leading block.
Further, horizontal well is tested dynamic lifting device and is also comprised: fixed pulley gripper shoe placed in the middle, and be arranged on casing coupling, fixed pulley placed in the middle is arranged in fixed pulley gripper shoe placed in the middle rotationally; Leading block gripper shoe, be connected with fixed pulley gripper shoe placed in the middle rotationally, leading block is arranged in leading block gripper shoe rotationally.
Further, horizontal well is tested dynamic lifting device and is also comprised: junction plate, and one end of junction plate is connected rotationally with fixed pulley gripper shoe placed in the middle, and the other end of junction plate is connected rotationally with leading block gripper shoe; Screw mandrel joint, one end of screw mandrel joint is connected rotationally with fixed pulley gripper shoe placed in the middle, and screw mandrel joint is connected with the one end away from fixed pulley placed in the middle in fixed pulley gripper shoe placed in the middle; Screw mandrel, is connected with screw mandrel joint, and leading block gripper shoe is arranged on screw mandrel movably away from one end of leading block.
Operating principle of the present invention and the course of work: consult Fig. 1.When carrying out logging operation, first enter down horizontal well coiled tubing conveying dynamic logging process pipe string, base sealed packer, the anti-apical organ of grappling, tubing string is thrown off from on-off connector, discharge opeing, enter down horizontal well coiled tubing conveying dynamic logging technique roofbolt again, adopt coiled tubing to remove and test.
Beneficial effect of the present invention: adopt horizontal well coiled tubing conveying dynamic logging technique rod tube post, carry out horizontal wellbore logging, realize dynamic logging, adopt coiled tubing to remove, rigidity, good toughness.
Accompanying drawing explanation
When considered in conjunction with the accompanying drawings, by referring to detailed description below, more completely can understand the present invention better and easily learn wherein many adjoint advantages, but accompanying drawing described herein is used to provide a further understanding of the present invention, form a part of the present invention, schematic description and description of the present invention, for explaining the present invention, does not form inappropriate limitation of the present invention, as schemed wherein:
Fig. 1 is structural representation of the present invention;
Fig. 2 is that horizontal well of the present invention tests dynamic lifting device schematic diagram;
Fig. 3 is coiled tubing well head guiding device structural representation of the present invention;
Fig. 4 is coiled tubing well head guiding device working state schematic representation of the present invention.
Below in conjunction with drawings and Examples, the present invention is further described.
Detailed description of the invention
Obviously, the many modifications and variations that those skilled in the art do based on aim of the present invention belong to protection scope of the present invention.
Embodiment 1: as shown in Figure 1, Figure 2, Figure 3, Figure 4,
Horizontal well coiled tubing conveying dynamic logging technique rod tube post, carries dynamic logging process pipe string, horizontal well coiled tubing to carry dynamic logging technique roofbolt to form by horizontal well coiled tubing;
Horizontal well coiled tubing conveying dynamic logging process pipe string, primarily of oil pipe, disjointed device, anti-apical organ, packer, horizontal well test hollow pump, horn mouth composition, the structure connected from bottom to top is: 2 7/ 8in horn mouth, 2 7/ 8the test of in oil pipe, horizontal well hollow pump, Y211-114 packer, anti-apical organ, disjointed device and 2 7/ 8in oil pipe, 2 7/ 8in oil pipe receives well head always;
Horizontal well coiled tubing conveying dynamic logging technique roofbolt, connect to form primarily of coiled tubing, cable head, flexible nipple, downhole instrument centralizer, downhole instrument top connects flexible nipple, cable head, coiled tubing, and downhole instrument two ends are connected to downhole instrument centralizer;
Consult Fig. 1.When carrying out logging operation, first enter down horizontal well coiled tubing conveying dynamic logging process pipe string, base sealed packer, the anti-apical organ of grappling, tubing string is thrown off from on-off connector, discharge opeing:
Set: upper lifting pipe post height 1.3m, slowly transfer tubing string, be pressurized to 6 ~ 8t, base sealed packer.Continue slowly to transfer tubing string, be pressurized to 10t, the anti-apical organ of grappling;
Disconnect: slowly upper lifting pipe post, controls suspending weight 15.5 ~ 16t, reversion oil pipe 20 ~ 24 encloses, and tubing string is thrown off from on-off connector;
Discharge opeing: control stroke≤4.5m, jig frequency 2 ~ 3min -1, discharge liquid millpond and reclaim, after lifting rate meets the demands, start test.
Enter down horizontal well coiled tubing conveying dynamic logging technique roofbolt again, adopt coiled tubing to remove and test.
Embodiment 2:
As shown in Figure 1, a kind of horizontal continuity oil pipe conveying dynamic logging process pipe string, has the first downhole instrument centralizer 1, second downhole instrument centralizer 16, downhole instrument 2, flexible nipple 3, coiled tubing 4, horn mouth 5, oil pipe 6, horizontal well to test hollow pump 7, packer 8, anti-apical organ 9, on-off connector 10 in well head splicing sleeve 11; Horizontal well coiled tubing conveying dynamic logging process pipe string, tubular column structure is from bottom to top: oil pipe horn mouth 5 connected pipes 6, the other end of oil pipe 6 connects horizontal well test hollow pump 7, the other end of horizontal well test hollow pump 7 connects packer 8, the other end of packer 8 connects anti-apical organ 9, and the other end of anti-apical organ 9 connects disjointed device 10, the other end connected pipes 6 of disjointed device 10, oil pipe 6 receives well head always, well head splicing sleeve 11; The other end connecting downhole instrument 2 of the first downhole instrument centralizer 1, the other end of downhole instrument 2 connects the other end connection flexible nipple 3 of the second downhole instrument centralizer 16, second downhole instrument centralizer 16; The other end of flexible nipple 3 connects coiled tubing 4; The other end of coiled tubing 4 is connected to the continuous-tube implement 12 on ground.
As shown in Figure 2, well head splicing sleeve 11, has horn mouth 5, oil pipe 6, packer 8, anti-apical organ 9, on-off connector 10, connecting rod 20 and horizontal well to test hollow pump 7 in sleeve pipe 11;
Horn mouth 5 connected pipes 6, oil pipe 6 connects horizontal well test hollow pump 7, the other end of horizontal well test hollow pump 7 connects packer 8, the other end of packer 8 connects anti-apical organ 9, the other end of anti-apical organ 9 connects connecting rod 20, the other end of connecting rod 20 connects on-off connector 10, the other end connected pipes 6 of on-off connector 10, and the other end of oil pipe 6 connects self-sealing blowout preventer 14;
Sleeve pipe 11 connects self-sealing blowout preventer 14, and self-sealing blowout preventer 14 connects production rig 19.
Horizontal well dynamic logging lifting device, forms primarily of production rig 19, self-sealing blowout preventer 14, oil pipe 6, SCT-62 type on-off connector 10, connecting rod 20, the anti-apical organ 9 of SCF-62 type, Y211-114 type packer 8, SCB-40 type horizontal well test hollow pump 7, horn mouth 5; Oil pipe 6, through self-sealing blowout preventer 14, passes through 2 with SCT-62 type on-off connector 10 7/ 8heavy wall tubing is threaded; SCT-62 type on-off connector 10 is by 2 7/ 8heavy wall tubing screw thread is connected with the anti-apical organ 9 of SCF-62 type; The anti-apical organ 9 of SCF-62 type is by 2 7/ 8heavy wall tubing screw thread is connected with Y211-114 type packer 8; Y211-114 type packer 8 is by 2 7/ 8heavy wall tubing screw thread is tested hollow pump 7 with SCB-40 type horizontal well and is connected; SCB-40 type horizontal well test hollow pump 7 is by 2 7/ 8heavy wall tubing screw thread is connected with oil pipe horn mouth 5; The length of connecting rod 20 is 9.5m, external diameter 48.3mm, internal diameter 40mm, and its two ends are respectively with the pin thread of M48 × 2.5, and the hollow plunger testing hollow pump 7 respectively with the male of SCT-62 type on-off connector 10 and SCB-40 type horizontal well is connected.
Embodiment 3: consult Fig. 2.A kind of horizontal well coiled tubing conveying dynamic logging process pipe string, primarily of production rig, self-sealing blowout preventer, oil pipe, SCT-62 type on-off connector, connecting rod, the anti-apical organ of SCF-62 type, Y211-114 type packer, SCB-40 type horizontal well test hollow pump, horn mouth composition; Oil pipe, through self-sealing blowout preventer, passes through 2 with SCT-62 type on-off connector 7/ 8heavy wall tubing is threaded; SCT-62 type on-off connector is by 2 7/ 8heavy wall tubing screw thread is connected with the anti-apical organ of SCF-62 type; The anti-apical organ of SCF-62 type is by 2 7/ 8heavy wall tubing screw thread is connected with Y211-114 type packer; Y211-114 type packer is by 2 7/ 8heavy wall tubing screw thread is tested hollow pump with SCB-40 type horizontal well and is connected; SCB-40 type horizontal well test hollow pump is by 2 7/ 8heavy wall tubing screw thread is connected with oil pipe horn mouth; The length of connecting rod is 9.5m, external diameter 48.3mm, internal diameter 40mm, and its two ends are respectively with the pin thread of M48 × 2.5, and the hollow plunger testing hollow pump respectively with the male of SCT-62 type on-off connector and SCB-40 type horizontal well is connected.
Embodiment 4: for a coiled tubing well head guiding device, the present invention is described in further detail.
Consult Fig. 3.Coiled tubing well head guiding device of the present invention, forms primarily of casing coupling 1301, fixed pulley gripper shoe 1303 placed in the middle, fixed pulley 1304 placed in the middle, fixed pulley axis 1305, junction plate 1306, leading block 1307, leading block axle 1308, pivot pin 1309, leading block gripper shoe 1310, nut 1311, screw mandrel 1312 and bearing pin 1314 placed in the middle.
Casing coupling 1301 is cylindrical shape, and the outer wall of casing coupling 1301 is welded with two parallel fixed pulley gripper shoes 1303 rectangular placed in the middle, and the length of fixed pulley gripper shoe 1303 placed in the middle is 400mm, width 70mm.The centerline parallel of fixed pulley gripper shoe 1303 placed in the middle and casing coupling 1301.Be connected with a fixed pulley 1304 placed in the middle in the upper end of two fixed pulley gripper shoes 1303 placed in the middle by fixed pulley axis 1305 placed in the middle, fixed pulley 1304 placed in the middle is in the centre of two fixed pulley gripper shoes 1303 placed in the middle.The diameter of fixed pulley 1304 placed in the middle is 150mm.A screw mandrel joint 1313 is connected with by bearing pin 1314 in the bottom of two fixed pulley gripper shoes 1303 placed in the middle, screw mandrel joint 1313 cross section is square, the pin shaft hole of a transverse direction is had in one end of screw mandrel joint 1313, have pin hole in the bottom of two fixed pulley gripper shoes 1303 placed in the middle, bearing pin 1314 passes pin shaft hole and two fixed pulley gripper shoe 1303 pin holes placed in the middle of screw mandrel joint 1313.Have center screw at the other end of screw mandrel joint 1313, screw mandrel joint 1313 other end center screw internal fixtion has the screw mandrel 1312 of a M20, and the center line of screw mandrel joint 1313 and the center line of screw mandrel 1312 are on same straight line.Screw mandrel 1312 there is the nut 1311 of a M20.Cover has a sliding sleeve in the bottom of nut 1311 and on screw mandrel 1312, sliding sleeve outer wall is symmetrically welded with two to ship and resell on another market, the bottom of two leading block gripper shoes 1310 has a hole of shipping and reselling on another market respectively, ships and resell on another market for two and inserts the shipping and reselling on another market in hole of two leading block gripper shoe 1310 bottoms respectively.
Two leading block gripper shoes 1310 are rectangular flat board, and the length of leading block gripper shoe 1310 is 1000mm, width 100mm.There is pin hole the upper end of two leading block gripper shoes 1310 respectively, a leading block axle 1308 is had in the pin hole of two leading block gripper shoe 1310 upper ends, leading block axle 1308 is connected with leading block 1307, leading block 1307 is in the middle of two leading block gripper shoes 1310.Have pin hole at the middle part of two leading block gripper shoes 1310, the pin hole at the middle part of leading block gripper shoe 1310 to leading block gripper shoe 1310 upper end pin hole between distance be 450mm.Pivot pin 1309 is had in pin hole in the middle part of two leading block gripper shoes 1310, pivot pin 1309 is through the pin hole of the pin hole in the middle part of two leading block gripper shoes 1310 and junction plate 1306 one end, and junction plate 1306 is connected to the middle part of two leading block gripper shoes 1310 by pivot pin 1309.
Have pin shaft hole in the middle part of fixed pulley gripper shoe 1303 placed in the middle, be installed with bearing pin in the pin shaft hole of fixed pulley gripper shoe 1303 placed in the middle, the other end of junction plate 1306 is connected to the two ends of bearing pin.The length of junction plate 1306 is 350mm.
Embodiment 5:
A technique rod tube post for horizontal well coiled tubing conveying dynamic logging,
Horizontal well coiled tubing conveying dynamic logging technique rod tube post, is tested dynamic lifting device formed by horizontal well coiled tubing conveying dynamic logging process pipe string, horizontal well coiled tubing conveying dynamic logging technique roofbolt, horizontal well,
Horizontal well coiled tubing conveying dynamic logging process pipe string, primarily of oil pipe, disjointed device, anti-apical organ, packer, horizontal well test hollow pump, horn mouth composition, syndeton is from bottom to top: horn mouth, oil pipe, horizontal well test hollow pump, packer, anti-apical organ, disjointed device are connected successively with oil pipe, and oil pipe receives well head always;
Horizontal well coiled tubing conveying dynamic logging technique roofbolt, primarily of compositions such as coiled tubing, cable head, flexible nipple, downhole instrument centralizers, downhole instrument top connects flexible nipple, cable head, coiled tubing, and downhole instrument two ends are connected to downhole instrument centralizer;
Operating principle of the present invention and the course of work: consult Fig. 1.When carrying out logging operation, first enter down horizontal well coiled tubing conveying dynamic logging process pipe string, base sealed packer, the anti-apical organ of grappling, tubing string is thrown off from on-off connector, discharge opeing, enter down horizontal well coiled tubing conveying dynamic logging technique roofbolt again, adopt coiled tubing to remove and test.
Coiled tubing well head guiding device, forms primarily of casing coupling 1301, fixed pulley gripper shoe 1303 placed in the middle, fixed pulley 1304 placed in the middle, fixed pulley axis 1305, junction plate 1306, leading block 1307, leading block axle 1308, pivot pin 1309, leading block gripper shoe 1310, nut 1311, screw mandrel 1312 and bearing pin 1314 placed in the middle.It is characterized in that: casing coupling 1301 is cylindrical shape, the tubing coupling that casing coupling 1301 can be enclosed within well head during well logging is used for fixing guiding device.The outer wall of casing coupling 1301 is welded with two parallel fixed pulley gripper shoes 1303 rectangular placed in the middle, the centerline parallel of fixed pulley gripper shoe 1303 placed in the middle and casing coupling 1301; Be connected with a fixed pulley 1304 placed in the middle in the upper end of two fixed pulley gripper shoes 1303 placed in the middle by fixed pulley axis 1305 placed in the middle, fixed pulley 1304 placed in the middle is in the centre of two fixed pulley gripper shoes 1303 placed in the middle; A screw mandrel joint 1313 is connected with by bearing pin 1314 in the bottom of two fixed pulley gripper shoes 1303 placed in the middle, screw mandrel joint 1313 cross section is circular or square, pin shaft hole is had in one end of screw mandrel joint 1313, have pin hole in the bottom of two fixed pulley gripper shoes 1303 placed in the middle, bearing pin 1314 passes pin shaft hole and two fixed pulley gripper shoe 1303 pin holes placed in the middle of screw mandrel joint 1313; Screw mandrel joint 1313 can rotate along pivot pin 1314; Have center screw at the other end of screw mandrel joint 1313, screw mandrel joint 1313 other end center screw internal fixtion has screw mandrel 1312, and the center line of screw mandrel joint 1313 and the center line of screw mandrel 1312 are on same straight line; Screw mandrel 1312 there is nut 1311; Cover has a sliding sleeve in the bottom of nut 1311 and on screw mandrel 1312, sliding sleeve outer wall is symmetrically welded with two to ship and resell on another market, shipping and reselling on another market hole in the bottom of two leading block gripper shoes 1310, ships and resell on another market for two and insert the shipping and reselling on another market in hole of two leading block gripper shoe 1310 bottoms respectively.
Two leading block gripper shoes 1310 are rectangular flat board; There is pin hole the upper end of two leading block gripper shoes 1310 respectively, a leading block axle 1308 is had in the pin hole of two leading block gripper shoe 1310 upper ends, leading block axle 1308 is connected with leading block 1307, leading block 1307 is in the middle of two leading block gripper shoes 1310;
Pin hole is had at the middle part of two leading block gripper shoes 1310, pivot pin 1309 is had in pin hole in the middle part of two leading block gripper shoes 1310, pivot pin 1309 is through the pin hole of the pin hole in the middle part of two leading block gripper shoes 1310 and junction plate 1306 one end, and junction plate 1306 is connected to the middle part of two leading block gripper shoes 1310 by pivot pin 1309; Have pin shaft hole in the middle part of fixed pulley gripper shoe 1303 placed in the middle, be installed with bearing pin in the pin shaft hole of fixed pulley gripper shoe 1303 placed in the middle, the other end of junction plate 1306 is connected to the two ends of bearing pin.
The operating principle of coiled tubing well head guiding device and the course of work: consult Fig. 3.Before lower coiled tubing 1302, first casing coupling 1301 is enclosed within the tubing coupling of well head.Then coiled tubing 1302 is middle through two leading block gripper shoes 1310.Now nut 1311 is at the far-end of screw mandrel 1312.Consult Fig. 4.First leading block 1307 is unloaded, the hole slot that coiled tubing 1302 has through leading block gripper shoe 1310 one end, install leading block 1307 and rotary screw rod 1312, leading block 1307 is moved inward, after making to there is certain distance between coiled tubing 1302 and working rig travelling block, coiled tubing 1302 can be transferred.When the lower coiled tubing 1302 of needs, rotating nut 1311, makes nut 1311 rotate to screw mandrel 1312 one end near screw mandrel joint 1313.Due to fixed pulley gripper shoe 1303 placed in the middle, junction plate 1306, between leading block gripper shoe 1310 and screw mandrel joint 1313, form a quadrangle, make leading block gripper shoe 1310 parallel with fixed pulley gripper shoe 1303 placed in the middle, leading block gripper shoe 1310 drives leading block 1307 away from the top of casing coupling above well head 1301.Now coiled tubing 1302 leaves above well head at the draught line of leading block 1307.After under operation, coiled tubing 1302 starts, coiled tubing 1302 can be avoided working rig travelling block and avoid coiled tubing 1302 and the friction of working rig travelling block, prevents coiled tubing 1302 from wearing and tearing.Then, coiled tubing 1302 enters in well head through the guiding of fixed pulley 1304 placed in the middle, make coiled tubing 1302 can not with wellhead casing pipe or oil pipe friction, decrease the wearing and tearing of cable.
Horizontal well tests dynamic lifting device, and be made up of production rig, self-sealing blowout preventer, oil pipe, on-off connector, connecting rod, anti-apical organ, packer, horizontal well test hollow pump, horn mouth, oil pipe, through self-sealing blowout preventer, passes through 2 with on-off connector 7/ 8heavy wall tubing is threaded; On-off connector is by 2 7/ 8heavy wall tubing screw thread is connected with anti-apical organ; Anti-apical organ is by 2 7/ 8heavy wall tubing screw thread is connected with packer; Packer is by 2 7/ 8heavy wall tubing screw thread and horizontal well are tested hollow pump and are connected; Horizontal well test hollow pump is by 2 7/ 8heavy wall tubing screw thread is connected with oil pipe horn mouth; The length of connecting rod is 9.5m, external diameter 48.3mm, internal diameter 40mm, and its two ends are respectively with the pin thread of M48 × 2.5, and the hollow plunger testing hollow pump respectively with the male of on-off connector and horizontal well is connected.
Horizontal well tests operating principle and the course of work of dynamic lifting device: in horizontal well test lifting, enter down oil pipe horn mouth, oil pipe, horizontal well test hollow pump, packer, anti-apical organ successively, under enter connecting rod and be connected with the plunger that horizontal well tests hollow pump, connecting rod is connected with oil manifold uncoupling machine male through oil manifold uncoupling machine female, then oil manifold uncoupling machine male is connected with mistake oil manifold uncoupling machine female.Oil manifold uncoupling machine male top connected pipes, until well head; At well head place, self-sealing blowout preventer is installed.
Enter after below horizontal well producing fluid level under horizontal well test hollow pump, set packer, transfer tubing string pressurization, the anti-apical organ of grappling, reversion oil pipe, oil manifold uncoupling machine male is separated with oil manifold uncoupling machine female, and ground working rig handling oil pipe can drive the plunger reciprocates of oil manifold uncoupling machine male and connecting rod and horizontal well test hollow pump, and the down-hole liquid of lifting discharges well head by oil sets annular space.Hollow plunger in oil pipe, connecting rod, horizontal well test hollow pump provides test channel for tester.
Horizontal well tests the beneficial effect of dynamic lifting device: lifting discharge opeing is reliable and stable, and test channel is smooth and easy.
Embodiment 6:
For the lifting device of a horizontal well dynamic logging, the present invention is described in further detail.
This real invention horizontal well dynamic logging lifting device is primarily of production rig, self-sealing blowout preventer, oil pipe, SCT-62 type oil manifold uncoupling machine, connecting rod, the anti-apical organ of SCF-62 type, Y211-114 type packer, the hollow test pump of SCB-40 type horizontal well, horn mouth composition; Oil pipe, through self-sealing blowout preventer, passes through 2 with SCT-62 type oil manifold uncoupling machine 7/ 8heavy wall tubing is threaded; SCT-62 type oil manifold uncoupling machine is by 2 7/ 8heavy wall tubing screw thread is connected with the anti-apical organ of SCF-62 type; The central passage of the anti-apical organ of SCF-62 type is 62 millimeters; The anti-apical organ of SCF-62 type is by 2 7/ 8heavy wall tubing screw thread is connected with Y211-114 type packer; The central tube of Y211-114 type packer is 62 millimeters; Y211-114 type packer is by 2 7/ 8heavy wall tubing screw thread is connected with the hollow test pump of SCB-40 type horizontal well; The pump barrel of the hollow test pump of SCB-40 type horizontal well is a steel pipe, and length is 8 meters, and external diameter is 110 millimeters; SCB-40 type horizontal well hollow test pump plunger external diameter is 90 millimeters; The hollow test pump of SCB-40 type horizontal well is by 2 7/ 8heavy wall tubing screw thread is connected with oil pipe horn mouth; The length of connecting rod is 9.5 meters, external diameter 48.3 millimeters, internal diameter 40 millimeters, and its two ends, respectively with the pin thread of rice 48 × 2.5, are connected with the male of SCT-62 type oil manifold uncoupling machine and the hollow plunger of the hollow test pump of SCB-40 type horizontal well respectively.
Embodiment 7:
Horizontal well dynamic logging lifting method embodiment.
1) go into the well: connected pipes horn mouth, oil pipe, SCB-40 type horizontal well hollow test pump, Y211-114 type packer, the anti-apical organ of SCF-62 type, SCT-62 type oil manifold uncoupling machine combine process pipe string, under lower going-into-well successively.
3) well head is installed: install self-sealing blowout preventer at well head, because self-sealing blowout preventer can select Multiple Type, and the method is routine techniques for underground work art, is not described in detail in this.
2) set.After entering lower 200 meters ~ 500 meters of producing fluid level under SCB-40 type horizontal well hollow test pump, upper lifting pipe post height 1.3 meters, slowly transfers tubing string, is pressurized to 6 ~ 8 tons, setting Y211-114 type packer; Continue slowly to transfer tubing string, be pressurized to 10 tons, the anti-apical organ of grappling SCF-62 type.
3) disconnect: slowly upper lifting pipe post, controlling suspending weight is the above tubing weight of Y211-114 type packer, and reversion oil pipe 12 ~ 14 encloses, and tubing string is thrown off from SCT-62 type oil manifold uncoupling machine.
4) lifting: control stroke 3 meters ~ 5 meters, jig frequency 2 ~ 3min -1.Discharge liquid millpond to reclaim.
5) trip out: slowly transfer tubing string and pressurize 0.5 ton, rotate forward oil pipe 16 and enclose, slow upper lifting pipe post.Confirm that docking completes and after Y211-114 type removing seal for packer, trips out the various instrument in down-hole successively.
As mentioned above, embodiments of the invention are explained, but as long as do not depart from inventive point of the present invention in fact and effect can have a lot of distortion, this will be readily apparent to persons skilled in the art.Therefore, such variation is also all included within protection scope of the present invention.

Claims (11)

1. a horizontal well coiled tubing conveying dynamic logging technique rod tube post, is characterized in that:
Horizontal well coiled tubing conveying dynamic logging technique rod tube post, is tested dynamic lifting device formed by horizontal well coiled tubing conveying dynamic logging process pipe string, horizontal well coiled tubing conveying dynamic logging technique roofbolt, horizontal well,
Horizontal well coiled tubing conveying dynamic logging process pipe string, primarily of oil pipe, disjointed device, anti-apical organ, packer, horizontal well test hollow pump, horn mouth composition, syndeton is from bottom to top: horn mouth, oil pipe, horizontal well test hollow pump, packer, anti-apical organ, disjointed device are connected successively with oil pipe, and oil pipe receives well head always;
Horizontal well coiled tubing conveying dynamic logging technique roofbolt, primarily of compositions such as coiled tubing, cable head, flexible nipple, downhole instrument centralizers, downhole instrument top connects flexible nipple, cable head, coiled tubing, and downhole instrument two ends are connected to downhole instrument centralizer;
Horizontal well tests dynamic lifting device, and be made up of production rig, self-sealing blowout preventer, oil pipe, on-off connector, connecting rod, anti-apical organ, packer, horizontal well test hollow pump, horn mouth, oil pipe, through self-sealing blowout preventer, passes through 2 with on-off connector 7/ 8heavy wall tubing is threaded; On-off connector is by 2 7/ 8heavy wall tubing screw thread is connected with anti-apical organ; Anti-apical organ is by 2 7/ 8heavy wall tubing screw thread is connected with packer; Packer is by 2 7/ 8heavy wall tubing screw thread and horizontal well are tested hollow pump and are connected; Horizontal well test hollow pump is by 2 7/ 8heavy wall tubing screw thread is connected with oil pipe horn mouth; The length of connecting rod is 9.5m, external diameter 48.3mm, internal diameter 40mm, and its two ends are respectively with the pin thread of M48 × 2.5, and the hollow plunger testing hollow pump respectively with the male of on-off connector and horizontal well is connected.
2. the logging technique rod tube post of a kind of horizontal well coiled tubing conveying dynamic logging according to claim 1, it is characterized in that coiled tubing well head guiding device, primarily of casing coupling, fixed pulley gripper shoe placed in the middle, fixed pulley placed in the middle, fixed pulley axis, junction plate, leading block, leading block axle, pivot pin, leading block gripper shoe, nut, screw mandrel and bearing pin composition placed in the middle; Casing coupling is cylindrical shape, the outer wall of casing coupling is welded with two parallel fixed pulley gripper shoes rectangular placed in the middle, the centerline parallel of fixed pulley gripper shoe placed in the middle and casing coupling; Be connected with a fixed pulley placed in the middle in the upper end of two fixed pulley gripper shoes placed in the middle by fixed pulley axis placed in the middle, fixed pulley placed in the middle is in the centre of two fixed pulley gripper shoes placed in the middle; A screw mandrel joint is had by pinned connection in the bottom of two fixed pulley gripper shoes placed in the middle, screw mandrel joint cross section is circular or square, pin shaft hole is had in one end of screw mandrel joint, have pin hole in the bottom of two fixed pulley gripper shoes placed in the middle, bearing pin passes pin shaft hole and two fixed pulley gripper shoe pin holes placed in the middle of screw mandrel joint; Have center screw at the other end of screw mandrel joint, screw mandrel joint other end center screw internal fixtion has screw mandrel, and the center line of screw mandrel joint and the center line of screw mandrel are on same straight line; Screw mandrel there is nut; Cover has a sliding sleeve in the bottom of nut and on screw mandrel, sliding sleeve outer wall is symmetrically welded with two and ships and resell on another market, and ships and resell on another market hole in the bottom of two leading block gripper shoes, two ship and resell on another market insert two leading block gripper shoe bottoms respectively ship and resell on another market in hole;
Two leading block gripper shoes are rectangular flat board; There is pin hole the upper end of two leading block gripper shoes respectively, and in the pin hole of two leading block gripper shoe upper ends, have a leading block axle, leading block axle is connected with leading block, leading block is in the middle of two leading block gripper shoes;
Pin hole is had at the middle part of two leading block gripper shoes, pivot pin is had in pin hole in the middle part of two leading block gripper shoes, pivot pin is through the pin hole of the pin hole in the middle part of two leading block gripper shoes and junction plate one end, and junction plate is connected to the middle part of two leading block gripper shoes by pivot pin; Have pin shaft hole in the middle part of fixed pulley gripper shoe placed in the middle, be installed with bearing pin in the pin shaft hole of fixed pulley gripper shoe placed in the middle, the other end of junction plate is connected to the two ends of bearing pin.
3. the logging method of a kind of horizontal well coiled tubing conveying well measuring technique rod tube post according to claim 1 and 2, is characterized in that containing following steps;
The leading block of coiled tubing well head guiding device is unloaded, the hole slot that coiled tubing has through leading block gripper shoe one end, install leading block and rotary screw rod, leading block is moved inward, after making to there is certain distance between coiled tubing and working rig travelling block, coiled tubing can be transferred; When the lower coiled tubing of needs, rotating nut, makes nut rotate to screw mandrel one end near screw mandrel joint; Due to fixed pulley gripper shoe placed in the middle, junction plate, between leading block gripper shoe and screw mandrel joint, form a quadrangle, make leading block gripper shoe parallel with fixed pulley gripper shoe placed in the middle, leading block gripper shoe drives leading block away from the top of casing coupling above well head; Now coiled tubing leaves above well head at the draught line of leading block; After under operation, coiled tubing starts, coiled tubing can avoid the friction that working rig travelling block avoids coiled tubing and working rig travelling block, prevents coiled tubing from wearing and tearing; Then, coiled tubing enters in well head through the guiding of fixed pulley placed in the middle, make coiled tubing can not with wellhead casing pipe or oil pipe friction, decrease the wearing and tearing of cable.
4. a horizontal well coiled tubing conveying dynamic logging technique rod tube post, be arranged in horizontal well, described horizontal well has sleeve pipe (11), it is characterized in that, described horizontal well coiled tubing conveying dynamic logging technique rod tube post comprises:
Horizontal well coiled tubing conveying dynamic logging process pipe string, is arranged in described sleeve pipe (11);
Horizontal well coiled tubing conveying dynamic logging technique roofbolt, described horizontal well coiled tubing conveying dynamic logging technique roofbolt is arranged in described sleeve pipe (11) through described horizontal well coiled tubing conveying dynamic logging process pipe string, described horizontal well coiled tubing conveying dynamic logging technique roofbolt comprises downhole instrument (2), cable head and coiled tubing (4), described coiled tubing (4) is connected with described downhole instrument (2), described cable head is electrically connected with described downhole instrument (2) through described coiled tubing (4), described cable head is used for being connected with the cable of described horizontal well outside,
Horizontal well for lifting tests dynamic lifting device, is arranged on described horizontal well inner.
5. horizontal well coiled tubing conveying dynamic logging technique rod tube post according to claim 4, it is characterized in that, described horizontal well coiled tubing conveying dynamic logging process pipe string comprises:
Oil pipe (6), is arranged in described sleeve pipe (11), and described coiled tubing (4) can pass from described oil pipe (6).
6. horizontal well coiled tubing conveying dynamic logging technique rod tube post according to claim 5, it is characterized in that, described horizontal well coiled tubing conveying dynamic logging process pipe string also comprises:
Disjointed device (10), packer (8) and the anti-apical organ of oil pipe (9), described disjointed device (10), the anti-apical organ of oil pipe (9) are connected in turn with packer (8), and described packer (8) is communicated with described oil pipe (6).
7. horizontal well coiled tubing conveying dynamic logging technique rod tube post according to claim 6, it is characterized in that, described horizontal well rod tube conveying dynamic logging process pipe string also comprises:
Horizontal well test hollow pump (7), is arranged between described packer (8) and described oil pipe (6).
8. horizontal well coiled tubing conveying dynamic logging technique rod tube post according to claim 4, it is characterized in that, described horizontal well is tested dynamic lifting device and is comprised:
Casing coupling (1301), is arranged on the well head of described horizontal well;
For the pulley assembly of described coiled tubing (4) of leading, be arranged on described casing coupling (1301).
9. horizontal well coiled tubing conveying dynamic logging technique rod tube post according to claim 8, it is characterized in that, described pulley assembly comprises:
Fixed pulley placed in the middle (1304), is arranged on described casing coupling (1301);
Leading block (1307), be arranged on described casing coupling (1301) rotationally, described coiled tubing (4) coordinates to change described coiled tubing (4) moving direction with described leading block (1307) by described fixed pulley placed in the middle (1304).
10. horizontal well coiled tubing conveying dynamic logging technique rod tube post according to claim 9, it is characterized in that, described horizontal well is tested dynamic lifting device and is also comprised:
Fixed pulley gripper shoe (1303) placed in the middle, is arranged on described casing coupling (1301), and described fixed pulley placed in the middle (1304) is arranged on described fixed pulley gripper shoe (1303) placed in the middle rotationally;
Leading block gripper shoe (1310), be connected with described fixed pulley gripper shoe (1303) placed in the middle rotationally, described leading block (1307) is arranged on described leading block gripper shoe (1310) rotationally.
11. horizontal well coiled tubing conveying dynamic logging technique rod tube posts according to claim 10, it is characterized in that, described horizontal well is tested dynamic lifting device and is also comprised:
Junction plate (1306), one end of described junction plate (1306) is connected rotationally with described fixed pulley gripper shoe (1303) placed in the middle, and the other end of described junction plate (1306) is connected rotationally with described leading block gripper shoe (1310);
Screw mandrel joint (1313), one end of described screw mandrel joint (1313) is connected rotationally with described fixed pulley gripper shoe (1303) placed in the middle, and described screw mandrel joint (1313) is connected with the one end away from described fixed pulley placed in the middle (1304) on described fixed pulley gripper shoe (1303) placed in the middle;
Screw mandrel (1312), be connected with described screw mandrel joint (1313), the one end away from described leading block (1307) on described leading block gripper shoe (1310) is arranged on described screw mandrel (1312) movably.
CN201510227830.2A 2014-05-14 2015-05-06 Rod tubular column for horizontal-well coiled tubing transportation dynamic logging process Pending CN105089655A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510227830.2A CN105089655A (en) 2014-05-14 2015-05-06 Rod tubular column for horizontal-well coiled tubing transportation dynamic logging process

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201410203948 2014-05-14
CN201510227830.2A CN105089655A (en) 2014-05-14 2015-05-06 Rod tubular column for horizontal-well coiled tubing transportation dynamic logging process

Publications (1)

Publication Number Publication Date
CN105089655A true CN105089655A (en) 2015-11-25

Family

ID=54570886

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510227830.2A Pending CN105089655A (en) 2014-05-14 2015-05-06 Rod tubular column for horizontal-well coiled tubing transportation dynamic logging process

Country Status (1)

Country Link
CN (1) CN105089655A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089624A (en) * 2014-05-14 2015-11-25 中国石油天然气股份有限公司 Horizontal-well coiled tubing conveying dynamic logging method
CN107780850A (en) * 2016-08-31 2018-03-09 中国石油天然气股份有限公司 A kind of method of cable built in coiled tubing

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4700778A (en) * 1986-07-24 1987-10-20 Halliburton Company Wet connector for use with drill pipe conveyed logging apparatus
EP0313374A1 (en) * 1987-10-23 1989-04-26 Halliburton Company Well-logging method using a drill pipe conveyed logging system
WO2000060212A1 (en) * 1999-04-01 2000-10-12 Baker Hughes Incorporated Pipe conveyed logging system and method
CN201144690Y (en) * 2007-11-27 2008-11-05 中国石油天然气集团公司 Casing horizontal well logging device
CN101377127A (en) * 2008-09-26 2009-03-04 大庆油田有限责任公司 Method for testing horizontal well oil conduit transportation under pumping state
CN101382069A (en) * 2007-09-04 2009-03-11 中国石油天然气集团公司 Continuous tube horizontal borehole process and device
US20090194271A1 (en) * 2007-02-27 2009-08-06 Harold Steven Bissonnette Carrier Assembly for a Pipe Conveyed Well Logging Assembly
CN102953725A (en) * 2012-11-16 2013-03-06 中国石油天然气股份有限公司 Horizontal well logging dynamic lifting device
CN102953724A (en) * 2012-11-16 2013-03-06 中国石油天然气股份有限公司 Horizontal well logging anti-lift unlocking device
CN102953702A (en) * 2012-11-16 2013-03-06 中国石油天然气股份有限公司 Horizontal well logging hanging unlocking device
CN202953764U (en) * 2012-11-16 2013-05-29 中国石油天然气股份有限公司 Horizontal well logging well mouth guide device
CN103470245A (en) * 2013-08-29 2013-12-25 辽河石油勘探局 Production test system for mechanized horizontal well coiled tubing
CN204804836U (en) * 2014-05-14 2015-11-25 中国石油天然气股份有限公司 Horizontal well coiled tubing carries dynamic logging technology pole tubular column
CN105089624A (en) * 2014-05-14 2015-11-25 中国石油天然气股份有限公司 Horizontal-well coiled tubing conveying dynamic logging method

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4700778A (en) * 1986-07-24 1987-10-20 Halliburton Company Wet connector for use with drill pipe conveyed logging apparatus
EP0313374A1 (en) * 1987-10-23 1989-04-26 Halliburton Company Well-logging method using a drill pipe conveyed logging system
WO2000060212A1 (en) * 1999-04-01 2000-10-12 Baker Hughes Incorporated Pipe conveyed logging system and method
US20090194271A1 (en) * 2007-02-27 2009-08-06 Harold Steven Bissonnette Carrier Assembly for a Pipe Conveyed Well Logging Assembly
CN101382069A (en) * 2007-09-04 2009-03-11 中国石油天然气集团公司 Continuous tube horizontal borehole process and device
CN201144690Y (en) * 2007-11-27 2008-11-05 中国石油天然气集团公司 Casing horizontal well logging device
CN101377127A (en) * 2008-09-26 2009-03-04 大庆油田有限责任公司 Method for testing horizontal well oil conduit transportation under pumping state
CN102953725A (en) * 2012-11-16 2013-03-06 中国石油天然气股份有限公司 Horizontal well logging dynamic lifting device
CN102953724A (en) * 2012-11-16 2013-03-06 中国石油天然气股份有限公司 Horizontal well logging anti-lift unlocking device
CN102953702A (en) * 2012-11-16 2013-03-06 中国石油天然气股份有限公司 Horizontal well logging hanging unlocking device
CN202953764U (en) * 2012-11-16 2013-05-29 中国石油天然气股份有限公司 Horizontal well logging well mouth guide device
CN103470245A (en) * 2013-08-29 2013-12-25 辽河石油勘探局 Production test system for mechanized horizontal well coiled tubing
CN204804836U (en) * 2014-05-14 2015-11-25 中国石油天然气股份有限公司 Horizontal well coiled tubing carries dynamic logging technology pole tubular column
CN105089624A (en) * 2014-05-14 2015-11-25 中国石油天然气股份有限公司 Horizontal-well coiled tubing conveying dynamic logging method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089624A (en) * 2014-05-14 2015-11-25 中国石油天然气股份有限公司 Horizontal-well coiled tubing conveying dynamic logging method
CN107780850A (en) * 2016-08-31 2018-03-09 中国石油天然气股份有限公司 A kind of method of cable built in coiled tubing
CN107780850B (en) * 2016-08-31 2019-03-15 中国石油天然气股份有限公司 A kind of method of cable built in coiled tubing

Similar Documents

Publication Publication Date Title
CN105134165A (en) Method for dynamic logging with conveying by horizontal well tractor
CN103075143B (en) Method for testing fluid-producing section of horizontal pump well
CN105089624A (en) Horizontal-well coiled tubing conveying dynamic logging method
CN102296950B (en) Hydraulic shearing type sampling drilling tool
CN105089629A (en) Horizontal well rod conveying well-logging method
CN105089552A (en) Fully intelligent well completion method of oil (gas) field production well
CN204804820U (en) Dynamic logging technology pole tubular column is carried to horizontal well pole pipe
CN204804836U (en) Horizontal well coiled tubing carries dynamic logging technology pole tubular column
CN105089625A (en) Horizontal well rod pipe conveying dynamic logging method
CN204804819U (en) Dynamic logging technology pole tubular column is carried to horizontal well pole
CN105089655A (en) Rod tubular column for horizontal-well coiled tubing transportation dynamic logging process
CN105089628A (en) Horizontal well tractor conveying dynamic well logging process rod and pipe column
CN204804822U (en) Dynamic logging technology pole tubular column is carried to horizontal well tractor
US20120031627A1 (en) Control Line Installation Unit
CN105089631A (en) Horizontal well rod conveying dynamic logging method
CN205977150U (en) Punching cable logging carries technology tubular column in horizontal well coiled tubing
CN104514703A (en) Nonmetal pipe submersible screw pump oil extraction device
CN203223249U (en) Deep well slurry full-pipe gravity-flow mobile pumped filling system
RU115821U1 (en) TECHNOLOGICAL COMPLEX FOR RECOVERY OF THE OPERATIONAL CONDITION OF OIL AND GAS PRODUCING WELL WITH A HORIZONTAL AND / OR SUBORGORIZONTAL END IN THE OPERATION PROCESS
CN114856495B (en) Underground device for testing gas water production profile of coal bed gas combined well
CN105089627A (en) Horizontal well rod and pipe conveying dynamic well logging process rod and pipe column
CN203516030U (en) Non-metallic pipe oil-submersible screw pump oil production plant
CN105089630B (en) Horizontal well bar conveys dynamic logging technique rod tube column and application method
CN109826597B (en) Vertical well fixed face hydraulic perforation fracturing device and method
CN105089626A (en) Horizontal well rod and pipe conveying well logging method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20151125