CN105064419A - 海上大直径钢管桩极限抗拔承载力的估算方法 - Google Patents

海上大直径钢管桩极限抗拔承载力的估算方法 Download PDF

Info

Publication number
CN105064419A
CN105064419A CN201510470586.2A CN201510470586A CN105064419A CN 105064419 A CN105064419 A CN 105064419A CN 201510470586 A CN201510470586 A CN 201510470586A CN 105064419 A CN105064419 A CN 105064419A
Authority
CN
China
Prior art keywords
centerdot
stake
pile
steel pipe
diameter steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510470586.2A
Other languages
English (en)
Inventor
狄圣杰
汪明元
潘登
侯靖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201510470586.2A priority Critical patent/CN105064419A/zh
Publication of CN105064419A publication Critical patent/CN105064419A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明涉及一种海上大直径钢管桩极限抗拔承载力的估算方法。本发明的目的是提出一种海上大直径钢管桩极限抗拔承载力的估算方法,该方法在考虑桩基自重和外侧摩阻力影响的同时,还将同时考虑土芯有效自重和内侧摩阻力的影响,以此作为海上大直径钢管桩极限抗拔承载力的简化计算方法。本发明的技术方案是:海上大直径钢管桩极限抗拔承载力的估算方法,该估算方法考虑了大直径钢管桩内具有与地层相对应的桩内土芯,在上拨荷载的作用下,大直径钢管桩在顶层土、第i层土及持力层分别产生桩外极限侧摩阻力、在桩内土芯分别产生的桩内极限侧摩阻力或者是桩内土芯有效自重、以及上部结构和基桩自重,则计算公式如下:桩基极限抗拨承载力Tk=Tk1+Tk2

Description

海上大直径钢管桩极限抗拔承载力的估算方法
技术领域
本发明涉及一种海上大直径钢管桩极限抗拔承载力的估算方法。适用于近海海洋工程、水利工程、港口通航工程等涉海项目中桩径大于1.5m的大直径钢管桩抗拨承载力的估算。
背景技术
我国已制定建设海洋强国的基本国策,目前涉海工程中如港口码头、钻采平台、跨海大桥、高压输电线塔、海上风电场、海上潮汐潮流电站等建设工程大量应用大直径钢管桩,其具备较高的承载能力、较强的抗弯能力及相对适宜海上作业的施工工艺等优势。海上构筑物除承受竖向荷载、水平向荷载外,同时某些工况还承受竖向的上拔荷载,其竖向抗拔承载力对桩径大小、埋深及工程材料用量起到至关重要的影响。海上钢管桩桩基直径较大,一般大于1.5m,甚至达到6~7m。如此之大的桩径,其极限抗压和抗拔设计与传统管桩有本质力学性能和荷载传递的区别。如《建筑桩基技术规范》与《港口工程桩基规范》中对极限抗拔承载力的计算均是以各层土的极限外侧摩阻力乘以抗拔系数后求和,再加上桩与桩内土的有效自重而得,上述方法显然未考虑大直径桩基形成的内部土芯的侧摩阻力大小,即内极限侧摩阻力影响,与海上试桩成果相差甚远,同时内极限侧摩阻力与土芯有效自重如何区别对待,何种情况下分别考虑内极限侧摩阻力和土芯有效自重,也是值得关注并急需解决的问题。
发明内容
本发明要解决的技术问题是:鉴于上述分析,在基于大量的海上大直径钢管桩试桩实测分析资料的基础上,提出一种海上大直径钢管桩极限抗拔承载力的估算方法,该方法在考虑桩基自重和外侧摩阻力影响的同时,还将同时考虑土芯有效自重和内侧摩阻力的影响,以此作为海上大直径钢管桩极限抗拔承载力的简化计算方法。
本发明所采用的技术方案是:海上大直径钢管桩极限抗拔承载力的估算方法,其特征在于:该估算方法考虑了大直径钢管桩内具有与地层相对应的桩内土芯,在上拨荷载的作用下,大直径钢管桩在顶层土、第i层土及持力层分别产生桩外极限侧摩阻力、在桩内土芯分别产生的桩内极限侧摩阻力或者是桩内土芯有效自重、以及上部结构和基桩自重,则计算公式如下,
桩基极限抗拨承载力Tk=Tk1+Tk2
Tk1为按常规方法只考虑上部结构和基桩自重和桩外极限侧摩阻力,表达式为:
T k 1 = G 0 + π D · ( q s k 1 w · H 1 · λ ] + q s k i w · H i · λ i + q s k n w · H n · λ n ) = G 0 + π D · Σ i = 1 n q s k i w · H i · λ i ;
Tk2为桩内极限侧摩阻力与桩内土芯有效自重的较小值,表达式为:
T k 2 = π d · ( q s 1 k n · h 1 · λ 1 + q s i k n · h i · λ i + q s n k n · h n · λ n , G 1 + G i + G n ) min = π d · ( Σ i = 1 n q s i k n · h i · λ i , Σ i = 1 n G i ) min ;
只考虑Tk1对于海上大直径钢管桩而言,受力不完整,需考虑土芯有效自重或桩内极限侧摩阻力对抗拔力的贡献Tk2,故建立的统一方法可表述为:
T k = T k 1 + T k 2 = G 0 + π D · Σ i = 1 n q s k i w · H i · λ i + π d · ( Σ i = 1 n q s i k n · h i · λ i , Σ i = 1 n G i ) min
式中,
D为大直径钢管桩外径,d为大直径钢管桩内径,Hi为i层的大直径钢管桩入土深度,hi为i层的桩内土芯长度,G0为上部结构和基桩自重,qskiw为i层的桩外极限侧摩阻力,qsikn为i层的桩内极限侧摩阻力,λi为i层的地层抗拔系数,Gi为i层的桩内土芯的土芯有效自重。
本发明的有益效果是:1、计算方法综合考虑了大直径钢管桩桩内土芯的影响,包括地层分布特征下土芯有效自重和桩内极限侧摩阻力;2、计算方法在常规计算方法的基础上,比选了土芯有效自重和桩内极限侧摩阻力的大小,更符合大直径钢管桩荷载传递和受力状态,计算方法简便,可操作性好。
附图说明
图1是本发明实施例的立面受力状况示意图。
具体实施方式
海上大直径钢管桩的桩基极限抗拔承载力可分解为三部分:一、上部结构和基桩自重,二、地层对桩基产生的向下的桩外极限侧摩阻力(表示为qskw),三、地层对桩基产生的向下的桩内极限侧摩阻力(表示为qskn)或桩内的土芯有效自重(表示为G)。其中前两项对于小直径桩和闭口桩均产生作用,但第三项只针对大直径钢管桩产生作用。
但桩内极限侧摩阻力(qskn)和土芯有效自重(G)在同一时刻不可能同时发挥作用,如果桩内极限侧摩阻力的总和大于土芯有效自重的总和,则土芯仍锁定在桩管内,土芯不会产生向下的滑移,此时土体与桩体仍属于界面间的极限摩擦状态,桩内极限摩擦力可按土芯有效自重考虑;反之,如果桩内极限侧摩阻力的总和小于土芯有效自重的总和,锁定力不足,土芯则会在重力作用下向下滑移,此时的桩内极限摩擦力则等于桩内极限侧摩阻力。下面通过具体实施方法来进一步加以说明:
如图1所示,大直径钢管桩1打入至海床泥面2下,穿越顶层土3,第i层土4,桩底到达持力层5至设计标高,上部结构和基桩自重可表示为G0,此时在大直径钢管桩1内会产生与地层相对应的桩内土芯6。
在上拔荷载7的作用下,大直径钢管桩1在顶层土3内桩长为H1,产生桩外极限侧摩阻力Ⅰ8,其值表示为qs1kw,在第i层土4内桩长为Hi,产生桩外极限侧摩阻力Ⅱ9,其值表示为qsikw,在持力层5内桩长为Hn,产生桩外极限侧摩阻力10Ⅲ,其值表示为qsnkw
此时,大直径钢管桩1在顶层土3内壁亦有可能产生桩内极限侧摩阻力Ⅰ11,其值表示为qs1kn,对应抗拔系数为λ1,对应桩内土芯6长度为h1;在第i层土4产生桩内极限侧摩阻力Ⅱ12,其值表示为qsikn,对应抗拔系数为λi,对应桩内土芯6长度为hi;在持力层5产生桩内极限侧摩阻力13,表示为qsnkn,对应抗拔系数为λn,对应桩内土芯长度为hn
同时,大直径钢管桩1桩内土芯6会产生重力作用,其顶层土3的土芯有效自重Ⅰ14表示为G1,第i层土4的土芯有效自重Ⅱ15表示为Gi,持力层5的土芯有效自重Ⅲ16表示为Gn
第一步,按常规方法只考虑上部结构和基桩自重、桩外极限侧摩阻力,则桩基的极限抗拔承载力Tk1为:
T k 1 = G 0 + π D · ( q s k 1 w · H 1 · λ ] + q s k i w · H i · λ i + q s k n w · H n · λ n ) = G 0 + π D · Σ i = 1 n q s k i w · H i · λ i ;
第二步,桩内土芯6产生极限抗拔承载力Tk2为桩内极限侧摩阻力与桩内土芯有效自重的较小值:
T k 2 = π d · ( q s 1 k n · h 1 · λ 1 + q s i k n · h i · λ i + q s n k n · h n · λ n , G 1 + G i + G n ) min = π d · ( Σ i = 1 n q s i k n · h i · λ i , Σ i = 1 n G i ) min ;
则海上大直径钢管桩1的极限抗拔承载力Tk为上部结构和基桩自重、桩外极限侧摩阻力、桩内极限侧摩阻力与桩内土芯有效自重的较小值的总和:
T k = T k 1 + T k 2 = G 0 + π D · Σ i = 1 n q s k i w · H i · λ i + π d · ( Σ i = 1 n q s i k n · h i · λ i , Σ i = 1 n G i ) min
对于海上大直径钢管桩的极限抗压承载力的计算与本发明方法类似,此处不再赘述。

Claims (1)

1.一种海上大直径钢管桩极限抗拔承载力的估算方法,其特征在于:该估算方法考虑了大直径钢管桩(1)内具有与地层相对应的桩内土芯(6),在上拨荷载(7)的作用下,大直径钢管桩(1)在顶层土(3)、第i层土(4)及持力层(5)分别产生桩外极限侧摩阻力、在桩内土芯(6)分别产生的桩内极限侧摩阻力或者是桩内土芯(6)有效自重、以及上部结构和基桩自重,则计算公式如下:
桩基极限抗拨承载力Tk=Tk1+Tk2
Tk1为按常规方法只考虑上部结构和基桩自重和桩外极限侧摩阻力,表达式为:
T k 1 = G 0 + π D · ( q s k 1 w · H 1 · λ 1 + q s k i w · H i · λ i + q s k n w · H n · λ n ) = G 0 + π D · Σ i = 1 n q s k i w · H i · λ i ;
Tk2为桩内极限侧摩阻力与桩内土芯(6)有效自重的较小值,表达式为:
T k 2 = π d · ( q s 1 k n · h 1 · λ 1 + q s i k n · h i · λ i + q s n k n · h n · λ n , G 1 + G i + G n ) min = π d · ( Σ i = 1 n q s i k n · h i · λ i , Σ i = 1 n G i ) min ;
只考虑Tk1对于海上大直径钢管桩而言,受力不完整,需考虑土芯(6)有效自重或桩内极限侧摩阻力对抗拔力的贡献Tk2,故建立的统一方法可表述为:
T k = T k 1 + T k 2 = G 0 + π D · Σ i = 1 n q s k i w · H i · λ i + π d · ( Σ i = 1 n q s i k n · h i · λ i , Σ i = 1 n G i ) min
式中,
D为大直径钢管桩(1)外径,d为大直径钢管桩(1)内径,Hi为i层的大直径钢管桩(1)入土深度,hi为i层的桩内土芯(6)长度,G0为上部结构和基桩自重,qskiw为i层的桩外极限侧摩阻力,qsikn为i层的桩内极限侧摩阻力,λi为i层的地层抗拔系数,Gi为i层的桩内土芯(6)的土芯有效自重。
CN201510470586.2A 2015-08-04 2015-08-04 海上大直径钢管桩极限抗拔承载力的估算方法 Pending CN105064419A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510470586.2A CN105064419A (zh) 2015-08-04 2015-08-04 海上大直径钢管桩极限抗拔承载力的估算方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510470586.2A CN105064419A (zh) 2015-08-04 2015-08-04 海上大直径钢管桩极限抗拔承载力的估算方法

Publications (1)

Publication Number Publication Date
CN105064419A true CN105064419A (zh) 2015-11-18

Family

ID=54493906

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510470586.2A Pending CN105064419A (zh) 2015-08-04 2015-08-04 海上大直径钢管桩极限抗拔承载力的估算方法

Country Status (1)

Country Link
CN (1) CN105064419A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105926689A (zh) * 2016-05-18 2016-09-07 中铁上海设计院集团有限公司 跟钻法铁路管桩的单桩容许承载力计算方法
CN106013269A (zh) * 2016-06-21 2016-10-12 中国电建集团华东勘测设计研究院有限公司 管桩内外侧壁摩阻力测试方法
CN109914494A (zh) * 2019-03-28 2019-06-21 中交路桥建设有限公司 一种桩基土层极限侧摩阻力测试系统
CN110952602A (zh) * 2019-11-15 2020-04-03 长江岩土工程总公司(武汉) 利用护壁套管估算桩基土的极限侧阻力的方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102660968A (zh) * 2012-06-04 2012-09-12 化学工业岩土工程有限公司 一种单桩竖向承载力估算方法
JP2012184596A (ja) * 2011-03-07 2012-09-27 Taisei Corp 杭の載荷試験方法
CN103147468A (zh) * 2013-03-27 2013-06-12 上海市机械施工有限公司 测试桩基承载力的方法
CN103266634A (zh) * 2013-01-09 2013-08-28 交通运输部公路科学研究所 一种超长钻孔灌注桩承载力确定方法
CN102587427B (zh) * 2012-04-05 2014-09-03 铁道第三勘察设计院集团有限公司 基于触探技术估算桩基沉降变形的分析方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012184596A (ja) * 2011-03-07 2012-09-27 Taisei Corp 杭の載荷試験方法
CN102587427B (zh) * 2012-04-05 2014-09-03 铁道第三勘察设计院集团有限公司 基于触探技术估算桩基沉降变形的分析方法
CN102660968A (zh) * 2012-06-04 2012-09-12 化学工业岩土工程有限公司 一种单桩竖向承载力估算方法
CN103266634A (zh) * 2013-01-09 2013-08-28 交通运输部公路科学研究所 一种超长钻孔灌注桩承载力确定方法
CN103147468A (zh) * 2013-03-27 2013-06-12 上海市机械施工有限公司 测试桩基承载力的方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
徐向阳等: "大直径钢管桩土体闭塞效应分析", 《中国水运》 *
林岳: "开口管桩承载力计算方法及桩基模型研究", 《水运工程》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105926689A (zh) * 2016-05-18 2016-09-07 中铁上海设计院集团有限公司 跟钻法铁路管桩的单桩容许承载力计算方法
CN106013269A (zh) * 2016-06-21 2016-10-12 中国电建集团华东勘测设计研究院有限公司 管桩内外侧壁摩阻力测试方法
CN109914494A (zh) * 2019-03-28 2019-06-21 中交路桥建设有限公司 一种桩基土层极限侧摩阻力测试系统
CN110952602A (zh) * 2019-11-15 2020-04-03 长江岩土工程总公司(武汉) 利用护壁套管估算桩基土的极限侧阻力的方法
CN110952602B (zh) * 2019-11-15 2021-07-30 长江岩土工程有限公司 利用护壁套管估算桩基土的极限侧阻力的方法

Similar Documents

Publication Publication Date Title
Abdel-Rahman et al. Finite element modelling of horizontally loaded monopile foundations for offshore wind energy converters in Germany
Lian et al. Bearing capacity and technical advantages of composite bucket foundation of offshore wind turbines
Zhu et al. Deflection-based bearing capacity of suction caisson foundations of offshore wind turbines
CN105064419A (zh) 海上大直径钢管桩极限抗拔承载力的估算方法
CN101545462B (zh) 一种钢-混凝土组合重力式海上风电机组基础结构
CN105297765A (zh) 一种海上风电场风机复合式嵌岩桩基础及其施工方法
Petaccia et al. The collapse of the Sella Zerbino gravity dam
CN105297764B (zh) 海上风电场风机单桩基础及其施工方法
Dai et al. Application of bi-directional static loading test to deep foundations
CN205116207U (zh) 一种海上风电场风机复合式嵌岩桩基础
CN203977417U (zh) 一种深水桩基础用加强肋嵌入式钢护筒
Li et al. Advanced concept design and numerical study of suction bucket foundation in deep ocean
Huo et al. Field test research of inclined large-scale steel pipe pile foundation for offshore wind farms
CN205907673U (zh) 一种用于河道陡坡基岩上的桥梁主墩承台基坑的钢板桩结构
CN213358703U (zh) 一种塔楼抗浮锚杆的布置结构
CN201649077U (zh) 变桩径单桩基础
CN204000856U (zh) 内撑灌浆式水平抗侧变刚度桩基
CN211873069U (zh) 组合结构海上风机翼板单桩基础
CN205116208U (zh) 海上风电场风机单桩基础
CN209603167U (zh) 一种海上风机重力式基础复合地基
CN203145025U (zh) 一种软土地基深基坑支护拉锚结构
Chao et al. Study on vertical bearing capacity of the riser composite pile in clay
CN202359564U (zh) 一种拱形钢板桩支护结构
CN205712162U (zh) 海上风电场浅覆盖层地基两级嵌岩桩风机基础
Xu et al. Geotechnical analysis of building foundation in beihai sand dam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20151118