CN105003210B - Drill stem hoisting device - Google Patents

Drill stem hoisting device Download PDF

Info

Publication number
CN105003210B
CN105003210B CN201510393889.9A CN201510393889A CN105003210B CN 105003210 B CN105003210 B CN 105003210B CN 201510393889 A CN201510393889 A CN 201510393889A CN 105003210 B CN105003210 B CN 105003210B
Authority
CN
China
Prior art keywords
hydraulic cylinder
channel
dead line
hoisting device
section steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510393889.9A
Other languages
Chinese (zh)
Other versions
CN105003210A (en
Inventor
刘伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510393889.9A priority Critical patent/CN105003210B/en
Publication of CN105003210A publication Critical patent/CN105003210A/en
Application granted granted Critical
Publication of CN105003210B publication Critical patent/CN105003210B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The present invention relates to a kind of drill stem hoisting device.Main solve aids in small winch wire rope not come into line present in drilling well existing weaponry and equipment, causes steel wire rope to play pile, fracture of wire and triggers the unsafe problem of production, it is characterised in that:Described drill stem hoisting device, mainly include hydraulic cylinder main frame and channel-section steel deck, described hydraulic cylinder main frame upper end hinge is provided with fixed pulley group, piston rod upper end is provided with running block, plunger shaft oil inlet is provided with hydraulic control one-way valve and one-way throttle valve, described channel-section steel deck is mainly made up of derrick panel buckle, channel-section steel deck main body and hydraulic cylinder buckle, and dead line pull bar and buffer spring are provided with the dead line otic placode of channel-section steel deck main body.Interior extrapolation method wire rope handling is used between described fixed pulley group, running block, steel wire rope dead line end is fixed on the dead line pull bar of channel-section steel deck, what live line end bypassed drilling derrick uphangs pulley equipped with suspension hook.The drill stem hoisting device have steel wire rope not disorderly, the characteristics of speed is easy to control, to hang speed different.

Description

Drill stem hoisting device
Technical field
Equipment is hung the present invention relates to a kind of drilling rod applied in oil drill equipment field, it is drilling rod lifting dress to refer in particular to Put.
Background technology
At present, at home, outer oil drilling scene, hang in the operations such as drill bit, drill collar, drilling rod or breaking down, setting of casing, Puffer is aided in using hydraulic small winch provided, pneumatic puffer or electronic puffer etc., but there is steel wire in these auxiliary puffers Rope can not come into line problem, cause steel wire rope to play pile, fracture of wire, there is potential safety hazard.
The content of the invention
The technical problems to be solved by the invention are overcome present in background technology using steel wire rope during auxiliary puffer Can not come into line causes steel wire rope to play pile, the unsafe problem of fracture of wire initiation production, and provides a kind of drill stem hoisting device, the drilling rod Lifting device have steel wire rope not disorderly, hang that speed is different, the manageable feature of speed.
The problem of present invention is solved in background technology is realized by following technical solution:The drill stem hoisting device, mainly Including hydraulic cylinder main frame and channel-section steel deck, described hydraulic cylinder main frame includes hydraulic cylinder, and the hydraulic cylinder upper end is filled by hinge There is fixed pulley group, hydraulic cylinder piston rod upper end is provided with running block, the hydraulic cylinder lock by T-shape frame and is provided with liquid Control plunger shaft oil inlet below check valve, hydraulic cylinder lock and one-way throttle valve is installed;The channel-section steel deck includes channel-section steel deck Main body, the channel-section steel deck main body back side is provided with multiple derrick panel buckles, channel-section steel deck main body front upper, middle part, lower part Righting otic placode, dead line otic placode, ear plate base are not connected to;Hydraulic cylinder buckle, righting are installed before the righting otic placode, dead line otic placode Otic placode both sides are symmetrically connected to wire rope handling pipe, and dead line otic placode both sides, which are symmetrically connected with spring base, spring base, is installed with dead line pull bar, described Draw ring is terminated with dead line pull bar;Buffer spring is cased with outside spring base, buffer spring lower end is against the spring compressor of dead line pull bar On;The hydraulic cylinder main frame is by hydraulic cylinder buckle on channel-section steel deck, and hydraulic cylinder main frame bottom wears pin and is fixed on ear plate base On.
The present invention can have the advantages that compared with background technology:The drill stem hoisting device is due to using above-mentioned knot Structure, is fixed on many crossbeams of drilling derrick back side eminence entirely through derrick panel buckle, when piston rod stretches, movable pulley Group is moved together in company with piston rod, and n × n is constituted between fixed and moving assembly pulley(Note:N is even number)Train group, twine between train group Often stretch out or retract 1 meter around 2 × n strand steel wire ropes, i.e. piston rod, be then installed on suspension hook i.e. raising or the decentralization at steel wire rope live line end 2 × n meters, lifting, decentralization weight operation are realized with this.Because dead line end is higher by some rice of drilling floor surface, if by being had more in derrick Dry rice steel wire rope and suspension hook deadweight, the wire rope rope can be tensed naturally, realize not heap rope, job-hopping between train.Transfer weight mistake Cheng Zhong, suddenly after brake, the impact kinetic energy that weight inertia is produced is then by steel wire rope, dead line pull bar, spring compressor by buffer spring Absorb, realize steady brake.Because the drill stem hoisting device is using as above technical scheme, steel wire in background technology is efficiently solved The winding of steel wire rope need not be observed in the problem of rope is uneven, operation process, so hydraulic operation case can move forward to rig floor Place situation is observed in front side, more conducively operating personnel, hangs, to put operation safer.
Brief description of the drawings:
Accompanying drawing 1 is the front view of the present invention;
Accompanying drawing 2 is the side view of the present invention;
Accompanying drawing 3 is the front view of the hydraulic cylinder main frame of the present invention;
Accompanying drawing 4 is the side view of accompanying drawing 3;
Accompanying drawing 5 is the structural representation of the channel-section steel deck of the present invention;
Accompanying drawing 6 is along the A-A of accompanying drawing 5 to sectional view;
Accompanying drawing 7 is the B-B direction sectional view along accompanying drawing 5;
Accompanying drawing 8 is the enlarged diagram of the I parts of accompanying drawing 5;
Accompanying drawing 9 is apparatus of the present invention hydraulic control piping diagram(A is hydraulic control system of the invention in figure;B is the hydraulic control of existing rig Pipeline).
In figure:1- hydraulic cylinders;2- hinges;3- fixed pulley groups;The anti-springboards of 4-;5- running blocks;The anti-pogo sticks of 6-; 7- T-shape framves;8- piston rods;9- oil inlet pipes;10- locks;11- high-pressure rubber pipes;12- one-way throttle valves;13- hydraulic controls Check valve;14- ear plate bases;15-connecting rod;16- channel-section steel deck main bodys;17- derrick panel buckles;18-dead line otic placode; 19- righting otic placodes;20- hydraulic cylinder buckles;21- wire rope handling pipes;22- draw rings;23- dead line pull bars;24- spring bases;25- Buffer spring;26- spring compressors.
Embodiment:
The invention will be further described below in conjunction with the accompanying drawings:
As shown in accompanying drawing 1, Fig. 2, Fig. 3, Fig. 4, the drill stem hoisting device, including hydraulic cylinder main frame and channel-section steel deck, it is described Hydraulic cylinder main frame include hydraulic cylinder 1, the upper end of hydraulic cylinder 1 is equipped with fixed pulley group 3 by hinge 2, on hydraulic cylinder piston rod 8 End is provided with running block 5 by T-shape frame 7, and hydraulic cylinder lower end lock 10 is connected with rod end chamber oil inlet by oil inlet pipe 9 Connect, plunger shaft oil inlet below hydraulic control one-way valve 13, hydraulic cylinder lock is installed on hydraulic cylinder lock 10 one-way throttle is installed Valve 12, plunger shaft return flow is can control by adjusting one-way throttle valve, limits the highest retraction speed of piston rod, and then control The maximum lowering velocity of suspension hook;Below hydraulic cylinder lock 10 high-pressure glue is all connected with below rod end chamber oil inlet and one-way throttle valve Pipe 11;As shown in Fig. 5, Fig. 6, Fig. 7, Fig. 8, the channel-section steel deck includes channel-section steel deck main body 16, the back side of channel-section steel deck main body 16 Several derrick panel buckles 17 are installed, the front upper of channel-section steel deck main body 16, middle part, bottom are welded with righting otic placode respectively 19th, dead line otic placode 18, ear plate base 14;The righting otic placode 19, dead line otic placode 18 are above provided with hydraulic cylinder buckle 20, righting ear The both sides of plate 19 are symmetrically welded with oval wire rope handling pipe 21, and the both sides of dead line otic placode 18 are symmetrically welded with spring base 24, spring base 24 and are installed with Dead line pull bar 23, the upper end of dead line pull bar 23 is welded with " U " type draw ring 22, to fixed steel wire rope;The outside of spring base 24 is cased with Buffer spring 25, the lower end of buffer spring 25 is against on the spring compressor 26 of dead line pull bar;The company of being welded between dead line otic placode 18, ear plate base 14 Extension bar 15, the connecting rod ensure dead line otic placode stress after do not upwarp, it is indeformable;The hydraulic cylinder main frame passes through hydraulic cylinder buckle 20 On channel-section steel deck, hydraulic cylinder main frame bottom is worn pin and is fixed on ear plate base 14;Described fixed pulley group 3 and running block 5 Axially it is mutually perpendicular to, interior extrapolation method wire rope handling is used between fixed pulley group, running block, to improve the stability of piston rod.Described Anti- springboard 4 is equipped between fixed pulley group 3, prevents the steel wire rope that winch fast line jumps between fixed pulley group and dead line pull bar upper end from jumping out calmly Between assembly pulley;The described outside of running block 5 is fixed with 3 anti-pogo sticks 6, prevents that other ropes are jumped between running block on derrick And the groove skipping of steel rope while between train.Described steel wire rope dead line end is fixed on the dead line pull bar of channel-section steel deck, and live line end is bypassed The pulley of uphanging of drilling derrick is provided with suspension hook.
The drill stem hoisting device is fixed on the drilling derrick back side due to using said structure entirely through derrick panel buckle On many crossbeams of eminence, when piston rod stretches, running block is moved together in company with piston rod, and n is constituted between fixed and moving assembly pulley ×n(N is even number)Train group, winding 2 × n strand steel wire ropes, i.e. piston rod often stretch out or retracted 1 meter between train group, then pacify Suspension hook loaded on steel wire rope live line end is 2 × n meters of raising or decentralization, and lifting, decentralization weight operation are realized with this.Because dead line end is high Go out some rice of drilling floor surface, conduct oneself with dignity by some meters of steel wire ropes and suspension hook being had more in derrick, the wire rope rope can be tensed naturally, Realize not heap rope, job-hopping between train.Transfer during weight, suddenly after brake, the impact kinetic energy that weight inertia is produced then passes through Steel wire rope, dead line pull bar, spring compressor are absorbed by buffer spring, realize steady brake.Because the drill stem hoisting device is using as above Technical scheme, twining for steel wire rope need not be observed by efficiently solving in the problem of steel wire rope is uneven in background technology, operation process Around situation, so hydraulic operation case can be moved forward on front side of rig floor, more conducively operating personnel observe place situation, hang, put operation more Plus safety.
As shown in Figure 9, the drill stem hoisting device utilizes the existing hydraulic station of drilling crew and supporting with drill stem hoisting device Hydraulic operation case, oil pressure and control are provided to it.Its hydraulic control system of described hydraulic cylinder is connected in existing rig fluid path, hydraulic pressure Cylinder and existing hydraulic control equipment concurrently-acting, meet produce reality needs;Its hydraulic control system of described hydraulic cylinder is located at existing bore Machine hydraulic operation platform and liquid gas tong upstream, to reduce the influence to existing rig hydraulic control equipment.
Start hydraulic station, above push away hand-operated direction valve handle, hydraulic cylinder piston chamber oil-feed promotes piston rod and running block to stretch Go out, sling suspension hook and weight.Handle returns middle position or stops hydraulic station, and hydraulic control one-way valve is closed automatically, and oily in trap plunger shaft Liquid, realizes brake.Hand-operated direction valve handle, hydraulic cylinder piston rod cavity oil-feed are pulled down, and opens hydraulic control one-way valve, plunger shaft fluid Discharged by hydraulic control one-way valve and one-way throttle valve, piston rod and running block are retracted, decentralization suspension hook and weight are single by adjusting Plunger shaft return flow is can control to choke valve, the highest retraction speed of piston rod is limited, and then control the maximum decentralization of suspension hook Speed.Different by above pushing away or pulling down handle angle, control enters hydraulic cylinder fluid uninterrupted, and then controls hydraulic cylinder piston Bar stretches out or retraction speed, realizes that flexibly control suspension hook is sling or lowering velocity.During decentralization weight, suddenly after brake, The impact kinetic energy that weight inertia is produced then is absorbed by steel wire rope, dead line pull bar, spring compressor by buffer spring, and realization is steadily stopped Car.
The drill stem hoisting device lifts weight using the plunger shaft oil-feed of hydraulic cylinder, and weight is transferred using rod end chamber oil-feed Thing, because piston rod side effective area is less than piston side effective area, so under hydraulic station same displacement, lowering velocity is faster than lifting Speed, is more suitable for the operation needs such as drilling well setting of casing, breaking down.
The drill stem hoisting device is arranged on the crossbeam of the derrick back side by channel-section steel deck, does not change original derrick geometry, main If stress between hydraulic cylinder and piston rod, derrick is subjected only to drill stem hoisting device deadweight(Downwards)With the weight of lifted weight (Upwards), overall structure, the force analysis of derrick are not influenceed.

Claims (6)

1. a kind of drill stem hoisting device, including hydraulic cylinder main frame and channel-section steel deck, it is characterised in that:Described hydraulic cylinder main frame bag Include hydraulic cylinder(1), the hydraulic cylinder(1)Upper end passes through hinge(2)Equipped with fixed pulley group(3), hydraulic cylinder piston rod(8)Upper end leads to Cross T-shape frame(7)Running block is installed(5), the hydraulic cylinder lock(10)On hydraulic control one-way valve is installed(13), hydraulic cylinder Plunger shaft oil inlet is provided with one-way throttle valve below lock(12);The channel-section steel deck includes channel-section steel deck main body(16), groove Steel deck main body(16)The back side is provided with multiple derrick panel buckles(17), channel-section steel deck main body(16)Front upper, middle part, under Portion is connected to righting otic placode respectively(19), dead line otic placode(18), ear plate base(14);The righting otic placode(19), dead line otic placode(18) Hydraulic cylinder buckle is above installed(20), righting otic placode(19)Both sides are symmetrically connected to wire rope handling pipe(21), dead line otic placode(18)Both sides It is symmetrically connected with spring base(24), spring base(24)Inside it is installed with dead line pull bar(23), the dead line pull bar(23)On be terminated with draw Ring(22);Spring base(24)Outside is cased with buffer spring(25), buffer spring(25)Lower end is against the spring compressor of dead line pull bar (26)On;The hydraulic cylinder main frame passes through hydraulic cylinder buckle(20)On channel-section steel deck, hydraulic cylinder main frame bottom is worn pin and fixed In ear plate base(14)On.
2. drill stem hoisting device according to claim 1, it is characterised in that:Described fixed pulley group(3)With running block (5)Axially it is mutually perpendicular to;Described fixed pulley group(3), running block(5)By interior extrapolation method wire rope handling, n × n train group is constituted, Wherein n is even number.
3. drill stem hoisting device according to claim 1 or 2, it is characterised in that:Described dead line otic placode(18), ear plate base (14)Between be connected to connecting rod(15).
4. drill stem hoisting device according to claim 1 or 2, it is characterised in that:The fixed pulley group(3)Between be equipped with it is anti-jump Plate(4);Running block(5)Outside is fixed with some anti-pogo sticks(6).
5. drill stem hoisting device according to claim 1 or 2, it is characterised in that:Described draw ring(22)Drawn for " U " type Ring.
6. drill stem hoisting device according to claim 1 or 2, it is characterised in that:Described wire rope handling pipe(21)For ellipse.
CN201510393889.9A 2015-07-07 2015-07-07 Drill stem hoisting device Active CN105003210B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510393889.9A CN105003210B (en) 2015-07-07 2015-07-07 Drill stem hoisting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510393889.9A CN105003210B (en) 2015-07-07 2015-07-07 Drill stem hoisting device

Publications (2)

Publication Number Publication Date
CN105003210A CN105003210A (en) 2015-10-28
CN105003210B true CN105003210B (en) 2017-07-25

Family

ID=54376041

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510393889.9A Active CN105003210B (en) 2015-07-07 2015-07-07 Drill stem hoisting device

Country Status (1)

Country Link
CN (1) CN105003210B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108331802A (en) * 2017-12-27 2018-07-27 湖北华舟重工应急装备股份有限公司 A kind of emergent bridge nose girder support cylinder buffer system
CN108412424B (en) * 2018-03-30 2023-09-29 中国水利水电第六工程局有限公司 Tool for preventing drill rod from rebounding in directional drilling and dragging construction and application method thereof
CN108678689A (en) * 2018-04-23 2018-10-19 廖恒伟 A kind of oil-well rig hydraulic hoisting machine host
CN108397143A (en) * 2018-05-11 2018-08-14 廖恒伟 A kind of oil-well rig hydraulic lifting device
CN108915617A (en) * 2018-08-03 2018-11-30 四川诺克钻探机械有限公司 A kind of double lifting rail bars with ratcheting mechanism
CN110094172B (en) * 2019-05-06 2020-03-17 青州市春晖科技发展有限公司 Hydraulic lifting device for drilling and workover tools
CN111977545B (en) * 2020-08-31 2021-04-06 青州市春晖科技发展有限公司 Double-head safety lifting device for drilling and workover

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001018350A1 (en) * 1999-10-19 2001-03-15 Huisman Special Lifting Equipment B.V. Hoisting device, with compensator built into hoisting cable system
CN101812977A (en) * 2009-02-25 2010-08-25 北京Tsc海洋石油装备有限公司 Drilling platform pipe racking system and method
CN102140897A (en) * 2011-04-02 2011-08-03 建湖县鸿达阀门管件有限公司 Automatic racking device for drill rod
CN102409973A (en) * 2011-11-30 2012-04-11 连云港天明装备有限公司 Vehicle-mounted full hydraulic multifunctional deep well drilling machine
CN204729028U (en) * 2015-07-07 2015-10-28 刘伟 Drill stem hoisting device

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NO326329B1 (en) * 2006-06-19 2008-11-10 Nat Oilwell Norway As Lifting device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001018350A1 (en) * 1999-10-19 2001-03-15 Huisman Special Lifting Equipment B.V. Hoisting device, with compensator built into hoisting cable system
CN101812977A (en) * 2009-02-25 2010-08-25 北京Tsc海洋石油装备有限公司 Drilling platform pipe racking system and method
CN102140897A (en) * 2011-04-02 2011-08-03 建湖县鸿达阀门管件有限公司 Automatic racking device for drill rod
CN102409973A (en) * 2011-11-30 2012-04-11 连云港天明装备有限公司 Vehicle-mounted full hydraulic multifunctional deep well drilling machine
CN204729028U (en) * 2015-07-07 2015-10-28 刘伟 Drill stem hoisting device

Also Published As

Publication number Publication date
CN105003210A (en) 2015-10-28

Similar Documents

Publication Publication Date Title
CN105003210B (en) Drill stem hoisting device
AU2011269931B2 (en) A telescopic elevator bail, vessel comprising such the elevator bail and method of using the elevator bail
CN107500170A (en) A kind of pulley lifting system and its drilling platforms
CN104444756A (en) Segmented retardant discharging device
CN103863938B (en) For carrying the safty hoisting device of wind tunnel experiment car
CN205275009U (en) Pneumatic autospasy hook block frame of ton bagging -off
CN203740992U (en) Working table with lifting and overturning device
CN204729028U (en) Drill stem hoisting device
CN105819319B (en) The main hoisting rope adjusting apparatus and its adjusting method of a kind of mine shaft hoist system
CN207999212U (en) Rotary drilling rig
CN103264980B (en) Two bar reach hydraulic blowout preventer hangs moving device
EA018864B1 (en) Oil well plunger pumping
CN201747299U (en) Hydraulic cylinder-type hanging tongs balancing device
CN106167234B (en) A kind of driller room lifting mechanism
CN107758509A (en) Integral hoisting device for rapid and method
CN202610787U (en) Cordless high trigger type dynamic compaction automatic detacher
CN202440240U (en) Cylinder type crane for well drilling
CN2608760Y (en) Hydraulic damper
CN109972606A (en) A kind of mechanical relief device
CN203806944U (en) Safe lifting device for carrying wind tunnel experiment vehicle
CN108128683A (en) Extra deep shaft promotes rope tension automatic adjusument head sheave group and its adjusting method
CN203877746U (en) Special multi-claw hanger for annular object
CN106246613A (en) Discharge mechanism and dynamic compaction machinery
CN114016937B (en) Deblocking workover rig
CN106744453A (en) A kind of brakes of dynamic compaction machinery lifting device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant