CN105002868B - Platform basin installation lengthens the construction technology of internal thread bend pipe - Google Patents

Platform basin installation lengthens the construction technology of internal thread bend pipe Download PDF

Info

Publication number
CN105002868B
CN105002868B CN201510438947.5A CN201510438947A CN105002868B CN 105002868 B CN105002868 B CN 105002868B CN 201510438947 A CN201510438947 A CN 201510438947A CN 105002868 B CN105002868 B CN 105002868B
Authority
CN
China
Prior art keywords
internal thread
bend pipe
thread bend
groove
lengthening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510438947.5A
Other languages
Chinese (zh)
Other versions
CN105002868A (en
Inventor
黄国民
颜伟阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Shengdu Home Furnishing Decoration Co.
Original Assignee
Holy Home Furnishing Decoration Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Holy Home Furnishing Decoration Co filed Critical Holy Home Furnishing Decoration Co
Priority to CN201510438947.5A priority Critical patent/CN105002868B/en
Publication of CN105002868A publication Critical patent/CN105002868A/en
Application granted granted Critical
Publication of CN105002868B publication Critical patent/CN105002868B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Pipe Accessories (AREA)

Abstract

The construction technology for lengthening internal thread bend pipe is installed the invention discloses a kind of platform basin, including step:Groove is vertically opened up on metope, further includes following steps:Internal thread bend pipe will be lengthened to connect with feed pipe, and be laid in groove, wherein the silk head interface for lengthening internal thread bend pipe protrudes the distance range of metope between 4 centimetres to 6 centimetres;The silk head for lengthening internal thread bend pipe is fixed on groove top, blocks silk head;Groove is filled up, completes to lengthen the installation of internal thread bend pipe.The mounting process that the present invention lengthens internal thread bend pipe has the prominent advantages that:Go out the reduction of distance to silk head process in view of later stage installation, reserve sufficient space in order to lengthen taking between internal thread bend pipe and platform basin;The coating that waterproofing slurry is carried out after internal thread bend pipe is connect with feed pipe will be lengthened, prevent the infiltration in later stage wall;Leak test and EXIT POINT leakproof repairing are carried out before groove is filled up, further avoids leak.

Description

Platform basin installation lengthens the construction technology of internal thread bend pipe
Technical field
The present invention relates to the construction technologies that interior decoration field more particularly to a kind of installation of platform basin lengthen internal thread bend pipe.
Background technology
In toilet and kitchen water pipe installation process, it is related to installing internal thread bend pipe below platform basin and is applied with what feed pipe was taken over Work technique.
When platform basin water pipe is connect with feed pipe, an end interface of platform basin water pipe and triangle vavle connects existing construction technology It connects, another end interface of silk head interface and triangle vavle for lengthening internal thread bend pipe connects, and lengthens the straight tube interface of internal thread bend pipe.It lengthens Internal thread bend pipe refers to the internal thread bend pipe to be formed that inner thread elbow is connected with straight tube.Internal thread bending process is lengthened in existing platform basin In, consider for space-saving and aesthetic.The silk head interface water outlet for lengthening internal thread bend pipe maintains an equal level with metope, is actually applying During work, due to usually also to increase cabinet below platform basin, and the sidewall thickness of cabinet can cause to lengthen the curved of internal thread bend pipe The interface position of pipeline section cannot protrude the side wall of cabinet, this is resulted in the water pipe of platform basin and the silk head interface for lengthening internal thread bend pipe Be connected when because cabinet side wall interference can caused by hinder, for by the water pipe of platform basin with lengthen internal thread bend pipe connect, continued access pipeline general The problem of interface extension protrudes cabinet side wall is that the place of taking over is the position for being easiest to occur leak, this can increase the several of leak Rate brings a great deal of trouble later maintenance.
For this reason, it may be necessary to the construction technology that the installation of internal thread bend pipe is lengthened to platform basin is improved, to avoid the silk of inner thread elbow Head interface causes prominent planar section to reduce the connection difficult problem caused by even disappearing because of the construction in later stage.
Invention content
The present invention to solve the above-mentioned problems, provide a kind of construction technology, can make lengthening internal thread bend pipe install after Convenient for the installation in later stage.
A kind of platform basin installation lengthens the construction technology of internal thread bend pipe, and the lengthening internal thread bend pipe includes silk head and straight tube, institute It states construction technology and includes step:Groove is vertically opened up on metope, further includes following steps:
Internal thread bend pipe will be lengthened to connect with feed pipe, and be laid in groove, wherein lengthening the silk head interface of internal thread bend pipe The distance range of prominent metope is between 4 centimetres to 6 centimetres;
It is fixed to lengthen internal thread bend pipe, block silk head;
Sealed groove is completed to lengthen the installation of internal thread bend pipe.
The silk head for lengthening internal thread bend pipe is exposed 4 to 6 centimetres of metope by the mounting means, has fully considered that later stage installation causes Silk head interface protrudes the reduction of distance, convenient for platform basin and lengthens the connection between internal thread bend pipe.
Furthermore, it is fixed lengthen female elbow before first the length direction of recess sidewall upper edge groove every 8~ 10 centimetres of arrangements, one support element.
It is swayed forwards and backwards in order to avoid lengthening internal thread bend pipe when fixing along depth of groove direction, a head process is caused to go out metope Distance is unable to reach desired value, for the too deep groove of depth, support element can be installed on side wall, the support element plays limit Position effect, and support element arranges one every a distance, is reserved between support element and groove both ends and adjacent supporting piece Space is held lengthening internal thread bend pipe for installation personnel and is taken over, and the connection to lengthen internal thread bend pipe and feed pipe provides just Profit.There are many fixed form of support element, including cement block, stone, have certain thickness steel plate, can be fixed by spiral or Bonding mode is fixed in recess sidewall.
Furthermore, each support element includes a pair of of elastic clip, and the end of each elastic clip is circumferential along straight tube Extension is respectively formed extension at towards slot opening, and extension has the clamping part of protrusion relative to each other;
Accordingly, the encapsulating method of the groove includes:
It fills up groove top and lengthens the gap between internal thread bend pipe;
According to the slot opening shape joints cement plate after filling up;
Installation and the matched plate of elastic clip on the cement plate poured;
Cement plate is hinged on to the bottom of the slot opening, cement plate is sealed into slot opening, makes clamping part phase interworking Co-clip holds the plate, completes the sealing.
General groove is filled up groove using cement and is sealed, but this mode is very unfavorable for later period maintenance, The situation that internal thread bend pipe usually appears in wall inside points leak in the long-term use is lengthened, if filled up using cement Form, it is necessary to dig wall again, very big influence caused for the wall fitted up and ground.By using the water of flexible connection Mud plate sealed groove, groove need to be only opened when needing to safeguard, this mode avoids later maintenance to wall and ground Caused by destruction, and due to that would generally add cabinet face below platform basin, cabinet wall can shelter from metope, therefore will not cause aesthetically Influence.
The lengthening internal thread bend pipe mounting height is that the altitude range of silk head center line to ground is at 45 centimetres to 50 centimetres Between.
In order to reduce platform basin and lengthen taking between internal thread bend pipe, silk grease head highness should close to platform basin, meanwhile, in order to avoid Platform basin bottom surface hinders taking at the silk head for lengthening internal thread bend pipe, and mounting height is most preferably between 45 centimetres to 50 centimetres.
Furthermore, first lengthening internal thread outer surface of bent pipe coating waterproofing slurry is carried out again after silk head is blocked described Groove is filled up.
Lengthening internal thread bend pipe is embedded in after installation is complete in wall, is ruptured if lengthening internal thread bend pipe, water can ooze Enter wall to damage, internal thread outer surface of bent pipe coating waterproof material, waterproof are being lengthened for leak is avoided to damage wall The slurry slurries such as including polyurethane.
Furthermore, step is further included before it will lengthen internal thread bend pipe and be fixed on groove top:By groove top with It is filled with cement in gap between silk overhead.
For the ease of lengthen internal thread bend pipe fixation, prevent lengthen internal thread bend pipe before and after loosening and convenient for using manage Card is fixed on internal thread bend pipe is lengthened on groove top, is first filled in the gap between groove top and silk overhead with cement, Again groove top is fixed on by internal thread bend pipe is lengthened with pipe clamp.
Furthermore, step is further included before groove is filled up:
Supply water to feed pipe, test lengthen internal thread bend pipe whether leak;
If leak, leakproof repairing is carried out at leak and is retested, until test passes through.
In order to further prevent lengthening female elbow tube leakage, it can first carry out water supply test before groove is filled up, look into It sees with the presence or absence of EXIT POINT, then can timely be repaired if any EXIT POINT, avoid that the later stage opens that wall repaired as far as possible can It can property.
General lengthen is attached between internal thread bend pipe and feed pipe using sweat soldering mode, therefore dismounting lengthens again The complexity that internal thread bend pipe increases operation is larger, in order to timely leakproof, while avoids complicated operation, furthermore, For waterproof gasket cement being used to carry out the leakproof repairing at leak.
The mounting process that the present invention lengthens internal thread bend pipe has the prominent advantages that:Distance is gone out to silk head process in view of later stage installation Reduction, reserved sufficient space in order to lengthen taking between internal thread bend pipe and platform basin;Internal thread bend pipe will be lengthened with supplying water The coating of waterproofing slurry is carried out after pipe connection, prevents the infiltration in later stage wall;Before groove is filled up carry out leak test with And EXIT POINT leakproof repairing, further avoid leak.
Description of the drawings
Fig. 1 is the method flow diagram of one embodiment of the invention;
Fig. 2 is the structural side view after present example of the present invention installs;
Fig. 3 is the structure front view after present example of the present invention installs.
Specific embodiment
In order to the present invention it is apparent, be explained in detail in conjunction with embodiment and Figure of description.
The method of present example of the present invention is as shown in Figure 1, including step:
Step 1 vertically opens up groove on metope.
In the present example, opening up for groove is carried out by groover, the groove surfaces that this mode opens up are relatively more flat It is whole.Wherein groove length and width are by needing lengthening internal thread bend pipe specification to be mounted to determine.Depth of groove is too deep, then after increasing The workload that phase groove is filled and led up;Depth of groove is excessively shallow, then so that the silk head process for lengthening internal thread bend pipe to go out metope too many, for beauty Degree and space availability ratio all have an impact.In view of lengthening the silk head length and pipe thickness of internal thread bend pipe, to ensure silk head dew Go out the distance of 4 to 6 centimetres of metope, while the installation convenient for lengthening internal thread bend pipe, it is however generally that, depth of groove is 4 to 8 centimetres. The distance that present example silk head interface protrudes metope is 4 centimetres.It is 6 centimetres that preset groove, which opens up depth,.
Step 2 compares the distance between depth of groove and predetermined depth, if depth of groove is more than predetermined depth, A support element is fixed in the groove side wall upper edge groove length direction opposite with opening every 8 centimetres to 10 centimetres, makes groove Depth is equal with predetermined depth.
In present example, the depth of groove after measurement is 7 centimetres, in order to avoid lengthening internal thread bend pipe when fixing along recessed Groove depth direction sways forwards and backwards, and the distance that a head process goes out metope is caused to be unable to reach desired predetermined depth, too deep for depth Groove, support element can be installed on side wall.
Support element plays position-limiting action, and support element arranges one every a distance, support element and groove both ends and The space reserved between adjacent supporting piece for installation personnel hold lengthen internal thread bend pipe take over, for lengthen internal thread bend pipe with The connection of feed pipe provides facility.There are many fixed form of support element, including cement block, stone, have certain thickness steel plate, It can be fixed by fixing pieces such as screws or be fixed in recess sidewall with bonding mode.In present example, as shown in Fig. 2, Support element includes a pair of of elastic clip 12, and the end of each elastic clip 12 is respectively formed along straight tube is circumferential towards extending at slot opening Extension, and extension has the clamping part of protrusion relative to each other.
Step 3 will lengthen internal thread bend pipe and be connect with feed pipe, and be laid in groove.
In order to reduce platform basin and lengthen taking between internal thread bend pipe, silk grease head highness should close to platform basin, meanwhile, in order to avoid Platform basin bottom surface hinders taking at the silk head for lengthening internal thread bend pipe, and mounting height is most preferably between 45 centimetres to 50 centimetres.When In preceding embodiment, the distance for lengthening silk head center line to the ground of internal thread bend pipe is 50 centimetres.
Step 4 fills in the gap between groove top and lengthening female elbow tube top portion with cement.
Blind prevents from lengthening the loosening before and after internal thread bend pipe convenient for lengthening the fixation of internal thread bend pipe.
The silk head for lengthening internal thread bend pipe is fixed on groove top, blocks silk head by step 5.
Wherein the fixation of silk head envelopes a head using pipe clamp, and carries out spiral using screw and fix.After fixation, silk Head is blocked using silk plug or trim, and being wrapped at closure using raw material band again after closure further increases leakproofness.
In order to further prevent lengthening female elbow tube leakage, it can first carry out water supply test before groove is filled up, look into It sees with the presence or absence of EXIT POINT, then can timely be repaired if any EXIT POINT, avoid that the later stage opens that wall repaired as far as possible can It can property.
Step 6, to lengthening internal thread outer surface of bent pipe coating waterproofing slurry.In present example, waterproofing slurry uses poly- ammonia Ester.
Step 7 supplies water to feed pipe, test lengthen between internal thread bend pipe and feed pipe whether leak and test Elbow interface whether leak;If leak, leakproof repairing is carried out at leak and is retested, until test passes through.
Internal thread bend pipe passes through there may be some second-rate or seepy questions caused by closure is not carried out Test can be to avoid seeping water in later stage wall.General lengthen is connected between internal thread bend pipe and feed pipe using sweat soldering mode It connects, therefore the complexity that the increase of dismounting lengthening internal thread bend pipe operates again is larger, in order to timely leakproof, while avoids complexity Operation, leakproof repairing is carried out using waterproof gasket cement for (i.e. EXIT POINT) at leak in present example.
Step 8, sealed groove are completed to lengthen the installation of internal thread bend pipe.
Specifically, groove encapsulating method includes:
It fills up groove top and lengthens the gap between internal thread bend pipe;
According to the slot opening shape joints cement plate after filling up;
Installation and the matched plate of elastic clip on the cement plate poured;
Cement plate is hinged on to the bottom of the slot opening, cement plate is sealed into slot opening, makes clamping part phase interworking Co-clip holds plate.
After installing, as shown in Fig. 2, the straight tube 23 for lengthening internal thread bend pipe 2 is fixed in groove 1, and silk head interface 21 Prominent 5 centimetres of wall, pipe clamp 15 envelope silk head 22, and fix with the top 16 of groove from 22 bottom of silk head, will lengthen internal thread The elbow part of bend pipe 2 is fixed with groove 1, and top 16 and the gap lengthened between internal thread bend pipe 2 are filled with cement.It is current to implement In example, there are four support elements, each to include a pair of of elastic clip 12, supports straight tube 23.Cement plate 14 is cut with scissors by articulation piece 13 It is connected on metope, after cement plate 14 and recess cover close, the clamping part of each pair of elastic clip 12 cooperates, and clamps plate 11, ensure that cement plate 14 firmly seals up groove 1.
Externally, effect such as Fig. 3, silk head interface 21 are exposed at outside wall, are blocked with silk plug, and cement plate 14 is close by groove It seals.
The mounting process that the present invention lengthens internal thread bend pipe has the prominent advantages that:Distance is gone out to silk head process in view of later stage installation Reduction, reserved sufficient space in order to lengthen taking between internal thread bend pipe and platform basin;Internal thread bend pipe will be lengthened with supplying water The coating of waterproofing slurry is carried out after pipe connection, prevents the infiltration in later stage wall;Before groove is filled up carry out leak test with And EXIT POINT leakproof repairing, further avoid leak.

Claims (6)

1. a kind of platform basin installation lengthens the construction technology of internal thread bend pipe, the lengthening internal thread bend pipe includes silk head and straight tube, described Construction technology includes step:Groove is vertically opened up on metope, which is characterized in that further include following steps:
Internal thread bend pipe will be lengthened to connect with feed pipe, and be laid in groove, wherein the silk head interface for lengthening internal thread bend pipe protrudes The distance range of metope is between 4 centimetres to 6 centimetres;
It is fixed to lengthen internal thread bend pipe, block silk head;
Sealed groove is completed to lengthen the installation of internal thread bend pipe;First in recess sidewall upper edge groove before fixed lengthening female elbow Length direction every 8~10 centimetres arrange a support element;
Each support element includes a pair of of elastic clip, and the end of each elastic clip is circumferential towards extension at slot opening along straight tube Extension is respectively formed, and extension has the clamping part of protrusion relative to each other;
Accordingly, the encapsulating method of the groove includes:
It fills up groove top and lengthens the gap between internal thread bend pipe;
According to the slot opening shape joints cement plate after filling up;
Installation and the matched plate of elastic clip on the cement plate poured;
Cement plate is hinged on to the bottom of the slot opening, cement plate is sealed into slot opening, clamping part is made to cooperate and is pressed from both sides The plate is held, completes the sealing.
2. platform basin installation as described in claim 1 lengthens the construction technology of internal thread bend pipe, which is characterized in that the lengthening female elbow The silk head center line of pipe to ground altitude range between 45 centimetres to 50 centimetres.
3. platform basin installation as described in claim 1 lengthens the construction technology of internal thread bend pipe, which is characterized in that after silk head is blocked First the groove is carried out again to lengthening internal thread outer surface of bent pipe coating waterproofing slurry to fill up.
4. platform basin installation as described in claim 1 lengthens the construction technology of internal thread bend pipe, which is characterized in that will lengthen internal thread Bend pipe further includes step before being fixed on groove top:Gap between groove top and silk overhead is filled with cement.
5. platform basin installation as described in claim 1 lengthens the construction technology of internal thread bend pipe, which is characterized in that before groove is filled up Further include step:
Supply water to feed pipe, test lengthen internal thread bend pipe whether leak;
If leak, leakproof repairing is carried out at leak and is retested, until test passes through.
6. platform basin installation as claimed in claim 5 lengthens the construction technology of internal thread bend pipe, which is characterized in that for being used at leak Waterproof gasket cement carries out leakproof repairing.
CN201510438947.5A 2015-07-24 2015-07-24 Platform basin installation lengthens the construction technology of internal thread bend pipe Active CN105002868B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510438947.5A CN105002868B (en) 2015-07-24 2015-07-24 Platform basin installation lengthens the construction technology of internal thread bend pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510438947.5A CN105002868B (en) 2015-07-24 2015-07-24 Platform basin installation lengthens the construction technology of internal thread bend pipe

Publications (2)

Publication Number Publication Date
CN105002868A CN105002868A (en) 2015-10-28
CN105002868B true CN105002868B (en) 2018-06-08

Family

ID=54375712

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510438947.5A Active CN105002868B (en) 2015-07-24 2015-07-24 Platform basin installation lengthens the construction technology of internal thread bend pipe

Country Status (1)

Country Link
CN (1) CN105002868B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110863540A (en) * 2019-11-27 2020-03-06 圣都家居装饰有限公司 S-shaped bent pipe drainage construction method capable of avoiding blockage

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1451821A (en) * 2002-04-17 2003-10-29 李容椿 Wall embedded water pipe tank
EP1598488A2 (en) * 2004-05-13 2005-11-23 Jürgen Klein Device for kitchen or bath
CN201561225U (en) * 2009-10-22 2010-08-25 上海皮尔萨管业有限公司 Right-angled internal-threaded elbow for concealed construction
CN201588262U (en) * 2009-08-05 2010-09-22 允登实业有限公司 Box body structure of embedded type tap
CN201713888U (en) * 2010-06-30 2011-01-19 刘宪武 Drainage pipeline system in building wall body
RU2418912C1 (en) * 2010-03-11 2011-05-20 Закрытое акционерное общество "Научно-производственное предприятие "МОРСКАЯ ТЕХНИКА" Method to assemble knife gates in chambers of sewage and water ducts of gravity flow networks
CN103590466A (en) * 2013-11-01 2014-02-19 苏州金螳螂建筑装饰股份有限公司 Cabinet mounting structure for water supply and drainage pipe on wall surface,

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1451821A (en) * 2002-04-17 2003-10-29 李容椿 Wall embedded water pipe tank
EP1598488A2 (en) * 2004-05-13 2005-11-23 Jürgen Klein Device for kitchen or bath
CN201588262U (en) * 2009-08-05 2010-09-22 允登实业有限公司 Box body structure of embedded type tap
CN201561225U (en) * 2009-10-22 2010-08-25 上海皮尔萨管业有限公司 Right-angled internal-threaded elbow for concealed construction
RU2418912C1 (en) * 2010-03-11 2011-05-20 Закрытое акционерное общество "Научно-производственное предприятие "МОРСКАЯ ТЕХНИКА" Method to assemble knife gates in chambers of sewage and water ducts of gravity flow networks
CN201713888U (en) * 2010-06-30 2011-01-19 刘宪武 Drainage pipeline system in building wall body
CN103590466A (en) * 2013-11-01 2014-02-19 苏州金螳螂建筑装饰股份有限公司 Cabinet mounting structure for water supply and drainage pipe on wall surface,

Also Published As

Publication number Publication date
CN105002868A (en) 2015-10-28

Similar Documents

Publication Publication Date Title
CN205716049U (en) Fixed wall pipe waterproof construction
CN103114863A (en) Tunnel secondary lining back arch grouting pipe reserving system
CN109853800A (en) A kind of assembly type low power consuming curtain wall system and its construction method
CN106088927A (en) Integrated door and window system and installation method thereof on prefabricated buildings PC component
CN104452949A (en) Embedded leak-proof joint
CN105002868B (en) Platform basin installation lengthens the construction technology of internal thread bend pipe
CN104358936A (en) Seepage prevention structure and method for periphery of floor-passing-through pipeline
CN203654328U (en) Assembly type water stop structure
CN109036613A (en) A kind of concrete liner steel linear water tank and its construction method
CN105672501A (en) Double U-groove and joint node structure using same
CN109750942A (en) A kind of the door and window pre-buried structure and its construction installation method of assembled architecture
CN107504277A (en) A kind of underground structure embedded wall penetration pipe water-tight device
CN108086640B (en) Connection structure of inspection port of drain pipe and pipe well and construction method thereof
CN204164532U (en) Pre-buried Matheson and Dresser joint system
CN206829623U (en) A kind of feed pipe wall ground leakproof tube seat structure
US20130343819A1 (en) Method Of Waterproofing A Containment Sump
CN210919087U (en) Concrete pipe piece caulking plugging device
CN104975686B (en) Airduct goes out the waterproofing node structure and its construction method at concrete structure hole
CN104727835B (en) A kind of tunnel-liner seam crossing percolating water antipriming and water-stop processing method
CN104358948B (en) Pre-buried Matheson and Dresser joint system
CN105020684A (en) Fixing support for outer wall lamp and installation method thereof
CN205637183U (en) Seam node structure in double -U -shaped groove and applied double -U -shaped groove
CN208702430U (en) Tunnel
CN105064682A (en) Pipe hole formwork-suspending device
CN206036410U (en) Pre -buried leak protection water is direct

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20170124

Address after: Gongshu District Hangzhou City, Zhejiang Province Road 310000 No. 589 (overseas sea Hangzhou city hall on the third floor room 801)

Applicant after: Zhejiang Shengdu Home Furnishing Decoration Co.

Address before: Hangzhou City, Zhejiang province 310014 Gongshu District Moganshan Road 1165 star Home Furnishing 4 floor D District No. 15-20

Applicant before: Hangzhou Sheng Dou Decoration Design Engineering Co., Ltd.

CB02 Change of applicant information
CB02 Change of applicant information

Address after: Gongshu District Hangzhou City, Zhejiang Province Road 310000 No. 589 (overseas sea Hangzhou city hall on the third floor room 801)

Applicant after: The Holy Home Furnishing Decoration Co.

Address before: Gongshu District Hangzhou City, Zhejiang Province Road 310000 No. 589 (overseas sea Hangzhou city hall on the third floor room 801)

Applicant before: Zhejiang Shengdu Home Furnishing Decoration Co.

GR01 Patent grant
GR01 Patent grant