CN104992265B - The appraisal procedure that firepower plant heating system valves leakage influences unit - Google Patents

The appraisal procedure that firepower plant heating system valves leakage influences unit Download PDF

Info

Publication number
CN104992265B
CN104992265B CN201510319775.XA CN201510319775A CN104992265B CN 104992265 B CN104992265 B CN 104992265B CN 201510319775 A CN201510319775 A CN 201510319775A CN 104992265 B CN104992265 B CN 104992265B
Authority
CN
China
Prior art keywords
interior
power
leakage
unit
consumption rate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510319775.XA
Other languages
Chinese (zh)
Other versions
CN104992265A (en
Inventor
吕海祯
祝令凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510319775.XA priority Critical patent/CN104992265B/en
Publication of CN104992265A publication Critical patent/CN104992265A/en
Application granted granted Critical
Publication of CN104992265B publication Critical patent/CN104992265B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Examining Or Testing Airtightness (AREA)

Abstract

The invention discloses a kind of appraisal procedures that firepower plant heating system valves leakage influences unit, including:It determines the degree of supercooling of condenser condensed water, and calculates the supercooling angle value and Condenser Design or the hot-well depression angle value ψ of first period acceptance test of going into operation0Difference;Leaking heat in calculating;Interior leaking heat is set as to the steam heat of leakage, it is calculated and is converted into the amount of interior power;According to the heat consumption rate value under the ratio and the interior quantity of power of the amount of interior power and generator power, the incrementss of unit net coal consumption rate caused by calculating interior leakage;Days running d and mark coal price lattice γ per ton is leaked in statistics, calculates economic benefit.Advantageous effect of the present invention:The incrementss of unit net coal consumption rate caused by leakage in the calculating that can be quantified, and then internally leak and quantitative assessment is made that the influence of unit economy, to determine whether that carrying out valve transformation to unit provides theoretical foundation.

Description

The appraisal procedure that firepower plant heating system valves leakage influences unit
Technical field
The present invention relates to a kind of appraisal procedures that firepower plant heating system valves leakage influences unit.
Background technology
The therrmodynamic system in thermal power plant is often referred to its comprehensive therrmodynamic system, is relative to design principle therrmodynamic system For, compared with the principled thermal system for emphasizing economy, comprehensive therrmodynamic system in order to ensure unit starting, stopping, Ensure unit safety in the case of load change, accident when normal operation, is provided with very more valves, makes unit safety and fortune Row flexibility greatly improves.These valves according to it by working medium whether go out therrmodynamic system and can be divided into two classes, one kind is System, referred to as leak outside valve, another kind of can not to be that system, mainly steam turbine side return to Condenser's Hot Well, referred to as interior Leak valve.
For first kind valve, that is, the valve to leak outside can measure its quality by leak rate test, no longer in detail Thin narration.The valve of interior leakage is then unable to measure, according to previous experiences, the influence of the valve of interior leakage to unit net coal consumption rate It is larger, but due to can not be measured to it, influence of the valve for leading to not leak in quantitative measuring and calculating to unit economy, Can not for whether to unit carry out valve transformation theory support is provided.
Invention content
The purpose of the present invention is exactly to solve the above-mentioned problems, to provide a kind of firepower plant heating system valves leakage pair The appraisal procedure that unit influences, this method can quantitatively calculate influence of the interior leakage to unit net coal consumption rate, be Unit Economic Property assessment provide reference frame.
To achieve the above object, the present invention uses following technical proposals:
A kind of appraisal procedure that firepower plant heating system valves leakage influences unit, includes the following steps:
Step 1:Unit condensing water temperature and the corresponding saturation temperature of exhaust steam pressure are acquired, determines condenser condensed water Degree of supercooling, and calculate the supercooling angle value and Condenser Design or the hot-well depression angle value ψ of first period acceptance test of going into operation0's Difference;
Step 2:The condensing water flow of Condenser's Hot Well is measured, interior leaking heat is calculated;
Step 3:Interior leaking heat is set as to the steam heat of leakage, it is calculated and is converted into the amount of interior power;
Step 4:According to the heat consumption rate value under the ratio and the interior quantity of power of the amount of interior power and generator power, meter The incrementss of unit net coal consumption rate caused by leakage in calculating;
Step 5:Days running d and mark coal price lattice γ per ton is leaked in statistics, calculates economic benefit.
In the step 1, the determination method of the degree of supercooling ψ of condenser condensed water is specially:
ψ=ts-t;
Wherein, t is condensing water temperature, tsFor the corresponding saturation temperature of exhaust steam pressure.
In the step 2, the computational methods of interior leaking heat are specially:
Q1=cD Δs t;
Wherein, c is the specific heat of water, and D is condensing water flow, Δ t=ψ-ψ0, it is the degree of supercooling and condensing of condenser condensed water Device designs or the difference of the hot-well depression angle value for period acceptance test of just going into operation.
In the step 3, the specific method for calculating the amount for being converted into interior power is:
Wherein, Q1For interior leaking heat, WrFor the amount of interior power.
In the step 4, the method for the incrementss of unit net coal consumption rate is specially caused by calculating interior leakage:
Wherein, WrFor the amount of interior power, W is generator power, HtFor the heat consumption rate under the generator power, ηglFor boiler Efficiency, ηgdFor pipeline efficiency,For station service power consumption rate.
In the step 5, the method for calculating economic benefit is specially:
X=Δs g × d × 24 × W × γ/10^8
Wherein, Δ g is the incrementss of unit net coal consumption rate caused by interior leakage, and d is interior leakage days running, and W is generator Power, γ are the price of mark coal per ton.
The beneficial effects of the invention are as follows:
The incrementss of unit net coal consumption rate caused by leakage in the calculating that the present invention can quantify, and then internally leak to unit The influence of economy is made that quantitative assessment, enables the advance fund funding of power plant's initial estimate valve transformation and the economy of transformation Effect, to determine whether that carrying out valve transformation to unit provides theoretical foundation.
Description of the drawings
Fig. 1 is the method for the present invention flow chart.
Specific implementation mode
The following further describes the present invention with reference to the drawings.
The hydrophobic water cooling that is cooled in condenser of steam discharge, the low-pressure heater of turbine low pressure cylinder, condenses into water and collects Into hot well, due to valve imprecision, leakage steam is directly pooled in Condenser's Hot Well in steam turbine pusher side, to condensed water It is heated, enters low-pressure heater after boosting by condensate pump in the form of hot well exports condensed water.
The condensate undercooling of Condenser Design does not consider influence of the interior leaking heat to temperature rise of condensate generally.Therefore, it coagulates The Wen Sheng born water needs to be calculated according to the condensate undercooling of actual measurement and the degree of supercooling of design.It is steamed due to being unable to measure interior leakage The quality and enthalpy of vapour, the heat that the present invention is internally leaked rise to estimate by condensing water flow and temperature.
Flow passage component of the interior leaking heat from steam turbine makes power in steam turbine reduce, and generator active power reduces, hair Electricity is reduced, and constant in circulation heat, unit heat consumption rate accordingly increases, due to station-service electricity, boiler efficiency, pipeline Efficiency is constant, and corresponding net coal consumption rate increases, and since power supply volume is decided by user, when power supply volume is constant, coal consumption increases.
If investment undergoes technological transformation, valves leakage is eliminated, the heat of interior leakage is made to return to Turbine Flow Path, steamer Power increases in machine, and generator active power increases, and station-service electricity, boiler efficiency, pipeline efficiency are constant, corresponding net coal consumption rate It reduces, when power supply volume is constant, coal consumption reduces.The cost conversion of coal in power plant cost reduction, reduction is enterprise profit.
Therefore, interior leaking heat is determined to quantitatively calculate interior influence of the leakage for unit operation economy, Jin Erwei Whether carry out valve transformation and theoretical foundation is provided.
The present invention proposes a kind of appraisal procedure that firepower plant heating system valves leakage influences unit, such as Fig. 1 institutes Show, includes the following steps:
Step 1:Unit condensing water temperature and the corresponding saturation temperature of exhaust steam pressure are acquired, determines condenser condensed water Degree of supercooling, and calculate the supercooling angle value and Condenser Design or the hot-well depression angle value ψ of first period acceptance test of going into operation0's Difference;
The determination method of the degree of supercooling ψ of condenser condensed water is specially:
ψ=ts-t;
Wherein, t is condensing water temperature, tsFor the corresponding saturation temperature of exhaust steam pressure.
Step 2:The condensing water flow of Condenser's Hot Well is measured, interior leaking heat is calculated;
The computational methods of interior leaking heat are specially:
Q1=cD Δs t;
Wherein, c is the specific heat of water, and D is condensing water flow, Δ t=ψ-ψ0, it is the degree of supercooling and condensing of condenser condensed water Device designs or the difference of the hot-well depression angle value for period acceptance test of just going into operation.
Step 3:Interior leaking heat is set as to the steam heat of leakage, it is calculated and is converted into the amount of interior power;
Calculating the specific method of amount for being converted into interior power is:
Wherein, Q1For interior leaking heat, WrFor the amount of interior power.
Step 4:According to the heat consumption rate value under the ratio and the interior quantity of power of the amount of interior power and generator power, meter The incrementss of unit net coal consumption rate caused by leakage in calculating;
The method of the incrementss of unit net coal consumption rate is specially caused by leakage in calculating:
Wherein, WrFor the amount of interior power, W is generator power, HtFor the heat consumption rate under the generator power, ηglFor boiler Efficiency, ηgdFor pipeline efficiency,For station service power consumption rate.
Step 5:Days running d and mark coal price lattice γ per ton is leaked in statistics, calculates economic benefit.
Calculate economic benefit method be specially:
X=Δs g × d × 24 × W × γ/10^8
Wherein, Δ g is the incrementss of unit net coal consumption rate caused by interior leakage, and d is interior leakage days running, and W is generator Power, γ are the price of mark coal per ton.
Test example:
Certain factory 300MW units, 75%THA operating modes Computer group Condenser's Hot Well is subcooled in thermal test before overhaul Degree is ψ=- 2.08 DEG C, and the condensing water flow for going out hot well is D=604.707t/h, and it is t=to go out hot well condensing water temperature 27.38 DEG C, the degree of supercooling according to design condensed water is ψ0=1.2 DEG C, generator power W=250MW, unit heat consumption rate is Ht= 8192kJ/kW.h.Station service power consumption rateBoiler efficiency is ηgl=92.89%, pipeline efficiency is ηgd=99%, according to inspection It looks into, all steam of valve of interior leakage, unit is run d=1200 days altogether, and unit average load rate is 75%, mark coal price lattice per ton γ=550 yuan.
Interior leakage steam makes condensed water increase Δ t=ψ-ψ0=1.2-2.08=3.28 DEG C;
Interior leaking heat is Q1=cD Δs t=604.707 × 3.28 × 4.1868=8304.26MJ/h;
Interior leaking heat comes from Turbine Flow Path, and the work(as done less is:
Net coal consumption rate is set to increase:
Unit is run d=1200 days altogether, and unit average load rate is 75%, mark coal price lattice per ton γ=550 yuan/ton.
The more consumption mark coal costs estimated as unit of currency:
=Δ g × d × 24 × W × γ/10^8
=2.99 × 1200 × 24 × 250 × 550/10^8Wan Yuan
=118.404 ten thousand yuan
The cost of investment being transformed with valve in conjunction with the consumption mark coal cost of estimation, it is determined whether valve is transformed.
Above-mentioned, although the foregoing specific embodiments of the present invention is described with reference to the accompanying drawings, not protects model to the present invention The limitation enclosed, those skilled in the art should understand that, based on the technical solutions of the present invention, those skilled in the art are not Need to make the creative labor the various modifications or changes that can be made still within protection scope of the present invention.

Claims (2)

1. a kind of appraisal procedure that firepower plant heating system valves leakage influences unit, characterized in that including following step Suddenly:
Step 1:Unit condensing water temperature and the corresponding saturation temperature of exhaust steam pressure are acquired, determines the supercooling of condenser condensed water Degree, and calculate the supercooling angle value and Condenser Design or the hot-well depression angle value ψ of first period acceptance test of going into operation0Difference Value;
Step 2:The condensing water flow of Condenser's Hot Well is measured, interior leaking heat is calculated;
Step 3:Interior leaking heat is set as to the steam heat of leakage, it is calculated and is converted into the amount of interior power;
Step 4:According to the heat consumption rate value under the ratio and the interior quantity of power of the amount of interior power and generator power, in calculating The incrementss of unit net coal consumption rate caused by leakage;
Step 5:Days running d and mark coal price lattice γ per ton is leaked in statistics, calculates economic benefit;
In the step 1, the determination method of the degree of supercooling ψ of condenser condensed water is specially:
ψ=ts-t;
Wherein, t is condensing water temperature, tsFor the corresponding saturation temperature of exhaust steam pressure;
In the step 2, the computational methods of interior leaking heat are specially:
Q1=cD Δs t;
Wherein, c is the specific heat of water, and D is condensing water flow, Δ t=ψ-ψ0, set with condenser for the degree of supercooling of condenser condensed water The difference of the hot-well depression angle value of meter or period acceptance test of just going into operation;
In the step 3, the specific method for calculating the amount for being converted into interior power is:
Wherein, Q1For interior leaking heat, WrFor the amount of interior power;
In the step 4, the method for the incrementss of unit net coal consumption rate is specially caused by calculating interior leakage:
Wherein, WrFor the amount of interior power, W is generator power, HtFor the heat consumption rate under the generator power, ηglFor boiler efficiency, ηgdFor pipeline efficiency,For station service power consumption rate.
2. a kind of appraisal procedure that firepower plant heating system valves leakage influences unit as described in claim 1, It is characterized in, in the step 5, the method for calculating economic benefit is specially:
X=Δs g × d × 24 × W × γ/10^8
Wherein, Δ g is the incrementss of unit net coal consumption rate caused by interior leakage, and d is interior leakage days running, and W is generator power, γ is the price of mark coal per ton.
CN201510319775.XA 2015-06-11 2015-06-11 The appraisal procedure that firepower plant heating system valves leakage influences unit Active CN104992265B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510319775.XA CN104992265B (en) 2015-06-11 2015-06-11 The appraisal procedure that firepower plant heating system valves leakage influences unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510319775.XA CN104992265B (en) 2015-06-11 2015-06-11 The appraisal procedure that firepower plant heating system valves leakage influences unit

Publications (2)

Publication Number Publication Date
CN104992265A CN104992265A (en) 2015-10-21
CN104992265B true CN104992265B (en) 2018-09-07

Family

ID=54304075

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510319775.XA Active CN104992265B (en) 2015-06-11 2015-06-11 The appraisal procedure that firepower plant heating system valves leakage influences unit

Country Status (1)

Country Link
CN (1) CN104992265B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112749205B (en) * 2020-12-09 2023-03-03 华能陕西发电有限公司 System and method for acquiring relation curve between power of coal-fired power generating unit and power supply coal consumption

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103942732A (en) * 2014-04-24 2014-07-23 国家电网公司 Economic evaluation method of modification effects of heat supply technology of pure condensing steam turbine unit

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103942732A (en) * 2014-04-24 2014-07-23 国家电网公司 Economic evaluation method of modification effects of heat supply technology of pure condensing steam turbine unit

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
"600MW超临界汽轮机热力性能诊断及供热分析";邓伟;《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》;20130715;第C042-621页 *
"电厂热力系统热经济性在线监测组态软件设计及计算模型";王萍;《中国优秀博硕士学位论文全文数据库 (硕士) 工程科技Ⅱ辑》;20050315;全文 *
"电厂热力系统设备性能监测与应用研究";苏晓静;《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》;20110915;全文 *
"电站机组运行优化指导系统平台设计";毕克;《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》;20090315;第C039-17页 *

Also Published As

Publication number Publication date
CN104992265A (en) 2015-10-21

Similar Documents

Publication Publication Date Title
CN102967464B (en) The improved method of evaluating performance of condensing turbine high back pressure
Ray et al. Exergy-based performance analysis for proper O&M decisions in a steam power plant
CN105201564B (en) Main-steam-flow-based steam turbine sliding pressure optimization control method
CN107201921B (en) Steam turbine heat consumption rate online monitoring system and measuring method
CN109325255B (en) Optimal vacuum on-line guiding system of wet cooling steam turbine based on fixed power
CN113719325B (en) Improved method for variable back pressure characteristic test of steam turbine
CN108691585B (en) Method for calculating low pressure cylinder efficiency of condensing steam turbine
CN111664504B (en) Method for predicting influence of turbine thermodynamic system micro-increment variable on turbine heat consumption
CN103225521A (en) Air cooling steam turbine cold end optimization method
CN111400875B (en) Steam turbine unit operation economy evaluation method and system
CN104992265B (en) The appraisal procedure that firepower plant heating system valves leakage influences unit
CN112127957B (en) Method for measuring main steam flow of steam turbine of thermal power plant
CN104459542A (en) Heat rate measurement method for reheating regeneration combined cycle unit
CN105787195B (en) Method for calculating steam inlet flow of external steam cooler in feedwater heating system
CN104483152B (en) The heat consumption rate assay method of non-reheat backheat combined-circulation unit
CN104636593B (en) Backheat work done ratio and backheat ratio of profit increase assay method during reheating embrittlement having heaters radiation loss
CN207623031U (en) A kind of condenser duty on-line monitoring system
Zabuga et al. Research based on mathematical modeling of CHP-10 power unit No 5 “Baikal Energy Company” LLC to assess the efficiency of its modernization
CN110131919B (en) Method for recovering waste heat of cooling circulating water
Vodeniktov et al. Control of condensate dissolved oxygen in steam surface condenser. Reconstruction experience
CN112100751A (en) Method and system for calculating influence of backpressure change of extraction and coagulation unit on unit power
CN109187036A (en) A kind of piping-main scheme back pressure turbine main steam flow calculation method
CN104462841B (en) Backheat work done ratio and backheat ratio of profit increase assay method when non-reheat unit has electrodynamic pump
CN216847679U (en) System for monitoring steam turbine exhaust dryness based on circulating cooling water
CN102735449A (en) Method for detecting influence of reheated attemperating water provided by center tap of feeding pump on performance of unit

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee after: SHANDONG ELECTRIC POWER Research Institute

Patentee after: STATE GRID CORPORATION OF CHINA

Address before: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee before: SHANDONG ELECTRIC POWER Research Institute

Patentee before: State Grid Corporation of China

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20220127

Address after: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee after: ELECTRIC POWER RESEARCH INSTITUTE OF STATE GRID SHANDONG ELECTRIC POWER Co.

Patentee after: STATE GRID CORPORATION OF CHINA

Address before: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee before: SHANDONG ELECTRIC POWER Research Institute

Patentee before: STATE GRID CORPORATION OF CHINA

TR01 Transfer of patent right