CN104988881A - Ocean engineering equipment module construction technology - Google Patents

Ocean engineering equipment module construction technology Download PDF

Info

Publication number
CN104988881A
CN104988881A CN201510267531.1A CN201510267531A CN104988881A CN 104988881 A CN104988881 A CN 104988881A CN 201510267531 A CN201510267531 A CN 201510267531A CN 104988881 A CN104988881 A CN 104988881A
Authority
CN
China
Prior art keywords
module
construction
debugging
equipment
requirements
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510267531.1A
Other languages
Chinese (zh)
Other versions
CN104988881B (en
Inventor
段凤江
罗子良
王振刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong COSCO Shipping Engineering Co., Ltd.
Original Assignee
Cosco Shipyard Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cosco Shipyard Group Co Ltd filed Critical Cosco Shipyard Group Co Ltd
Priority to CN201510267531.1A priority Critical patent/CN104988881B/en
Publication of CN104988881A publication Critical patent/CN104988881A/en
Application granted granted Critical
Publication of CN104988881B publication Critical patent/CN104988881B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses an ocean engineering equipment module construction technology. The module construction technology comprises a step of module construction, a step of module transporting and hoisting, and a step of module debugging. The module construction technology comprehensively takes the typical module structure, the hoisting capability and the construction process into account, optimizes a module construction scheme and process, and instructs the actual construction of a module. Through land construction and integral installation for the typical module, a construction period can be shortened, the reworking rate can be decreased, and the cost can be reduced. On the basis of the classification for structural forms of the typical module, the flow is straightened out, the construction scheme is set up, the production is organized, the construction for the module is targetedly instructed, and the efficiency is further improved.

Description

A kind of marine engineering equipment module build process
Technical field
The present invention relates to marine engineering equipment field, particularly relate to a kind of marine engineering equipment module build process.
Background technology
Ocean engineering refers to develop, utilize, protect, recover for the purpose of marine resources, and project subject is positioned at the newly-built, renovating and enlarging engineering of coastline to extra large side.Specifically comprise: Perioperative cardiac events, marine dam construction, man-made island, sea and seabed goods and materials storage facilities, Oversea bridge, seabed tunnel engineering, seabed pipeline, seabed electricity (light) cable engineering, oceanic mineral resources exploration and development and ancillary works thereof, marine tidal power station, wave energy power station, the marine energies such as temperature difference power station develop engineering, large-scale marine park, Artificial Fish-Reefs, salt pan, the multipurpose use of sea water engineerings such as desalinization, marine amusement and motion, sight exploitation engineering, and other ocean engineerings that national marine authorities specify together with environmental protection authorities of State Council.
The various main equipments adopted in ocean engineering are due to its handling difficulty in use, building course, and cause and consume comparatively farm labourer's phase in general ocean engineering, its rework rate is high simultaneously, and it is also problem to be solved in a hurry in this area that cost remains high.
Summary of the invention
In order to solve the problem, the invention provides one and considering the factors such as typical module structure, handling ability, construction technology, optimize module construction program and flow process, instruct the technical scheme of the actual construction of module:
A kind of marine engineering equipment module build process, comprises module construction, movement lifting and modular debugging three steps;
Module is built and is comprised module construction operation preparation and concrete operation;
The concrete steps of movement lifting are:
A) module operation of weighing prepares and concrete operation;
B) module movement operation prepares and concrete operation;
C) module hoisting operation prepares and concrete operation;
The concrete steps of modular debugging are;
(1) safety requirements and preparation is debugged;
(2) debugging tool instrument and instrument prepare;
(3) debugging efforts prepares;
(4) the corresponding file that applies for checking and examination in check system;
(5) temporary power equipment is debugged;
(6) debug in advance;
(7) module subsystem debugging;
(8) intermodule system integration and test;
(9) whole platform testing, relates to module and the combination of non-modular system;
(10) requirement of health, safety and environment is met.
As preferably, module is built operation and is prepared to comprise the following steps:
1) construction method is chosen according to modular structure form;
2) module build the side is selected and moulding bed layout, place election is carried out according to module whole size, weight, the load bearing requirements of all kinds of handling apparatus under for the national games turn of full load, place weight capacity, adopt angle steel or i iron as moulding bed, moulding bed referrer module is weighed, movement and total group require with stent-type or to be flatly connected with ground;
3) segmentation division and drawing technical papers of being correlated with prepare, and distinguish to structure division, machine dress and piping, electric part and in-built part the preparation carrying out drawing and technical papers;
4) work out precision controlling scheme, comprehensively work out the appointment that precision controlling scheme and requirement, surplus compensation rate control chart, establishment test stone and measuring method and accuracy standard carry out precision controlling scheme;
5) material prepare, capital equipment, equipment and materials are ordered goods, and to mechanical drawing and certificate urge want, simultaneously coordinate goods and materials storage with dispensing;
6) production schedule prepares, and produces construction schedule formulate technology research project, Health security system, target cost plan, design and the plan of publishing picture of drawing technological document, material installation procurement plan and module;
7) production management prepares, and sets up or improve module production management team and policy is built in establishment, receives phase table according to the overall balance of capacity loading adjustment main material equipment standard, and advance fitting-out plan, confirm that general inspection can issue order to commence by requirements for starting construction;
8) personnel prepare and response system;
9) HSE General Requirements.
As preferably, module is built concrete operation and is comprised the following steps:
A) steel surface pretreatment, performs according to the technical requirements that owner submits to;
B) blanking, cutting, pedestal General Requirements machining, to the support having required precision, its structural component should adopt Numerical control cutting, all gas cutting edges should arrange, remove slag and burr, to verge of opening application wheel deburring roundings such as manhole, passage, windows, the roughness of the component free margins of other cutting and processing should meet the requirement of regulation
C) prefabricated Ground arrangement;
D) fragment and group stand prefabricated;
E) advance fitting-out, steel work hot-working, pipeline, electrically support, turbine, electric fixtures, base, part pipeline, iron Xi part, handrail and railing are installed;
F) segmentation sanding paint;
G) equipment component and pipeline prepackage
H) welding quality and section construction precision are checked and accepted, and carry out NDT flaw detection according to textural classification;
I) precision process controls, and precision process controls to carry out management and control with the step of laying-down cutting → prefabricate → close up greatly → equipment installations → movement lifting, and checks and control according to code requirement, adjusts by code requirement overproof position;
J) size Control, excision remainder punching;
K) module is closed up Ground arrangement, is made and arrange moulding bed;
L) entirety is closed up;
M) main equipment and Accessory Members are installed;
N) final touch-up paint.
As preferably, module weighs concrete operation for installing the measuring system such as the hydraulic jacking system such as hydraulic cylinder, hydraulic power source and LOAD CELLS, debugging hydraulic jacking system and measuring system, start hydraulic jacking system and measuring system, hydraulic jacking system is stagnated when each hydraulic cylinder pressure reaches requirement, after system is steady, primer fluid cylinder pressure makes platform depart from ground simultaneously, stagnates hydraulic jacking system, checks that each support of confirmation is not connected with ground; If any connection, start this support hydraulic pressure system, make module depart from support ground and reach requirement distance, utilize laser transit to carry out horizontal survey, adjustment position of platform, make it be in level, after system is steady, carries out pressurize and weigh, image data, module is weighed and can repeatedly be carried out as required, at every turn all from zero-bit jacking to predetermined altitude, and separated in time survey data after leveling.
As preferably, module hoisting operation prepares to comprise modular structure finite element analysis, suspension centre strength check, the determination of weight center of gravity, hanger and lifting arrangement diagram, crane barge selects and simulation, hanger strength check, the selection determining hoisting, Current Collector Sleave, layout and installation drawing, plant area arrange and boats and ships stop layout, auxiliary tug and barge information, interference checking, to meet suspended object, crane, pitch requirements between arm and Current Collector Sleave, the preparation of Current Collector Sleave certificate and close to crane barge stability during limit lift heavy.
As preferably, debugging safety requirements and preparing content comprise:
1. commissioning staff carries Walkie talkie, and instruction is clear, unimpeded, strengthens inspection and link up in debug process;
2. high-tension electricity relates to equipment, region isolates, and forbids that unrelated person enters;
3. need to obtain safety before debugging and be responsible for license;
4. on-site cleanup work is carried out after debugging efforts;
5. protection against electric shock: related electric commissioning staff confirms the rear power transmission of safety, simultaneously to relevant device and zone isolation;
6. personnel fall: two-handed work system, be equipped with the safety equipment meeting safety in production;
7. check around without dangerous matter sources, withdraw all personnel irrelevant with debugging, forbid that unrelated person enters debugging region, and put up warning sign;
8. debugging relates to region and carries out special messenger and patrol and examine;
9. emergency escape passage is set.
Beneficial effect of the present invention is:
The present invention considers the factors such as typical module structure, handling ability, construction technology, optimizes module construction program and flow process, instructs the actual construction of module.By realizing land formation, the integral installation of typical module, thus the target reaching shortening production cycle, reduce rework rate, reduce costs.The form of structure of typical module classified, makes flow process on this basis in order, draft construction program, organize and produce, accomplished the construction instructing module targetedly, further increased efficiency.By optimization and the reinforcement technological preparation in early stage of construction program, flow process, reduce difficulty of construction, shortening production cycle.By improving the advance fitting-out of module, three-dimensional operation on platform is become the plane operation of land, substantially improve operating environment, impel the rationalization of construction work specialization and fitting-out work further, and to sophistication and special tooling, set up fixing production line and special assembly section very favourable.
Accompanying drawing explanation
Fig. 1 is operation process chart of the present invention.
Detailed description of the invention
For making goal of the invention of the present invention, technical scheme and advantage clearly, below in conjunction with accompanying drawing, embodiments of the present invention are described in further detail.
As shown in Figure 1, marine engineering equipment module build process, comprises module construction, movement lifting and modular debugging three steps;
Module is built and is comprised module construction operation preparation and concrete operation;
The concrete steps of movement lifting are:
A) module operation of weighing prepares and concrete operation;
B) module movement operation prepares and concrete operation;
C) module hoisting operation prepares and concrete operation;
The concrete steps of modular debugging are;
(1) safety requirements and preparation is debugged;
(2) debugging tool instrument and instrument prepare;
(3) debugging efforts prepares;
(4) the corresponding file that applies for checking and examination in check system;
(5) temporary power equipment is debugged;
(6) debug in advance;
(7) module subsystem debugging;
(8) intermodule system integration and test;
(9) whole platform testing, relates to module and the combination of non-modular system;
(10) requirement of health, safety and environment is met.
This process considers the factors such as typical module structure, handling ability, construction technology, optimizes module construction program and flow process, instructs the actual construction of module.By realizing land formation, the integral installation of typical module, thus the target reaching shortening production cycle, reduce rework rate, reduce costs.
Module is wherein built operation and is prepared to comprise the following steps:
1) construction method is chosen according to modular structure form;
2) module build the side is selected and moulding bed layout, place election is carried out according to module whole size, weight, the load bearing requirements of all kinds of handling apparatus under for the national games turn of full load, place weight capacity, adopt angle steel or i iron as moulding bed, moulding bed referrer module is weighed, movement and total group require with stent-type or to be flatly connected with ground;
3) segmentation division and drawing technical papers of being correlated with prepare, and distinguish to structure division, machine dress and piping, electric part and in-built part the preparation carrying out drawing and technical papers;
4) work out precision controlling scheme, comprehensively work out the appointment that precision controlling scheme and requirement, surplus compensation rate control chart, establishment test stone and measuring method and accuracy standard carry out precision controlling scheme;
5) material prepare, capital equipment, equipment and materials are ordered goods, and to mechanical drawing and certificate urge want, simultaneously coordinate goods and materials storage with dispensing;
6) production schedule prepares, and produces construction schedule formulate technology research project, Health security system, target cost plan, design and the plan of publishing picture of drawing technological document, material installation procurement plan and module;
7) production management prepares, and sets up or improve module production management team and policy is built in establishment, receives phase table according to the overall balance of capacity loading adjustment main material equipment standard, and advance fitting-out plan, confirm that general inspection can issue order to commence by requirements for starting construction;
8) personnel prepare and response system;
9) HSE General Requirements.
Module is built concrete operation and is comprised the following steps:
A) steel surface pretreatment, performs according to the technical requirements that owner submits to;
B) blanking, cutting, pedestal General Requirements machining, to the support having required precision, its structural component should adopt Numerical control cutting, all gas cutting edges should arrange, remove slag and burr, to verge of opening application wheel deburring roundings such as manhole, passage, windows, the roughness of the component free margins of other cutting and processing should meet the requirement of regulation
C) prefabricated Ground arrangement;
D) fragment and group stand prefabricated;
E) advance fitting-out, steel work hot-working, pipeline, electrically support, turbine, electric fixtures, base, part pipeline, iron Xi part, handrail and railing are installed;
F) segmentation sanding paint;
G) equipment component and pipeline prepackage
H) welding quality and section construction precision are checked and accepted, and carry out NDT flaw detection according to textural classification;
I) precision process controls, and precision process controls to carry out management and control with the step of laying-down cutting → prefabricate → close up greatly → equipment installations → movement lifting, and checks and control according to code requirement, adjusts by code requirement overproof position;
J) size Control, excision remainder punching;
K) module is closed up Ground arrangement, is made and arrange moulding bed;
L) entirety is closed up;
M) main equipment and Accessory Members are installed;
N) final touch-up paint.
Simultaneously, module weighs concrete operation for installing the measuring system such as the hydraulic jacking system such as hydraulic cylinder, hydraulic power source and LOAD CELLS, debugging hydraulic jacking system and measuring system, start hydraulic jacking system and measuring system, hydraulic jacking system is stagnated when each hydraulic cylinder pressure reaches requirement, after system is steady, primer fluid cylinder pressure makes platform depart from ground simultaneously, stagnates hydraulic jacking system, checks that each support of confirmation is not connected with ground; If any connection, start this support hydraulic pressure system, make module depart from support ground and reach requirement distance, utilize laser transit to carry out horizontal survey, adjustment position of platform, make it be in level, after system is steady, carries out pressurize and weigh, image data, module is weighed and can repeatedly be carried out as required, at every turn all from zero-bit jacking to predetermined altitude, and separated in time survey data after leveling.
And, module hoisting operation prepares to comprise modular structure finite element analysis, suspension centre strength check, the determination of weight center of gravity, hanger and lifting arrangement diagram, crane barge selects and simulation, hanger strength check, the selection determining hoisting, Current Collector Sleave, layout and installation drawing, plant area arrange and boats and ships stop layout, auxiliary tug and barge information, interference checking, to meet suspended object, crane, pitch requirements between arm and Current Collector Sleave, the preparation of Current Collector Sleave certificate and close to crane barge stability during limit lift heavy.
Debugging safety requirements and preparing content comprise:
1. commissioning staff carries Walkie talkie, and instruction is clear, unimpeded, strengthens inspection and link up in debug process;
2. high-tension electricity relates to equipment, region isolates, and forbids that unrelated person enters;
3. need to obtain safety before debugging and be responsible for license;
4. on-site cleanup work is carried out after debugging efforts;
5. protection against electric shock: related electric commissioning staff confirms the rear power transmission of safety, simultaneously to relevant device and zone isolation;
6. personnel fall: two-handed work system, be equipped with the safety equipment meeting safety in production;
7. check around without dangerous matter sources, withdraw all personnel irrelevant with debugging, forbid that unrelated person enters debugging region, and put up warning sign;
8. debugging relates to region and carries out special messenger and patrol and examine;
9. emergency escape passage is set.
Thus make the form of structure of this technology mode to typical module classify, make flow process on this basis in order, draft construction program, organize and produce, accomplished the construction instructing module targetedly, further increased efficiency.By optimization and the reinforcement technological preparation in early stage of construction program, flow process, reduce difficulty of construction, shortening production cycle.By improving the advance fitting-out of module, three-dimensional operation on platform is become the plane operation of land, substantially improve operating environment, impel the rationalization of construction work specialization and fitting-out work further, and to sophistication and special tooling, set up fixing production line and special assembly section very favourable.
Above-described embodiment is preferred embodiment of the present invention; it is not the restriction to technical solution of the present invention; as long as without the technical scheme that creative work can realize on the basis of above-described embodiment, all should be considered as falling within the scope of the rights protection of patent of the present invention.

Claims (6)

1. a marine engineering equipment module build process, is characterized in that: comprise module construction, movement lifting and modular debugging three steps;
Described module is built and is comprised module construction operation preparation and concrete operation;
The concrete steps of described movement lifting are:
A) module operation of weighing prepares and concrete operation;
B) module movement operation prepares and concrete operation;
C) module hoisting operation prepares and concrete operation;
The concrete steps of described modular debugging are:
(1) safety requirements and preparation is debugged;
(2) debugging tool instrument and instrument prepare;
(3) debugging efforts prepares;
(4) the corresponding file that applies for checking and examination in check system;
(5) temporary power equipment is debugged;
(6) debug in advance;
(7) module subsystem debugging;
(8) intermodule system integration and test;
(9) whole platform testing, relates to module and the combination of non-modular system;
(10) requirement of health, safety and environment is met.
2. a kind of marine engineering equipment module build process according to claim 1, is characterized in that: described module is built operation and prepared to comprise the following steps:
1) construction method is chosen according to modular structure form;
2) module build the side is selected and moulding bed layout, place election is carried out according to module whole size, weight, the load bearing requirements of all kinds of handling apparatus under for the national games turn of full load, place weight capacity, adopt angle steel or i iron as moulding bed, moulding bed referrer module is weighed, movement and total group require with stent-type or to be flatly connected with ground;
3) segmentation division and drawing technical papers of being correlated with prepare, and distinguish to structure division, machine dress and piping, electric part and in-built part the preparation carrying out drawing and technical papers;
4) work out precision controlling scheme, comprehensively work out the appointment that precision controlling scheme and requirement, surplus compensation rate control chart, establishment test stone and measuring method and accuracy standard carry out precision controlling scheme;
5) material prepare, capital equipment, equipment and materials are ordered goods, and to mechanical drawing and certificate urge want, simultaneously coordinate goods and materials storage with dispensing;
6) production schedule prepares, and produces construction schedule formulate technology research project, Health security system, target cost plan, design and the plan of publishing picture of drawing technological document, material installation procurement plan and module;
7) production management prepares, and sets up or improve module production management team and policy is built in establishment, receives phase table according to the overall balance of capacity loading adjustment main material equipment standard, and advance fitting-out plan, confirm that general inspection can issue order to commence by requirements for starting construction;
8) personnel prepare and response system;
9) HSE General Requirements.
3. a kind of marine engineering equipment module build process according to claim 1, is characterized in that: described module is built concrete operation and comprised the following steps:
A) steel surface pretreatment, performs according to the technical requirements that owner submits to;
B) blanking, cutting, pedestal General Requirements machining, to the support having required precision, its structural component should adopt Numerical control cutting, all gas cutting edges should arrange, remove slag and burr, to verge of opening application wheel deburring roundings such as manhole, passage, windows, the roughness of the component free margins of other cutting and processing should meet the requirement of regulation
C) prefabricated Ground arrangement;
D) fragment and group stand prefabricated;
E) advance fitting-out, steel work hot-working, pipeline, electrically support, turbine, electric fixtures, base, part pipeline, iron Xi part, handrail and railing are installed;
F) segmentation sanding paint;
G) equipment component and pipeline prepackage
H) welding quality and section construction precision are checked and accepted, and carry out NDT flaw detection according to textural classification;
I) precision process controls, and precision process controls to carry out management and control with the step of laying-down cutting → prefabricate → close up greatly → equipment installations → movement lifting, and checks and control according to code requirement, adjusts by code requirement overproof position;
J) size Control, excision remainder punching;
K) module is closed up Ground arrangement, is made and arrange moulding bed;
L) entirety is closed up;
M) main equipment and Accessory Members are installed;
N) final touch-up paint.
4. a kind of marine engineering equipment module build process according to claim 1, it is characterized in that: described module weighs concrete operation for installing the measuring system such as the hydraulic jacking system such as hydraulic cylinder, hydraulic power source and LOAD CELLS, debugging hydraulic jacking system and measuring system, start hydraulic jacking system and measuring system, hydraulic jacking system is stagnated when each hydraulic cylinder pressure reaches requirement, after system is steady, primer fluid cylinder pressure makes platform depart from ground simultaneously, stagnate hydraulic jacking system, check and confirm that each support is not connected with ground; If any connection, start this support hydraulic pressure system, make module depart from support ground and reach requirement distance, utilize laser transit to carry out horizontal survey, adjustment position of platform, make it be in level, after system is steady, carries out pressurize and weigh, image data, module is weighed and can repeatedly be carried out as required, at every turn all from zero-bit jacking to predetermined altitude, and separated in time survey data after leveling.
5. a kind of marine engineering equipment module build process according to claim 1, it is characterized in that: described module hoisting operation prepares to comprise modular structure finite element analysis, suspension centre strength check, the determination of weight center of gravity, hanger and lifting arrangement diagram, crane barge is selected and simulation, hanger strength check, determine hoisting, the selection of Current Collector Sleave, arrange and installation drawing, plant area arranges and layout stopped by boats and ships, auxiliary tug and barge information, interference checking, to meet suspended object, crane, pitch requirements between arm and Current Collector Sleave, the preparation of Current Collector Sleave certificate and close to crane barge stability during limit lift heavy.
6. a kind of marine engineering equipment module build process according to claim 1, is characterized in that: described debugging safety requirements and preparing content comprise:
1. commissioning staff carries Walkie talkie, and instruction is clear, unimpeded, strengthens inspection and link up in debug process;
2. high-tension electricity relates to equipment, region isolates, and forbids that unrelated person enters;
3. need to obtain safety before debugging and be responsible for license;
4. on-site cleanup work is carried out after debugging efforts;
5. protection against electric shock: related electric commissioning staff confirms the rear power transmission of safety, simultaneously to relevant device and zone isolation;
6. personnel fall: two-handed work system, be equipped with the safety equipment meeting safety in production;
7. check around without dangerous matter sources, withdraw all personnel irrelevant with debugging, forbid that unrelated person enters debugging region, and put up warning sign;
8. debugging relates to region and carries out special messenger and patrol and examine;
9. emergency escape passage is set.
CN201510267531.1A 2015-05-25 2015-05-25 A kind of marine engineering equipment module building technology Active CN104988881B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510267531.1A CN104988881B (en) 2015-05-25 2015-05-25 A kind of marine engineering equipment module building technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510267531.1A CN104988881B (en) 2015-05-25 2015-05-25 A kind of marine engineering equipment module building technology

Publications (2)

Publication Number Publication Date
CN104988881A true CN104988881A (en) 2015-10-21
CN104988881B CN104988881B (en) 2017-12-29

Family

ID=54300763

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510267531.1A Active CN104988881B (en) 2015-05-25 2015-05-25 A kind of marine engineering equipment module building technology

Country Status (1)

Country Link
CN (1) CN104988881B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836166A (en) * 2017-01-06 2017-06-13 天津博迈科海洋工程有限公司 Large marine man-made island module in-site installation site planning method
CN107300901A (en) * 2017-08-09 2017-10-27 中车洛阳机车有限公司 A kind of locomotive bogie frame suspension member package system device
CN108733931A (en) * 2018-05-24 2018-11-02 奥克斯空调股份有限公司 Circuit design and processing technology output method and device
CN109625173A (en) * 2018-12-18 2019-04-16 海洋石油工程(青岛)有限公司 The technique built for marine worker module
CN111652500A (en) * 2020-05-29 2020-09-11 广东电网有限责任公司 Automatic duty-on auxiliary system and equipment based on scheduling and report generation method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101100217A (en) * 2007-06-12 2008-01-09 烟台来福士海洋工程有限公司 Offshore platform integral constructing and hoisting method and special-purpose hoisting machine for the same
CN101136259A (en) * 2007-09-27 2008-03-05 中国核工业第二三建设公司 Modularize building method for nuclear reactor of nuclear plant
RU2347866C2 (en) * 2007-02-19 2009-02-27 Виктор Ильич Мищевич Method of constructing process platforms
CN101417693A (en) * 2008-11-14 2009-04-29 大连船舶重工集团有限公司 Oceanography engineering module integral hoisting method
CN103291075A (en) * 2013-06-27 2013-09-11 中广核工程有限公司 Method of manufacturing large-scale module of nuclear power plant
CN203319554U (en) * 2013-05-08 2013-12-04 中国海洋石油总公司 Multifunctional framework

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2347866C2 (en) * 2007-02-19 2009-02-27 Виктор Ильич Мищевич Method of constructing process platforms
CN101100217A (en) * 2007-06-12 2008-01-09 烟台来福士海洋工程有限公司 Offshore platform integral constructing and hoisting method and special-purpose hoisting machine for the same
CN101136259A (en) * 2007-09-27 2008-03-05 中国核工业第二三建设公司 Modularize building method for nuclear reactor of nuclear plant
CN101417693A (en) * 2008-11-14 2009-04-29 大连船舶重工集团有限公司 Oceanography engineering module integral hoisting method
CN203319554U (en) * 2013-05-08 2013-12-04 中国海洋石油总公司 Multifunctional framework
CN103291075A (en) * 2013-06-27 2013-09-11 中广核工程有限公司 Method of manufacturing large-scale module of nuclear power plant

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836166A (en) * 2017-01-06 2017-06-13 天津博迈科海洋工程有限公司 Large marine man-made island module in-site installation site planning method
CN107300901A (en) * 2017-08-09 2017-10-27 中车洛阳机车有限公司 A kind of locomotive bogie frame suspension member package system device
CN108733931A (en) * 2018-05-24 2018-11-02 奥克斯空调股份有限公司 Circuit design and processing technology output method and device
CN109625173A (en) * 2018-12-18 2019-04-16 海洋石油工程(青岛)有限公司 The technique built for marine worker module
CN111652500A (en) * 2020-05-29 2020-09-11 广东电网有限责任公司 Automatic duty-on auxiliary system and equipment based on scheduling and report generation method thereof

Also Published As

Publication number Publication date
CN104988881B (en) 2017-12-29

Similar Documents

Publication Publication Date Title
CN104988881A (en) Ocean engineering equipment module construction technology
CN101967886B (en) Assembly and installation methods of steel containment vessel of nuclear power station
CN105484267A (en) Deep-water high-flow-speed fixed-point accurate throwing and filling device and construction method
CN113431340A (en) Construction method of rose-shaped special-shaped space grid steel structure
CN104711930B (en) Ultra-wide river course major diameter pipe bridge construction method of installation
CN105369790A (en) Weight control method in ocean platform designing and building processes
CN104444851A (en) Installation method of marine crane
Komatsu et al. Development of offshore wind turbine floater that blends into Japanese waters
Koh et al. Floating performance stage at the Marina Bay, Singapore
Alonso Castro et al. Removal of Topside Units in a Single Lift: The Repsol Yme Field Case Study
CN102140802A (en) Design method for closed self-floating steel hanging box and drilling platform
Jung et al. Development of dual-lifting technique for installation of topside mega-modules
Sood Assessment of Lifting Criteria for Crane on a Heavy Lift Ship ‘load check and fatigue life calculation’
Hafez et al. Practical investigation of a monopod fabrication method and the numerical investigation of its up-righting process
Dach Eidesstattliche Erklärung
el Mouhandiz et al. Subsea templates installation at North Sea using HLV THIALF
Baker Mooring analysis of the Ocean Sentinel through field observation and numerical simulation
Ham et al. Physics-based salvage simulation for wrecked ship considering environmental loads
Kure et al. Record-Breaking Air Lifting Operation On The Gullfaks E Project
Zhong et al. Liuhua 11-1 FPS Dry-dock Upgrade and Life Extension-Project Scope and Execution
Liu et al. Challenges and solutions for dry dock life extension to a semisubmersible FPS
Wong et al. Decommissioning-Extended Lift of Large Topsides Module
Trowbridge et al. California Floating Offshore Wind Regional Ports Assessment. US Department of the Interior, Bureau of Ocean Energy Management. 61 p. Report No.: OCS Study BOEM 2023-010
CN117488815A (en) Ocean administration throwing system and method
Berger Frigg And MCP01 Decommissioning

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 226000 No. 1, COSCO Road, Jiangsu, Nantong

Patentee after: Nantong COSCO Shipping Engineering Co., Ltd.

Address before: 226000 No. 1, COSCO Road, Jiangsu, Nantong

Patentee before: COSCO Shipyard Group Co., Ltd.

CP01 Change in the name or title of a patent holder