CN104930264B - Pipe clip and pipe installation assembly - Google Patents
Pipe clip and pipe installation assembly Download PDFInfo
- Publication number
- CN104930264B CN104930264B CN201510271367.1A CN201510271367A CN104930264B CN 104930264 B CN104930264 B CN 104930264B CN 201510271367 A CN201510271367 A CN 201510271367A CN 104930264 B CN104930264 B CN 104930264B
- Authority
- CN
- China
- Prior art keywords
- pipe clamp
- pipeline
- pipe
- clip slot
- engaging
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L3/00—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
- F16L3/08—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing
- F16L3/12—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing comprising a member substantially surrounding the pipe, cable or protective tubing
- F16L3/13—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing comprising a member substantially surrounding the pipe, cable or protective tubing and engaging it by snap action
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Clamps And Clips (AREA)
- Supports For Pipes And Cables (AREA)
Abstract
The invention discloses a pipe clip used for fixing a pipe (2). The pipe clip (1) comprises two pipe clip sections and a connecting portion (12). The connecting portion (12) connects the tail ends of the two pipe clip sections, and a meshing portion (121) is arranged on the inner side of the connecting portion (12). One of the meshing portion (121) and one pipe clip section is provided with a meshing tooth (1211), and the other of the meshing portion (121) and one pipe clip section is provided with a meshing groove (113). The meshing tooth (1211) and the meshing groove (113) are meshed so as to provide force for butt joint of the head ends of the two pipe clip sections. The head ends of the two pipe clip sections are in butt joint so as to form a pipe fixing hole (14) used for fixing the pipe (2). The pipe clip can resolve the problem of low pipe loading and unloading efficiency in the background art. The invention further discloses a pipe installation assembly.
Description
Technical field
The present invention relates to pipeline technique for fixing field, more specifically, is related to a kind of pipe clamp and pipeline mounting assembly.
Background technology
With the development of automobile air conditioning technology, the function of on-board air conditioner is more and more perfect, advanced.The species of air-conditioning duct,
Trend is more complicated.Accordingly, air-conditioning duct install reliability, property easy to loading and unloading is increasingly taken seriously, and is technical staff
The important directions of research.
At present, first mounting and fixing bracket is needed when air-conditioning duct is fixedly mounted on automobile, then by Duct fixing clamp (such as half
Anchor ear) compress air-conditioning duct after be fixed on fixed support with threaded fastener.The above-mentioned fixed operation to air-conditioning duct is more
It is loaded down with trivial details, affect installation effectiveness.And, using the air-conditioning duct of above-mentioned fixed form installation when being keeped in repair, need screw thread
Securing member is first disassembled can implement maintenance operation to air-conditioning duct, and operation is relatively complicated, and then affects maintenance efficiency.In dimension
During repairing, maintainer is likely to be limited by separation space when threaded fastener is implemented and loaded and unloaded, and then causes screw thread tight
Firmware handling are difficult, and this further affects maintenance efficiency.
Above-mentioned only to illustrate by taking air-conditioning duct as an example, inventor has found that other set during invention the invention
It is standby upper, need fixed pipeline (such as oil pipe) to be also adopted by above-mentioned fixed form, and there is a problem of that the efficiency of loading and unloading is low.
To sum up, how to solve the problems, such as that current pipeline has an efficiency of loading and unloading low, be current those skilled in the art urgently
The problem of solution.
The content of the invention
It is an object of the invention to provide a kind of pipe clamp, low with the efficiency of loading and unloading for solving the pipeline presence described in background technology
Problem.
In order to solve above-mentioned technical problem, the present invention provides following technical scheme:
A kind of pipe clamp, for fixing pipeline;The pipe clamp includes two pipe clamp sections and connecting portion;Wherein:
The connecting portion connects the tail end of two pipe clamp sections, and the inner side of the connecting portion has engaging piece;It is described
In engaging piece and a pipe clamp section, engaging tooth is provided with one, engaging groove is provided with another one;The engaging tooth and
The engaging groove engagement is provided to relay with the head end as two pipe clamp sections;The head end of two pipe clamp sections is docked with shape
Into for fixing the pipeline fixing hole of the pipeline.
Preferably, in above-mentioned pipe clamp, the engaging tooth arranged in the pipe clamp section or the engaging groove are multiple and many
The individual engaging tooth or the engaging groove are sequentially distributed along the head end opening and closing rotation direction of two pipe clamp sections.
Preferably, in above-mentioned pipe clamp, the engaging piece is inner side direction of the connecting portion towards the pipeline fixing hole
Opisthotonos are formed.
Preferably, in above-mentioned pipe clamp, in the head end of two pipe clamp sections, clamping projection, another one in one, are provided with
On be provided with snap fit, the clamping is raised to be engaged by clamping with the snap fit.
Preferably, in above-mentioned pipe clamp, on the inwall of two pipe clamp sections, it is provided with semi-circular boss, two described half
Annular boss is radially extended along the pipeline fixing hole, and two semi-circular boss dock and to form the pipeline and fix
Hole.
Preferably, in above-mentioned pipe clamp, two semi-circular boss are made up of elastomeric material, and the pipeline fixing hole
External diameter of the diameter less than the pipeline.
Based on the pipe clamp of above-mentioned offer, present invention also offers a kind of pipeline mounting assembly, the pipeline installation group for being provided
Part includes mounting bracket, and the mounting bracket is used for being connected to installation foundation;The pipeline mounting assembly is also included as taken up an official post
Pipe clamp described in meaning one, the pipe clamp are fixedly linked with the mounting bracket.
Preferably, in above-mentioned pipeline mounting assembly, on the installation portion of the pipe clamp, it is provided with the first clip slot;Described installation is propped up
Plug Division is provided with frame;The Plug Division is coordinated with the first clip slot grafting.
Preferably, in above-mentioned pipeline mounting assembly, two avoidance gap in the mounting bracket, are provided with;Keep away described in two
Allow;The Plug Division surface relative with the installation portion arranges flexible pressure tongue;It is described
The second clip slot, second clip slot and the elasticity pressure tongue snap-fit is provided with installation portion.
Preferably, in above-mentioned pipeline mounting assembly, on the installation portion, it is provided with lead-in chamfered;The lead-in chamfered is used for
The guiding elasticity pressure tongue is slided in second clip slot;The guiding tail end of the lead-in chamfered is separated by with second clip slot
From.
The pipe clamp that the present invention is provided has the advantages that:
For the fixed form described in background technology, the pipe clamp that the present invention is provided is implementing fixed peace to pipeline
During dress, operator only need to two pipe clamp sections are broken into two with one's hands the opening for being capable of achieving pipe clamp towards contrary direction, so
Afterwards pipeline is placed in pipe clamp, two pipe clamp sections are finally compressed.Conversely, to only needing to break pipe into two with one's hands in pipeline unloading process
Folder.It can be seen that, the pipe clamp that the present invention is provided need not operate handling of the threaded fastener enforcement to pipeline by operator, only
Need to move pipe clamp manually.Therefore, pipe clamp provided in an embodiment of the present invention can solve the problem that the handling effect that current pipeline is present
The low problem of rate.
Simultaneously as threaded fastener is implemented to operate without the need for instrument, therefore the pipe clamp that the present invention is provided can avoid dress
Limited by separation space when unloading, and then be capable of the charge and discharge operations of convenient operator, finally conveniently can be keeped in repair.
Description of the drawings
In order to be illustrated more clearly that the embodiment of the present application or technical scheme of the prior art, below will be to institute in embodiment
The accompanying drawing that needs are used is briefly described, it should be apparent that, drawings in the following description are only described in the present invention
A little embodiments, for those of ordinary skill in the art, can be with according to these other accompanying drawings of accompanying drawings acquisition.
Fig. 1 is structural representation of the pipe clamp provided in an embodiment of the present invention in open configuration;
Fig. 2 is the part mplifying structure schematic diagram of Fig. 1;
Fig. 3 is structural representation of the pipe clamp provided in an embodiment of the present invention in closure state;
Fig. 4 is the structural representation of pipe clamp fixed -piping provided in an embodiment of the present invention;
Fig. 5 is the structural representation of mounting bracket provided in an embodiment of the present invention;
Fig. 6 is the structural representation of pipeline fixation kit provided in an embodiment of the present invention;
Fig. 7 is the structural representation of pipeline fixation kit fixed -piping provided in an embodiment of the present invention.
In above-mentioned Fig. 1-Fig. 7:
1- pipe clamps, 2- pipelines, 3- mounting brackets;
11- pipe clamp sections, 111- semi-circular boss, 112- clampings projection, 113- engaging grooves, 12- connecting portions, 121- engagement
Portion, 1211- engaging tooths, 13- pipe clamp sections, 131- semi-circular boss, 132- snap fits, the first clip slots of 133-, 134- lead-in chamfereds,
The second clip slots of 135-, 14- pipeline fixing holes, 31- installing holes, 32- avoid gap, 33- and avoid gap, 34- Plug Divisions, 35- bullets
Property pressure tongue, 36- pressure tongue apertures.
Specific embodiment
In order that those skilled in the art more fully understands technical scheme, below in conjunction with accompanying drawing to this
It is bright to be further detailed.
Refer to accompanying drawing 1 and Fig. 3, Fig. 1 and Fig. 3 respectively illustrates pipe clamp provided in an embodiment of the present invention 1 and is in and opens shape
The structure of state and closure state.A kind of pipe clamp 1 is embodiments provided, the pipe clamp 1 for being provided is used for fixing pipeline 2, such as
Shown in Fig. 3.
Pipe clamp provided in an embodiment of the present invention 1 includes pipe clamp section 11, connecting portion 12 and pipe clamp section 13.Wherein, connecting portion 12
For connecting the tail end of pipe clamp section 11 and pipe clamp section 13, to form whole pipe clamp 1.It should be noted that what tail end herein referred to
It is the non-folding end of pipe clamp section 11 and pipe clamp section 13.The tail end of pipe clamp section 11 and pipe clamp section 13 is not opened after connection easily,
Therefore under normal circumstances, the tail end of pipe clamp section 11 and pipe clamp section 13 is connected in non-removable mode.A kind of specific embodiment party
Formula is:Pipe clamp section 11, pipe clamp section 13 and connecting portion 12 are elastoplast and make, and are connected by integrated injection molding mode.
Incorporated by reference to Fig. 2 is referred to, Fig. 2 is the enlarged diagram of part-structure in Fig. 1.As shown in Figure 2, connecting portion 12 connects
Between pipe clamp section 11 and pipe clamp section 13, the inner side of connecting portion 12 has engaging piece 121.It should be noted that connecting portion 12
Inner side refers to connecting portion 12 towards pipe clamp section 11 and the side of pipe clamp section 13.Engaging piece 121 and pipe clamp section 11 or pipe clamp section 13
In, engaging tooth 1211 is provided with one, is provided with engaging groove 113 in another one.As shown in Figure 2, arrange on engaging piece 121
There is engaging tooth 1211, in pipe clamp section 11, be provided with engaging groove 113.It is of course also possible to be:Engaging groove is provided with engaging piece 121,
Engaging tooth, the invention is not limited in this regard is provided with pipe clamp section 11.
Engaging tooth 1211 and the engagement of engaging groove 113 coordinate to provide docking for the head end docking of pipe clamp section 11 and pipe clamp section 13
Power.Equally, it should be noted that the head end of pipe clamp section 11 and pipe clamp section 13 refers to the folding of pipe clamp section 11 and pipe clamp section 13
End, head end and tail end Relative distribution.The head end of pipe clamp section 11 and pipe clamp section 13 realizes opening for pipe clamp 1 after opening, such as Fig. 1 institutes
Show;Pipe clamp section 11 and the closure of pipe clamp section 13 realize the closure of pipe clamp 1, while pipeline fixing hole 14 is formed, as shown in Figure 3.Need
Illustrate, it is so-called that relay is referred to maintain pipe clamp section 11 and pipe clamp section 13 in mated condition to form pipeline fixing hole
14 power.
As described above, the pipe clamp 1 in the embodiment of the present invention provides a kind of pipeline fixation side for being different from background technology
After formula, pipe clamp section 11 and the closure of pipe clamp section 13, engaging groove 113 and engaging tooth 1211 are engaged, to provide pipe clamp section 11 and pipe clamp section 13
Head end docking to relay.After pipe clamp section 11 and pipe clamp section 13 are opened, pipe clamp 1 is in open configuration, and operator will can manage
Road 2 is placed in the region that pipe clamp section 11 and pipe clamp section 13 are surrounded, and then presses pipe clamp section 11 and pipe clamp section 13.11 He of pipe clamp section
Pipe clamp section 13 forms pipeline fixing hole 14 after closing and fixes pipeline 2, and now engaging groove 113 and the engagement of engaging tooth 1211 is provided
To relay ensureing the head end of pipe clamp section 11 and pipe clamp section 13 in mated condition, it is achieved thereby that the fixation to pipeline 2, such as
Shown in Fig. 3.
For the fixed form described in background technology, pipe clamp provided in an embodiment of the present invention is real to pipeline 2
During applying fixed installation, operator are real by only needing to break pipe clamp section 11 and pipe clamp section 13 towards contrary direction into two with one's hands
The opening of existing pipe clamp 1, is then placed into pipeline 2 in pipe clamp 1, finally compresses pipe clamp section 11 and pipe clamp section 13.Conversely, right
Only need to break pipe clamp 1 into two with one's hands in 2 unloading process of pipeline.
By the operating process of epimere, pipe clamp provided in an embodiment of the present invention 1 is without the need for operating spiral shell by operator
Stricture of vagina securing member implements the handling to pipeline 2, it is only necessary to move pipe clamp 1 manually.Therefore, pipe clamp provided in an embodiment of the present invention
Can solve the problem that the low problem of the efficiency of loading and unloading that current pipeline is present.Simultaneously as threaded fastener is implemented to operate without the need for instrument,
Therefore pipe clamp provided in an embodiment of the present invention 1 can avoid being limited by separation space during handling, being capable of convenient operator
The charge and discharge operations of member, finally conveniently can keep in repair.
It is a kind of preferred embodiment in, the number of engaging tooth 1211 or engaging groove 113 in pipe clamp section 11 or pipe clamp section 13
Measure as multiple, multiple engaging tooths 1211 or engaging groove 113 are along in the head end opening and closing rotation direction of pipe clamp section 11 and pipe clamp section 13
It is sequentially distributed.In such cases, the opening and closing process of engaging tooth 1211 and engaging groove 113 in pipe clamp section 11 and pipe clamp section 13
In persistently engage, and then pipe clamp section 11 and pipe clamp section 13 is progressively opened or is closed, can finally optimize pipe clamp section 11 and pipe
The controllability that folder section 13 is opened or closed.
In order to further improve the operability of 1 opening and closing of pipe clamp, it is preferred that engaging piece 121 is by 12 court of connecting portion
Form to the inner side direction opisthotonos of pipeline fixing hole 14, as shown in figure 1, corresponding, connecting portion 12 is corresponding with engaging piece 121
It is outer then formed one depression.The generation type of above-mentioned engaging piece 121 can increase opening between pipe clamp section 11 and pipe clamp section 13
Elasticity is opened, and then on the premise of ensureing that pipe clamp section 11 and pipe clamp section 13 are docked, both flaring operations can be facilitated.
In actual operating process, what between engaging groove 113 and engaging tooth 1211, engagement was provided may not to relay
It is sufficient so that the 13 reliable docking of pipe clamp section 11 and pipe clamp section, in order to optimize docking fastness, in the embodiment of the present invention, pipe clamp section 11
In both, clamping projection 112 is provided with one, snap fit 132, clamping 112 Hes of projection are provided with another one with pipe clamp section 13
Snap fit 132 is engaged by clamping.For the ease of both clampings, the clamping approaching side of clamping raised 112 and snap fit 132 be it is progressive tiltedly
Face.
In pipe clamp provided in an embodiment of the present invention 1, reinforcement can be set in pipe clamp section 11, connecting portion 12 and pipe clamp section 13
Muscle, to improve the intensity of whole pipe clamp 1.Meanwhile, the setting of reinforcement ensure that fixing intensity of the pipe clamp 1 to pipeline 2.
Referring again to accompanying drawing 1,3 and 4, in the embodiment of the present invention, can be equal on the inwall of pipe clamp section 11 and pipe clamp section 13
It is provided with semi-circular boss, i.e. pipe clamp section 11 and is provided with semi-circular boss 111, in pipe clamp section 13, is provided with semi-circular boss
131.Semi-circular boss 111 and semi-circular boss 131 radially extending along pipeline fixing hole 14, semi-circular boss 111 and half
The docking of annular boss 131 forms pipeline fixing hole 14.Certainly, pipeline fixing hole 14 can be with by pipe clamp section 11 and pipe clamp section 13 pairs
Other structures after connecing are formed, it is not limited to this.
In the scheme being more highly preferred to, semi-circular boss 111 and semi-circular boss 131 are made by elastomeric material, and by partly
External diameter of the diameter of the pipeline fixing hole 14 formed by annular boss 111 and semi-circular boss 131 less than pipeline 2.This kind of situation
Under, pipe clamp section 11 and pipe clamp section 13 dock after due to semi-circular boss 111 and semi-circular boss 131 elastic deformation and by pipeline
2 compress, so as to realize the fixation more stable to pipeline 2.Certainly, it should be noted that in such cases, semi-circular boss
Intensity of 111 intensity more than pipe clamp section 11, the elasticity of semi-circular boss 131 are more than the intensity of pipe clamp section 13.
Accompanying drawing 5-7 is refer to, based on pipe clamp provided in an embodiment of the present invention 1, the embodiment of the present invention additionally provides a kind of pipe
Road mounting assembly.The pipeline mounting assembly for being provided includes mounting bracket 3 and pipe clamp, and mounting bracket 3 is used for being connected to installation base
On plinth (such as vehicle chassis), pipe clamp is embodiment of the present invention pipe clamp 1 provided above, and pipe clamp 1 is fixed with mounting bracket 3
It is connected.
Pipeline mounting assembly provided in an embodiment of the present invention can realize the installation of pipeline 2 so that the pipe after fixed pipeline
Folder 1 is fixed on installation foundation.Accompanying drawing 5-7 is refer to, installing hole 31 in mounting bracket 3, is usually provided with, mounting bracket 3 passes through
The connector coordinated with installing hole 31 is connected with installation foundation.
In a kind of specific embodiment, the first clip slot 133 on the installation portion of pipe clamp 1, is provided with.Specifically, the first clip slot
133 can be arranged in pipe clamp section 11, it is also possible to be arranged in pipe clamp section 13.Plug Division 34, grafting is provided with mounting bracket 3
Portion 34 and 133 grafting of the first clip slot coordinate.Pipe clamp 1 is detachably fixed mode with mounting bracket 3 by grafting is this, can enter one
The convenient handling to pipeline 2 of step.Operator are during handling pipeline 2, it is possible to achieve between pipe clamp 1 and mounting bracket 3
Write, then realize the handling of pipe clamp 1 and pipeline 2.This can improve the degree of freedom to the handling of pipeline 2.
Referring again to accompanying drawing 5, mounting bracket 3 can be plate-like piece.Plug Division 34 can be formed in a cantilever fashion
In mounting bracket 3, certain cantilever can be formed in the way of overhanging, it is also possible to formed in the way of built-in.In order to reduce installation
Taking up room for support 3, is provided with two avoidance gap in mounting bracket 3, respectively avoid gap 32 and avoid gap 33, keep away
Allow Plug Division 34 is formed between gap 32 and avoidance gap 33.In the embodiment of the present invention, so-called avoidance gap refers to one end
The bar hole of opening.133 snap-fit of Plug Division 34 and the first clip slot, during installation, Plug Division 34 is along the first folder
The direction propulsion of the extension of groove 133, until the end edge of the first clip slot 133 props up the bottom for avoiding gap.
In a kind of specific embodiment being more highly preferred to, the surface relative with installation portion of Plug Division 34 can also arrange elasticity
Pressure tongue 35, specifically, elasticity pressure tongue 35 can open up in mounting bracket 3 pressure tongue apertures 36 after bending form, or with
Pressure tongue apertures 36 is integrally formed.In such cases, the second clip slot 135, the second clip slot 135 and elasticity pressure tongue 35 is provided with installation portion
Snap-fit.In specific installation process, elasticity pressure tongue 35 is advanced to after setpoint distance the bullet at oneself with Plug Division 34
Block in nearly second clip slot 135 under property restitution.The cooperation of elasticity pressure tongue 35 and the second clip slot 135 causes pipe clamp 1 and props up with installing
Cooperation between frame 3 is more consolidated.Specifically, the second clip slot 135 can be semienclosed slot, and the first clip slot 133 can also be half
Enclosed slot, it is blind end to be located at the end at end with the opening of the first clip slot 133 on the second clip slot 135.In such cases,
The other end of two clip slots 135 is opening, facilitates operator to provoke elasticity pressure tongue 35 and then cause elasticity pressure tongue 35 to depart from the
Two clip slots 135, and then the dismounting of mounting bracket 3 and Plug Division 34 can be facilitated.
Referring again to accompanying drawing 3, lead-in chamfered 134 on the installation portion of pipe clamp 1, can be provided with, lead-in chamfered 134 is used for
Guiding elasticity pressure tongue 35 is slided in the second clip slot 135, and lead-in chamfered 134 is used for guiding elasticity pressure tongue 35 to slide into the second clip slot 35
Interior, the guiding tail end of lead-in chamfered 134 isolates distribution with the second clip slot 135.During installation, with 34 free of Plug Division
Advance in first clip slot 133, elasticity pressure tongue 35 can be smoothly entered in the second clip slot 135 along the guiding of lead-in chamfered 134,
The cooperation of mounting bracket 3 and pipe clamp 1 can finally be facilitated.Herein, the guiding tail end of lead-in chamfered 134 and the second clip slot 135
It is isolated, the guiding tail end for referring to lead-in chamfered 134 is at least above the bottom surface of the second clip slot 135, to ensure elastic pressure
Tongue 35 is trapped in the second clip slot 135 under the guiding of lead-in chamfered 134, the final clamping engagement for realizing both.
Some one exemplary embodiments of the present invention are described above by way of explanation only, undoubtedly, for ability
The those of ordinary skill in domain, in the case of without departing from the spirit and scope of the present invention, can with a variety of modes to institute
The embodiment of description is modified.Therefore, above-mentioned accompanying drawing and description are inherently illustrative, should not be construed as to the present invention
The restriction of claims.
Claims (6)
1. a kind of pipeline mounting assembly, including mounting bracket (3), described mounting bracket (3) are used for being connected to installation foundation;Institute
Stating pipeline mounting assembly also includes pipe clamp (1), and pipe clamp (1) is fixedly linked with the mounting bracket (3), for fixing pipeline
(2);Characterized in that,
Described pipe clamp (1) includes two pipe clamp sections and connecting portion (12);Wherein:
Described connecting portion (12) connect the tail end of two pipe clamp sections, and the inner side of the connecting portion (12) has engaging piece
(121);In engaging piece (121) and a pipe clamp section, engaging tooth (1211) in one, is provided with, is arranged in another one
There is engaging groove (113);The engagement of engaging tooth (1211) and the engaging groove (113) thinks that the head end of two pipe clamp sections is carried
For to relay;The head end of two pipe clamp sections docks to form the pipeline fixing hole (14) for fixing the pipeline (2);
The first clip slot (133) is provided with the installation portion of pipe clamp (1);Plug Division is provided with mounting bracket (3)
(34);Plug Division (34) are coordinated with the first clip slot (133) grafting;
Two avoidance gap are provided with mounting bracket (3);Two described avoidance form the Plug Division between gap
(34);Plug Division (34) surface relative with the installation portion arranges flexible pressure tongue (35);Arrange on the installation portion
There are the second clip slot (135), the second clip slot (135) and elasticity pressure tongue (35) snap-fit;
Lead-in chamfered (134) is provided with the installation portion;Described lead-in chamfered (134) are used for guiding elasticity pressure tongue (35)
Slide in the second clip slot (135);The guiding tail end of lead-in chamfered (134) is isolated with the second clip slot (135).
2. pipeline mounting assembly according to claim 1, it is characterised in that the engaging tooth arranged in the pipe clamp section
Or the engaging groove (113) is for multiple, and multiple engaging tooths (1211) or the engaging groove (113) are along two (1211)
The head end opening and closing rotation direction of the pipe clamp section is sequentially distributed.
3. pipeline mounting assembly according to claim 1 and 2, it is characterised in that described engaging piece (121) are the connection
Portion (12) is formed towards the inner side direction opisthotonos of pipeline fixing hole (14).
4. pipeline mounting assembly according to claim 1, it is characterised in that in the head end of two pipe clamp sections, one
On be provided with clamping projection (112), be provided with snap fit (132) in another one, clamping projection (112) and the snap fit
(132) it is engaged by clamping.
5. the pipeline mounting assembly according to claim 1,2 or 4, it is characterised in that on the inwall of two pipe clamp sections
It is provided with semi-circular boss, two semi-circular boss radially extending along pipeline fixing hole (14), two institutes
State semi-circular boss to dock to form pipeline fixing hole (14).
6. pipeline mounting assembly according to claim 5, it is characterised in that two semi-circular boss are by elastomeric material
Make, and the diameter of the pipeline fixing hole (14) is less than the external diameter of the pipeline (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510271367.1A CN104930264B (en) | 2015-05-25 | 2015-05-25 | Pipe clip and pipe installation assembly |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510271367.1A CN104930264B (en) | 2015-05-25 | 2015-05-25 | Pipe clip and pipe installation assembly |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104930264A CN104930264A (en) | 2015-09-23 |
CN104930264B true CN104930264B (en) | 2017-03-22 |
Family
ID=54117567
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510271367.1A Active CN104930264B (en) | 2015-05-25 | 2015-05-25 | Pipe clip and pipe installation assembly |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104930264B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110143177B (en) * | 2019-07-01 | 2023-01-24 | 安徽江淮汽车集团股份有限公司 | Multifunctional wire clamp for automobile |
CN110873234B (en) * | 2019-11-27 | 2021-02-05 | 安徽江淮汽车集团股份有限公司 | Pipeline clamp |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1529995A1 (en) * | 2003-11-07 | 2005-05-11 | Wermuth Enterprises | Pipe holding device |
CN201262279Y (en) * | 2008-08-22 | 2009-06-24 | 上海金亭汽车线束有限公司 | Fastener of bellows |
CN204647572U (en) * | 2015-05-25 | 2015-09-16 | 安徽江淮汽车股份有限公司 | A kind of pipe clamp and pipeline mounting assembly |
-
2015
- 2015-05-25 CN CN201510271367.1A patent/CN104930264B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN104930264A (en) | 2015-09-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104930264B (en) | Pipe clip and pipe installation assembly | |
CN106969481A (en) | Mobile air conditioner | |
CN103794922B (en) | The junctor of electric car charger | |
CN204647572U (en) | A kind of pipe clamp and pipeline mounting assembly | |
CN107300049A (en) | The tube joint assembly and air conditioner of a kind of Anti-dismantling | |
CN113895370B (en) | Car body wire harness structure and car | |
CN208689210U (en) | It is a kind of that quick and dust-proof optical fiber connector is installed | |
CN209054212U (en) | A kind of flange being easily installed | |
CN207539846U (en) | A kind of multifunctional lamp positioner | |
CN206771674U (en) | Mobile air conditioner | |
CN207369234U (en) | Soft and hard glue combined folding panel | |
CN207160922U (en) | Window catching device | |
CN207437933U (en) | A kind of Duct fixing clamp | |
CN110273575A (en) | A kind of steel tent top cloth installation and adjustment structure | |
CN207195302U (en) | A kind of compressor scroll mounting structure | |
CN207178928U (en) | A kind of three-chip type fire-extinguishing sprinkling soft pipe adapter fastener | |
CN207697431U (en) | Motor compressor supply lines assembly for electric vehicle | |
CN110307422A (en) | A kind of mechanical metal fastener | |
CN106175732B (en) | Adapter plate for quickly disassembling and assembling sphygmomanometer cuff | |
CN208919078U (en) | A kind of sliding block for avoiding installation from malfunctioning | |
CN213083153U (en) | Air duct in light composite board | |
CN108978133A (en) | Baking passage system and washing machine | |
CN209372935U (en) | A kind of electrical clamp on amperemeter for detecting installation easy to disassemble | |
CN220189830U (en) | Ultra-high temperature battery fixing device | |
CN220421348U (en) | Protection tube for cable |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
CB02 | Change of applicant information |
Address after: 230601 Anhui Province, Hefei City Industrial Park, the Peach Blossom Road No. 669 Applicant after: Anhui Jianghuai Automobile Group Limited by Share Ltd Address before: 230601 Anhui Province, Hefei City Industrial Park, the Peach Blossom Road No. 669 Applicant before: Anhui Jianghuai Automotive Co., Ltd. |
|
COR | Change of bibliographic data | ||
GR01 | Patent grant |