CN104929242A - Hollow core tube structure system of high-rise building frame - Google Patents
Hollow core tube structure system of high-rise building frame Download PDFInfo
- Publication number
- CN104929242A CN104929242A CN201510301101.7A CN201510301101A CN104929242A CN 104929242 A CN104929242 A CN 104929242A CN 201510301101 A CN201510301101 A CN 201510301101A CN 104929242 A CN104929242 A CN 104929242A
- Authority
- CN
- China
- Prior art keywords
- wall
- vierendeel girder
- cylinder
- shear wall
- hollow core
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
The invention discloses a hollow core tube structure system of a high-rise building frame. The hollow core tube structure system comprises shear walls, connecting beams, peripheral columns, frame beams and a slab. The shear walls are arranged at the center of the high-rise building and are vertically arranged, the connecting beams are erected between the adjacent shear walls, the shear walls and the connecting beams enclose a hollow core tube, the peripheral columns are arranged on the periphery of the hollow core tube and are vertical steel pipe concrete columns, a part of the frame beams are erected between the peripheral columns and the shear walls, and the other frame beams are erected between the two adjacent peripheral columns. A plurality of inside-tube columns are arranged in the hollow core tube in a staggered manner, two ends of the inside-tube columns are overlapped on the shear walls respectively so as to reduce weight of the hollow core tube and reduce basic load and structural seismic force and manufacturing cost. The hollow core tube structure system can give the function of a second defense line of the peripheral columns into play.
Description
Technical field
The present invention relates to a kind of architectural construction, specifically refer to a kind of frame hollow core wall structure system of highrise building.
Background technology
Tube shear wall is widely used in highrise building well because of its lateral resistance behavior, existing wall of High-building cylindrical shell building system as shown in Figure 1, comprise shear wall 1, coupling beam 4, peripheral post 2, Vierendeel girder 3, shear wall 5 and floor in cylinder, shear wall 1 is vertically arranged, be positioned at the center position of highrise building, shear wall 1 is the vertical multi-disc arranged, between adjacent shear wall 1, erection has coupling beam 4, shear wall 1 and coupling beam 4 collar form a hollow core cylinder, peripheral post 2 is positioned at the periphery of hollow core cylinder, peripheral post 2 is the many steel core concrete columns vertically arranged, Vierendeel girder 3 is also many, the two ends of Vierendeel girder 3 are erected between peripheral post 2 and shear wall 1 respectively, in cylinder, shear wall 5 is built in hollow core cylinder cylinder, in cylinder, shear wall 5 is multiple, be rigidly connected between shear wall 5 and shear wall 1 in cylinder, in cylinder, shear wall 5 and shear wall 1 are rigidly connected formation integral rigidity body.
Above-mentioned wall of High-building cylindrical shell building system have employed Frame-Shear wall, Frame-Shear wall refers to the structural system that the frame system that is made up of peripheral beam column and central cylinder form jointly, the building structure that outside framework comprises Vierendeel girder 3 and is arranged between Vierendeel girder 3, exterior frame column refers to the combining structure that peripheral post 2 and Vierendeel girder 3 are formed, the main Lateral Resistant System of structure is hollow core cylinder, by the synergy with outside framework, to provide enough anti-side and the torsional rigidity of structure.Be characterized in that form of structure is conducive to improving the stress performance of structural entity, thus improve high-rise building anti-seismic performance.Frame-Shear wall becomes because of the flexibility of its good stress performance and inner space the predominate architecture form adopted in current international super highrise building, has a wide range of applications in super highrise building.
But also there is following defect in above-mentioned wall of High-building cylindrical shell building system:
One, owing to arranging shear wall 5 in cylinder in hollow core cylinder cylinder, in cylinder, shear wall 5 weight is excessive, increases the seismic forces of basic load and structure, and cost is high simultaneously.
They are two years old, outside framework is connected with hollow core cylinder by Vierendeel girder 3, connection between Vierendeel girder 3 and hollow core cylinder belongs to varied rigid link, here varied rigid link has certain relative displacement or relative deformation between shear wall 5 in referring in peripheral hollow core cylinder and hollow core cylinder cylinder, part moment of flexure can only be born, there is certain corner, and be connected by shear wall in cylinder 5 in hollow core cylinder, rigidity is very large, belong to and be rigidly connected, here be rigidly connected relative displacement in referring in peripheral hollow core cylinder and hollow core cylinder cylinder between shear wall or relative deformation very little, almost nil, that is hollow core cylinder is connected in order to an entirety with shear wall in the cylinder in cylinder, there is relative deformation hardly, cause the internal force of hollow core cylinder excessive, be unfavorable for the performance in the defence line, exterior frame column two road that peripheral post and Vierendeel girder are formed.
Because old specification is to the fire protection requirement of high-level structure, the Frame-Shear wall area of plane can not more than 2000m
2, and the fire compartmentation regulation flooring area of plane of new criteria can exceed 2000mm
2, in practical engineering application, floor area reaches 3000m
2above, floor area is large, and the area of Core Walls Structure also can increase, thus causes the shear wall in Core Walls Structure too much, and preponderance, economy is bad.
Summary of the invention
The object of this invention is to provide a kind of frame hollow core wall structure system of highrise building, this structural system can reduce the weight of hollow core cylinder, reduce the seismic forces of basic load and structure, reduce cost, the effect in defence line, exterior frame column two road can also be given full play to.
Above-mentioned purpose of the present invention realizes by following technical solution: a kind of frame hollow core wall structure system of highrise building, this structural system comprises shear wall, coupling beam, peripheral post, Vierendeel girder and floor, described shear wall is positioned at the center position of highrise building, shear wall is the vertical multi-disc arranged, between adjacent shear wall, erection has described coupling beam, shear wall and coupling beam collar form a hollow core cylinder, described peripheral post is positioned at the periphery of hollow core cylinder, peripheral post is the many steel core concrete columns vertically arranged, Vierendeel girder is also many, part frame erection is between peripheral post and shear wall, remaining Vierendeel girder is erected between two adjacent peripheral posts, it is characterized in that: the inside of described hollow core cylinder is also staggeredly equipped with many cylinder inner beams, the two ends of cylinder inner beam are overlapped on shear wall respectively, to reduce the weight of hollow core cylinder, reduce the seismic forces of basic load and structure, and can cost be reduced.
Structural system of the present invention, by cancelling shear wall in the cylinder in hollow core cylinder, changes into and adopts cylinder inner beam overlap joint, significantly can reduce the weight of hollow core cylinder, reduce the seismic forces of basic load and structure, and can reduce cost.Simultaneously, outside framework is connected with hollow core cylinder by Vierendeel girder, connection between Vierendeel girder and hollow core cylinder belongs to varied rigid link, and in hollow core cylinder, adopt cylinder inner beam overlap joint, formed hinged between cylinder inner beam and hollow core cylinder, in the cylinder of therefore hollow core cylinder, outside cylinder, be varied rigid link, there will not be the situation that local stiffness is excessive, more can give full play to the effect in the defence line, exterior frame column two road that peripheral post and Vierendeel girder are formed simultaneously.
In the present invention, described hollow core cylinder is rectangular cylinder, and many described cylinder inner beams longitudinally, are laterally vertically arranged in groined type.
In the present invention, in described shear wall, Partial Shear wall body of wall is provided with the wall limb stretched in hollow core cylinder cylinder, the structure of wall limb is identical with shear wall, in many cylinder inner beams, part cylinder inner beam is overlapped on described wall limb, all the other inner beams are overlapped on shear wall and do not arrange on the body of wall of wall limb, be erected in the Vierendeel girder between peripheral post and shear wall, the frame segment body of wall arranging wall limb with shear wall of setting a roof beam in place is connected, this part Vierendeel girder lays respectively at the both sides of wall limb with the cylinder inner beam be overlapped on corresponding wall limb, be located along the same line with corresponding wall limb and cylinder inner beam, this part Vierendeel girder is also connected with the cylinder inner beam be overlapped on corresponding wall limb simultaneously, the body of wall that all the other Vierendeel girders and shear wall do not arrange wall limb is connected.
In the present invention, the length of described wall limb is 1.5 ~ 2.5m, and the cylinder inner beam that can ensure in hollow core cylinder is overlapped on wall limb and forms larger coupling stiffness.
In the present invention, the breadth of section being overlapped on the cylinder inner beam on described wall limb is identical with the thickness of wall limb, and thickness is 0.2 ~ 0.8m, and depth of section is 0.8 ~ 1.5m, and span is larger, and highly higher, span is less, and height can get the small value.
In the present invention, described wall limb is multiple, and the shape that is centrosymmetric centered by the center line of rectangular hollow Core Walls Structure distributes.
Shear wall in the cylinder in hollow core cylinder is cancelled in the present invention, and adopt shear wall in the cylinder in concrete tube inner beam replacement Core Walls Structure, concrete tube inner beam directly connects the wall limb of hollow core cylinder shear wall or shear wall by conventional construction technological means in prior art, therefore the dead load that can effectively reduce in hollow core cylinder, increase the building flexibility in hollow core cylinder, simultaneously owing to increasing short-limb wall limb, the span of an inner beam can be shortened, the depth of section of an inner beam also can be reduced, thus effectively solve in highrise building because shear wall in the cylinder in hollow core cylinder is too much, dead load excessive and make structural cost excessive between contradictory problems, by cancelling shear wall in cylinder, and increase the form of short-limb wall limb and cylinder inner beam, its rigidity of structure also can structure ductility and requirement for bearing capacity.
In structural system of the present invention, the annexation of cylinder inner beam, Vierendeel girder and shear wall is comparatively complicated, and the syndeton at diverse location place is different, and concrete syndeton is as follows:
In the present invention, be arranged in corresponding wall limb both sides and the Vierendeel girder be located along the same line and cylinder inner beam, described Vierendeel girder is Vierendeel girder gluten, muscle at the bottom of Vierendeel girder, tie up the reinforced concrete beam that the Vierendeel girder stirrup of muscle at the bottom of Vierendeel girder gluten and Vierendeel girder and concreting are formed, described cylinder inner beam is cylinder inner beam gluten, muscle at the bottom of cylinder inner beam, the reinforced concrete beam that in the cylinder tying up muscle at the bottom of an inner beam gluten and cylinder inner beam, beam stirrup and concreting are formed, described Vierendeel girder gluten is connected through after shear wall and wall limb with cylinder inner beam gluten, muscle at the bottom of described Vierendeel girder stretches in wall limb through after shear wall, muscle at the bottom of Vierendeel girder is positioned at the length >=LabE of shear wall and wall limb, at the bottom of described cylinder inner beam, muscle is positioned at the below of muscle at the bottom of Vierendeel girder, be upper and lower overlapping shape with muscle at the bottom of Vierendeel girder, muscle at the bottom of described cylinder inner beam stretches in shear wall through after wall limb, at the bottom of cylinder inner beam, muscle is positioned at the length >=LabE of wall limb and shear wall, described Vierendeel girder and shear wall and wall limb are formed and just connect in succession, described cylinder inner beam and shear wall and wall limb are also formed and just connect in succession.
In the present invention, connection between the body of wall that Vierendeel girder and shear wall do not arrange wall limb is for just to connect in succession, described Vierendeel girder is Vierendeel girder gluten, muscle at the bottom of Vierendeel girder, tie up the reinforced concrete beam that the Vierendeel girder stirrup of muscle at the bottom of Vierendeel girder gluten and Vierendeel girder and concreting are formed, bend straight down after described Vierendeel girder gluten stretches into shear wall, it stretches into the lateral length >=0.4LabE of shear wall, difference in height >=the LabE bottom and between the bottom surface of Vierendeel girder bent straight down, at the bottom of described Vierendeel girder, muscle bends after stretching into shear wall straight up, it stretches into the lateral length >=0.4LabE of shear wall, lateral length and the height sum >=LabE bent straight up.
In the present invention, overlap joint between the body of wall that cylinder inner beam and shear wall do not arrange wall limb is for being articulated and connected, described cylinder inner beam is cylinder inner beam gluten, muscle at the bottom of cylinder inner beam, the reinforced concrete beam that in the cylinder tying up muscle at the bottom of an inner beam gluten and cylinder inner beam, beam stirrup and concreting are formed, bend straight down after described cylinder inner beam gluten stretches into shear wall, it stretches into the lateral length >=0.4LabE of shear wall, the height bent straight down is 15d1, d1 is a diameter for inner beam gluten, muscle at the bottom of described cylinder inner beam is vertically upper after stretching into shear wall to be bent, it stretches into the lateral length >=0.4LabE of shear wall, the height bent straight up is 15d2, d2 is the diameter of muscle at the bottom of an inner beam.
In the present invention, described highrise building refers to that the number of plies is the building of 20 layers ~ 60 layers; The area of described hollow core cylinder is 300m
2~ 600m
2, in many described cylinder inner beams, the span of the cylinder inner beam longitudinally arranged is 7m ~ 20m, and the span of the cylinder inner beam transversely arranged is 7m ~ 30m.
Compared with prior art, the present invention has following remarkable result:
1, structural system of the present invention is owing to cancelling shear wall in the cylinder in hollow core cylinder cylindrical shell, effectively can reduce the weight of cylindrical shell, reduces the seismic forces of basic load and structure, effectively reduces structural cost.
2, structural system of the present invention makes the cylinder inner structure of the hollow core barrel structure system of Tall Building Frame arrange more flexibly, because the cylinder inner beam being arranged on hollow core cylinder inside allows the rotation of slight amplitude, makes in cylinder and outside framework compatibility of deformation.Because Vierendeel girder exists corner when being connected with hollow core cylinder, and cancel shear wall in cylinder in hollow core cylinder and after increasing cylinder inner beam, also there is corner, in the cylinder of therefore hollow core cylinder, outside cylinder, being varied rigid link, there will not be the situation that local stiffness is excessive.And due to the existence of shear wall in cylinder in prior art, making for being rigidly connected in the cylinder of hollow core cylinder, cylinder is outward varied rigid link, not only deformation, and easily occurs the situation that local stiffness is excessive.
3, structural system of the present invention is by cancelling shear wall in the cylinder in hollow core cylinder cylindrical shell, and adopt cylinder inner beam to overlap, make to form varied rigid link between the cylinder inner beam in hollow core cylinder cylinder and hollow core cylinder, partly brisance is assigned to peripheral post and Vierendeel girder, can give full play to the effect in the defence line, exterior frame column two road of peripheral post and Vierendeel girder formation.
4, structural system of the present invention can reduce the axle pulling force of shear wall under geological process effectively, for the shear wall occurring larger pulling force, to the pulling force highly significant reducing shear wall.
5, the hollow core cylinder of structural system of the present invention speed of application compared with regular core cylinder is accelerated, and construction period shortens, and has obvious economic benefit.
6, structural system of the present invention is larger for hollow core cylinder especially, and Core Walls Structure width is greater than 12m, and Core Walls Structure is excessively firm, overweight, when in Core Walls Structure, most of shear wall ratio of axial compressive force to axial compressive ultimate capacity of section is less than 0.8 times of Criterion restriction, is applied in conventional building structure.
7, the groined slab floor system energy flexible adaptation architectural composition in structural system hollow core cylinder of the present invention, and total system weight is light, stressed good, there is good marketing and application prospect.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the present invention is described in further detail.
Fig. 1 is the integral planar arrangement diagram of the frame-shear wall tube structure system of prior art middle-high building;
Fig. 2 is the integral planar arrangement diagram of the frame hollow core wall structure system implementation example one of highrise building of the present invention;
Fig. 3 is the partial structurtes schematic diagram of the frame hollow core wall structure system implementation example one of highrise building of the present invention, shows the position relationship between Vierendeel girder, shear wall, wall limb and cylinder inner beam and annexation that are located along the same line;
Fig. 4 is the partial structurtes schematic diagram of the frame hollow core wall structure system implementation example one of highrise building of the present invention, the position relationship between the body of wall that display box is set a roof beam in place and shear wall does not arrange wall limb and annexation;
Fig. 5 is the partial structurtes schematic diagram of the frame hollow core wall structure system implementation example one of highrise building of the present invention, and display barrel inner beam and shear wall do not arrange position relationship between the body of wall of wall limb and annexation;
Fig. 6 is the integral planar arrangement diagram of the frame hollow core wall structure system implementation example two of highrise building of the present invention;
Fig. 7 is that Fig. 6 is not through A-A view of wall limb;
Fig. 8 is B-B view that Fig. 6 passes wall limb.
Description of reference numerals
1, shear wall; 2, peripheral post; 3, Vierendeel girder; 31, Vierendeel girder gluten; 32, muscle at the bottom of Vierendeel girder;
33, Vierendeel girder stirrup; 4, coupling beam; 5, shear wall in cylinder; 6, cylinder inner beam;
61, cylinder inner beam gluten; 62, muscle at the bottom of cylinder inner beam; 63, beam stirrup in cylinder; 7, wall limb
Detailed description of the invention
Embodiment one
The embodiment one of the frame hollow core wall structure system of a kind of highrise building of the present invention as shown in Figures 2 to 5, the number of plies of highrise building is 50 layers, this structural system comprises shear wall 1, coupling beam 4, peripheral post 2, Vierendeel girder 3 and floor, shear wall 1 is vertically arranged, be positioned at the center position of highrise building, shear wall 1 is the vertical multi-disc arranged, between adjacent shear wall 1, erection has coupling beam 4, shear wall 1 and coupling beam 4 collar form a rectangular hollow core cylinder, peripheral post 2 is positioned at the periphery of hollow core cylinder, peripheral post 2 is the many steel core concrete columns vertically arranged, Vierendeel girder 3 is also many, frame segment is set a roof beam in place and 3 is erected between peripheral post 2 and shear wall 1, remaining Vierendeel girder 3 is erected between two adjacent peripheral posts 2, the inside of hollow core cylinder is also staggeredly equipped with many cylinder inner beams 6, many cylinder inner beams 6 longitudinally, laterally vertically arrange in groined type, the two ends of cylinder inner beam 6 are overlapped on shear wall 1 respectively, to reduce the weight of hollow core cylinder, reduce the seismic forces of basic load and structure, and can cost be reduced.
In the present embodiment, the area of rectangular hollow core cylinder is 300m
2, in many cylinder inner beams 6, the span of the cylinder inner beam 6 longitudinally arranged is 15m, and the span of the cylinder inner beam 6 transversely arranged is 20m.
In the shear wall 1 of the present embodiment, Partial Shear wall 1 body of wall is provided with the wall limb 7 stretched in hollow core cylinder cylinder, the structure of wall limb 7 is identical with shear wall 1, wall limb 7 is two, the shape that is centrosymmetric centered by the center line of rectangular hollow Core Walls Structure distributes, the length of wall limb 7 is 2m, in many cylinder inner beams 6, part cylinder inner beam 6 is overlapped on wall limb 7, all the other inner beams 6 are overlapped on shear wall 1 and do not arrange on the body of wall of wall limb 7, be erected in the Vierendeel girder 3 between peripheral post 2 and shear wall 1, frame segment is set a roof beam in place and 3 to be connected with the body of wall that shear wall 1 arranges wall limb 7, this part Vierendeel girder 3 lays respectively at the both sides of wall limb 7 with the cylinder inner beam 6 be overlapped on corresponding wall limb 7, be located along the same line with corresponding wall limb 7 and cylinder inner beam 6, this part Vierendeel girder 3 is also connected with the cylinder inner beam 6 be overlapped on corresponding wall limb 7 simultaneously, the body of wall that all the other Vierendeel girders 3 and shear wall 1 do not arrange wall limb 7 is connected, the breadth of section being overlapped on the cylinder inner beam 6 on wall limb 7 is identical with the thickness of wall limb 7, thickness is 0.6m, depth of section is 1.2m.
Cylinder inner beam 6 in structural system of the present invention, Vierendeel girder 3 is comparatively complicated with the annexation of shear wall 1, because shear wall 1 is only provided with two wall limbs 7, therefore the cylinder inner beam 6 of hollow core cylinder is arranged in, part cylinder inner beam 6 is only had to be overlapped on wall limb 7, the Vierendeel girder 3 being simultaneously positioned at hollow core cylinder periphery is all connected with the body of wall of shear wall 1, the body of wall that the Vierendeel girder 3 wherein had and shear wall 1 arrange wall limb 7 is connected, at this moment this part Vierendeel girder 3 and the cylinder inner beam 6 be overlapped on corresponding wall limb 7 lay respectively at the both sides of wall limb 7, be located along the same line with corresponding wall limb 7 and cylinder inner beam 6, this part Vierendeel girder 3 is also connected with the cylinder inner beam 6 be overlapped on corresponding wall limb 7 simultaneously, namely the Vierendeel girder 3 be located along the same line, shear wall 1, all interconnected relationship is there is between wall limb 7 and cylinder inner beam 6, and the Vierendeel girder 3 be not located along the same line, wall limb 7 and cylinder inner beam 6, Vierendeel girder 3, all only and between shear wall 1 there is annexation in cylinder inner beam 6.
In the present embodiment, be arranged in corresponding wall limb 7 both sides and the Vierendeel girder 3 be located along the same line and cylinder inner beam 6, Vierendeel girder 3, shear wall 1, position relationship between wall limb 7 and cylinder inner beam 6 and annexation are as shown in Figure 3, Vierendeel girder 3 is Vierendeel girder gluten 31, muscle 32 at the bottom of Vierendeel girder, tie up the reinforced concrete beam that Vierendeel girder gluten 31 is formed with Vierendeel girder stirrup 33 and the concreting of muscle 32 at the bottom of Vierendeel girder, cylinder inner beam 6 is cylinder inner beam gluten 61, muscle 62 at the bottom of cylinder inner beam, tie up the reinforced concrete beam that an inner beam gluten 61 is formed with beam stirrup 63 in the cylinder of muscle 62 at the bottom of cylinder inner beam and concreting, Vierendeel girder gluten 31 is connected through after shear wall 1 and wall limb 7 with cylinder inner beam gluten 61, at the bottom of Vierendeel girder, muscle 32 stretches in wall limb 7 through after shear wall 1, muscle 32 at the bottom of Vierendeel girder is positioned at the length >=LabE of shear wall 1 and wall limb 7, wherein, LabE is the basic anchorage length of tensile reinforcement antidetonation, it is the dialect of national regulation, at the bottom of cylinder inner beam, muscle 62 is positioned at the below of muscle 32 at the bottom of Vierendeel girder, with muscle at the bottom of Vierendeel girder 32 in upper and lower overlapping shape, at the bottom of cylinder inner beam, muscle 62 stretches in shear wall 1 through after wall limb 7, at the bottom of cylinder inner beam, muscle 62 is positioned at the length >=LabE of wall limb 7 and shear wall 1, Vierendeel girder 3 is formed with shear wall 1 and wall limb 7 and just connects in succession, cylinder inner beam 6 is also formed with shear wall 1 and wall limb 7 and just connects in succession.
In the present embodiment, connection between the body of wall that Vierendeel girder 3 and shear wall 1 do not arrange wall limb 7 is for just to connect in succession, as shown in Figure 4, Vierendeel girder 3 is Vierendeel girder gluten 31, muscle 32 at the bottom of Vierendeel girder, tie up the reinforced concrete beam that Vierendeel girder gluten 31 is formed with Vierendeel girder stirrup 33 and the concreting of muscle 32 at the bottom of Vierendeel girder, Vierendeel girder gluten 31 bends after stretching into shear wall 1 straight down, it stretches into the lateral length >=0.4LabE of shear wall 1, difference in height >=the LabE bottom and between the bottom surface of Vierendeel girder 3 bent straight down, at the bottom of Vierendeel girder, muscle 32 bends after stretching into shear wall 1 straight up, it stretches into the lateral length >=0.4LabE of shear wall 1, lateral length and the height sum >=LabE bent straight up.
In the present embodiment, as shown in Figure 5, overlap joint between the body of wall that cylinder inner beam 6 and shear wall 1 do not arrange wall limb 7 is for being articulated and connected, cylinder inner beam 6 is cylinder inner beam gluten 61, muscle 62 at the bottom of cylinder inner beam, tie up the reinforced concrete beam that an inner beam gluten 61 is formed with beam stirrup 63 in the cylinder of muscle 62 at the bottom of cylinder inner beam and concreting, bend straight down after cylinder inner beam gluten 61 stretches into shear wall 1, it stretches into the lateral length >=0.4LabE of shear wall 1, the height bent straight down is 15d1, d1 is a diameter for inner beam gluten 61, 15d1 is the minimum length of code requirement, meet this length, muscle 62 at the bottom of cylinder inner beam is vertically upper after stretching into shear wall 1 to be bent, it stretches into the lateral length >=0.4LabE of shear wall 1, the height bent straight up is 15d2, d2 is the diameter of muscle 62 at the bottom of an inner beam, at the bottom of cylinder inner beam, muscle 62 is identical with the structure of cylinder inner beam gluten 61, diameter is identical, namely d1 and d2 is identical, 15d2 is the minimum length of code requirement, meet this length.
The result of calculation that table 1 gives the present embodiment hollow core cylinder and frame-generic Core Walls Structure contrasts.
Table 1: hollow core cylinder of the present invention and the frame-generic Core Walls Structure result of calculation table of comparisons
As known from Table 1, structural entity quality reduces 5133t, and typical floor Core Walls Structure quality reduces 9%, and seismic forces reduces 5.9% ~ 8.6%, and structural cycle only increases 0.5% ~ 3.1%, and increase degree is less than the reduction degree of seismic forces.Overall story drift and the shear wall ratio of axial compressive force to axial compressive ultimate capacity of section of structure all meet Criterion restriction requirement.According to the amount of concrete reduced, shear force wall reinforcing steel bar amount, Foundation Design amount COMPREHENSIVE CALCULATING, can save cost about 8,000,000, accounts for total cost about 3%.
Calculated known by software simulation, shear wall damage results under the effect that large shake occurs is known, frame-generic Core Walls Structure scheme and frame hollow Core Walls Structure scheme mainly coupling beam are surrendered, respective location shear wall occurs that pressurized damages, but damage range is less, the maximum story drift of frame-generic Core Walls Structure scheme is 1/187, and the maximum story drift of frame hollow Core Walls Structure scheme is 1/179, illustrates that collapsing does not appear in structure under large shake effect.
As the conversion of the present embodiment, hollow core cylinder can adopt the rectangular cylinder of rectangle cylinder or square cylinder, also can adopt the cylindrical shells such as other structures such as circular cylinder.
As the conversion of the present embodiment, wall limb 7 is multiple, the shape that is centrosymmetric centered by the center line of rectangular hollow Core Walls Structure distributes, the length of wall limb 7 can within the scope of 1.5 ~ 2.5m value, the breadth of section being overlapped on the cylinder inner beam 6 on wall limb 7 is identical with the thickness of wall limb 7, thickness can within the scope of 0.2 ~ 0.8m value, depth of section can within the scope of 0.8 ~ 1.5m value.
Highrise building in the application refers to that the number of plies is the building of 20 layers ~ 60 layers; The area of hollow core cylinder is 300m
2~ 600m
2, in many cylinder inner beams 6, the span of the cylinder inner beam 6 longitudinally arranged is 7m ~ 20m, and the span of the cylinder inner beam 6 transversely arranged is 7m ~ 30m.
Embodiment two
The embodiment two of the frame hollow core wall structure system of a kind of highrise building of the present invention as shown in Figure 6 to 8, with embodiment one unlike, wall limb 7 in this present embodiment is four, lay respectively at four sides in hollow core cylinder inner core face, the shape that is centrosymmetric centered by the center line of hollow core cylinder distributes, and is positioned at the Vierendeel girder 3 of wall limb 7 both sides, cylinder inner beam 6 is all located along the same line with wall limb 7 three.
The above embodiment of the present invention is not limiting the scope of the present invention; embodiments of the present invention are not limited thereto; all this kind is according to foregoing of the present invention; according to ordinary technical knowledge and the customary means of this area; do not departing under the present invention's above-mentioned fundamental technics thought prerequisite; to the amendment of other various ways that said structure of the present invention is made, replacement or change, all should drop within protection scope of the present invention.
Claims (10)
1. the frame hollow core wall structure system of a highrise building, this structural system comprises shear wall (1), coupling beam (4), peripheral post (2), Vierendeel girder (3) and floor, described shear wall (1) is positioned at the center position of highrise building, shear wall (1) is the vertical multi-disc arranged, between adjacent shear wall (1), erection has described coupling beam (4), shear wall (1) and coupling beam (4) collar form a hollow core cylinder, described peripheral post (2) is positioned at the periphery of hollow core cylinder, peripheral post (2) is the many steel core concrete columns vertically arranged, Vierendeel girder (3) is also many, frame segment is set a roof beam in place (3) is erected between peripheral post (2) and shear wall (1), remaining Vierendeel girder (3) is erected between two adjacent peripheral posts (2), it is characterized in that: the inside of described hollow core cylinder is also staggeredly equipped with many cylinder inner beams (6), the two ends of cylinder inner beam (6) are overlapped on shear wall (1) respectively, to reduce the weight of hollow core cylinder, reduce the seismic forces of basic load and structure, and can cost be reduced.
2. the frame hollow core wall structure system of highrise building according to claim 1, is characterized in that: described hollow core cylinder is rectangular cylinder, and many described cylinder inner beams (6) longitudinally, are laterally vertically arranged in groined type.
3. the frame hollow core wall structure system of highrise building according to claim 2, it is characterized in that: in described shear wall (1), Partial Shear wall (1) body of wall is provided with the wall limb (7) stretched in hollow core cylinder cylinder, the structure of wall limb (7) is identical with shear wall (1), in many cylinder inner beams (6), part cylinder inner beam (6) is overlapped on described wall limb (7), all the other inner beams (6) are overlapped on shear wall (1) and do not arrange on the body of wall of wall limb (7), be erected in the Vierendeel girder (3) between peripheral post (2) and shear wall (1), the body of wall that frame segment is set a roof beam in place (3) with shear wall (1) arranges wall limb (7) is connected, this part Vierendeel girder (3) lays respectively at the both sides of wall limb (7) with the cylinder inner beam (6) be overlapped on corresponding wall limb (7), be located along the same line with corresponding wall limb (7) and cylinder inner beam (6), this part Vierendeel girder (3) is also connected with the cylinder inner beam (6) be overlapped on corresponding wall limb (7) simultaneously, the body of wall that all the other Vierendeel girders (3) do not arrange wall limb (7) with shear wall (1) is connected.
4. the frame hollow core wall structure system of highrise building according to claim 3, is characterized in that: the length of described wall limb (7) is 1.5 ~ 2.5m.
5. the frame hollow core wall structure system of highrise building according to claim 3, it is characterized in that: the breadth of section being overlapped on the cylinder inner beam (6) on described wall limb (7) is identical with the thickness of wall limb (7), thickness is 0.2 ~ 0.8m, and depth of section is 0.8 ~ 1.5m.
6. the frame hollow core wall structure system of highrise building according to claim 3, is characterized in that: described wall limb (7) is for multiple, and the shape that is centrosymmetric centered by the center line of rectangular hollow Core Walls Structure distributes.
7. the frame hollow core wall structure system of the highrise building according to any one of claim 3 to 6, it is characterized in that: be arranged in corresponding wall limb (7) both sides and the Vierendeel girder be located along the same line (3) and cylinder inner beam (6), described Vierendeel girder (3) is Vierendeel girder gluten (31), muscle at the bottom of Vierendeel girder (32), tie up the reinforced concrete beam that Vierendeel girder gluten (31) is formed with Vierendeel girder stirrup (33) and the concreting of muscle (32) at the bottom of Vierendeel girder, described cylinder inner beam (6) is cylinder inner beam gluten (61), muscle (62) at the bottom of cylinder inner beam, tie up the reinforced concrete beam that an inner beam gluten (61) is formed with beam stirrup (63) in the cylinder of muscle (62) at the bottom of cylinder inner beam and concreting, described Vierendeel girder gluten (31) is connected through after shear wall (1) and wall limb (7) with cylinder inner beam gluten (61), muscle (32) at the bottom of described Vierendeel girder is through stretching in wall limb (7) after shear wall (1), muscle at the bottom of Vierendeel girder (32) is positioned at the length >=LabE of shear wall (1) and wall limb (7), at the bottom of described cylinder inner beam, muscle (62) is positioned at the below of muscle at the bottom of Vierendeel girder (32), with muscle at the bottom of Vierendeel girder (32) in upper and lower overlapping shape, muscle (62) at the bottom of described cylinder inner beam is through stretching in shear wall (1) after wall limb (7), at the bottom of cylinder inner beam, muscle (62) is positioned at the length >=LabE of wall limb (7) and shear wall (1), described Vierendeel girder (3) is formed with shear wall (1) and wall limb (7) and just connects in succession, described cylinder inner beam (6) is also formed with shear wall (1) and wall limb (7) and just connects in succession.
8. the frame hollow core wall structure system of the highrise building according to any one of claim 3 to 6, it is characterized in that: the connection between the body of wall that Vierendeel girder (3) and shear wall (1) do not arrange wall limb (7) is for just to connect in succession, described Vierendeel girder (3) is Vierendeel girder gluten (31), muscle at the bottom of Vierendeel girder (32), tie up the reinforced concrete beam that Vierendeel girder gluten (31) is formed with Vierendeel girder stirrup (33) and the concreting of muscle (32) at the bottom of Vierendeel girder, bend straight down after described Vierendeel girder gluten (31) stretches into shear wall (1), it stretches into the lateral length >=0.4LabE of shear wall (1), difference in height >=the LabE bottom and between the bottom surface of Vierendeel girder (3) bent straight down, at the bottom of described Vierendeel girder, muscle (32) bends after stretching into shear wall (1) straight up, it stretches into the lateral length >=0.4LabE of shear wall (1), lateral length and the height sum >=LabE bent straight up.
9. the frame hollow core wall structure system of the highrise building according to any one of claim 3 to 6, it is characterized in that: the overlap joint between the body of wall that cylinder inner beam (6) and shear wall (1) do not arrange wall limb (7) is for being articulated and connected, described cylinder inner beam (6) is cylinder inner beam gluten (61), muscle (62) at the bottom of cylinder inner beam, tie up the reinforced concrete beam that an inner beam gluten (61) is formed with beam stirrup (63) in the cylinder of muscle (62) at the bottom of cylinder inner beam and concreting, bend straight down after described cylinder inner beam gluten (61) stretches into shear wall (1), it stretches into the lateral length >=0.4LabE of shear wall (1), the height bent straight down is 15d1, d1 is a diameter for inner beam gluten (61), muscle (62) at the bottom of described cylinder inner beam stretches into shear wall (1) vertically upper bending afterwards, it stretches into the lateral length >=0.4LabE of shear wall (1), the height bent straight up is 15d2, d2 is the diameter of muscle (62) at the bottom of an inner beam.
10. the frame hollow core wall structure system of highrise building according to claim 2, is characterized in that: described highrise building refers to that the number of plies is the building of 20 layers ~ 60 layers; The area of described hollow core cylinder is 300m
2~ 600m
2, in many described cylinder inner beams (6), the span of the cylinder inner beam (6) longitudinally arranged is 7m ~ 20m, and the span of the cylinder inner beam (6) transversely arranged is 7m ~ 30m.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510301101.7A CN104929242B (en) | 2015-06-05 | 2015-06-05 | Hollow core tube structure system of high-rise building frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510301101.7A CN104929242B (en) | 2015-06-05 | 2015-06-05 | Hollow core tube structure system of high-rise building frame |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104929242A true CN104929242A (en) | 2015-09-23 |
CN104929242B CN104929242B (en) | 2017-02-01 |
Family
ID=54116649
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510301101.7A Active CN104929242B (en) | 2015-06-05 | 2015-06-05 | Hollow core tube structure system of high-rise building frame |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104929242B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105544982A (en) * | 2015-12-08 | 2016-05-04 | 上海市机械施工集团有限公司 | Construction method for hyperboloid torsional steel column |
CN106223466A (en) * | 2016-09-08 | 2016-12-14 | 靳开元 | A kind of lamination courtyard-style building |
CN107338869A (en) * | 2017-09-06 | 2017-11-10 | 北京汇筑建筑科技有限公司 | Strengthening concrete Core Walls Structure and the structural system of concrete-filled rectangular steel tube Special-Shaped Column |
CN107366352A (en) * | 2017-04-10 | 2017-11-21 | 深圳市建筑设计研究总院有限公司 | Strong housing super-high building structure |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101914947A (en) * | 2010-07-30 | 2010-12-15 | 广州市设计院 | Novel frame-core tube combination structure system for high-rise |
CN201933619U (en) * | 2010-12-08 | 2011-08-17 | 香港华艺设计顾问(深圳)有限公司 | Reinforced layer structure applied to high-rise building |
CN102454217A (en) * | 2011-11-08 | 2012-05-16 | 浙江东南网架股份有限公司 | Bunchy tube structure for concrete core tubes and integrally-assembled space steel grids |
CN203347008U (en) * | 2013-07-11 | 2013-12-18 | 中建四局第六建筑工程有限公司 | Novel composite floor system for super high-rise building |
CN204715526U (en) * | 2015-06-05 | 2015-10-21 | 广东省建筑设计研究院 | A kind of frame hollow core wall structure system of highrise building |
-
2015
- 2015-06-05 CN CN201510301101.7A patent/CN104929242B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101914947A (en) * | 2010-07-30 | 2010-12-15 | 广州市设计院 | Novel frame-core tube combination structure system for high-rise |
CN201933619U (en) * | 2010-12-08 | 2011-08-17 | 香港华艺设计顾问(深圳)有限公司 | Reinforced layer structure applied to high-rise building |
CN102454217A (en) * | 2011-11-08 | 2012-05-16 | 浙江东南网架股份有限公司 | Bunchy tube structure for concrete core tubes and integrally-assembled space steel grids |
CN203347008U (en) * | 2013-07-11 | 2013-12-18 | 中建四局第六建筑工程有限公司 | Novel composite floor system for super high-rise building |
CN204715526U (en) * | 2015-06-05 | 2015-10-21 | 广东省建筑设计研究院 | A kind of frame hollow core wall structure system of highrise building |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105544982A (en) * | 2015-12-08 | 2016-05-04 | 上海市机械施工集团有限公司 | Construction method for hyperboloid torsional steel column |
CN105544982B (en) * | 2015-12-08 | 2017-08-25 | 上海市机械施工集团有限公司 | A kind of hyperboloid reverses steel column construction method |
CN106223466A (en) * | 2016-09-08 | 2016-12-14 | 靳开元 | A kind of lamination courtyard-style building |
CN107366352A (en) * | 2017-04-10 | 2017-11-21 | 深圳市建筑设计研究总院有限公司 | Strong housing super-high building structure |
CN107338869A (en) * | 2017-09-06 | 2017-11-10 | 北京汇筑建筑科技有限公司 | Strengthening concrete Core Walls Structure and the structural system of concrete-filled rectangular steel tube Special-Shaped Column |
Also Published As
Publication number | Publication date |
---|---|
CN104929242B (en) | 2017-02-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Takeuchi et al. | Study on a concrete filled structure for nuclear power plants | |
CN104929242A (en) | Hollow core tube structure system of high-rise building frame | |
JP6010215B2 (en) | Composite girders with abdominal members with various patterns | |
CN106149882A (en) | A kind of lateral resisting and antigravity separate steel structure of housing system and construction method thereof | |
CN106978873A (en) | A kind of removable bed die steel bar truss floor support plate structure and its construction method | |
CN204715526U (en) | A kind of frame hollow core wall structure system of highrise building | |
CN105696719B (en) | A kind of flexion-proof energy consumption supporting structure constrained using GFRP angle steel | |
CN103924739A (en) | Box-type steel bone-confined concrete column with round steel draw bars and fabrication method of column | |
CN107386481A (en) | A kind of substation structure rigidity intensifier | |
CN109653376A (en) | A kind of high-performance is greatly across heavily loaded multistory industrial buildings fabricated construction system | |
CN110714576A (en) | Corrugated steel pipe restricts steel core concrete column that UHPC component is strengthened | |
CN214833739U (en) | Novel assembled shear force wall | |
CN112459316B (en) | Vertical long cantilever truss structure for spiral ascending type curtain wall support and application | |
CN105951878A (en) | Steel box-type underground comprehensive pipe gallery provided with arched girder structure | |
CN206015882U (en) | The steel structure of housing system that a kind of lateral resisting and antigravity separate | |
CN112302170A (en) | Assembly armpit support type top and bottom angle steel beam column connecting steel frame | |
CN111910834B (en) | Design method of long longitudinal rib bent frame structure beam end reinforcement structure | |
CN206957320U (en) | Buckling restrained brace and building containing L-type dissipative cell | |
CN116084587A (en) | Steel wire mesh shear wall and construction method thereof | |
CN105155866A (en) | Separable sheath floor-adding structure of masonry buildings and floor-adding method thereof | |
CN104563390A (en) | FRP (fiber reinforce plastic) tube-concrete-multiple steel tube hollow combined single-box or multi-box multi-compartment beam | |
CN112069584B (en) | Design method of ductile structural pier for railway | |
CN214364054U (en) | Assembly armpit support type top and bottom angle steel beam column connecting steel frame | |
CN110184916B (en) | Main tower of cable-stayed bridge | |
CN209975734U (en) | High-performance large-span heavy-load multi-storey industrial building assembly type structure system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address | ||
CP03 | Change of name, title or address |
Address after: No.97 Liuhua Road, Liwan District, Guangzhou City, Guangdong Province 510010 Patentee after: Guangdong Architectural Design and Research Institute Co., Ltd Address before: Guangzhou City, Guangdong province 510010 Liuhua Road No. 97 Patentee before: ARCHITECTURAL DESIGN Research Institute OF GUANGDONG PROVINCE |