CN104915898A - 一种电压质量原因分析的方法和装置 - Google Patents

一种电压质量原因分析的方法和装置 Download PDF

Info

Publication number
CN104915898A
CN104915898A CN201510360541.XA CN201510360541A CN104915898A CN 104915898 A CN104915898 A CN 104915898A CN 201510360541 A CN201510360541 A CN 201510360541A CN 104915898 A CN104915898 A CN 104915898A
Authority
CN
China
Prior art keywords
voltage
analysis
data
decision tree
quality
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510360541.XA
Other languages
English (en)
Other versions
CN104915898B (zh
Inventor
于永军
方春明
祁晓笑
罗耀强
李敏
罗定志
查鸣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING ESTABLE ELECTRIC POWER TECHNOLOGY Co Ltd
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Xinjiang Electric Power Co Ltd
Original Assignee
NANJING ESTABLE ELECTRIC POWER TECHNOLOGY Co Ltd
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Xinjiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANJING ESTABLE ELECTRIC POWER TECHNOLOGY Co Ltd, State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Xinjiang Electric Power Co Ltd filed Critical NANJING ESTABLE ELECTRIC POWER TECHNOLOGY Co Ltd
Priority to CN201510360541.XA priority Critical patent/CN104915898B/zh
Publication of CN104915898A publication Critical patent/CN104915898A/zh
Application granted granted Critical
Publication of CN104915898B publication Critical patent/CN104915898B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Measurement Of Current Or Voltage (AREA)

Abstract

本发明公开了一种电压质量原因分析的方法和装置。该方法包括如下步骤:获取专家经验数据,然后生成决策树,然后根据生成的决策树对输入的电压指标数据进行分析,分析得到电压质量原因分析结果再由工作人员对结果评分,将评分值存入专家经验数据库中。本发明以评分值作为决策树生成的权重,使得生成的决策树更为合理,同时,本发明的决策树根据分析结果迭代累加,使得决策树分析结果更为接近实际。

Description

一种电压质量原因分析的方法和装置
技术领域
本发明涉及大数据处理,特别涉及机器学习在电压质量原因分析中的应用。
背景技术
决策树是一个利用树状的图形或决策模型的决策支持工具。决策树学习是使用决策树作为预测模型的机器学习方法。目前,机器学习算法越来越多地应用于各种大数据处理领域。
现有技术下,电压质量原因分析大部分需要依赖于人工。机器实现的电压质量原因分析通常由固定的程式所设定。当出现固定的程式所设定的范围外的情形,电压质量原因分析也就无法分析或者会作出错误的判断。
将机器学习算法特别是将决策树学习算法引入至电压质量原因分析是一个非常棒的手段。因为采用该方法后,决策树分析过程不再依赖于程序本身而依赖于其数据来源。就像加密算法中,加密算法的安全性不应当依赖于算法本身,而应当依赖于其加密的密钥。
发明内容
本发明所要解决的问题是:将决策树学习和决策树分析引入至电压质量原因分析。
为解决上述问题,本发明采用的方案如下:
根据本发明的一种电压质量原因分析的方法,包括如下步骤:
S1:获取专家经验数据,所述专家经验数据包括电压指标数据、电压质量原因分析结果以及评分值;
S2:根据专家经验数据采用决策树生成算法生成电压指标数据与电压质量原因分析结果的决策树,生成决策树时以评分值作为节点权重;
S4:根据电压指标数据与电压质量原因分析结果的决策树以及输入的电压指标数据进行分析得到电压质量原因分析结果;
S5:获得电压质量原因分析结果的评分值;
S6:将输入的电压指标数据、步骤S4得到的电压质量原因分析结果以及步骤S5得到的评分值组成专家经验数据存入数据库。
根据本发明的一种电压质量原因分析的装置,包括专家数据输入模块、专家数据存储模块、决策树生成模块、决策树存储模块、决策树分析模块以及分析结果评价模块;所述专家数据输入模块用于获取专家经验数据;所述专家数据存储模块用于存储专家经验数据;所述决策树生成模块用于根据专家数据存储模块存储的专家经验数据采用决策树生成算法生成电压指标数据与电压质量原因分析结果的决策树,生成决策树时以评分值作为节点权重;所述决策树存储模块用于存储电压指标数据与电压质量原因分析结果的决策树;所述决策树分析模块用于根据电压指标数据与电压质量原因分析结果的决策树以及输入的电压指标数据进行分析得到电压质量原因分析结果;所述分析结果评价模块用于向工作人员显示电压质量原因分析结果,并由工作人员评分后得到电压质量原因分析结果的评分值。
本发明的技术效果是:1、采用决策树学习和决策树分析,使得电压质量原因分析过程不再依赖于程序本身而依赖于其数据来源。2、本发明采用了评分值作为构建决策树时的一个权重参数使得构建的决策树更为合理。
附图说明
图1为本发明电压质量原因分析的装置的模块关系示意图。
具体实施方式
下面结合附图对本发明做进一步描述。
如图1所示,一种电压质量原因分析的装置,包括专家数据输入模块101、专家数据存储模块102、决策树生成模块103、决策树存储模块104、决策树分析模块105和分析结果评价模块106。专家数据输入模块101用于获取专家经验数据。
专家数据输入模块101获得的专家经验数据是最初始的专家经验数据,可以通过手工方式输入,也可以将数据编辑成特点格式的文本、或者Excel表格数据进行输入。专家经验数据电压指标数据、电压质量原因分析结果以及评分值组成。电压指标数据通常是由多个电压指标的条件语句组成,比如在高峰时间段内输出电压平均值小于215V。电压指标数据构成了电压质量标准评价。电压质量原因分析结果是电压指标数据所对应电压质量标准未达到要求的原因分析结果,比如主变调压能力不足、或者主变供电能力不足等等。评分值是由人工判断得到的电压指标数据至电压质量原因分析结果关系的可信性评价,分为五个等级1、2、3、4、5,评分高表示可信性程度较高。比如在高峰时间段内输出电压平均值小于215V时,原因分析结果对应的是主变调压能力不足,评分值可设为1;而在高峰时间段内输出电压平均值小于205V时,原因分析结果对应的是主变调压能力不足,评分值可设为4。
专家数据存储模块102用于存储专家经验数据。专家数据存储模块102通常由数据库实现,通过非易失性存储介质存储专家经验数据。专家数据存储模块102存储的专家经验数据不仅有来自专家数据输入模块101获得的初始的专家经验数据,还包括来自分析结果评价模块对决策树分析模块分析得到的分析结果进行评分后得到的数据。
决策树生成模块103用于根据专家数据存储模块存储的专家经验数据采用决策树生成算法生成电压指标数据与电压质量原因分析结果的决策树,生成决策树时以评分值作为节点权重。现有技术下决策树生成算法有很多种比如典型的ID3算法,不再累述。由于专家数据存储模块102存储的专家经验数据包括来自分析结果评价模块对决策树分析模块分析得到的分析结果进行评分后得到的数据,因此整个系统构成了一个迭代循环的过程。决策树生成模块103生成的电压指标数据与电压质量原因分析结果的决策树通过决策树存储模块104以数据库内容的形式存储在非易失性存储介质内。使得得到的电压指标数据与电压质量原因分析结果的决策树保持相对的稳定,只有当专家数据存储模块102存储的专家经验数据更新至一定状态时,才重新生成电压指标数据与电压质量原因分析结果的决策树。比如每隔一个星期或一个月生成一次电压指标数据与电压质量原因分析结果的决策树。
决策树分析模块105用于根据电压指标数据与电压质量原因分析结果的决策树以及输入的电压指标数据进行分析得到电压质量原因分析结果。该模块的输入是电压指标数据与电压质量原因分析结果的决策树以及输入的电压指标数据。决策树分析模块105得到的电压质量原因分析结果与输入的电压指标数据将输入分析结果评价模块106。分析结果评价模块106用于向工作人员显示电压质量原因分析结果,并由工作人员评分后得到电压质量原因分析结果的评分值。分析结果评价模块106得到的评分值与电压质量原因分析结果以及输入的电压指标数据将被作为专家经验数据存入专家数据存储模块102内。上述各个模块的工作过程可表示成下述步骤:
S1:获取专家经验数据,所述专家经验数据包括电压指标数据、电压质量原因分析结果以及评分值;
S2:根据专家经验数据采用决策树生成算法生成电压指标数据与电压质量原因分析结果的决策树,生成决策树时以评分值作为节点权重;
S4:根据电压指标数据与电压质量原因分析结果的决策树以及输入的电压指标数据进行分析得到电压质量原因分析结果;
S5:获得电压质量原因分析结果的评分值;
S6:将输入的电压指标数据、步骤S4得到的电压质量原因分析结果以及步骤S5得到的评分值组成专家经验数据存入数据库。

Claims (2)

1.一种电压质量原因分析的方法,其特征在于,包括如下步骤:
S1:获取专家经验数据,所述专家经验数据包括电压指标数据、电压质量原因分析结果以及评分值;
S2:根据专家经验数据采用决策树生成算法生成电压指标数据与电压质量原因分析结果的决策树,生成决策树时以评分值作为节点权重;
S4:根据电压指标数据与电压质量原因分析结果的决策树以及输入的电压指标数据进行分析得到电压质量原因分析结果;
S5:获得电压质量原因分析结果的评分值;
S6:将输入的电压指标数据、步骤S4得到的电压质量原因分析结果以及步骤S5得到的评分值组成专家经验数据存入数据库。
2.一种电压质量原因分析的装置,其特征在于,包括专家数据输入模块、专家数据存储模块、决策树生成模块、决策树存储模块、决策树分析模块以及分析结果评价模块;所述专家数据输入模块用于获取专家经验数据;所述专家数据存储模块用于存储专家经验数据;所述决策树生成模块用于根据专家数据存储模块存储的专家经验数据采用决策树生成算法生成电压指标数据与电压质量原因分析结果的决策树,生成决策树时以评分值作为节点权重;所述决策树存储模块用于存储电压指标数据与电压质量原因分析结果的决策树;所述决策树分析模块用于根据电压指标数据与电压质量原因分析结果的决策树以及输入的电压指标数据进行分析得到电压质量原因分析结果;所述分析结果评价模块用于向工作人员显示电压质量原因分析结果,并由工作人员评分后得到电压质量原因分析结果的评分值。
CN201510360541.XA 2015-06-26 2015-06-26 一种电压质量原因分析的方法和装置 Active CN104915898B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510360541.XA CN104915898B (zh) 2015-06-26 2015-06-26 一种电压质量原因分析的方法和装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510360541.XA CN104915898B (zh) 2015-06-26 2015-06-26 一种电压质量原因分析的方法和装置

Publications (2)

Publication Number Publication Date
CN104915898A true CN104915898A (zh) 2015-09-16
CN104915898B CN104915898B (zh) 2019-01-11

Family

ID=54084941

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510360541.XA Active CN104915898B (zh) 2015-06-26 2015-06-26 一种电压质量原因分析的方法和装置

Country Status (1)

Country Link
CN (1) CN104915898B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106054104A (zh) * 2016-05-20 2016-10-26 国网新疆电力公司电力科学研究院 一种基于决策树的智能电表故障实时预测方法
CN111026863A (zh) * 2018-10-09 2020-04-17 中国移动通信集团河北有限公司 客户行为预测方法、装置、设备及介质

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101609986A (zh) * 2008-06-20 2009-12-23 上海申瑞电力科技股份有限公司 基于决策树的多级联合协调自动电压控制方法
CN103729804A (zh) * 2014-01-02 2014-04-16 东南大学 一种应对电能质量预警的在线决策支持方法
CN104463706A (zh) * 2014-12-10 2015-03-25 深圳供电局有限公司 一种用于电网检测电压暂降事件原因的方法和系统

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101609986A (zh) * 2008-06-20 2009-12-23 上海申瑞电力科技股份有限公司 基于决策树的多级联合协调自动电压控制方法
CN103729804A (zh) * 2014-01-02 2014-04-16 东南大学 一种应对电能质量预警的在线决策支持方法
CN104463706A (zh) * 2014-12-10 2015-03-25 深圳供电局有限公司 一种用于电网检测电压暂降事件原因的方法和系统

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106054104A (zh) * 2016-05-20 2016-10-26 国网新疆电力公司电力科学研究院 一种基于决策树的智能电表故障实时预测方法
CN106054104B (zh) * 2016-05-20 2019-01-11 国网新疆电力公司电力科学研究院 一种基于决策树的智能电表故障实时预测方法
CN111026863A (zh) * 2018-10-09 2020-04-17 中国移动通信集团河北有限公司 客户行为预测方法、装置、设备及介质

Also Published As

Publication number Publication date
CN104915898B (zh) 2019-01-11

Similar Documents

Publication Publication Date Title
CN103903086A (zh) 一种基于业务模型驱动的管理信息系统开发方法及系统
CN102629204B (zh) 网页源代码生成方法及装置
US20160004794A1 (en) System and method using generative model to supplement incomplete industrial plant information
CN104268291A (zh) 一种数据一致性处理方法和系统
CN102870309A (zh) 便于设计高压(hvdc)控制系统的方法和系统、hvdc系统和优化hvdc系统的方法
US10360066B2 (en) Workflow generation from natural language statements
EP2897401A1 (en) Method and device for guaranteeing consistency of planning data
CN109299785A (zh) 一种机器学习模型的实现方法及装置
Garkina et al. Principles of optimal control in the synthesis of composite materials
CN104915898A (zh) 一种电压质量原因分析的方法和装置
US10760549B2 (en) Method and system for configuring wind turbines
CN103559350A (zh) 车辆的载荷文件处理方法和装置
CN104636397B (zh) 用于分布式计算的资源分配方法、计算加速方法以及装置
CN107562703A (zh) 字典树重构方法及系统
JP5113023B2 (ja) 勤務計画作成装置
CN104598554A (zh) 网页页面加载方法及装置
CN110110050A (zh) 一种新闻事件生成式问答数据集的生成方法
CN114239568A (zh) 基于自适应注意力机制的电网公文自动生成方法及装置
CN112486475A (zh) 基于大数据平台的可视化业务建模及模型管理系统
US9117187B2 (en) Presenting a filtered list of work items
Abdullah et al. Multicollinearity remedial techniques in model-building
CN110020833A (zh) 一种自动生成项目施工方案的方法
Zhang et al. A Three‐Stage Birandom Program for Unit Commitment with Wind Power Uncertainty
US20230288882A1 (en) Aging aware reward construct for machine teaching
CN113051750B (zh) 一种飞机可靠性数据资产风险闭环控制方法及装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Yu Yongjun

Inventor after: Jiao Chunlei

Inventor after: Du Bo

Inventor after: Luo Yaoqiang

Inventor after: Luo Dingzhi

Inventor after: Cha Ming

Inventor after: Li Min

Inventor after: Qi Xiaoxiao

Inventor after: Wang Chen

Inventor after: Zhu Jianhua

Inventor after: Zheng Shaopeng

Inventor after: Wang Fangnan

Inventor after: Zhao Zilong

Inventor after: Qin Yanhui

Inventor after: Liu Dagui

Inventor before: Yu Yongjun

Inventor before: Fang Chunming

Inventor before: Qi Xiaoxiao

Inventor before: Luo Yaoqiang

Inventor before: Li Min

Inventor before: Luo Dingzhi

Inventor before: Cha Ming

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20160310

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: Electric Power Research Institute, State Grid Xinjiang Electric Power Company

Applicant after: Nanjing Estable Electric Power Technology Co., Ltd.

Address before: The central city of Nanjing road 210009 Jiangsu xinliji No. 258-27 Building 9 floor

Applicant before: Nanjing Estable Electric Power Technology Co., Ltd.

Applicant before: State Grid Corporation of China

Applicant before: Electric Power Research Institute, State Grid Xinjiang Electric Power Company

GR01 Patent grant
GR01 Patent grant