- CN104895536B CN104895536B CN201510239370.5A CN201510239370A CN104895536B CN 104895536 B CN104895536 B CN 104895536B CN 201510239370 A CN201510239370 A CN 201510239370A CN 104895536 B CN104895536 B CN 104895536B
- Authority
- CN
- China
- Prior art keywords
- injection
- column jacket
- production column
- pipe
- sleeve pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The invention provides a kind of method and injection-production column jacket for noting gas recovery well reducing completion, this method comprises the following steps:Step 1: installing the upper sleeve pipe (1) and setting of casing (2) for completion in well, the external diameter of upper sleeve pipe (1) is more than the external diameter of setting of casing (2);Step 2: in gas drive oil recovery stage injection-production column jacket of tripping in first into the sleeve pipe;Step 3: the external diameter for first taking out the oil pipe used in first injection-production column jacket injection-production column jacket of tripping in second into the sleeve pipe again, second injection-production column jacket out of this sleeve pipe in the gas storage stage is more than the external diameter of the oil pipe used in first injection-production column jacket.The method and injection-production column jacket of the note gas recovery well reducing completion can look after the low demand with fluence of gas drive early stage in the case where not digging a well again, and the high demand for matching somebody with somebody fluence of gas production stage completion can also be noted in the later stage.
Description
Technical field
It is particularly a kind of to note gas recovery well reducing completion the present invention relates to oil field gas storage note gas recovery well completion technique field
Method, a kind of or injection-production column jacket used in the method for the note gas recovery well reducing completion.
Background technology
During non-exhausted type oil-gas reservoir gas storage reconstruction, often in two stages:First stage is that gas drive is recovered the oil the stage, in order to
The stable exploitation of gas drive oil recovery is realized, its gas drive gas injection rate at initial stage is relatively low, and durations are longer, for reduction cost of investment, general first
Design uses small size sleeve pipe, and the gas injection productive completion tubing string of supporting reduced size ensures gas injection;Second stage is gas storage
In the stage, to meet the demand of emergency peak regulation, it is typically designed using large scale sleeve pipe, and supporting large-size note gas production productive completion
Tubing string ensures note gas production, and this design method is primarily present the shortcoming of following several respects:
If the 1, gas drive recovers the oil the stage directly using large scale oil pipe and sleeve pipe, higher and very long gas drive mistake is once put into
Journey has made original gas injection oil pipe be damaged, and turns also to need to change a tubing string during exploitation of later stage gas storage, equally causes wave
Take.
If the 2, gas drive recovers the oil the stage using large scale sleeve pipe, small size oil pipe is matched, then occurs that little oil pipe is supported the use
Big packer design, around the stress problem such as dynamic deformation when can increase tubing string gas injection, it is necessary to use small size packer and correspondence note
Gas and oil tubing string, then should use small size sleeve pipe.
Once it can not be changed in stage small casing lower going-into-well if 3, gas drive is recovered the oil, when the later stage switchs to gas storage well, individual well
Certainly will significantly it be adjusted upward with yield, original gas injection oil pipe can not be met with production demand, then needs to dig a well again,
Change large scale sleeve pipe.
In addition original small casing gas injection well needs shut-in well, that is, adds potential safety hazard, also result in waste.
The content of the invention
In order to solve that existing oil field gas storage note gas recovery well completion technique occurs in former and later two stages it is above-mentioned the problem of,
The invention provides a kind of method and injection-production column jacket for noting gas recovery well reducing completion, the method for the note gas recovery well reducing completion can be with
In the case where not digging a well again, that is, the low demand with fluence of gas drive early stage is looked after, can also be completed in the note gas production stage in later stage
Height matches somebody with somebody the demand of fluence.
The technical solution adopted for the present invention to solve the technical problems is:A kind of method for noting gas recovery well reducing completion, bag
Include following steps:
Step 1: install the sleeve pipe for completion in well, the sleeve pipe include the upper sleeve pipe being sequentially connected from the top down and
Setting of casing, the external diameter of upper sleeve pipe is more than cased external diameter, and the area of passage of upper sleeve pipe is more than cased area of passage;
Step 2: in gas drive oil recovery stage injection-production column jacket of tripping in first into the sleeve pipe;
Step 3: first taking out first injection-production column jacket tripping in second into the sleeve pipe again out of this sleeve pipe in the gas storage stage
The external diameter of the second oil pipe used in injection-production column jacket, second injection-production column jacket is more than the first oil used in first injection-production column jacket
The area of passage of the second oil pipe used in the external diameter of pipe, second injection-production column jacket is more than the used in first injection-production column jacket
The area of passage of one oil pipe.
The step of also including specially playing technology drilling well using oil reservoirs before step one.
Upper sleeve pipe is located at 50m~100m above well head to the top circle of oil reservoirs.
The external diameter of upper sleeve pipe is more than or equal to 177.8mm, and the wall thickness of upper sleeve pipe is 9mm~10mm, and cased external diameter is less than
177.8mm, cased wall thickness is 7mm~9mm.
Step 2 be gas drive recover the oil the stage initial stage into the sleeve pipe injection-production column jacket of tripping in first, first injection-production column jacket
Circulation slide sleeve, retrievable packer, blocking including being sequentially connected from the top down by first oil pipe are located pipe nipple, test and sat
Fall pipe nipple and horn mouth, retrievable packer is set in cased top.
The external diameter of first oil pipe used in first injection-production column jacket is 88.9mm, is used in first injection-production column jacket
The wall thickness of first oil pipe is 6mm~8mm.
Second injection-production column jacket includes flowing pipe nipple, the downhole safety being sequentially connected from the top down by second oil pipe
Valve, flowing pipe nipple, circulation slide sleeve, retrievable packer, blocking are located pipe nipple, test and are located pipe nipple and horn mouth, retrievable envelope
Set every device in the bottom of upper sleeve pipe.
The external diameter of second oil pipe used in second injection-production column jacket is 114.3mm, is used in second injection-production column jacket
Second oil pipe wall thickness be 6mm~13mm.
A kind of injection-production column jacket, the injection-production column jacket is the second above-mentioned injection-production column jacket, and second injection-production column jacket is included by oil
Manage the flowing pipe nipple being sequentially connected from the top down, storm valve, flowing pipe nipple, circulation slide sleeve, retrievable packer, blocking seat
Fall pipe nipple, test and be located pipe nipple and horn mouth.
Pipe nipple is located in blocking and test is located pipe nipple and connected by punching oil pipe.
The beneficial effects of the invention are as follows the method and injection-production column jacket of the note gas recovery well reducing completion can not dig a well again
In the case of, that is, the low demand with fluence of gas drive early stage is looked after, the high need for matching somebody with somebody fluence of gas production stage completion can also be noted in the later stage
Ask, improve the service life of note gas recovery well, taken into account oil reservoir gas drive demand in the demand of gas storage reconstruction, effectively reduced and build
Kucheng's sheet.
Brief description of the drawings
The present invention is described in further detail below in conjunction with the accompanying drawings.
Fig. 1 is the schematic diagram in gas drive oil recovery stage injection-production column jacket of tripping in first into sleeve pipe.
Fig. 2 is the schematic diagram in gas storage stage injection-production column jacket of tripping in second into sleeve pipe.
Fig. 3 is bell-mouthed structural representation in the first injection-production column jacket and the second injection-production column jacket.
Sleeve pipe on wherein 1., 2. setting of casings, 3. oil reservoirs;
11. pipe nipple is located in circulation slide sleeve, 12. retrievable packers, 13. blockings, pipe nipple, 15. loudspeaker are located in 14. tests
Mouthful.
21. pipe nipple is flowed, 22. storm valves, 23. circulation slide sleeves, 24. retrievable packers, 25. blockings are located short
Pipe nipple, 28. horn mouths are located in section, 26. punching oil pipes, 27. tests.
Embodiment
It should be noted that in the case where not conflicting, the feature in embodiment and embodiment in the application can phase
Mutually combination.Describe the present invention in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
A kind of method for noting gas recovery well reducing completion, comprises the following steps:
Step 1: installing the sleeve pipe for completion in well, the sleeve pipe includes the He of upper sleeve pipe 1 being sequentially connected from the top down
Setting of casing 2, the area of passage that the external diameter of upper sleeve pipe 1 is more than in the external diameter of setting of casing 2, upper sleeve pipe 1 is more than in setting of casing 2 excessively stream
Area;
Step 2: being recovered the oil thinner the first injection-production column jacket of stage tripping in into the sleeve pipe in gas drive, as shown in Figure 1;
Step 3: first taking out first injection-production column jacket out of this sleeve pipe in the gas storage stage, into the sleeve pipe, tripping in is thicker again
The second injection-production column jacket, the external diameter of the second oil pipe used in second injection-production column jacket is more than what is used in first injection-production column jacket
The area of passage in second oil pipe used in the external diameter of first oil pipe, second injection-production column jacket is more than first injection-production column jacket
Area of passage in middle the first oil pipe used, as shown in Figure 2.
The external diameter of upper sleeve pipe 1 is more than the excessively stream that the area of passage in the external diameter of setting of casing 2, upper sleeve pipe 1 is more than in setting of casing 2
Area, is no longer changed after the upper sleeve pipe 1 of different-diameter and the tripping in of setting of casing 2, so can be in the set that is changed without of not digging a well again
In the case of pipe, that is, the low demand with fluence of early stage is looked after, the high demand for matching somebody with somebody fluence of gas production stage completion can also be noted in the later stage, is carried
The high service life of note gas recovery well, has taken into account oil reservoir gas drive demand in the demand of gas storage reconstruction, has reduced later stage shut-in well
Potential safety hazard, it is therefore prevented that waste, effectively reduce and build Kucheng's sheet.
Also included drilling well specially beats technology during the drilling well to oil reservoirs 3 using reservoir before step one, should
Reservoir is specially beaten technology and is no longer discussed in detail for prior art.
In the present embodiment, upper sleeve pipe 1 is located at 50m above well head to the top circle of oil reservoirs 3 (i.e. A is 50m in Fig. 1), under
Sleeve pipe 2 is located at the lower section of upper sleeve pipe 1, i.e. setting of casing 2 and is located at below 50m above the top circle of the oil reservoirs 3 and the oil reservoirs 3.On
The external diameter of sleeve pipe 1 is that more than or equal to 177.8mm, the wall thickness of upper sleeve pipe 1 is 9mm~10mm, the external diameter of setting of casing 2 be less than
177.8mm, the wall thickness of setting of casing 2 is 7mm~9mm.The setting of casing 2 of certain length minor diameter is left in cap rock bottom, before being easy to
The demand of gas drive phase, workover treatment stage.
Step 2 be gas drive recover the oil the stage initial stage into the sleeve pipe injection-production column jacket of tripping in first, first injection-production column jacket
Including the circulation slide sleeve 11 being sequentially connected from the top down by first oil pipe, retrievable packer 12, block be located pipe nipple 13,
Pipe nipple 14 and horn mouth 15 are located in test, and retrievable packer 12 is set in the top in setting of casing 2, as shown in Figure 1.This first
The external diameter of the oil pipe used in injection-production column jacket is 88.9mm, and the wall thickness of first oil pipe used in first injection-production column jacket is
6mm~8mm.
Second injection-production column jacket includes flowing pipe nipple 21, the downhole safety being sequentially connected from the top down by second oil pipe
Valve 22, flowing pipe nipple 21, circulation slide sleeve 23, retrievable packer 24, blocking are located pipe nipple 25, test and are located pipe nipple 27 and loudspeaker
Mouthfuls 28, retrievable packer 24 is set in the bottom in upper sleeve pipe 2, as shown in Fig. 2 used in second injection-production column jacket this
The wall thickness of second oil pipe used in the external diameter 114.3mm of two oil pipes, second injection-production column jacket is 6mm~13mm.Horn mouth
28 structure can reduce gas injection erosion, if while testing tool tripping in is oily as shown in figure 3, have chamfering inside the horn mouth 28
When below pipeline section, facilitate bailing.
In the present embodiment, pipe nipple 25 is located in blocking and test is located pipe nipple 27 and connected by punching oil pipe 26.Punching oil
Pipe 26 is the oil pipe that side wall contains through hole, and storm valve 22 is also associated with liquid controling pipe line.
Second injection-production column jacket, which contains, to be had the advantage that:
1st, it is simple in construction, deblocking is easy to using retrievable packer, deblocking workload is small, is easy to later stage operation to safeguard, no
The normal operation of gas storage can be influenceed.
2nd, second injection-production column jacket considers the influence of storm valve necking down, and flowing short circuit is equipped with its upper and lower side, with
The generation of erosion is prevented, it is safe.
3rd, second injection-production column jacket employs larger-diameter design of string pipe, can avoid under abnormal conditions to oil pipe completely
Erosion adopted by force with injection, reduce gas well unloading risk, ensure gas storage gas supply capacity while, as far as possible increase oil
The need for pipe diameter is to meet single well productivity.
4th, the injection-production column jacket body of second injection-production column jacket uses L8013Cr type stainless steel tubes, with stronger anticorrosive
Property, extend the service life of tubing string.
5th, each connection member of second injection-production column jacket is threadedly coupled using hermetic seal, so as to ensure that each is connected
Air-tightness between part.
It is described above, it is only the specific embodiment of the present invention, it is impossible to which the scope implemented is invented with its restriction, so it is equivalent
The displacement of component, or the equivalent variations made according to scope of patent protection of the present invention and modification, should all still fall within what this patent was covered
Category.In addition, between technical characteristic and technical characteristic in the present invention, between technical characteristic and technical scheme, technical scheme with
It can be used between technical scheme with independent assortment.
Claims (5)
1. it is a kind of note gas recovery well reducing completion method, it is characterised in that the method for the note gas recovery well reducing completion include with
Lower step:
Step 1: install the sleeve pipe for completion in well, the sleeve pipe include the upper sleeve pipe (1) being sequentially connected from the top down and under
Sleeve pipe (2), the external diameter of upper sleeve pipe (1) is more than the external diameter of setting of casing (2), and the area of passage of upper sleeve pipe (1) is more than setting of casing (2)
Area of passage, upper sleeve pipe (1) is located at 50m~100m above the top circle of oil reservoirs (3), and the upper sleeve pipe (1) is from oil reservoirs
(3) 50m~100m extends to well head above top circle;
Step 2: in gas drive oil recovery stage injection-production column jacket of tripping in first into the sleeve pipe;
First injection-production column jacket includes circulation slide sleeve (11), the retrievable packer being sequentially connected from the top down by the first oil pipe
(12), block and be located pipe nipple (13), test and be located pipe nipple (14) and horn mouth (15), the retrievable packing of first injection-production column jacket
Device (12) is set in the top of setting of casing (2);
Step 3: first taking out first injection-production column jacket out of this sleeve pipe in the gas storage stage, into the sleeve pipe, the note of tripping in second is adopted again
The external diameter of the second oil pipe used in tubing string, second injection-production column jacket is more than the first oil pipe used in first injection-production column jacket
The area of passage of the second oil pipe used in external diameter, second injection-production column jacket is more than the first oil used in first injection-production column jacket
The area of passage of pipe;
Second injection-production column jacket includes flowing pipe nipple (21), the storm valve being sequentially connected from the top down by second oil pipe
(22), flowing pipe nipple (21), circulation slide sleeve (23), retrievable packer (24), blocking are located pipe nipple (25), test and are located pipe nipple
(27) and horn mouth (28), the retrievable packer (24) of second injection-production column jacket is set in the bottom of upper sleeve pipe (1).
2. the method for note gas recovery well reducing completion according to claim 1, it is characterised in that also include before step one
The step of specially technology drilling well being played using oil reservoirs (3).
3. the method for note gas recovery well reducing completion according to claim 1, it is characterised in that the external diameter of upper sleeve pipe (1) is big
It is 9mm~10mm in the wall thickness equal to 177.8mm, upper sleeve pipe (1), the external diameter of setting of casing (2) is less than 177.8mm, setting of casing (2)
Wall thickness be 7mm~9mm.
4. the method for note gas recovery well reducing completion according to claim 1, it is characterised in that make in first injection-production column jacket
The external diameter of first oil pipe is 88.9mm, the wall thickness of first oil pipe used in first injection-production column jacket for 6mm~
8mm。
5. the method for note gas recovery well reducing completion according to claim 1, it is characterised in that make in second injection-production column jacket
The external diameter of second oil pipe is 114.3mm, the wall thickness of second oil pipe used in second injection-production column jacket for 6mm~
13mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510239370.5A CN104895536B (en) | 2015-05-12 | 2015-05-12 | A kind of method and injection-production column jacket for noting gas recovery well reducing completion |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510239370.5A CN104895536B (en) | 2015-05-12 | 2015-05-12 | A kind of method and injection-production column jacket for noting gas recovery well reducing completion |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104895536A CN104895536A (en) | 2015-09-09 |
CN104895536B true CN104895536B (en) | 2017-10-17 |
Family
ID=54028452
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510239370.5A Active CN104895536B (en) | 2015-05-12 | 2015-05-12 | A kind of method and injection-production column jacket for noting gas recovery well reducing completion |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104895536B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112081534B (en) * | 2019-06-14 | 2022-06-28 | 中国石油化工股份有限公司 | Anti-erosion injection-production pipe column structure |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2431770C1 (en) * | 2010-05-18 | 2011-10-20 | Государственное образовательное учреждение высшего профессионального образования Военный инженерно-технический университет | Underground storage of liquefied natural gas |
DE102010024363A1 (en) * | 2010-06-18 | 2011-12-22 | Nasser Berg Energie Gmbh | Method for natural and artificial underground storage of e.g. natural gas, involves utilizing carbon dioxide as sustained proportionate or entire base gas, where hydrocarbon is provided as process gas |
CN202645521U (en) * | 2012-06-25 | 2013-01-02 | 中国石油天然气股份有限公司 | Horizontal well injecting and extracting pipe column of gas reservoir |
CN103089199A (en) * | 2011-11-03 | 2013-05-08 | 大港油田集团有限责任公司 | Depleted oil-gas reservoir underground gas storage injection-production string and operating method thereof |
CN203925434U (en) * | 2014-05-15 | 2014-11-05 | 中国石油天然气股份有限公司 | Underground natural gas storage tank horizontal well completion tubular pile |
CN203959096U (en) * | 2014-06-30 | 2014-11-26 | 中国石油天然气股份有限公司 | Gas storage is observed well completion tubular column |
CN104373053A (en) * | 2014-11-28 | 2015-02-25 | 中国石油天然气集团公司 | Underground natural gas storage injection-production pipe column designing method |
-
2015
- 2015-05-12 CN CN201510239370.5A patent/CN104895536B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2431770C1 (en) * | 2010-05-18 | 2011-10-20 | Государственное образовательное учреждение высшего профессионального образования Военный инженерно-технический университет | Underground storage of liquefied natural gas |
DE102010024363A1 (en) * | 2010-06-18 | 2011-12-22 | Nasser Berg Energie Gmbh | Method for natural and artificial underground storage of e.g. natural gas, involves utilizing carbon dioxide as sustained proportionate or entire base gas, where hydrocarbon is provided as process gas |
CN103089199A (en) * | 2011-11-03 | 2013-05-08 | 大港油田集团有限责任公司 | Depleted oil-gas reservoir underground gas storage injection-production string and operating method thereof |
CN202645521U (en) * | 2012-06-25 | 2013-01-02 | 中国石油天然气股份有限公司 | Horizontal well injecting and extracting pipe column of gas reservoir |
CN203925434U (en) * | 2014-05-15 | 2014-11-05 | 中国石油天然气股份有限公司 | Underground natural gas storage tank horizontal well completion tubular pile |
CN203959096U (en) * | 2014-06-30 | 2014-11-26 | 中国石油天然气股份有限公司 | Gas storage is observed well completion tubular column |
CN104373053A (en) * | 2014-11-28 | 2015-02-25 | 中国石油天然气集团公司 | Underground natural gas storage injection-production pipe column designing method |
Also Published As
Publication number | Publication date |
---|---|
CN104895536A (en) | 2015-09-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103015955B (en) | Open-hole horizontal well multi-cluster sliding sleeve staged fracturing string and fracturing method thereof | |
CN102979495B (en) | Many bunches of Limited entry fracturing tubing strings of open-hole horizontal well and fracturing process thereof | |
CN201212387Y (en) | Gas injection, gas production and brine discharge integration process pipe column for underground gas storage | |
CN107489397A (en) | A kind of solvable bridging plug and oil gas well shaft insulate method temporarily | |
CN105804680B (en) | A kind of oil gas field workover operation device with pressure and method | |
CN204703876U (en) | A kind of bridge-type concentric separated-injection tubing string | |
NO329656B1 (en) | Coupling isolation device for use in multilateral well processing operation | |
CN102454381B (en) | Oil-gas reservoir barefoot well cementing and completion method and device | |
CN107304661A (en) | Single current valve module, gas lift valve, gaslift instrument and integrated pipe column | |
CN203308443U (en) | Circulating gas injection pipe column | |
CN206668234U (en) | A kind of ball-throwing type selective sand control process pipe string | |
CN109611061B (en) | Method for floating and running sieve tube | |
CN104895536B (en) | A kind of method and injection-production column jacket for noting gas recovery well reducing completion | |
CN205605156U (en) | Workover device is pressed in oil gas field area | |
CN104989325B (en) | A kind of method using two-tube gas well liquid loading tubing string gas production arranged side by side | |
CN205000922U (en) | Built -in coiled tubing completion pipe string | |
CN104879098B (en) | A kind of concentric double pipe gas well liquid loading tubing string | |
CN204703779U (en) | A kind of injection-production column jacket | |
CN112081535A (en) | Ultra-deep high-sulfur-content gas well completion pipe string and construction method thereof | |
CN112177581B (en) | Repeated fracturing method for old well | |
CN104420841B (en) | The method for removing flow string with pressure | |
CN111058792A (en) | Coiled tubing perforation-free under-pressure operation-free well completion device and method | |
CN207686691U (en) | Tubing string for being layered gas drive | |
EP3052750B1 (en) | Flexible zone inflow control device | |
CN104265231A (en) | Circulation blanking plug and application method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |