CN104895058B - The all-hydraulic two-tube compound club-footed pile machine of static pressure and its construction method - Google Patents

The all-hydraulic two-tube compound club-footed pile machine of static pressure and its construction method Download PDF

Info

Publication number
CN104895058B
CN104895058B CN201510331164.7A CN201510331164A CN104895058B CN 104895058 B CN104895058 B CN 104895058B CN 201510331164 A CN201510331164 A CN 201510331164A CN 104895058 B CN104895058 B CN 104895058B
Authority
CN
China
Prior art keywords
tube
pile
inner tube
base expanding
outer tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510331164.7A
Other languages
Chinese (zh)
Other versions
CN104895058A (en
Inventor
沈国勤
欧国兴
于启亮
沈飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Jinzhuang Geotechnical Technology Co ltd
Jianji Construction Group Co ltd
Original Assignee
JIANJI CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANJI CONSTRUCTION GROUP CO Ltd filed Critical JIANJI CONSTRUCTION GROUP CO Ltd
Priority to CN201510331164.7A priority Critical patent/CN104895058B/en
Publication of CN104895058A publication Critical patent/CN104895058A/en
Application granted granted Critical
Publication of CN104895058B publication Critical patent/CN104895058B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a kind of all-hydraulic two-tube compound club-footed pile machine of static pressure and construction method, including clip pile system and be lifted on it is compound two-tube in clip pile system, described compound two-tube including inner and outer tubes, said inner tube is sleeved on outer tube, is fixed using coupling arrangement on inner and outer pipes top;The clip pile system can be made up of upper pile clamping box and lower pile clamping box, upper and lower 35 meters of two sets of pile clamping box effective travels, and lower pile clamping box clamps outer tube, and upper pile clamping box can not only clamp outer tube but also can clamp inner tube, and press to form base expanding and base expanding effect using inner tube.Or the clip pile system includes a lower pile clamping box, lower clip pile upper box part is provided with a clamp support for 2 meters of clear height, piling stroke is 34 meters, top pressure transverse beam system is provided with clamp support, the top pressure transverse beam system square top pressure inner tube on inner pipe, the top pressure transverse beam system square back-pressure inner tube on inner pipe, forms base expanding and base expanding effect.The present invention is a kind of without friction, noiselessness, free of contamination construction machinery and construction technology.

Description

The all-hydraulic two-tube compound club-footed pile machine of static pressure and its construction method
Technical field
The present invention relates to a kind of all-hydraulic two-tube compound club-footed pile machine of static pressure and its construction method, belong to Construction Technology Field.
Background technology
The compound club-footed pile of strong rammer vibration is a kind of two-tube compound bottom-enlarging filling pile of hammering vibration, and bavin is used in work progress Used as power is rammed, during hammering, diesel oil produces outburst energy to oil hammer through the atomization of cylinder, and soil property is harder, impact capacity Bigger, noise is bigger;Soil property is softer, and diesel oil atomization is bad, and black smoke is more, thus diesel hammer in work progress to job site Surrounding enviroment produce strong noise and vibration, and the black smoke for producing also pollutes environment.Due to these disadvantages, seriously constrain Diesel hammer is in the regional popularization such as old town, resident living area, hospital, school and uses.
The content of the invention
The technical problem to be solved in the invention is that the defect for overcoming prior art, there is provided a kind of all-hydraulic static pressure is double Pipe compound club-footed pile machine and its construction method.
In order to solve the above technical problems, the present invention is adopted the following technical scheme that:
A kind of all-hydraulic two-tube compound club-footed pile machine of static pressure of the present invention, including clip pile system and be lifted in clip pile system Compound two-tube, described compound two-tube including inner and outer tubes, said inner tube is sleeved on outer tube, and inner tube external diameter is less than in outer tube More than footpath 5cm, inner tube 10-20cm shorter than outer tube, inner tube upper seal steel plate with diameter greater than outer tube external diameter 2-3cm, and inside and outside Pipe top is fixed using coupling arrangement;Outer tube thickness of steel pipe must not be less than 2cm.
The clip pile system is made up of upper pile clamping box and lower pile clamping box, upper and lower 3-5 meters of two sets of pile clamping box effective travels, under Pile clamping box clamps outer tube, and upper pile clamping box can not only clamp outer tube but also can clamp inner tube, and press to form base expanding and base expanding effect using inner tube.
Or, the clip pile system includes a lower pile clamping box, and lower clip pile upper box part is provided with a clamp for 2 meters of clear height Support, piling stroke is 3-4 meters, and top pressure transverse beam system is provided with clamp support, and the top pressure transverse beam system is square on inner pipe Top pressure inner tube, the top pressure transverse beam system square back-pressure inner tube on inner pipe, forms base expanding and base expanding effect.
The present invention discloses a kind of all-hydraulic two-tube compound pedestal pile constructing process of static pressure, one is connected and fixed It is inside and outside two-tube hang in pile clamping box, it is inside and outside it is two-tube higher than 0.5 meter of ground surface soil when, clamping oil cylinder starts to clamp work in pile clamping box Make, outer tube is embraced jail, stake machine flatness is adjusted followed by hydraulic traveling mechanism, inside and outside total powerstation and the two-way correction of theodolite Pipe perpendicularity, it is ensured that perpendicularity is within code requirement;
1)Pressure pipe top cylinder system is opened, ensures for inner and outer pipes to be pressed onto design mark by 2-4 meters of height of each stroke It is high;
2)Inner and outer pipes top coupling arrangement is released, inner tube outer tube is extracted into using random crane or crawler crane, in outer tube Inside pour into 0.25-0.3m3Input material, input material height be H=2-2.5 meter, input material be particle diameter 15-30cm stone, concrete block And fragment of brick;
3)Interior effective loop wheel machine is put into outer tube and fastens input material, outer tube, jacking cylinder are embraced in subsequent clip pile system work System starts, 1-1.5 meters will be pulled out by design requirement on outer tube, stop jacking apparatus work, releases grasping system work, folder Hold oil cylinder and reply internal, about 1.8 meters of a stroke while jacking cylinder system is up walked then is replied and falls piling bottom portion Start the second stroke and reach inside top, subsequent grasping system work, clamping oil cylinder clips inner tube top steel pipe and down walks, directly Former design stake bottom absolute altitude is synchronously pressed onto to static pressure to inside and outside steel pipe, stake end forms first time auxiliary material base expanding and base expanding, then according to design It is required that carry out secondary batching, feed intake for three times, all-hydraulic static pressure base expanding and base expanding is through multiple auxiliary material base expanding and base expanding;
4)According to design and test pile result, with reference to last time static pressure base expanding and base expanding maximum pressure value, reached end resistance is met To design requirement;
5)Inner tube is extracted, 0.2-0.3M3 is added, the slump is the concrete of the C30-C50 of 3-6cm, by that analogy, repeatedly complete Hydraulic static companding bottom, final hydraulic control indoor static pressure, when pressure value meets design requirement untill, otherwise repeatedly said procedure, Until meeting design load single pile requirement;
6), extract inner tube decentralization steel reinforcement cage:Inner tube is extracted, steel reinforcement cage is disposed, hangs muscle is welded in steel reinforcement cage upper end, use steel wire Rope is connected with inner tube and steel reinforcement cage, it is ensured that steel reinforcement cage is in the middle of vertical hanging pipe in outer tube, while ensuring that steel reinforcement cage bottom is being expanded In major part between 0.5-1 meters;
7), concrete perfusion pull out outer tube:Place and irrigate immediately after steel reinforcement cage concrete, concrete slump control 8-10cm it Between;It is pressed in the outer tube for having filled concrete using inner tube own wt after filling concrete, it is ensured that the packing of concrete, is then turned on jacking oil Cylinder system starts tube drawing, until outer tube extracts ground 15-25cm, cuts steel reinforcement cage hanging steel bar, forms a complete club-footed pile.
Non- Squeezing Soil Pile construction procedure is to increase the dry step that fetches earth before soil compaction pile construction method step is implemented, using two-tube The dry step that fetches earth is:
Flap valve opening drawing out soil equipment is set in inner tube bottom, inner and outer pipe superposition is nested together, with diesel hammer by inner tube with Outer tube synchronously bury by impact, can not be opened downwards because the flap valve that fetches earth of flap valve opening drawing out soil equipment can only close up upwards, During burying, the outside soil flap valve that will fetch earth is squeezed upwards, and soil constantly enters in inner tube;Inner and outer tubes are often buried 4-6m Extract inner tube to fetch earth once, during inner tube is extracted, the flap valve that fetches earth lives the grave in inner tube;Inner tube pulls away outer tube completely Afterwards, strike inner tube fetches earth end socket steel plate downwards, and the drive flap valve that fetches earth is downward so that the flap valve that fetches earth depart from bottom of the tube, in inner tube Soil be freely scattered;
According to stake it is long inner tube aligned with geological condition at any time extract unload native number of times, until base expanding and base expanding end is fetched earth completion, reach Projected depth.
The all-hydraulic two-tube compound club-footed pile geological conditions of static pressure is:Silt, flour sand, supporting course thickness must not be less than three meters, Supporting course earth bearing strength is more than 16T/m3, static pressure base expanding and base expanding auxiliary material uses rubble, concrete block or the block brick of 15-30cm, according to design The requirement of bearing capacity of single pile, it is determined that the quantity and number of times of filling static pressure base expanding and base expanding auxiliary material, according to the gross weight of static pressure equipment, selection is most Static pressure oil pressure tabular value conversion press-in static pressure afterwards, and align on inner and outer pipe degree of lifting and determine bellout diameter, it is ensured that static pressure auxiliary material Design load, i.e. test pile test value reference value are not less than through the end resistance after static pressure base expanding and base expanding, wanting for design bearing capacity is can be only achieved Ask;Multiple tracks triangle protection muscle is welded with steel reinforcement cage.
Patent of the present invention is the noiselessness, without friction, free of contamination extended on the basis of " strong rammer vibration compound club-footed pile " Construction, technique is the process innovation again of the hammering two-tube compound bottom-enlarging filling pile of vibration, of the invention by clip pile system system Cause upper and lower two sets of pile clamping boxes, effective travel 3-5 meters, bottom pile clamping box clamping outer tube, top pile clamping box can not only clamp outer tube but also Inner tube can be clamped, presses to form base expanding and base expanding effect using inner tube.Or, using top pressure transverse beam system square back-pressure inner tube on inner pipe, Form base expanding and base expanding effect.
The present invention, using rubble, concrete block or brickbat static(al) reinforcing pile end bearing stratum, is to solve stake at present to support power There is meagre soft interlayer in layer and supporting course moisture content is high and influence one of bearing capacity of single pile most efficient method.Applied using pile tube The same bearing capacity of single pile of work, stake is long, and all at 30-45 meters or so, overall cost will improve 40% or so, using this construction technology than former The cast-in-situ bored pile for coming wants saving construction cost 20-35% or so, is a kind of cheap and good-quality new pile-type, new technology.
Brief description of the drawings
Fig. 1 is structural representation of the two-tube compound club-footed pile machine of all-hydraulic static pressure of the invention using top pressure transverse beam system structure Figure.
Fig. 2 is compound double pipe structure schematic diagram of the present invention.
Fig. 3 is the all-hydraulic two-tube compound club-footed pile double fastener stake box structure schematic diagram of the present invention.
Specific embodiment
Embodiment 1
A kind of two-tube compound club-footed pile machine of all-hydraulic static pressure, as shown in figure 1, including clip pile system 10 and being lifted on clip pile system Multiple tube 20 in system, as shown in Fig. 2 the multiple tube includes inner tube 1 and outer tube 2, said inner tube is sleeved on outer tube, interior Pipe external diameter be less than more than outer tube diameter 5cm, inner tube 10-20cm shorter than outer tube, inner tube upper seal steel plate with diameter greater than outer tube outside Footpath 2-3cm, and fixed using coupling arrangement 3 on inner and outer pipes top;Outer tube thickness of steel pipe must not be less than 2cm;
As shown in figure 1, the clip pile system includes a lower pile clamping box 10, lower clip pile upper box part is provided with a clear height 2 The clamp support 4 of rice, piling stroke is 3-4 meters, and top pressure transverse beam system 5, the top pressure transverse beam system are provided with clamp support Square top pressure inner tube on inner pipe, the top pressure transverse beam system square back-pressure inner tube on inner pipe, forms base expanding and base expanding effect.
Embodiment 2
As shown in figure 3, the clip pile system is made up of upper pile clamping box 30 and lower pile clamping box 10, upper and lower two sets of pile clamping boxes have 3-5 meters of stroke of effect, lower pile clamping box clamps outer tube, and upper pile clamping box can not only clamp outer tube but also can clamp inner tube, using inner tube pressure shape Into base expanding and base expanding effect.In Fig. 3,20 is compound two-tube, and 10 is lower pile clamping box, and 30 is upper pile clamping box, and 40 is pile clamping box stroke track.
Embodiment 3
An inner tube set in outer tube during construction(Inner tube external diameter is necessarily less than more than outer tube diameter 5cm), inner tube ratio The short 10-20cm of outer tube, when being buried with profit, acts on as native plug, prevents underground water from pouring in outer tube, inner tube upper seal steel plate diameter More than outer tube external diameter 2-3cm, and fixed using coupling arrangement on inner and outer pipes top.Using random crane or outside crawler crane handle One be connected and fixed inside and outside two-tube hang in pile clamping box.It is inside and outside it is two-tube it is high 0.5 meter with ground surface soil when, general 8 in pile clamping box Individual clamping fuel tank, at most also starts to clamp work, outer tube with 20 clamping oil cylinders(Thickness of steel pipe must not be less than 2cm)Embrace jail, Stake machine flatness is adjusted followed by hydraulic traveling mechanism, with total powerstation, the two-way correction inner and outer pipes perpendicularity of theodolite, it is ensured that hang down Directly spend within code requirement.1. opens pressure pipe top cylinder system, ensures inner and outer pipes by 2-4 meters of speed of each stroke It is pressed onto designed elevation.2. releases inner and outer pipes top coupling arrangement, inner sleeve is extracted using random crane or crawler crane outer Set, then pours into height for H=2-2.5 meters of 0.25-0.3m in outer tube3, the stone of particle diameter 15-30cm, concrete block and fragment of brick. 3. be put into interior effective loop wheel machine in outer tube and fasten input material by, and steel outer tube is embraced in subsequent clip pile system work, and jacking cylinder system is opened Beginning work, pulling out 1-1.5 meters on outer tube(By design requirement), stop jacking apparatus work, release grasping system work, clamping oil Cylinder replys internal, about 1.8 meters of a stroke while jacking cylinder system is up walked, and then reply is fallen piling bottom portion and started Second stroke reaches inside top, and subsequent grasping system work, clamping oil cylinder clips inner tube top steel pipe and down walks, until quiet It is depressed into inside and outside steel pipe and is synchronously pressed onto former design stake bottom absolute altitude, stake end forms first time auxiliary material base expanding and base expanding, then according to design requirement Secondary batching is carried out, is fed intake for three times, all-hydraulic static pressure base expanding and base expanding is through multiple auxiliary material base expanding and base expanding.4. according to design and test pile result, with reference to Last time static pressure base expanding and base expanding maximum pressure value, design requirement is reached end resistance is met.5. extracts inner tube, adds 0.2- 0.3m3, the slump is the concrete of the C30-C50 of 3-6cm, by that analogy, multiple all-hydraulic static pressure base expanding and base expanding, final hydraulic control room Interior static pressure, when pressure value meets design requirement untill, otherwise repeatedly said procedure, until meeting design load single pile requirement.⑥、 Extract inner tube decentralization steel reinforcement cage:Extract inner tube, dispose steel reinforcement cage, hangs muscle is welded in steel reinforcement cage upper end, with steel wire rope and inner tube and Steel reinforcement cage is connected, it is ensured that steel reinforcement cage is in the middle of vertical hanging pipe in outer tube, while ensuring steel reinforcement cage bottom 0.5-1 in enlarged footing Between rice;7., concrete perfusion pulls out outer tube:Concrete is irrigated immediately after placing steel reinforcement cage, and concrete slump is controlled between 8-10cm; It is pressed in the outer tube for having filled concrete using inner tube own wt after filling concrete, it is ensured that the packing of concrete, is then turned on jacking cylinder System starts tube drawing, until outer tube extracts ground 15-25cm, cuts steel reinforcement cage hanging steel bar, forms a complete club-footed pile.
Secondly:Due to make full use of former pile compacting equipment(200 tons -1200 tons)Before cost of investment is reduced as far as possible Put, my company increases the column of 2 meters of clear height in former clip pile upper box part, and transverse beam system is set at the top of it(Due to original clamping system System only possesses a set of grasping system, inadequate to inner tube base expanding and base expanding stroke), after inner and outer pipe is pressed onto designed elevation simultaneously, extract internal pressure Pipe, irrigates base expanding and base expanding auxiliary material and base expanding and base expanding concrete, and subsequent inner tube resets, and 1-1.5 meters is pulled out on clamping outer tube, and outer tube grasping system unclamps, folder It is spacing that stake case jack-up system rises to highest, at the top of subsequent upper beam system reset to interior pressure pipe, subsequent pile clamping box jacking system System is down walked, and drives crossbeam to push down inner tube, forms base expanding and base expanding technique, by that analogy, completes the round program of auxiliary material and concrete base expanding and base expanding Pile(NM other techniques, are carried out with reference to two sets of new grasping system techniques).
Non- Squeezing Soil Pile construction procedure is to increase the dry step that fetches earth before soil compaction pile construction method step is implemented, using two-tube The dry step that fetches earth is:
Flap valve opening drawing out soil equipment is set in inner tube bottom, inner and outer pipe superposition is nested together, with diesel hammer by inner tube with Outer tube synchronously bury by impact, can not be opened downwards because the flap valve that fetches earth of flap valve opening drawing out soil equipment can only close up upwards, During burying, the outside soil flap valve that will fetch earth is squeezed upwards, and soil constantly enters in inner tube;Inner and outer tubes are often buried 4-6m Extract inner tube to fetch earth once, during inner tube is extracted, the flap valve that fetches earth lives the grave in inner tube;Inner tube pulls away outer tube completely Afterwards, strike inner tube fetches earth end socket steel plate downwards, and the drive flap valve that fetches earth is downward so that the flap valve that fetches earth depart from bottom of the tube, in inner tube Soil be freely scattered;
According to stake it is long inner tube aligned with geological condition at any time extract unload native number of times, until base expanding and base expanding end is fetched earth completion, reach Projected depth.
Inner tube external diameter is less than outer tube diameter 5cm.
The all-hydraulic two-tube compound club-footed pile geological conditions of static pressure is:Silt, flour sand, supporting course thickness must not be less than three meters, Supporting course earth bearing strength is more than 16T/m3, static pressure base expanding and base expanding auxiliary material uses rubble, concrete block or the block brick of 15-30cm, according to design The requirement of bearing capacity of single pile, it is determined that the quantity and number of times of filling static pressure base expanding and base expanding auxiliary material, according to the gross weight of static pressure equipment, selection is most Static pressure oil pressure tabular value conversion press-in static pressure afterwards, and align on inner and outer pipe degree of lifting and determine bellout diameter, it is ensured that static pressure auxiliary material Design load is not less than through the end resistance after static pressure base expanding and base expanding(Test pile test value reference value), can be only achieved wanting for design bearing capacity Ask.Multiple tracks triangle protection muscle is welded with steel reinforcement cage.
Patent of the present invention is the noiselessness, without friction, free of contamination extended on the basis of " strong rammer vibration compound club-footed pile " Construction, technique is process innovation again of the hammering two-tube compound bottom-enlarging filling pile of vibration, using rubble, concrete block or Brickbat static(al) reinforcing pile end bearing stratum, is to solve there is meagre soft interlayer and supporting course moisture content is high in bearing course at pile end at present And influence one of bearing capacity of single pile most efficient method.Using the same bearing capacity of single pile of tube pile construction, stake is long all left at 30-45 meters The right side, overall cost will improve 40% or so, want saving construction cost 20-35% left than original cast-in-situ bored pile using this construction technology The right side, is a kind of cheap and good-quality new pile-type, new technology.
The all-hydraulic two-tube compound club-footed pile machine of static pressure of the present invention and construction method set Group Co., Ltd " strong by building capital construction The compound club-footed pile of the rammer vibration " patent No. is ZL2013100569681:(Jiangsu Province's house and the assessment of result of the town and country construction Room are changed to: " the two-tube compound bottom-enlarging filling pile technology of hammering vibration ")On the basis of develop another without friction, noiselessness of growth, pollution-free Construction machinery and construction technology.
Finally it should be noted that:Obviously, above-described embodiment is only intended to clearly illustrate example of the present invention, and simultaneously The non-restriction to implementation method.For those of ordinary skill in the field, can also do on the basis of the above description Go out the change or variation of other multi-forms.There is no need and unable to be exhaustive to all of implementation method.And thus drawn Obvious change that Shen goes out or among changing still in protection scope of the present invention.

Claims (1)

1. the two-tube compound pedestal pile constructing process of a kind of all-hydraulic static pressure, it is characterised in that:All-hydraulic static pressure used by construction method Two-tube compound club-footed pile machine, including clip pile system and be lifted on it is compound two-tube in clip pile system, it is described be combined it is two-tube including interior Pipe and outer tube, said inner tube are sleeved on outer tube, and inner tube external diameter is less than outer tube diameter 5cm, inner tube 10-20cm shorter than outer tube, Inner tube upper seal steel plate is fixed on inner and outer pipes top with diameter greater than outer tube external diameter 2-3cm using coupling arrangement;Outer tube steel pipe Wall thickness must not be less than 2cm;The clip pile system is made up of upper pile clamping box and lower pile clamping box, upper and lower two sets of pile clamping box effective travels 3-5 meters, lower pile clamping box clamps outer tube, and upper pile clamping box can not only clamp outer tube but also can clamp inner tube, and press to form base expanding and base expanding using inner tube Effect;
Methods described is specifically included, by one be connected and fixed inside and outside it is two-tube hang in lower pile clamping box, it is inside and outside it is two-tube above Ground When table is native 0.5 meter, clamping oil cylinder starts to clamp work in lower pile clamping box, and outer tube armful is firm, is adjusted followed by hydraulic traveling mechanism Whole stake machine flatness, with total powerstation and the two-way correction inner and outer pipes perpendicularity of theodolite, it is ensured that perpendicularity is within code requirement;
1)Jacking cylinder system is opened, ensures for inner and outer pipes to be pressed onto designed elevation by 2-4 meters of height of each stroke;
2)Inner and outer pipes top coupling arrangement is released, inner tube is extracted into outer tube using random crane or crawler crane, filled in outer tube Enter 0.25-0.3m3Input material, input material height is H=2-2.5 meter, and input material is the stone of particle diameter 15-30cm, concrete block and brick Block;
3)Interior effective loop wheel machine is put into outer tube and fastens input material, outer tube, jacking are embraced in then upper pile clamping box grasping system work Cylinder system is started working, and 1-1.5 meters will be pulled out on outer tube by design requirement, stops the work of jacking cylinder system, is pressed from both sides in releasing The grasping system work of stake case, 1.8 meters of a stroke while jacking cylinder system is up walked, upper pile clamping box bottom reaches inner tube Top starts the second stroke, then upper pile clamping box grasping system work, and clamping oil cylinder clips inner tube top steel pipe and down walks, directly Former design stake bottom absolute altitude is synchronously pressed onto to static pressure to inside and outside steel pipe, stake end forms first time auxiliary material base expanding and base expanding, then according to design It is required that carry out secondary batching, feed intake for three times, all-hydraulic static pressure base expanding and base expanding is through multiple auxiliary material base expanding and base expanding;
4)According to design and test pile result, with reference to last time static pressure base expanding and base expanding maximum pressure value, meet end resistance and reach design It is required that;
5)Inner tube is extracted, 0.2-0.3m is added3, the slump is the concrete of the C30-C50 of 3-6cm, by that analogy, repeatedly all-hydraulic quiet Companding bottom, when final hydraulic control pressure value meets design requirement untill, otherwise repeatedly said procedure, until meeting design load Single pile requirement;
6)Extract inner tube decentralization steel reinforcement cage:Extract inner tube, dispose steel reinforcement cage, steel reinforcement cage upper end weld hangs muscle, with steel wire rope with Inner tube and steel reinforcement cage are connected, it is ensured that steel reinforcement cage is in the middle of vertical hanging pipe in outer tube, while ensuring steel reinforcement cage bottom in enlarged footing Between interior 0.5-1 meters;
7)Concrete perfusion pulls out outer tube:Concrete is irrigated immediately after placing steel reinforcement cage, and concrete slump is controlled between 8-10cm;Fill It is pressed in the outer tube for having filled concrete using inner tube own wt after concrete, it is ensured that the packing of concrete, is then turned on jacking cylinder system Start tube drawing, until outer tube extracts ground 15-25cm, cut steel reinforcement cage hanging steel bar, form a complete club-footed pile;
Non- Squeezing Soil Pile construction procedure is to increase the dry step that fetches earth before soil compaction pile construction method step is implemented, and dry is taken using two-tube Native step is:
Flap valve opening drawing out soil equipment is set in inner tube bottom, inner and outer pipe superposition is nested together, with diesel hammer by inner tube and outer tube Synchronous impact is buried, and can not be opened downwards because the flap valve that fetches earth of flap valve opening drawing out soil equipment can only close up upwards, is being buried During, the outside soil flap valve that will fetch earth is squeezed upwards, and soil constantly enters in inner tube;Inner and outer tubes often bury 4-6m extraction Inner tube fetches earth once, and during inner tube is extracted, the flap valve that fetches earth lives the grave in inner tube;After inner tube pulls away outer tube completely, Strike inner tube fetches earth end socket steel plate downwards, and the drive flap valve that fetches earth is downward so that the flap valve that fetches earth depart from bottom of the tube, the soil in inner tube Freely it is scattered;
According to stake it is long inner tube adjusted with geological condition at any time extract unload native number of times, until base expanding and base expanding end is fetched earth completion, reach design Depth;
The all-hydraulic two-tube compound club-footed pile geological conditions of static pressure is:Silt, flour sand, supporting course thickness must not be less than three meters, holding force Layer earth bearing strength is more than 16T/m3, static pressure base expanding and base expanding auxiliary material uses rubble, concrete block or the block brick of 15-30cm, according to design single pile The requirement of bearing capacity, it is determined that the quantity and number of times of filling static pressure base expanding and base expanding auxiliary material, according to the gross weight of static pressure equipment, selection is last quiet Force feed pressure tabular value conversion press-in static pressure, and adjust on inner and outer pipe degree of lifting and determine bellout diameter, it is ensured that static pressure auxiliary material is through quiet End resistance behind companding bottom is not less than design load, i.e. test pile test value reference value, can be only achieved the requirement of design bearing capacity;Steel Multiple tracks triangle protection muscle is welded with muscle cage.
CN201510331164.7A 2015-06-16 2015-06-16 The all-hydraulic two-tube compound club-footed pile machine of static pressure and its construction method Active CN104895058B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510331164.7A CN104895058B (en) 2015-06-16 2015-06-16 The all-hydraulic two-tube compound club-footed pile machine of static pressure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510331164.7A CN104895058B (en) 2015-06-16 2015-06-16 The all-hydraulic two-tube compound club-footed pile machine of static pressure and its construction method

Publications (2)

Publication Number Publication Date
CN104895058A CN104895058A (en) 2015-09-09
CN104895058B true CN104895058B (en) 2017-06-27

Family

ID=54027987

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510331164.7A Active CN104895058B (en) 2015-06-16 2015-06-16 The all-hydraulic two-tube compound club-footed pile machine of static pressure and its construction method

Country Status (1)

Country Link
CN (1) CN104895058B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105926594A (en) * 2016-04-29 2016-09-07 朱龙 Double-pipe construction method for static pressure pipe-sinking carrier cast-in-place pile
CN106400774A (en) * 2016-08-30 2017-02-15 中铁十九局集团矿业投资有限公司 Construction method and device for strengthening soft foundation

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2599074Y (en) * 2002-12-26 2004-01-14 长沙天和工程机械有限公司 Environmental protection type contract press top press dual purpose hydraulic static pole press machine
JP4831511B2 (en) * 2006-04-19 2011-12-07 三谷セキサン株式会社 Construction method of foundation pile
CN201665873U (en) * 2010-03-21 2010-12-08 周立强 Static pile-pressing machine of double pile-pressing system
CN103114579B (en) * 2013-02-22 2015-01-07 建基建设集团有限公司 Dynamic compaction vibration compound base-expanded pile machine and construction method of dynamic compaction vibration compound base-expanded pile
CN204703152U (en) * 2015-06-16 2015-10-14 建基建设集团有限公司 All-hydraulic static pressure two-tube compound expanded bore pile machine

Also Published As

Publication number Publication date
CN104895058A (en) 2015-09-09

Similar Documents

Publication Publication Date Title
CN102383431B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN105178861A (en) Drilling hole enlarging mechanism
CN104727308B (en) Immersed tube compaction pile or cast-in-place concrete pile construction device and method
CN106759442A (en) A kind of single-pile elevated bearing-platform and anchor cable tower-crane foundation structure and its construction method
CN101597898B (en) Rigid drainage pile and construction method thereof
CN105113478A (en) Dynamic compaction treatment method of deep foundation displacement
CN107338781A (en) A kind of compacting pile construction device and its construction method
CN104929125A (en) Carrier pile construction equipment and carrier pile construction method
CN101196004A (en) Diving casting cast-in-place pile construction method for constructing in scree layer and sand layer
CN203213101U (en) Embedding grouting combined pile
CN104047280B (en) Soft foundation sharp separation compacting method
CN104895058B (en) The all-hydraulic two-tube compound club-footed pile machine of static pressure and its construction method
CN105926594A (en) Double-pipe construction method for static pressure pipe-sinking carrier cast-in-place pile
CN102345287A (en) Construction method of large-diameter cast-in-situ thin-wall concrete composite pile and special hole forming device
CN102995637A (en) Equipment and method for constructing immersed tube compaction pile on large-thickness backfilling or self-weight collapsible loess field
CN105133568A (en) Improved dynamic compaction hammer
CN105951863B (en) A kind of construction method of the construction equipment of active assembled open caisson
CN102677657A (en) Construction method of row cast thin-walled concrete compound pile wall and special hole forming device thereof
CN207277312U (en) A kind of compacting pile construction device
CN107130632A (en) A kind of steel pipe embeds no-dig technique cantilever retaining wall and its construction method
CN103132511A (en) Pile-forming method and pile-forming device for static pressure immersed tube expanded-base cast-in-place pile
CN102758434B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN204703152U (en) All-hydraulic static pressure two-tube compound expanded bore pile machine
CN207004431U (en) Soft soil foundation exciting drilling device
CN109944238A (en) Pile construction method is rammed in full-sleeve full-rotation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Shen Guoqin

Inventor after: Ou Guoxing

Inventor after: Yu Qiliang

Inventor after: Shen Fei

Inventor before: Shen Guoqin

Inventor before: Ou Guoxing

Inventor before: Shen Fei

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230902

Address after: 214263 Zhou tie Zhen Xia Jia Jie, Yixing City, Wuxi City, Jiangsu Province

Patentee after: JIANJI CONSTRUCTION GROUP Co.,Ltd.

Patentee after: Jiangsu Jinzhuang geotechnical Technology Co.,Ltd.

Address before: 9F, Dongyi Building, No. 888 Jiefang East Road, Yixing City, Wuxi City, Jiangsu Province, 214200

Patentee before: JIANJI CONSTRUCTION GROUP Co.,Ltd.