CN104866664A - Method for predicting construction difficulty of water seepage prevention curtain-grouting - Google Patents

Method for predicting construction difficulty of water seepage prevention curtain-grouting Download PDF

Info

Publication number
CN104866664A
CN104866664A CN201510254481.3A CN201510254481A CN104866664A CN 104866664 A CN104866664 A CN 104866664A CN 201510254481 A CN201510254481 A CN 201510254481A CN 104866664 A CN104866664 A CN 104866664A
Authority
CN
China
Prior art keywords
construction
difficulty
factor
pile
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510254481.3A
Other languages
Chinese (zh)
Other versions
CN104866664B (en
Inventor
阳吉宝
倪琦
任海平
韩炳辰
冯明伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINESE PEOPLE'S LIBERATION ARMY NAVAL ENGINEERING DESIGN INSTITUTE
Shanghai Construction Group Design Institute Co Ltd
Original Assignee
CHINESE PEOPLE'S LIBERATION ARMY NAVAL ENGINEERING DESIGN INSTITUTE
Shanghai Construction Group Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINESE PEOPLE'S LIBERATION ARMY NAVAL ENGINEERING DESIGN INSTITUTE, Shanghai Construction Group Design Institute Co Ltd filed Critical CHINESE PEOPLE'S LIBERATION ARMY NAVAL ENGINEERING DESIGN INSTITUTE
Priority to CN201510254481.3A priority Critical patent/CN104866664B/en
Publication of CN104866664A publication Critical patent/CN104866664A/en
Application granted granted Critical
Publication of CN104866664B publication Critical patent/CN104866664B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention discloses a method for predicting construction difficulty of water seepage prevention curtain-grouting, wherein the method includes the following steps: performing construction for the water seepage prevention curtain-grouting by using a construction equipment and combing with geologic conditions in a construction field; performing layer division and classification to each factor cooperative with analyzing each factor affecting construction difficulty, and forming grading evaluation criteria of each construction difficulty with respect to each factor; and analyzing each factor by using the analytic hierarchy process (AHP) to obtain index weight of each factor affecting construction difficulty. The appraising system according to the present invention is concise and convenient, and has a simple operation. The construction difficulty is predicted in advance according to the factor affecting the construction difficulty of the water seepage prevention curtain-grouting, which can evaluate a project in detail, and the result is more rational and sound; the factor having a high level of risk can be circumvented or adjusted in advance, thereby achieving a fundamental purpose of reducing the duration, saving the cost, and reducing the construction difficulty.

Description

A kind of Impermeable underground wall curtain body construction difficulty Forecasting Methodology
Technical field
The present invention relates to geotechnical engineering design and construction field, particularly relating to is a kind ofly carry out advanced prediction based on AHP-TOPSIS scoring model, evaluate area of bordering on the sea containing the method for coral reef chip stratum water-stop curtain body construction complexity.
Background technology
The regional rock deep foundation pit construction difficulty that enters that borders on the sea is the focus that foundation construction personnel study, pay close attention to always.Wherein, construction site environment is changeable, complex geologic conditions, and construction treating methods difference that is various and preparation of construction type selecting all produces larger impact by difficulty of construction.But border on the sea less into rock deep foundation pit construction case, construction experience that can be for reference is also few, lacks the various factor analysis affecting construction quality.Therefore, it may be necessary theoretical research and case history application, analyze further, sum up and border on the sea into the construction quality influence factor of rock deep basal pit Impermeable underground wall curtain body, thus obtain field construction difficulty defining method more accurately.
Existing construction site difficulty evaluation method is mainly divided into geological analysis predicted method and the large class of geophysics predicted method two.Geological analysis predicted method mainly comprises advanced levels, vertically holes, engineering geological survey method etc.; Geophysics predicted method comprises sonic test, infrared acquisition, wave velocity method and Electromagnetic Wave Method etc.Advanced levels, vertical boring are one of advanced prediction most effectual ways, but also Shortcomings part: better to the geologic structure face value of forecasting of Vertical dimension, and the forecast of horizontal direction structural plane is poor, need take the longer construction operation time, costly; Engineering geological survey method is the method used in geologic prediction the earliest, the method be by inquiry with analysis earth's surface engineering geological condition, understand the geological structure characteristic in location residing for engineering, infer geological condition herein according to the engineering project of similar vicinity; Sonic test, infrared acquisition, wave velocity method and Electromagnetic Wave Method etc. are all utilize geophysical prospecting method to carry out prospecting prediction to construction site, have certain reference value.But it can only know the information on stratum itself briefly, thus evaluate the influence degree of stratum for construction itself, the impact for work progress such as working measure and plant equipment cannot be considered.
Summary of the invention
The object of the invention is to border on the sea containing a design and construction difficult problem for coral reef chip stratum Impermeable underground wall curtain body for solving better, a kind of Impermeable underground wall curtain body construction difficulty Forecasting Methodology is proposed, it can carry out comprehensive anticipation to area of bordering on the sea containing coral reef soil layer difficulty of construction in advance according to field engineering geologic condition, the factor such as preparation of construction intending taking measures and intend to adopt, for the selection of construction method and preparation of construction provides certain reference, evade adverse risk in advance, optimum selecting, thus carry out site operation more fast, efficiently, economically.
For solving the problems of the technologies described above, the invention provides following technical scheme:
A kind of Impermeable underground wall curtain body construction difficulty Forecasting Methodology, comprises the steps:
Step 1, preparation of construction is utilized to carry out an Impermeable underground wall curtain body construction in conjunction with geologic condition on construction ground;
Step 2, the comprehensive each factor analyzing Effect Field ground difficulty of construction, carry out distinguishing hierarchy to described each factor and sort out, forming each construction difficulty or ease grade evaluation criterion for every class factor;
Step 3, utilize APH analytical hierarchy process analyze described each factor, obtain the index weights that each factor affects for difficulty of construction;
Step 4, in conjunction with TOPSIS similarity to ideal solution ranking method, respectively risk class division is carried out to the influence factor of same level according to above-mentioned difficulty of construction grade evaluation criterion, determine the influential effect of each level factor.
Optionally, in above-mentioned Impermeable underground wall curtain body construction difficulty Forecasting Methodology, according to the influential effect of each level factor, adjust arrangement and method for construction and/or the preparation of construction of next block Impermeable underground wall curtain body in time, evade adverse risk in advance.
Optionally, in above-mentioned Impermeable underground wall curtain body construction difficulty Forecasting Methodology, the described each factor affecting place difficulty of construction is divided into geologic condition, preparation of construction and working measure three class.
Optionally, in above-mentioned Impermeable underground wall curtain body construction difficulty Forecasting Methodology, described geologic condition comprises the thickness of overburden layer, the homogeneity of upper overburden layer, the fluctuating quantity of bedrock surface, Coral Reef Rock distribution situation and severely-weathered layer distribution situation; Described preparation of construction comprises mixing pile stake machine type, jet grouting pile driving machine, inspecting hole, draws drilling machine and water power standby condition; And working measure comprises examination pore-forming, inspecting hole, draws hole and lower pipe.
Optionally, in above-mentioned Impermeable underground wall curtain body construction difficulty Forecasting Methodology, described construction site is positioned at borders on the sea containing Coral Reef Rock area, geologic structure is from top to bottom followed successively by: containing the soil layer of Coral Reef Rock rock mass, severely-weathered layer and middle waste mantle, and described Impermeable underground wall curtain body adopts the combined enclosure form of three axes agitating pile and high-pressure rotary jet grouting pile on vertical section.
Optionally, in above-mentioned Impermeable underground wall curtain body construction difficulty Forecasting Methodology, the construction procedure of described Impermeable underground wall curtain body comprises:
Step 11, carries out examination pile to construction site, tentatively determines the construction parameter of three axes agitating pile and high-pressure rotary jet grouting pile;
Step 12, adopts rig to carry out inspecting hole, verifies the bedrock surface buried depth situation containing the Coral Reef Rock depth of stratum in the soil layer of Coral Reef Rock, severely-weathered layer thickness and middle waste mantle;
Step 13, for containing the soil layer of Coral Reef Rock and severely-weathered stratum, adopt single cover to make three axes agitating pile stake machine and construct, three axes agitating pile injection is to the bedrock surface above 1.0-1.5 rice degree of depth;
Step 14, carries out drawing hole, draws more than 1m under hole to bedrock surface after three axes agitating pile has been constructed, can whole hole after guaranteeing to enter basement rock projected depth, and pore-forming aperture is not less than 130mm, and perpendicularity deviation is not more than 1/200, and the biased difference in hole is not more than 20mm;
Step 15, it is complete with down tube to draw hole, and adopt pvc pipe, by pvc pipe back cover, interior mud grouting, transfers more than 1m to bedrock surface from drawing hole;
Step 16, utilize jet grouting pile driving machine construction high-pressure rotary jet grouting pile, enter bedrock surface more than 1.0 meters under high-pressure rotary jet grouting pile, high-pressure rotary jet grouting pile and three axes agitating pile effectively overlap more than 1.0 meters.
Optionally, in above-mentioned Impermeable underground wall curtain body construction difficulty Forecasting Methodology, in step 15, if the sludge of precipitation is thicker at the bottom of hole, necessary clear hole deslagging, guarantees that pvc pipe enters below bedrock surface more than 1.0 meters.
From above disclosed technical scheme, compared with prior art, beneficial effect of the present invention is as follows:
(1) the present invention is according to utilizing preparation of construction to carry out the situation of an Impermeable underground wall curtain body construction in conjunction with geologic condition on construction ground, the first comprehensive principal element analyzing Effect Field ground difficulty of construction, and classification that above-mentioned factor is summarized, AHP analytical hierarchy process is utilized to obtain the weighing factor of each factor, finally in conjunction with TOPSIS method, grade judgement is carried out to each factor, thus the difficulty of construction risk class of each factor can be known more concisely, for the factor that risk class is higher, can process in advance when next Impermeable underground wall curtain body process, carry out in advance evading or adjusting, thus reach the minimizing duration, cost-saving, reduce the basic goal of difficulty of construction.
(2) the present invention will affect the geologic condition of difficulty of construction, preparation of construction and the interrelated and comprehensive analysis of working measure, and can do one to some engineerings all sidedly and evaluate in detail, result has more rationality and integrity.
(3) the present invention can so that realize foundation pit waterproof curtain design and construction cost and the estimating of construction period.
(4) difficulty of construction appraisement system of the present invention succinctly facilitates, workable, to the South Sea border on the sea containing coral reef chip stratum construction evaluation have better applicability.
Accompanying drawing explanation
Fig. 1 is the concrete construction flow chart of Impermeable underground wall curtain body;
Fig. 2 is the hierarchy Model setting up difficulty of construction prediction by AHP method according to geologic condition, preparation of construction and working measure.
Embodiment
Below in conjunction with the drawings and specific embodiments, the Impermeable underground wall curtain body construction difficulty Forecasting Methodology that the present invention proposes is described in further detail.According to the following describes and claims, advantages and features of the invention will be clearer.It should be noted that, accompanying drawing all adopts the form that simplifies very much and all uses non-ratio accurately, only in order to object that is convenient, the aid illustration embodiment of the present invention lucidly.
Present embodiment discloses a kind of Impermeable underground wall curtain body construction difficulty Forecasting Methodology, this method is successfully applied to the South Sea and borders on the sea containing in certain engineering in Coral Reef Rock area, the geologic structure bordered on the sea containing Coral Reef Rock area in the South Sea is from top to bottom followed successively by: containing the soil layer of Coral Reef Rock, severely-weathered layer and middle waste mantle, described Impermeable underground wall curtain body adopts the combined enclosure form of three axes agitating pile and high-pressure rotary jet grouting pile on vertical section.Described Impermeable underground wall curtain body construction difficulty Forecasting Methodology specifically comprises the steps:
1, preparation of construction is utilized to carry out an Impermeable underground wall curtain body construction in conjunction with geologic condition on construction ground.
The construction site of the present embodiment is positioned at borders on the sea containing Coral Reef Rock area, and therefore, on vertical section, the preferential combined enclosure pattern that adopts carries out water-stop curtain design.Foundation pit waterproof curtain is designed to: on vertical section, adopt combined enclosure pattern, that is: for containing the soil layer of Coral Reef Rock and severely-weathered layer, the three axes agitating pile adopting single cover to beat Φ 850@1200 is constructed, three axes agitating pile injection is to bedrock surface 1.0 meters of degree of depth, then on mixing pile, adopt the concentric preexisting hole of conventional drill to enter more than 1.0 meters, basement rock, to construct again high-pressure rotary jet grouting pile, make water seepage prevention fender body enter the relatively fluid-tight middle waste mantle of basement rock.Enter 1.0 meters, basement rock under high-pressure rotary jet grouting pile, upper and three axes agitating pile effectively overlaps 1.0 meters.
Under the prerequisite that geologic condition and preparation of construction have been selected, in advance to construction site examination pore-forming, briefly should understand construction condition, determine design parameter, then adopt inspecting hole, draw the measure such as hole and lower pipe and carry out construction performance prediction.The concrete construction technology process of described Impermeable underground wall curtain body is as shown in Figure 1:
(1) step 11, examination pile, namely carries out examination pile to construction site, tentatively determines the construction parameter of three axes agitating pile and high-pressure rotary jet grouting pile
Before design and construction, tackle construction site carry out examination bore forming, determine the design construction parameter of three axes agitating pile and high-pressure rotary jet grouting pile.
(2) step 12, inspecting hole, namely adopts rig to carry out inspecting hole, verifies the upper overburden layer of more than bedrock surface namely containing the bedrock surface buried depth situation of Coral Reef Rock depth of stratum, severely-weathered layer thickness and the middle waste mantle in the soil layer of Coral Reef Rock;
Because engineering geological condition is complicated, Coral Reef Rock rock stratum skewness, bedrock surface fluctuations is larger, in order to verify the situations such as Coral Reef Rock depth of stratum, severely-weathered layer thickness, bedrock surface buried depth of top surface, G-150 type rig is first adopted to carry out inspecting hole, inspecting hole is to bedrock surface, and the spacing of inspecting hole must be equal with the three axes agitating pile machine centre distance of this project construction usage, and inspecting hole spacing is 1.2m.Record Coral Reef Rock depth of stratum, severely-weathered layer thickness, bedrock surface absolute altitude, to instruct three axes agitating pile mechanical execution.
Three are had to the object that position, every secondary mixing pile place rig carries out inspecting hole: 1. identify whether or not Coral Reef Rock distribution and depth of stratum thereof before construction three axes agitating pile, when distributing without Coral Reef Rock, employing normal triaxial mixing pile construction; When there being Coral Reef Rock to distribute, but its in the axial direction length be less than 2.0 meters and its thickness is less than 1.5 meters time, three axes agitating pile of can directly constructing, it should be noted that when injection three axes agitating pile adopt corresponding construction parameter; When its in the axial direction length be greater than 2 meters or its thickness be greater than 1.5 meters time, the heavy caliber reciprocating drill rig in 1.2 meters, a footpath should be adopted first to carry out punching process, behind complete broken Coral Reef Rock rock stratum, backfill sand again and compacting, three axes agitating pile of then constructing.2. severely-weathered layer thickness is determined, because severely-weathered layer thickness is uneven, and soil layer disproportionately graded, the more difficult control of three axes agitating pile construction quality, according to the severely-weathered layer thickness that inspecting hole obtains, and the severely-weathered level situation of joining is recorded in inspecting hole table, construction parameter is advised.3. determine bedrock surface buried depth of top surface, below, in work progress, mixing pile stops beating 1 ~ 1.5m more than bedrock surface, in order to avoid three axes agitating pile stake machine stirring-head is encountered basement rock and damages a machine, occurs embracing the problems such as brill, bit freezing.
(3) step 13, three axes agitating pile pile driving construction
For containing the soil layer of Coral Reef Rock and severely-weathered stratum, the three axes agitating pile stake machine adopting single cover to beat Φ 850@1200 is constructed, and three axes agitating pile injection is to the bedrock surface above 1.0-1.5 rice degree of depth.
(4) step 14, draws hole
Carry out drawing hole and high-pressure rotary jet grouting pile preexisting hole, 1m under preexisting hole to bedrock surface after three axes agitating pile has been constructed, can whole hole after guaranteeing to enter basement rock projected depth.Pore-forming aperture is not less than 130mm, and perpendicularity deviation is not more than 1/200, and the biased difference in hole is not more than 20mm.
(5) step 15, lower pipe
Draw hole complete after, transfer pvc pipe, adopt pvc pipe, tubing intensity is 1.0-1.5Mpa, pipe external diameter is the pvc pipe of 120mm, by the blanking of the preexisting hole degree of depth.By pvc pipe back cover, interior mud grouting, transfers 1m to bedrock surface from drawing hole, if the sludge of precipitation is thicker at the bottom of hole, necessary clear hole deslagging, guarantees that pvc pipe enters below bedrock surface 1.0 meters.
(6) step 16, Construction of High Pressure Jet Grouting Pile
Utilize jet grouting pile driving machine construction high-pressure rotary jet grouting pile, (making water seepage prevention fender body entirety enter this velatively waterproof layer of middle waste mantle), enter bedrock surface more than 1.0 meters under high-pressure rotary jet grouting pile, high-pressure rotary jet grouting pile and three axes agitating pile effectively overlap more than 1.0 meters.
When high-pressure rotary jet grouting pile is constructed for the first time, with mixing pile concentric axis by 0.6 meter of spacing preexisting hole, injection high-pressure rotary jet grouting pile; Then, as found after testing, to there is pile quality bad, when there is breakthrough again at former construction axial offset by different spacing injection high-pressure rotary jet grouting pile to reinforce pile body.Concrete construction process is illustrated in fig. 1 shown below:
2, the comprehensive each factor analyzing Effect Field ground difficulty of construction, carries out distinguishing hierarchy to described each factor and sorts out, forming each construction difficulty or ease grade evaluation criterion for every class factor.
By researching and analysing step 1, the each factor affecting place difficulty of construction is divided into geologic condition, preparation of construction and working measure three class, wherein, described geologic condition comprises the thickness of overburden layer, the homogeneity of upper overburden layer, the fluctuating quantity of bedrock surface, Coral Reef Rock distribution situation and severely-weathered layer distribution situation; Described preparation of construction comprises mixing pile stake machine type, jet grouting pile driving machine, inspecting hole, draws drilling machine and water power standby condition; And working measure comprises examination pore-forming, inspecting hole, draws hole and lower pipe.Difficulty of construction is divided Three Estate according to numerical values recited by geologic condition, preparation of construction and working measure three influence factors, is respectively more easily, more difficult, be difficult to.Construction difficulty or ease grade evaluation criterion is as shown in following table 1 to table 3, wherein difficulty of construction grade evaluation criterion one, two, three difference corresponding geologic condition, preparation of construction and working measure three class influence factor, wherein, Geological condition data N to be evaluated is the condition of construction gained according to step 1.
Table 1 difficulty of construction grade evaluation criterion one
Table 2 difficulty of construction grade evaluation criterion two
Table 3 difficulty of construction grade evaluation criterion three
Grade of difficulty Examination pile Inspecting hole Draw hole Lower pipe
N1 (easier) 7 7 7 7
N2 (more difficult) 3 3 3 3
N3 (being difficult to) 1 1 1 1
Working measure data N to be evaluated 8.5 8.2 7.5 7.4
3, utilize APH analytical hierarchy process to analyze described each factor, obtain the index weights that each factor affects for difficulty of construction.
(1) scale is compared
According to the scale that compares between two with judge principle, the index of correlation of employing paried comparison method to same level compares assignment, and scoring criteria is as shown in table 4 below.Standard value 2,4,6,8 represent that the importance of phase specific factor is between 2 adjacent ranks, if W ij=r i/ r j, then 1/W ij=r j/ r i,wherein, r ibe i-th factor value, r jfor a jth factor value.
Table 4 index significance level classification scoring criteria
Standard value Definition Explanation
1 Of equal importance Factor ri is identical with rj importance
3 Important a little Factor ri and rj importance slightly high
5 Important Factor ri and rj importance higher
7 Obviously important Factor ri and rj importance obviously high
9 Definitely important Factor ri and rj importance definitely high
(2) Judgement Matricies
If judgment matrix is R, due to every one deck index factor all with each index factor of adjacent last layer for object of reference, therefore can Judgement Matricies R:r by comparing Scale Method between two ijrepresent r i/ r j, i.e. i-th factor value and a jth factor value importance comparison, alternatively, i-th index factor and a jth index factor importance comparison)
R is positive definite reciprocal matrix, for positive definite reciprocal matrix, and its eigenvalue of maximum λ maxto exist and unique.Make a ij=W i/ W j, the weight shared by certain factor of judgment matrix R and characteristic vector W iwith eigenvalue of maximum λ maxcomputing formula as follows:
W ~ ij = a ij / Σ j = 1 n a ij
W i = Π j = 1 n W ~ ij n / Σ i = 1 n Π j = ` n W ~ ij n
λ max = Σ i = 1 n ( RW ) i nW i
(3) consistency check and calculating weight vectors
Whether, due to complicacy and the subjective one-sidedness of systems engineering, there is error in judgment matrix unavoidably, reasonable for solving weight allocation, needs to carry out consistency check to judgment matrix.The formula of definition consistency check is:
CR = CI RI = λ max - n ( n - 1 ) RI
In formula: n is the exponent number of paired comparative factor, CI is consistency check index, and RI is Aver-age Random Consistency Index, gets different values according to the exponent number of paired comparative factor, and value standard is as shown in table 5 below.Whether meet the demands (i.e. CR<0.1) according to the consistance of result of calculation judgment matrix, otherwise need adjustment weight to make judgment matrix meet consistency check.
Table 5 Aver-age Random Consistency Index scoring criteria
Exponent number RI
1 0.00
2 0.00
3 0.58
4 0.90
5 1.12
6 1.24
7 1.32
8 1.41
9 1.45
10 1.49
If judgment matrix meets consistency check, illustrate that the structure of multi-level judgment matrix meets mathematical logic, the calculating of weights can be carried out according to this matrix, try to achieve weight vector.
In the present embodiment, set up the hierarchy Model of difficulty of construction foundation by AHP method according to geologic condition, preparation of construction and working measure, as shown in Figure 2, importance degree evaluation is carried out to index, the judgment matrix of construction rules layer P and each factor of indicator layer R.A-P, P1-R, P2-R, P3-R judgment matrix is respectively as shown in table 6 ~ 9.
Table 6 A-P judgment matrix
A-P P 1 P 2 P 3
P 1 1 3 3
P 2 1/3 1 2
P 3 1/3 1/2 1
Table 7 P 1-R judgment matrix
P 1-R r 1 r 2 r 3 r 4 r 5
r 1 1 1/3 1/2 1/5 1/4
r 2 3 1 5 1/2 3
r 3 2 1/5 1 1/4 1/5
r 4 5 2 4 1 2
r 5 4 1/3 5 1/2 1
Table 8 P 2-R judgment matrix
P 2-R r 6 r 7 r 8 r 9
r 6 1 1/3 1/2 1/3
r 7 3 1 3 5
r 8 2 1/3 1 4
r 9 1/3 1/5 1/4 1
Table 9 P 3-R judgment matrix
P 3-R r 10 r 11 r 12 r 13
r 10 1 1/3 1/4 1/4
r 11 3 1 1/2 1/3
r 12 4 2 1 2
r 13 4 3 1/2 1
Finally, the difficulty of construction prediction weight shown in table 10 is obtained.
Table 10 total hierarchial sorting result
4, in conjunction with TOPSIS similarity to ideal solution ranking method, respectively risk class division is carried out to the influence factor of same level according to above-mentioned difficulty of construction grade evaluation criterion, determine the influential effect of each level factor.Its principle is as follows:
(1) initial Judgement Matrix
If scheme collection P={P 1, P 2..., P m, each scheme judging quota collection r={r 1, r 2..., r n, judging quota r ijrepresent a jth judging quota of i-th scheme, wherein i ∈ [1, m], j ∈ [1, n], initial Judgement Matrix can be expressed as:
(2) standardization decision matrix
Judging quota can be divided into expendable index and rentability index, and for expendable index, be worth the smaller the better, for rentability index, value is the bigger the better.Because each judging quota has different dimensions and dimensional unit, do not possess comparable degree, in order to eliminate the incommensurability of index, needing that dimension one is carried out to judging quota and changing process.For standardization decision matrix B=(b ij) m × n, computing formula is:
For rentability index, have
b ij = r ij - mi n ( r ij ) j max ( r ij ) j - min ( r ij ) j
For expendable index, have
b ij = min ( r ij ) j - r ij max ( r ij ) j - min ( r ij ) j
Wherein: for jth row minimum value, for jth row maximal value.
(3) weighting standard decision matrix
The indicator layer total hierarchial sorting weights W that the column vector of matrix B and AHP method are determined nbe multiplied, weighting standard decision matrix R can be obtained 1for
(4) approach degree analysis
Rentability index set J 1positive ideal solution be the maximal value of row vector, minus ideal result is the minimum value of row vector, expendable index set J 2value in contrast, can be expressed as
R 1 + = { ( max n w n b mn | m &Element; J 1 ) , ( min n w n b mn | m &Element; J 2 ) } R 1 - = { ( min n w n b mn | m &Element; J 1 ) , ( max n w n b mn | m &Element; J 2 ) }
In formula: R 1 +with R 1 -be respectively positive ideal solution and minus ideal result.The distance passing judgment on object and ideal solution is
D i + = &Sigma; j = 1 n ( r ij - r j + ) 2 D i - = &Sigma; j = 1 n ( r ij - r j - ) 2
In formula: D i +, D i -be respectively the distance passing judgment on object and positive ideal solution and minus ideal result; r i +, r i -be respectively R 1 +with R 1 -corresponding element.
The computing formula of approach degree analysis is
C i + = D i - / ( D i + + D i - ) ( 0 &le; C i + &le; 1 )
When judge object is positive ideal solution, C i +=1, when judge object is minus ideal result, C i +=0, generally pass judgment on object approach degree C i +value is (0,1), reflects and passes judgment on the degree that object presses close to positive ideal solution.
(5) AHP-TOPSIS scoring model
Construct Judgement Matrix by the approach degree analysis of TOPSIS method, in conjunction with the weight that AHP method calculates, passing judgment on object Comprehensive Evaluation result vector Q is
Q=W×C
In formula: C is the Judgement Matrix that the approach degree of each judge object and positive ideal solution is formed, W is the rule layer weight that AHP method calculates.
Concrete, in the present embodiment, the concrete steps of step 4 are as follows:
The Primary Judgement Matrix of three class influence factors is set up respectively according to difficulty of construction grade evaluation criterion and grade of difficulty criterion:
A. geologic condition: P = 10 1.5 2 10 5 20 4.5 4 20 3 30 7.5 6 30 1 26.6 7.86 6.13 46.7 1.92
In geologic condition, the distribution of soil thickness, bedrock relief, soil body homogeneity and Coral Reef Rock belongs to expendable index, is worth the smaller the better; Severely-weathered layer distribution belongs to rentability index, and value is the bigger the better.Calculate the distance of difficulty of construction opinion rating and positive ideal solution and minus ideal result and corresponding approach degree, as shown in table 11:
Table 11 geologic condition total hierarchial sorting result
Grade of difficulty Di + Di - Ci + Sequence
N 1 0.289 0.118 0.290 1
N 2 0.199 0.121 0.379 2
N 3 0.157 0.211 0.574 3
N 0.091 0.290 0.761 4
B. preparation of construction condition: P = 7.00 7.00 7.00 7.00 3.00 3.00 3 . 00 3.00 1.00 1.00 1.00 1.00 8.00 7.50 8.50 7.20
Preparation of construction all belongs to expendable index, is worth the smaller the better; Severely-weathered layer distribution belongs to rentability index, and value is the bigger the better.Calculate the distance of difficulty of construction opinion rating and positive ideal solution and minus ideal result and corresponding approach degree, as shown in table 12:
Table 12 preparation of construction total hierarchial sorting result
Grade of difficulty Di + Di - Ci + Sequence
N 1 0.133 0.017 0.112 2
N 2 0.044 0.104 0.701 3
N 3 0.000 0.148 1.000 4
N 0.148 0.000 0.000 1
C. working measure condition: P = 7.00 7.00 7.00 7.00 3.00 3.00 3.00 3.00 1.00 1.00 1.00 1.00 8.50 8.20 7.50 7.40
Working measure all belongs to expendable index, is worth the smaller the better; Severely-weathered layer distribution belongs to rentability index, and value is the bigger the better.Calculate the distance of difficulty of construction opinion rating and positive ideal solution and minus ideal result and corresponding approach degree, as shown in table 13:
Table 13 working measure total hierarchial sorting result
Grade of difficulty Di + Di - Ci + Sequence
N 1 0.081 0.008 0.088 2
N 2 0.027 0.061 0.694 3
N 3 0.000 0.088 1.000 4
N 0.088 0.000 0.000 1
D. with AHP-TOPSIS scoring model prediction difficulty of construction grade forecast
The weight of each judging quota of the rule layer calculated by AHP method is:
W=[0.594 0.249 0.157]
The Judgement Matrix of each judging quota approach degree structure obtained according to TOPSIS method is:
C = 0.290 0.379 0.574 0.761 0.112 0.701 1.000 0.000 0.088 0.694 1.000 0.000
Then evaluation result vector Q is:
Q=W×C=[0.214 0.508 0.747 0.452]
The Comprehensive Evaluation result that to sum up can obtain each construction difficulty or ease grade is respectively:
N 1=21.4%, N 2=50.8%, N 3=74.7%, N=45.2%, wherein N ∈ (N 1, N 2), obtaining difficulty of construction grade by predicting the outcome is N2 (generally).Although the geologic condition in this place is very complicated, difficulty of construction large, predicting the outcome, it is general to be still difficulty of construction, absolutely proves the vital role of preparation of construction and working measure.So must first analyze Geological condition, then for the evaluation result of Geological condition and difficulty of construction, select preparation of construction conditionally, take effective, necessary working measure.That is, can according to the influential effect of each level factor, the arrangement and method for construction of next block Impermeable underground wall curtain body of timely adjustment and/or preparation of construction, evade adverse risk in advance, thus realize bordering on the sea the difficulty of construction dynamic forecasting of regional foundation ditch Impermeable underground wall curtain and adjustment to the South Sea.
Regional foundation pit waterproof curtain design and construction difficulty is bordered on the sea comparatively greatly in the South Sea, comparatively different from the general foundation ditch in interior ground, and present stage is temporarily without good design and construction process, construction costs and the prediction and evaluation method of construction period.Utilize this method can carry out performance prediction to the South Sea typical foundation pit construction difficulty in area that borders on the sea, the arrangement and method for construction of next block Impermeable underground wall curtain body of timely adjustment and/or preparation of construction, evade adverse risk in advance, be convenient to estimate foundation pit waterproof curtain design and construction cost and construction period simultaneously.Difficulty of construction appraisement system of the present invention succinctly facilitates, workable, to the South Sea border on the sea containing coral reef chip stratum construction evaluation have better applicability.
Foregoing description is only the description to present pre-ferred embodiments, any restriction not to the scope of the invention, and any change that the those of ordinary skill in field of the present invention does according to above-mentioned disclosure, modification, all belong to the protection domain of claims.

Claims (7)

1. an Impermeable underground wall curtain body construction difficulty Forecasting Methodology, is characterized in that, comprise the steps:
Step 1, preparation of construction is utilized to carry out an Impermeable underground wall curtain body construction in conjunction with geologic condition on construction ground;
Step 2, the comprehensive each factor analyzing Effect Field ground difficulty of construction, carry out distinguishing hierarchy to described each factor and sort out, forming each construction difficulty or ease grade evaluation criterion for every class factor;
Step 3, utilize APH analytical hierarchy process analyze described each factor, obtain the index weights that each factor affects for difficulty of construction;
Step 4, in conjunction with TOPSIS similarity to ideal solution ranking method, respectively risk class division is carried out to the influence factor of same level according to above-mentioned difficulty of construction grade evaluation criterion, determine the influential effect of each level factor.
2. Impermeable underground wall curtain body construction difficulty Forecasting Methodology as claimed in claim 1, is characterized in that, according to the influential effect of each level factor, adjusts arrangement and method for construction and/or the preparation of construction of next block Impermeable underground wall curtain body in time, evades adverse risk in advance.
3. Impermeable underground wall curtain body construction difficulty Forecasting Methodology as claimed in claim 1, is characterized in that, the described each factor affecting place difficulty of construction is divided into geologic condition, preparation of construction and working measure three class.
4. Impermeable underground wall curtain body construction difficulty Forecasting Methodology as claimed in claim 3, it is characterized in that, described geologic condition comprises the thickness of overburden layer, the homogeneity of upper overburden layer, the fluctuating quantity of bedrock surface, Coral Reef Rock distribution situation and severely-weathered layer distribution situation; Described preparation of construction comprises mixing pile stake machine type, jet grouting pile driving machine, inspecting hole, draws drilling machine and water power standby condition; And working measure comprises examination pore-forming, inspecting hole, draws hole and lower pipe.
5. Impermeable underground wall curtain body construction difficulty Forecasting Methodology as claimed in claim 3, it is characterized in that, described construction site is positioned at borders on the sea containing Coral Reef Rock area, geologic structure is from top to bottom followed successively by: containing coral reef chip soil layer, severely-weathered layer and middle waste mantle, and described Impermeable underground wall curtain body adopts the combined enclosure form of three axes agitating pile and high-pressure rotary jet grouting pile on vertical section.
6. Impermeable underground wall curtain body construction difficulty Forecasting Methodology as claimed in claim 5, it is characterized in that, the construction procedure of described Impermeable underground wall curtain body comprises:
Step 11, carries out examination pile to construction site, tentatively determines the construction parameter of three axes agitating pile and high-pressure rotary jet grouting pile;
Step 12, adopts rig to carry out inspecting hole, verifies the bedrock surface buried depth situation containing the Coral Reef Rock depth of stratum in the soil layer of Coral Reef Rock, severely-weathered layer thickness and middle waste mantle;
Step 13, for containing the soil layer of Coral Reef Rock and severely-weathered layer, adopt single cover to make three axes agitating pile stake machine and construct, three axes agitating pile injection is to the above 1.0-1.5m degree of depth of bedrock surface;
Step 14, carries out drawing hole, draws more than 1m under hole to bedrock surface after three axes agitating pile has been constructed, can whole hole after guaranteeing to enter basement rock projected depth, and pore-forming aperture is not less than 130mm, and perpendicularity deviation is not more than 1/200, and the biased difference in hole is not more than 20mm;
Step 15, it is complete with down tube to draw hole, and adopt pvc pipe, by pvc pipe back cover, interior mud grouting, transfers more than 1m to bedrock surface from drawing hole;
Step 16, utilizes jet grouting pile driving machine construction high-pressure rotary jet grouting pile, enter bedrock surface more than 1.0 meters under high-pressure rotary jet grouting pile, high-pressure rotary jet grouting pile and three axes agitating pile effectively overlap more than 1.0 meters.
7. Impermeable underground wall curtain body construction difficulty Forecasting Methodology as claimed in claim 6, is characterized in that, in step 15, if the sludge of precipitation is thicker at the bottom of hole, necessary clear hole deslagging, guarantees that pvc pipe enters below bedrock surface more than 1.0m.
CN201510254481.3A 2015-05-19 2015-05-19 A kind of Impermeable underground wall curtain body construction difficulty Forecasting Methodology Active CN104866664B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510254481.3A CN104866664B (en) 2015-05-19 2015-05-19 A kind of Impermeable underground wall curtain body construction difficulty Forecasting Methodology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510254481.3A CN104866664B (en) 2015-05-19 2015-05-19 A kind of Impermeable underground wall curtain body construction difficulty Forecasting Methodology

Publications (2)

Publication Number Publication Date
CN104866664A true CN104866664A (en) 2015-08-26
CN104866664B CN104866664B (en) 2018-05-25

Family

ID=53912489

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510254481.3A Active CN104866664B (en) 2015-05-19 2015-05-19 A kind of Impermeable underground wall curtain body construction difficulty Forecasting Methodology

Country Status (1)

Country Link
CN (1) CN104866664B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106709653A (en) * 2016-12-28 2017-05-24 中国电建集团贵阳勘测设计研究院有限公司 Method for comprehensively and quantitatively evaluating construction quality of seepage-proof curtain of hydropower station
CN109034621A (en) * 2018-07-27 2018-12-18 重庆工程职业技术学院 The risk evaluating method of Impermeable underground wall curtain body construction duration and cost
CN113610337A (en) * 2021-06-22 2021-11-05 中铁建华南建设有限公司 Foundation pit engineering risk determination method and device, computer equipment and storage medium
CN114855748A (en) * 2022-05-24 2022-08-05 中交第四航务工程局有限公司 Output torque-based cement mixing pile soil layer identification method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011038338A (en) * 2009-08-12 2011-02-24 Shimizu Corp Ground deformation analysis device and ground deformation analysis program
CN102002962A (en) * 2010-11-01 2011-04-06 华北有色工程勘察院有限公司 Determining method for water-plugging curtain permeability inversion analysis construction
CN103530522A (en) * 2013-10-22 2014-01-22 北京交通大学 Risk ranking control method of shield penetrating through buildings at soft soil stratum
CN103926390A (en) * 2013-01-15 2014-07-16 中冶集团武汉勘察研究院有限公司 Comprehensive judgment method for bearing capacity of basalt in Zhanjiang area
CN104032736A (en) * 2014-06-25 2014-09-10 上海市建工设计研究院有限公司 Construction method of cement-soil mixed pile in coral-reef limestone stratum

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011038338A (en) * 2009-08-12 2011-02-24 Shimizu Corp Ground deformation analysis device and ground deformation analysis program
CN102002962A (en) * 2010-11-01 2011-04-06 华北有色工程勘察院有限公司 Determining method for water-plugging curtain permeability inversion analysis construction
CN103926390A (en) * 2013-01-15 2014-07-16 中冶集团武汉勘察研究院有限公司 Comprehensive judgment method for bearing capacity of basalt in Zhanjiang area
CN103530522A (en) * 2013-10-22 2014-01-22 北京交通大学 Risk ranking control method of shield penetrating through buildings at soft soil stratum
CN104032736A (en) * 2014-06-25 2014-09-10 上海市建工设计研究院有限公司 Construction method of cement-soil mixed pile in coral-reef limestone stratum

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106709653A (en) * 2016-12-28 2017-05-24 中国电建集团贵阳勘测设计研究院有限公司 Method for comprehensively and quantitatively evaluating construction quality of seepage-proof curtain of hydropower station
CN109034621A (en) * 2018-07-27 2018-12-18 重庆工程职业技术学院 The risk evaluating method of Impermeable underground wall curtain body construction duration and cost
CN113610337A (en) * 2021-06-22 2021-11-05 中铁建华南建设有限公司 Foundation pit engineering risk determination method and device, computer equipment and storage medium
CN113610337B (en) * 2021-06-22 2024-04-19 中铁建华南建设有限公司 Foundation pit engineering risk determination method, device, computer equipment and storage medium
CN114855748A (en) * 2022-05-24 2022-08-05 中交第四航务工程局有限公司 Output torque-based cement mixing pile soil layer identification method

Also Published As

Publication number Publication date
CN104866664B (en) 2018-05-25

Similar Documents

Publication Publication Date Title
CN104727828B (en) Tunnel pre-support management method based on deformation control
Schweizer et al. Uncertainty assessment in 3-D geological models of increasing complexity
Lo et al. Bayesian updating of subsurface spatial variability for improved prediction of braced excavation response
CN111691872B (en) Dynamic and accurate detection method for development range and degree of coal seam overlying strata fracture
Li et al. Risk assessment of floor water inrush using entropy weight and variation coefficient model
CN104452836A (en) Monitoring and early warning method of the stability of a foundation pit supporting structure
CN104179514A (en) Method for water inrush prediction and seepage control for underwater-tunnel broken surrounding rocks
CN104866664A (en) Method for predicting construction difficulty of water seepage prevention curtain-grouting
CN104899682A (en) Evaluation method for construction risk of antiseepage waterproof curtain of deep foundation fit in coastal area
Liu et al. Predicting the height of the water-conducting fractured zone using multiple regression analysis and GIS
Wang et al. Risk Assessment of Water Inrush in Karst Tunnels Based on the Efficacy Coefficient Method.
CN102253423B (en) Proper water supply position intelligent recognition technology based on multi-source hydrogeology survey information
Suh et al. Subsidence hazard assessment at the Samcheok coalfield, South Korea: a case study using GIS
CN109736796A (en) A kind of intensification blasthole forward probe mechanism and its forecasting procedure
CN104564069B (en) The dynamic settlement prediction in a kind of ground based on square mesh method and reclamation method
CN106055865A (en) Method and system for evaluating influences of tunnel construction on water environment
Xue et al. An analytical model for assessing soft rock tunnel collapse risk and its engineering application
CN115203945A (en) Hydrogeological parameter estimation method, hydrogeological parameter estimation device, hydrogeological parameter estimation equipment and storage medium
Hsu et al. Influence of geological uncertainty on the design of OWTF monopiles
Xue et al. A prediction model for overlying rock thickness of subsea tunnel: A hybrid intelligent system
Qi et al. Two-dimensional prediction of the interface of geological formations: A comparative study
Shi et al. Data-driven sequential development of geological cross-sections along tunnel trajectory
CN113010997A (en) Early warning treatment method for pile foundation impact hole-forming construction accidents in karst development area
Zhang et al. Quantitative evaluation and planning method of shallow surface water response in multi-face mining—Case study regarding Zhuanlongwan coal mine
Liu et al. A new risk zoning method for water inrush from separated layers at coal mines: a case study, Cuimu coal mine, China

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 200050 Changning District, Wuyi Road, No. 150,

Applicant after: Shanghai construction design and Research Institute Co Ltd

Applicant after: Chinese People's Liberation Army Naval Engineering Design Institute

Address before: 200050 Changning District, Wuyi Road, No. 150,

Applicant before: Shanghai Construction Group Design Institute Co., Ltd.

Applicant before: Chinese People's Liberation Army Naval Engineering Design Institute

CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Ren Haiping

Inventor after: Yang Jibao

Inventor after: Ni Qi

Inventor after: Han Bingchen

Inventor after: Feng Mingwei

Inventor before: Yang Jibao

Inventor before: Ni Qi

Inventor before: Ren Haiping

Inventor before: Han Bingchen

Inventor before: Feng Mingwei