CN104865042B - One kind building wind-tunnel can adjust wind and cut open passive simulation wedge device - Google Patents

One kind building wind-tunnel can adjust wind and cut open passive simulation wedge device Download PDF

Info

Publication number
CN104865042B
CN104865042B CN201510204355.7A CN201510204355A CN104865042B CN 104865042 B CN104865042 B CN 104865042B CN 201510204355 A CN201510204355 A CN 201510204355A CN 104865042 B CN104865042 B CN 104865042B
Authority
CN
China
Prior art keywords
wing
wind
tunnel
wedge
width adjusting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510204355.7A
Other languages
Chinese (zh)
Other versions
CN104865042A (en
Inventor
曹钧亮
满孝新
刘京
李悦
蒋永明
李壮壮
徐坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Engineering Design Group Corp Ltd
Original Assignee
China Construction Engineering Design Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Engineering Design Group Corp Ltd filed Critical China Construction Engineering Design Group Corp Ltd
Priority to CN201510204355.7A priority Critical patent/CN104865042B/en
Publication of CN104865042A publication Critical patent/CN104865042A/en
Application granted granted Critical
Publication of CN104865042B publication Critical patent/CN104865042B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Aerodynamic Tests, Hydrodynamic Tests, Wind Tunnels, And Water Tanks (AREA)

Abstract

Wind is can adjust the present invention relates to one kind building wind-tunnel and cuts open passive simulation wedge device, belongs to building wind-tunnel technique field.Including:Base, on the bottom surface of wind-tunnel;Wedge body, the bottom of wedge body are fixedly connected with base;Wedge body includes middle plate and wing plate, and one side of middle plate is fixedly connected on the one side of wing plate, make wing plate be divided into first wing while and during second wing;Width adjusting part, respectively along first wing while and install during second wing, by control width adjusting part first wing while and installation site during second wing realize the width adjusting of wedge device;Fixture, the fixture at the top of wedge body with being fixedly connected, for wedge body to be fixed on into wind-tunnel.The present invention can meet to the flexible modulation of target wind speed section during wind tunnel test, and process is rapid, and wind speed profile modeling precision is high, and wedge device of the present invention is simple in construction, be easily assembled to, applicability is wide, low manufacture cost.

Description

One kind building wind-tunnel can adjust wind and cut open passive simulation wedge device
Technical field
The invention belongs to build wind-tunnel technique field, it can adjust wind more particularly to kind of building wind-tunnel and cut open passive simulation Wedge device.
Background technology
, it is necessary to be simulated to the wind profile of different landforms in wind tunnel test is built, the method generally used now It is passive simulation method.The way of usual passive simulation method is that building wind turbine apparatus incoming is caused not by different blocking devices Same obstruction, make wind speed that required distribution be presented in vertical direction(That is wind profile, also known as wind cut open).Blocking device mainly includes Wedge and roughness element.Wedge stands on upwind, and upper and lower width is different, causes different obstructions to make upper and lower wind speed not to air Together.
In general way is substantially to determine the size of wedge by empirical equation and numerical simulation before the test at present, so Post-processing makes wedge, is then tested in actual wind-tunnel.Following problem be present in this way:
1st, width is difficult to change after wedge completes.Because of the complexity of wind tunnel test situation, using analogy method system The wedge of work is difficult the requirement for accurately meeting experimenter.Tested according to this wedge, test data will necessarily be reduced Precision, cause the inaccuracy of result of the test.If remaking wedge, just necessarily cause experimentation cost increase and the test period Increase.
2nd, the wedge to complete can only meet the wind speed profile modeling under single scaling factor, if carrying out more scaling factor works The experiment of condition causes increasing for experimentation cost it is necessary to separately make wedge.
The content of the invention
The present invention provides a kind of adjustable wind of building wind-tunnel and cuts open passive simulation wedge device, and technical problem to be solved is Width is difficult to change after the wedge of prior art completes, and wedge is difficult the requirement for accurately meeting experimenter, and system The wedge for making to complete can only meet the wind speed profile modeling under single scaling factor, experimentation cost height.
The technical scheme that the present invention solves above-mentioned technical problem is as follows:One kind building wind-tunnel can adjust wind and cut open passive simulation point Device is split, it includes:
Base, the floor installation is on the bottom surface of wind-tunnel;
Wedge body, the bottom of the wedge body are fixedly connected with the base;Wedge body includes middle plate and wing plate, One side of the middle plate is fixedly connected on the one side of the wing plate, make wing plate be divided into first wing while and during second wing;
Width adjusting part, respectively along first wing while and install during second wing, by controlling width adjusting part described First wing while and installation site during second wing realize the width adjusting of wedge device;
Fixture, the fixture at the top of wedge body with being fixedly connected, for wedge body to be fixed on into wind-tunnel.
Building wind-tunnel as described above of the invention can adjust wind and cut open passive simulation wedge device, further, first wing While there is spaced through hole;Second wing side has spaced through hole;The both ends interval of the width adjusting part It is provided with fixing hole;Bolt passes through corresponding fixing hole and through hole that width adjusting part is separately mounted into the first wing side and second wing Side.
Building wind-tunnel as described above of the invention can adjust wind and cut open passive simulation wedge device, and further, the width is adjusted Section part side there is groove, the section of width adjusting part be " Π " shape, by the groove of width adjusting part can enter the first wing side with/ Or second wing side.
Building wind-tunnel as described above of the invention can adjust wind and cut open passive simulation wedge device, further, first wing Side has the through hole that interval 4~8cm distances are set;Second wing side has the through hole that interval 4~8cm distances are set.
Building wind-tunnel as described above of the invention can adjust wind and cut open passive simulation wedge device, further, the fixture Including:Topmast strut, with being fixedly connected at the top of the wedge body, the other end is screw rod for one end of the topmast strut;It is long Set screw is spent, the length adjustment screw is screwed on the screw rod.
The beneficial effects of the invention are as follows:
1st, the present invention can meet to the flexible modulation of target wind speed section during wind tunnel test, and process is fast Speed, wind speed profile modeling precision are high.Traditional Wedge structure can only be by structures such as roughness element or rack saws to subaerial wind Fast section realizes fine setting, and the arbitrary height of wind profile can be adjusted for name of the present invention, and adjustable range is big, precision Height, so as to substantially increase the precision of experiment, save the time that wind profile is adjusted in experiment.
2nd, it is simple in construction, be easily assembled to, applicability is wide, low manufacture cost.The system composition structure is few, is easily assembled to, and makes Make relative inexpensiveness, relative to traditional Wedge structure, it is possible to achieve for the regulation requirement of a variety of scaling factors experiment, be applicable Scaling factor scope is 1/600-1/200, can apply to the wind profile regulation of most building wind-tunnel at present.
Brief description of the drawings
Fig. 1 cuts open passive simulation wedge device schematic diagram for a kind of adjustable wind of wind-tunnel of building provided in an embodiment of the present invention;
Fig. 2 is Fig. 1 schematic side view;
Fig. 3 is Fig. 1 Section A-A schematic diagram;
Fig. 4 is a kind of width adjusting part schematic diagram provided in an embodiment of the present invention;
Fig. 5 is Fig. 4 schematic side view.
In accompanying drawing, the list of parts representated by each label is as follows:
1st, base, 2, wedge body, 21, wing plate, 22, middle plate, 23, through hole, 3, topmast strut, 4, length adjustment screw, 5th, width adjusting part, 51, fixing hole.
Embodiment
The principle and feature of the present invention are described below in conjunction with accompanying drawing, the given examples are served only to explain the present invention, and It is non-to be used to limit the scope of the present invention.
The embodiment of the present invention needs to solve the problems, such as:Width is difficult to change after the wedge of prior art completes, Local modulation can not be realized, can only be aided in by other servicing units.This scheme can cause the test period to grow, experiment The problem of precision is low.In addition, the wedge to complete can only meet the wind speed profile modeling under single scaling factor, if carried out more The experiment of scaling factor operating mode, which will separately make wedge, causes increasing for experimentation cost.
As Figure 1-3, passive simulation wedge dress is cutd open for a kind of adjustable wind of wind-tunnel of building provided in an embodiment of the present invention Put schematic diagram.
The adjustable wind of building wind-tunnel, which cuts open passive simulation wedge device, to be included:
Base 1, the floor installation is on the bottom surface of wind-tunnel;
Wedge body 2, the bottom of the wedge body 2 are fixedly connected with the base 1;Wedge body includes the middle He of plate 22 Wing plate 21, one side of the middle plate 22 are fixedly connected on the one side of the wing plate 21, wing plate 21 is divided into the first wing side and Two wing sides;
Width adjusting part 5, respectively along first wing while and install during second wing, by controlling width adjusting part 5 in institute State first wing while and installation site during second wing realize the width adjusting of wedge device;
Fixture, the fixture are fixedly connected with the top of wedge body 2, for wedge body to be fixed on into wind-tunnel.
The use process that the adjustable wind of present invention building wind-tunnel cuts open passive simulation wedge device is as follows:
Before experiment, the size of wedge and the installation position of width adjusting part are determined by empirical equation and numerical simulation Put, then by width adjusting part respectively along first wing while and install during second wing.During experiment, base is placed in wind tunnel test Design attitude, wedge device is fixed in wind-tunnel by fixture.Tested in the wind-tunnel of arrangement wedge device, Obtained wind profile is cutd open with target wind and contrasted, and the regulation of respective width is carried out according to its difference, and it is suitable to finally give Target wind cuts open.
As shown in figure 1, first wing side has spaced through hole 23;Second wing side has spaced Through hole 23;In specific implementation process, first wing side has the through hole 23 that interval 4~8cm distances are set;Second wing Side has the through hole 23 that interval 4~8cm distances are set.In preferred implementation process, first wing side has interval 5cm The through hole 23 that distance is set;Second wing side has the through hole 23 that interval 5cm distances are set.The spacing and quantity of through hole 23 It can also be adjusted according to entire length, the degree of regulation demand of wedge body, within protection scope of the present invention.
As shown in figure 4, the both ends of the width adjusting part 5 are arranged at intervals with fixing hole 51;Bolt is fixed through corresponding Hole 51 and through hole 23 by width adjusting part 5 be separately mounted to first wing while and during second wing.
Width adjusting part has a variety of implementations in specific implementation process,
A kind of as shown in figure 5, width adjusting part schematic diagram for embodiment.The side of the width adjusting part has recessed Groove, the section of width adjusting part is " Π " shape, by the groove of width adjusting part can enter first wing while and/or during second wing.In order to Be easy to width adjusting part 5 be separately mounted to first wing while and form low wide and up narrow decrement structure, width adjusting part 5 during second wing For the different list of elements of width.For example, it is respectively 30 mm, 35 mm, 45 mm, 55 mm, 65 that width adjusting part, which all obtains width, Mm, 75 mm, 85 mm, 95 mm, groove thickness 20mm, adaptable wing plate thickness is 20mm therewith.
In the embodiment of another width adjusting part, the width adjusting part is platy structure, the two of width adjusting part End is arranged at intervals with fixing hole;The width adjusting part of this embodiment prepares more simple and efficient, width in specific implementation process Regulating part can use the higher iron plate of hardness to make.
In one embodiment, as depicted in figs. 1 and 2, the fixture includes:Topmast strut 3, the topmast strut 3 One end be fixedly connected with the top of the wedge body 2, the other end is screw rod;Length adjustment screw 4, the length adjustment spiral shell Silk is screwed on the screw rod.
The use process that the adjustable wind of the present embodiment building wind-tunnel cuts open passive simulation wedge device is as follows:
Base is placed in the design attitude of wind tunnel test, topmast is made by the length adjustment screw for rotating topmast strut end Strut elongation makes wedge device be fixed in wind-tunnel up to being held out against with wind-tunnel upper arm.
The lateral adjustments of system realize that the fixing hole of width adjusting part represents different by the fixing hole of width adjusting part Width, by width adjusting part respectively along first wing while and during second wing after installation test obtains current working Wind cuts open, and by the contrast cutd open with target wind, selects different width adjusting parts to adjust the width of wedge, so as to realize wedge device Control to transverse width.
Longitudinally adjust is realized jointly by the fixing hole of wedge body and width adjusting part.First wing while and during second wing it is equal With spaced through hole, different through holes represents different wedge height, width adjusting part and wedge body by with not Level through hole connection, so as to realize the longitudinally adjust of wedge device.
The foregoing is only presently preferred embodiments of the present invention, be not intended to limit the invention, it is all the present invention spirit and Within principle, any modification, equivalent substitution and improvements made etc., it should be included in the scope of the protection.

Claims (3)

1. one kind building wind-tunnel can adjust wind and cut open passive simulation wedge device, it is characterised in that including:
Base, the floor installation is on the bottom surface of wind-tunnel;
Wedge body, the bottom of the wedge body are fixedly connected with the base;Wedge body includes middle plate and wing plate, described One side of middle plate is fixedly connected on the one side of the wing plate, make wing plate be divided into first wing while and during second wing;
Width adjusting part, respectively along first wing while and install during second wing, by controlling width adjusting part described first The wing while and installation site during second wing realize the width adjusting of wedge device;
Fixture, the fixture at the top of wedge body with being fixedly connected, for wedge body to be fixed on into wind-tunnel;
First wing side has spaced through hole;Second wing side has spaced through hole;The width is adjusted The both ends of section part are arranged at intervals with fixing hole;Bolt passes through corresponding fixing hole and through hole that width adjusting part is separately mounted into the One wing while and during second wing;
The side of the width adjusting part has groove, and the section of width adjusting part is " Π " shape, by the groove of width adjusting part Can enter first wing while and/or during second wing;
Width adjusting part width is respectively 30 mm, 35 mm, 45 mm, 55 mm, 65 mm, 75 mm, 85 mm, 95 mm, groove Thickness is 20mm, and adaptable wing plate thickness is 20mm therewith.
2. building wind-tunnel according to claim 1 can adjust wind and cut open passive simulation wedge device, it is characterised in that described the One wing side has the through hole that interval 4~8cm distances are set;Second wing side has the through hole that interval 4~8cm distances are set.
3. building wind-tunnel according to claim 1 or 2 can adjust wind and cut open passive simulation wedge device, it is characterised in that institute Stating fixture includes:Topmast strut, with being fixedly connected at the top of the wedge body, the other end is for one end of the topmast strut Screw rod;Length adjustment screw, the length adjustment screw are screwed on the screw rod.
CN201510204355.7A 2015-04-27 2015-04-27 One kind building wind-tunnel can adjust wind and cut open passive simulation wedge device Expired - Fee Related CN104865042B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510204355.7A CN104865042B (en) 2015-04-27 2015-04-27 One kind building wind-tunnel can adjust wind and cut open passive simulation wedge device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510204355.7A CN104865042B (en) 2015-04-27 2015-04-27 One kind building wind-tunnel can adjust wind and cut open passive simulation wedge device

Publications (2)

Publication Number Publication Date
CN104865042A CN104865042A (en) 2015-08-26
CN104865042B true CN104865042B (en) 2017-12-12

Family

ID=53911026

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510204355.7A Expired - Fee Related CN104865042B (en) 2015-04-27 2015-04-27 One kind building wind-tunnel can adjust wind and cut open passive simulation wedge device

Country Status (1)

Country Link
CN (1) CN104865042B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109827739B (en) * 2019-04-02 2021-01-29 重庆科技学院 Telescopic turbulence device for wind tunnel test
CN109827743B (en) * 2019-04-02 2020-10-16 重庆科技学院 Multi-point multi-stage regulation turbulent flow wedge
CN109827744A (en) * 2019-04-02 2019-05-31 重庆科技学院 Wind tunnel test flow-disturbing wedge

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101957255A (en) * 2010-09-30 2011-01-26 浙江大学 Wind tunnel boundary layer simulating wedge and barrier combined device
CN204575292U (en) * 2015-04-27 2015-08-19 中国中建设计集团有限公司 The adjustable wind of a kind of building wind-tunnel cuts open passive simulation wedge device
CN106153287A (en) * 2015-04-08 2016-11-23 大连理工大学 A kind of device for fixing wind-tunnel wedge

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3229157B2 (en) * 1995-03-20 2001-11-12 三菱重工業株式会社 Boundary layer turbulence generator
JP2000266635A (en) * 1999-03-19 2000-09-29 Hitachi Zosen Corp Boundary layer turbulence-generating device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101957255A (en) * 2010-09-30 2011-01-26 浙江大学 Wind tunnel boundary layer simulating wedge and barrier combined device
CN106153287A (en) * 2015-04-08 2016-11-23 大连理工大学 A kind of device for fixing wind-tunnel wedge
CN204575292U (en) * 2015-04-27 2015-08-19 中国中建设计集团有限公司 The adjustable wind of a kind of building wind-tunnel cuts open passive simulation wedge device

Also Published As

Publication number Publication date
CN104865042A (en) 2015-08-26

Similar Documents

Publication Publication Date Title
CN104865042B (en) One kind building wind-tunnel can adjust wind and cut open passive simulation wedge device
CN104894977B (en) A kind of method utilizing three-dimensional adjustable jack device to set up magnetic levitation track girder
CN101210457A (en) Height mark adjustable ultra-flat terrace template, manufacturing method thereof and application of the same in construction
CN102776827A (en) Milling machine and milling depth monitoring device thereof
CN204575292U (en) The adjustable wind of a kind of building wind-tunnel cuts open passive simulation wedge device
CN204771511U (en) Product cabin section flexible assembly device
CN209493891U (en) A kind of cast-in-place guardrail reinforcing bar binding limiter of movable type
CN106466722A (en) Novel valve multi-spindle drilling machine
CN206173779U (en) Location structure of wave form steel web
CN205474636U (en) Line type positioner of F type section of track
CN203049873U (en) Vertical panel mounting structure with adjustable height
CN103883845A (en) Method and pad iron assembly for adjusting elevation of flat pad iron by aid of three bolt reinforcements
CN105089151A (en) Positioning device of node normal of space curved surface truss structure and determining method of positioning device
CN106381831B (en) A kind of method of determining air entraining facilities venthole cross-sectional area
CN204597304U (en) A kind of distributing box fixing device for installing
CN102501198A (en) Method for adjusting flexibility of assembly fixture of car body
CN202992543U (en) Sizing block adjusting device
CN203180383U (en) Mechanism case installation special device
JP6388712B2 (en) Wind power generator-tower and wind power generator-tower installation method
CN206737445U (en) The vertical dual-purpose adjuster of Simple horizontal
CN207452734U (en) A kind of Large Steel pipeline overhead lifting adjusting apparatus
CN207350914U (en) A kind of column tooling for fast installing of photo-thermal slot-type optical collector
CN206007541U (en) A kind of bionic hip-joint governor motion
CN204996898U (en) Door plant hem frock
CN203812861U (en) Manipulator structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171212