CN104831679B - The rib sill spacing measuring method of soft base energy dissipation type debris flow drainage groove and application - Google Patents
The rib sill spacing measuring method of soft base energy dissipation type debris flow drainage groove and application Download PDFInfo
- Publication number
- CN104831679B CN104831679B CN201510247582.8A CN201510247582A CN104831679B CN 104831679 B CN104831679 B CN 104831679B CN 201510247582 A CN201510247582 A CN 201510247582A CN 104831679 B CN104831679 B CN 104831679B
- Authority
- CN
- China
- Prior art keywords
- drainage groove
- rib sill
- debris flow
- spacing
- energy dissipation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
-
- G—PHYSICS
- G16—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR SPECIFIC APPLICATION FIELDS
- G16Z—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR SPECIFIC APPLICATION FIELDS, NOT OTHERWISE PROVIDED FOR
- G16Z99/00—Subject matter not provided for in other main groups of this subclass
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
The invention discloses rib sill spacing measuring method and the application of a kind of soft base energy dissipation type debris flow drainage groove.Described rib sill spacing measuring method first passes through large scale topographical map survey calculation or field investigation actual measurement determines drainage groove longitudinal river slope, then calculated by mud-rock flow severe computing formula or actual sampling actual measurement determines debris flow body severe, determine the rib sill spacing of soft base energy dissipation type debris flow drainage groove finally by spacing measure formula between rib sill.The method has considered drainage groove longitudinal river slope, debris flow body severe, the big factor of drainage groove rib sill buried depth three, and combine soft base energy dissipation type debris flow drainage groove rib sill layout feature, carry out data matching by simulation laboratory test result and obtain soft base energy dissipation type debris flow drainage groove rib sill spacing measure formula, can rationally determine the rib sill spacing under different situations, scientific basis is provided for disaster prevention engineering design, and this measuring method calculates simplicity, adapt to requirement of engineering.
Description
Technical field
The present invention relates to the rib sill spacing measuring method of a kind of soft base energy dissipation type debris flow drainage groove, and at prevention and cure project
Application during middle rib sill line space design.
Background technology
Mud-rock flow be a kind of between landslide and current between the two-phase solid-liquid fluid containing mud, sand and stone, in turbulent flow with
The kinestate of laminar flow, have outburst suddenly, motion quickly, energy is huge, impulsive force is strong, last the characteristic of activities such as of short duration, be
The geologic hazard type that mountain area is common.For Mu Qian, debris flow drainage groove is a kind of effective engineering of preventing and treating mud-stone flow disaster
Measure.Preventing and reducing natural disasters in practice at long-term mud-rock flow, the form of debris flow drainage groove gradually forms and perfect;The most conventional
One of debris flow drainage groove form is soft base energy dissipation type drainage groove, and this drainage groove uses the combination of separate type retaining wall rib sill
Structure, takes full advantage of the energy dissipating effect to mud-rock flow of ditch bed and rib sill, it is ensured that the safety excretion of mountain torrents and mud-rock flow.
Soft base energy dissipating principle is the high degree of agitation by being full of the mud-rock flow of clast and ditch bed matter, consumes mud-rock flow
Motion complementary energy, to maintain mud-rock flow Uniform Flow.The effect of rib sill is to maintain clast volumetric concentration in stilling pond, makes erosion and deposition reach
To balance, basis is not emptied, and by drop growth and decline (after rib sill) after sill, automatically adjusts mud position longitudinal river slope and flow velocity so that edge
Journey resistance and local resistance are coordinated, and keep the constant of mud-rock flow severe and defeated shifting power.Therefore, reasonable Arrangement rib sill spacing is soft base
The key factor of required consideration during the design of energy dissipating drainage groove.If drainage groove rib sill are arranged overstocked, it will cause the waste of resource;
If arranging dilute, ditch bed material is acted on by mud-rock flow retrogressive erosion, it would be possible to basis, rib sill rear portion can be caused to be rushed
Brush, affects rib sill stability, and then causes rib sill to destroy, affect the safe operation of engineering.
Determination currently, with respect to rib sill spacing can only be according to " debris flow control works design specification " (DZ/T0239-
2004) the rib sill line space design formula be given in, does not also have other the measuring and calculating about rib sill spacing to determine method.According to " mud
Rock glacier prevention and cure project design specification " (DZ/T0239-2004), rib sill spacing uses equation below to determine:
In formula, L is erosion control floor (i.e. rib sill) spacing (m);H is erosion control floor (i.e. rib sill) buried depth (m), typically takes H=
1.5~4.0m;Δ H is erosion control floor (i.e. rib sill) safe superelevation (m), typically takes Δ H=0.5m;I0Longitudinal gradient is designed for drainage groove
Fall (i.e. drainage groove longitudinal river slope);I ' be after washing away under floor (i.e. rib sill) drainage groove longitudinal gradient fall, typically take I '=(0.5~
0.25)I0.From above-mentioned formula analysis, the size of rib sill spacing L is affected bigger by drainage groove longitudinal river slope.With rib sill buried depth
It is 0.5m, I '=0.25I for 3.5m, safe superelevation0As a example by, rib sill distance computation value such as table 1 below under different drainage groove longitudinal river slopes:
Drainage groove longitudinal river slope | 0.050 | 0.080 | 0.100 | 0.125 | 0.150 | 0.175 | 0.200 | 0.225 | 0.250 | 0.275 | 0.300 |
Rib sill spacing (m) | 80.00 | 53.00 | 40.00 | 32.00 | 26.70 | 22.86 | 20.00 | 17.70 | 16.00 | 14.60 | 13.30 |
Rib sill distance computation value under the different drainage groove longitudinal river slope of table 1
As shown in Table 1, when drainage groove longitudinal river slope is relatively big, and when for example, 0.200~0.300, rib sill spacing excursion is
20.00m~13.30m, is consistent with engineering practice;But when drainage groove longitudinal river slope is less, for example, 0.050~0.080
Time, rib sill distance computation value excursion is 80.00m~53.00m, and result of calculation is bigger than normal, with existing case history not being inconsistent
Close.On the other hand, this rib sill distance computation formula only accounts for rib sill buried depth and drainage groove longitudinal river slope the two factor, not
Consider the mud-rock flow character relative influence to rib sill spacing.
Summary of the invention
The purpose of the present invention is aiming at the deficiencies in the prior art, it is provided that the rib of a kind of soft base energy dissipation type debris flow drainage groove
Sill spacing measuring method and application thereof, the method can rationally determine soft base energy dissipating drainage groove rib sill spacing, for rib sill spacing
Design provides foundation, calculates simplicity, and desired parameters is few, and computational solution precision is high, adapts to actual requirement of engineering.
For achieving the above object, the technical scheme is that
The present invention proposes the rib sill spacing measuring method of a kind of soft base energy dissipation type debris flow drainage groove, described soft base energy dissipation type
Debris flow drainage groove includes that some bottom lands arranged at a certain distance extend transversely through the drainage groove side wall of type rib sill and both sides thereof, rib
Spacing measuring method step between sill is as follows:
(1) surveyed by large scale topographical map survey calculation or field investigation, determine drainage groove longitudinal river slope I0;Pass through
Mud-rock flow severe computing formula calculates or actual sampling actual measurement, determines mud-rock flow severe γ, unit kN/m3。
(2) spacing L between rib sill is determined by below equation
In formula, the spacing between L rib sill, unit m;
h0Rib sill buried depth, takes " debris flow control works design specification " recommendation, value according to engineering practice
1.5-4.0m;
γ mud-rock flow severe, unit kN/m3, step () determine;
I0Drainage groove longitudinal river slope, is determined by step ().
The inventive method is based on more than 80 debris flow drainage groove simulation experiments, and combines soft base energy dissipating drainage groove rib sill layout
Feature, by simulation experiment result is carried out scale model, data matching etc., thus draws soft base energy dissipation type debris flow drainage groove
The computing formula of rib sill spacing, it is adaptable to the determination of soft base energy dissipation type debris flow drainage groove rib sill spacing in engineering design.
Compared with prior art, the invention has the beneficial effects as follows: considered drainage groove longitudinal river slope, mud-rock flow severe,
The big factor of drainage groove rib sill buried depth three, and combine soft base energy dissipation type debris flow drainage groove rib sill layout feature, pass through lab simulation
Result of the test carries out data matching and obtains soft base energy dissipation type debris flow drainage groove rib sill spacing measure formula, can rationally determine difference
In the case of rib sill spacing, provide scientific basis for disaster prevention engineering design, and this measuring method calculate simplicity, suitable
Answer requirement of engineering.
Accompanying drawing explanation
Fig. 1 is the longitudinal sectional view of soft base energy dissipation type debris flow drainage groove.
Fig. 2 is the schematic top plan view of soft base energy dissipation type debris flow drainage groove.
In figure, label is as follows:
1 rib sill 2 side wall
I0Spacing between drainage groove longitudinal river slope L rib sill
h0Rib sill buried depth
Detailed description of the invention
Below in conjunction with the accompanying drawings, the preferred embodiments of the present invention are further described.
Embodiment one
As shown in Figure 1 and Figure 2.Certain debris flow gully is a Zhigou of big Jinchuan, Upper Reaches of Dadu River master stream right bank, drainage area
For 8.5km2, the long 6.20km of tap drain, basin peak height above sea level 3650m, minimum point height above sea level 2700m, there is mountain height, Gu Shen, slope steep
Lineament, formation and activity for mud-rock flow provide favorable terrain geomorphologic conditions.
For alleviating local mud-stone flow disaster, intend building a soft base energy dissipation type debris flow drainage groove, institute in mud-rock flow tap drain road
State soft base energy dissipation type debris flow drainage groove and include that some bottom lands arranged at a certain distance extend transversely through type rib sill 1 and both sides thereof
Drainage groove side wall 2.Below the spacing between these drainage groove rib sill 1 is calculated, specifically comprise the following steps that
The first step, by large scale topographical map survey calculation, determines drainage groove longitudinal river slope I0It is 0.12;Pass through mud-rock flow
Severe computing formula calculates, and determines that mud-rock flow severe γ is 19kN/m3。
Second step, according to " debris flow control works design specification ", and incorporation engineering is actual, determines rib sill 1 buried depth h0For 2.0m;
The spacing between rib sill 1 is determined by below equation
According to this can this drainage groove design time rib sill 1 between spacing value be 22m.
Embodiment two
As shown in Figure 1 and Figure 2.Certain debris flow gully is a Zhigou of Sun Shui river, Along The Anning River tributary right bank, and tap drain is long
4.20km, drainage area 4.10km2, flow through certain county town, be a debris flow gully the most disastrous.This gully mud-rock flow forms district
Raceway groove is suddenly anxious, two sides side slope extremely unstable, and has landslide activity, often breaks out disastrous mud-rock flow in ditch.According to work of blocking
Journey, then quantities and investment are the biggest, and effect is the most obvious.
For alleviating local mud-stone flow disaster, intend building a soft base energy dissipation type debris flow drainage at mud-rock flow raceway groove accumulation area and lead
Groove, described soft base energy dissipation type debris flow drainage groove include some bottom lands arranged at a certain distance extend transversely through type rib sill 1 and
The drainage groove side wall 2 of both sides.Below the spacing between these drainage groove rib sill 1 is calculated, specifically comprise the following steps that
The first step, is surveyed by field investigation, determines drainage groove longitudinal river slope I0It is 0.15;By reality sampling actual measurement, really
Determining mud-rock flow severe γ is 17kN/m3。
Second step, according to " debris flow control works design specification ", and incorporation engineering is actual, determines rib sill 1 buried depth h0For 3.0m;
The spacing between rib sill 1 is determined by below equation According to this
Can this drainage groove design time rib sill 1 between spacing value be 19m.
Claims (2)
1. a rib sill spacing measuring method for soft base energy dissipation type debris flow drainage groove, described soft base energy dissipation type debris flow drainage groove
Extend transversely through the drainage groove side wall (2) of type rib sill (1) and both sides thereof including some bottom lands arranged at a certain distance, its feature exists
In: the spacing measuring method step between rib sill (1) is as follows:
(1) surveyed by large scale topographical map survey calculation or field investigation, determine drainage groove longitudinal river slope I0;Pass through mud-rock flow
Severe computing formula calculates or actual sampling actual measurement, determines mud-rock flow severe γ, unit kN/m3;
(2) spacing L between rib sill (1) is determined by below equation
In formula, the spacing between L-rib sill (1), unit m;
h0-rib sill (1) buried depth, value 1.5-4.0m;
γ-mud-rock flow severe, unit kN/m3, step () determine;
I0-drainage groove longitudinal river slope, is determined by step ().
The application of the rib sill spacing measuring method of soft base energy dissipation type debris flow drainage groove the most as claimed in claim 1, its feature
It is: be applicable to the determination of soft base energy dissipation type debris flow drainage groove rib sill spacing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510247582.8A CN104831679B (en) | 2015-05-15 | 2015-05-15 | The rib sill spacing measuring method of soft base energy dissipation type debris flow drainage groove and application |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510247582.8A CN104831679B (en) | 2015-05-15 | 2015-05-15 | The rib sill spacing measuring method of soft base energy dissipation type debris flow drainage groove and application |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104831679A CN104831679A (en) | 2015-08-12 |
CN104831679B true CN104831679B (en) | 2016-08-24 |
Family
ID=53809850
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510247582.8A Expired - Fee Related CN104831679B (en) | 2015-05-15 | 2015-05-15 | The rib sill spacing measuring method of soft base energy dissipation type debris flow drainage groove and application |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104831679B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105256768B (en) | 2015-09-09 | 2017-03-22 | 中国科学院水利部成都山地灾害与环境研究所 | Box energy dissipation section designing method of box energy dissipation debris flow discharging and guiding groove |
CN108708353B (en) * | 2018-05-29 | 2020-03-17 | 中国科学院、水利部成都山地灾害与环境研究所 | Design method for rib sill of soft foundation energy dissipation type debris flow drainage groove |
CN110499719B (en) * | 2019-08-28 | 2024-07-02 | 四川建筑职业技术学院 | Debris flow anti-collision rib sill structure and system |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2654683Y (en) * | 2003-11-27 | 2004-11-10 | 陈洪凯 | Mud-rock flow quick draining structure |
CN101886374A (en) * | 2010-07-07 | 2010-11-17 | 中国科学院水利部成都山地灾害与环境研究所 | Groove bottom-reinforced fully lined debris flow drainage groove and construction method thereof |
CN102373692A (en) * | 2011-11-25 | 2012-03-14 | 中国科学院水利部成都山地灾害与环境研究所 | Box body lining type mudslide discharging and guiding groove and application and construction method thereof |
CN102720160A (en) * | 2012-06-15 | 2012-10-10 | 中国科学院水利部成都山地灾害与环境研究所 | All-lining debris flow draining and guiding groove with roughened groove bottom and application thereof |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6904718B2 (en) * | 2003-11-07 | 2005-06-14 | Stephen P. Fox | Leaf guard for gutters |
-
2015
- 2015-05-15 CN CN201510247582.8A patent/CN104831679B/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2654683Y (en) * | 2003-11-27 | 2004-11-10 | 陈洪凯 | Mud-rock flow quick draining structure |
CN101886374A (en) * | 2010-07-07 | 2010-11-17 | 中国科学院水利部成都山地灾害与环境研究所 | Groove bottom-reinforced fully lined debris flow drainage groove and construction method thereof |
CN102373692A (en) * | 2011-11-25 | 2012-03-14 | 中国科学院水利部成都山地灾害与环境研究所 | Box body lining type mudslide discharging and guiding groove and application and construction method thereof |
CN102720160A (en) * | 2012-06-15 | 2012-10-10 | 中国科学院水利部成都山地灾害与环境研究所 | All-lining debris flow draining and guiding groove with roughened groove bottom and application thereof |
Also Published As
Publication number | Publication date |
---|---|
CN104831679A (en) | 2015-08-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Linderfelt et al. | Interaction between shallow groundwater, saline surface water and nutrient discharge in a seasonal estuary: the Swan–Canning system | |
Konrad | Location and timing of river-aquifer exchanges in six tributaries to the Columbia River in the Pacific Northwest of the United States | |
CN104848825B (en) | Method of calculating maximum scour depth of rear ditch bed of debris flow drainage canal transverse sill and applications | |
Tiron et al. | Flow and sediment processes in a cutoff meander of the Danube Delta during episodic flooding | |
Cloutier et al. | Controls of groundwater floodwave propagation in a gravelly floodplain | |
CN105256768A (en) | Box energy dissipation section designing method and application of box energy dissipation debris flow discharging and guiding groove | |
CN104831679B (en) | The rib sill spacing measuring method of soft base energy dissipation type debris flow drainage groove and application | |
CN103321190B (en) | Debris flow silt arrester overflow port overflowing flow measuring and calculating method and application thereof | |
Moyer et al. | Knowledge and understanding of dissolved solids in the Rio Grande–San Acacia, New Mexico, to Fort Quitman, Texas, and plan for future studies and monitoring | |
Ghomeshi | Reservoir sedimentation modelling | |
Gooseff et al. | Solute transport along stream and river networks | |
Xia et al. | Improved criterion for plunge of reservoir turbidity currents | |
Mishra et al. | Sediment TMDL development for the Amite River | |
Ma et al. | Reconstruction of catastrophic outburst floods of the Diexi ancient landslide-dammed lake in the Upper Minjiang River, Eastern Tibetan Plateau | |
Soothar et al. | Estimating seepage losses in different size of earthen watercourses at farm level | |
Esmaeili et al. | Three-dimensional numerical modeling of sediment flushing: Case study of Dashidaira Reservoir, Japan | |
Jia et al. | Integrating hydraulic equivalent sections into a hydraulic geometry study | |
Chen et al. | Application of mathematical model on deposition study of pumped-storage power reservoir | |
Somaratne et al. | Hydrological functions of sinkholes and characteristics of point recharge in groundwater basins | |
Rudiš et al. | Assessment of the deposition of polluted sediments transferred by a catastrophic flood and related changes in groundwater quality | |
Leake et al. | Potential depletion of surface water in the Colorado River and agricultural drains by groundwater pumping in the Parker-Palo Verde-Cibola Area, Arizona and California | |
Milési et al. | 3D Numerical Modeling of a Side-Channel Spillway: Simulation numérique 3D d’un évacuateurde crues à seuil latéral | |
Li et al. | Mud-Sand Flow Hazard Spatial Simulation and Analysis of Tailing Dam-Break under Different Preventive Measures | |
Ryan et al. | Incomplete mixing in a small, urban stream | |
Tabata et al. | Hydraulic analysis of sediment transportation in Yamada weir located in Chikugo river, Japan |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160824 Termination date: 20210515 |