CN104697504B - Method and device for observing layered settlement of high fill earth - Google Patents
Method and device for observing layered settlement of high fill earth Download PDFInfo
- Publication number
- CN104697504B CN104697504B CN201510120150.0A CN201510120150A CN104697504B CN 104697504 B CN104697504 B CN 104697504B CN 201510120150 A CN201510120150 A CN 201510120150A CN 104697504 B CN104697504 B CN 104697504B
- Authority
- CN
- China
- Prior art keywords
- reinforcing bar
- steel pipe
- backfill
- cross
- steel frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01C—MEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
- G01C5/00—Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels
Landscapes
- Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Radar, Positioning & Navigation (AREA)
- Remote Sensing (AREA)
- Road Repair (AREA)
Abstract
The invention specifically provides a method and a device for observing layered settlement of high fill earth, and aims at solving the problem that the height settlement data of the existing high fill earth cannot be observed and so that the potential risk cannot be early found out. The method comprises the steps of a, fixing a cross channel steel frame of which the center is fixed with a reinforcing steel bar body, observing the number and record; b, backfilling and rolling by layers, and recording the settlement value; c, continuously connecting when the backfilled earth reaches the top end of the reinforcing steel bar body; d, arranging the cross channel steel frame I when backfilling to reach the height of a second observing point, wherein a steel pipe body is fixed in the center of the cross channel steel frame I; recording the observing number; e, continuously backfilling rolling by layering, and recording the settlement value of each observing point; f, continuously connecting the steel pipe body when the backfilled earth reaches the top end of the steel pipe body; g, repeating steps from d to f when the earth is backfilled to reach the height of a third observing point until the backfilling and rolling are done. With the adoption of the method and the device, the layered observing of a plurality of observing points in vertical direction during backfilling can be achieved.
Description
Technical field
The present invention relates to construction settlement observation technology, specially a kind of high roadbed soil body layered settlement observation method and
Device.
Background technology
Architectural engineering high roadbed place would generally occur larger sedimentation, and generally existing infall process is longer and uneven
The problems such as sedimentation, the safety and stability of various engineering structures is affected larger, therefore, sedimentation to engineering structure foundation soil body, especially
It is that delaminating deposition feature is monitored having very important significance.
The method monitoring foundation soil body delaminating deposition at present, is after the completion of the backfill of high roadbed place, at the shallower place of ground
Setting observation station, is only capable of observing the settling data on backfill groundwork top the settlement number it is impossible to height each in backfilling process
According to being observed, and then the compaction rate of the high roadbed soil body cannot be ensured, stability is poor, there is potential safety hazard.
Content of the invention
The present invention cannot be observed to its each height settling data leading to presence to solve the existing high roadbed soil body
A kind of problem that potential safety hazard can not find in advance, there is provided high roadbed soil body layered settlement observation method and device.
The present invention adopts the following technical scheme that realization: high roadbed soil body layered settlement observation method, is walked using following
Rapid: when first step observation station being installed at a, the initial absolute altitude of backfill, interim fixed cross U-steel frame, the center of cross U-steel frame is fixed
There is the reinforcing bar body of vertical placement, with reference to chi observed reading and recorded with the external world by reinforcing bar body top;B, it is layered back
Fill out and roll, often backfill one layer, all observed by reinforcing bar bodies top, the settling amount of record first step observation station;C, work as backfill
Floor height close to reinforcing bar body top when, in piece reinforcing bar body of reinforcing bar body top continued access, make the reinforcing bar body top at top
It is always positioned above back fill course;When d, backfill reach the height that need to install second step observation station, placement cross U-steel frame i, ten
The center of word U-steel frame i is fixed with the steel pipe body being enclosed within reinforcing bar body, the observed reading on record steel pipe body top;E, continue
Continuous back-filling in layers rolls, and is observed by the steel pipe body top at reinforcing bar body top and top, records each observation station
Settling amount;F, when the floor height of backfill is close to steel pipe body top, in piece steel pipe body of steel pipe body top continued access, make top
The steel pipe body top in portion is always positioned above back fill course;When g, backfill reach the height that need to install the 3rd step observation station, press
Step d-f repeatable operation rolls and completes to backfill, in backfilling process, the reinforcing bar body top at top and the steel pipe of its outside top
Body top is in step condition all the time.
During operation, determine the number of settlement observation point according to the area of plane of embankment, determine that sedimentation is seen according to backfill thickness
The step number of measuring point, can obtain the data of backfilling process and layered settlement observation using the method, and can also continue in the completed
Tracking observation.
High roadbed soil body layered settlement observation method device, including the cross channel-section steel being arranged at the initial absolute altitude of backfill
Frame, the center of cross U-steel frame is fixed with the reinforcing bar being vertically formed by connecting by some reinforcing bar bodies, is provided with some outside reinforcing bar
The steel pipe of mutual socket, and every steel pipe is all vertically to be formed by connecting by some steel pipe bodies, steel pipe bottom from inside to outside according to
Secondary be fixed with the cross U-steel frame i arranging from down to up, and all cross U-steel frame i are respectively positioned on above cross U-steel frame.
The process step of the invention rationally reliable it is achieved that in backfilling process vertical multiple observation stations observation, and
And tracking observation can be continued in the completed, it is effectively guaranteed the stability of the high roadbed soil body, prevented potential safety hazard, simultaneously
There is process is simple, easy to operate and low cost.
Brief description
Fig. 1 is the structural representation of the present invention.
In figure: 1- cross U-steel frame, 2- reinforcing bar body, 3- steel pipe body, 4- cross U-steel frame i, 5- straight screw sleeve.
Specific embodiment
High roadbed soil body layered settlement observation method, using following steps: install the first step at a, the initial absolute altitude of backfill and see
During measuring point, interim fixed cross U-steel frame 1, the center of cross U-steel frame 1 is fixed with the reinforcing bar body 2 of vertical placement, by steel
Muscle body 2 top and is recorded with reference to chi observed reading with the external world;B, carry out back-filling in layers and roll, often backfill one layer, all by steel
Muscle body 2 top is observed, the settling amount of record first step observation station;C, when the floor height of backfill is close to reinforcing bar body 2 top,
In reinforcing bar body piece reinforcing bar body 2 of 2 top continued access, reinforcing bar body 2 top at top is made to be always positioned above back fill course;d、
When backfill reaches the height that need to install second step observation station, place cross U-steel frame i4, the center of cross U-steel frame i4 is fixed with
It is enclosed within the steel pipe body 3 on reinforcing bar body 2, the observed reading on record steel pipe body 3 top;E, continuation back-filling in layers roll, and lead to
Cross reinforcing bar body 2 top and steel pipe body 3 top at top to be observed, record the settling amount of each observation station;F, work as backfill
Soil floor height close to steel pipe body 3 top when, in steel pipe body piece steel pipe body 3 of 3 top continued access, make the steel pipe body at top
3 tops are always positioned above back fill course;When g, backfill reach the height that need to install the 3rd step observation station, by step d-f repeatedly
Operate to roll to backfill and complete, in backfilling process, reinforcing bar body 2 top at top and steel pipe body 3 top of its outside top
All the time it is in step condition.
High roadbed soil body layered settlement observation method device, including the cross U-steel frame being arranged at the initial absolute altitude of backfill
1, the center of cross U-steel frame 1 is fixed with the reinforcing bar being vertically formed by connecting by some reinforcing bar bodies 2, is provided with some outside reinforcing bar
The steel pipe of mutual socket, and every steel pipe is all vertically to be formed by connecting by some steel pipe bodies 3, steel pipe bottom from inside to outside according to
Secondary be fixed with the cross U-steel frame i4 arranging from down to up, and all cross U-steel frame i4 are respectively positioned on above cross U-steel frame 1.
In specific implementation process, the top that should keep top rebars body 2 during backfill is higher than backfill face more than 300mm, with
Convenient connection;The discrepancy in elevation of adjacent two step observation stations should be greater than 200mm;When all observation station installations, when reaching designed elevation,
For convenience of protecting and observing, the reinforcing bar body 2 at top need to be adjusted to 100mm with the steel pipe body 3 top discrepancy in elevation;Adjacent reinforcing bar is originally
Connected by straight screw sleeve 5 between body 2.
Claims (2)
1. a kind of high roadbed soil body layered settlement observation method it is characterised in that: adopt at following steps: a, the initial absolute altitude of backfill
When first step observation station is installed, interim fixed cross U-steel frame (1), the center of cross U-steel frame (1) is fixed with vertical placement
Reinforcing bar body (2), with reference to chi observed reading and is recorded with the external world by reinforcing bar body (2) top;B, carry out back-filling in layers and roll,
Often backfill one layer, all observed by reinforcing bar body (2) top, the settling amount of record first step observation station;C, when the layer of backfill
High close to reinforcing bar body (2) top when, in piece reinforcing bar body (2) of reinforcing bar body (2) top continued access, make the reinforcing bar body at top
(2) top is always positioned above back fill course;When d, backfill reach the height that need to install second step observation station, place cross channel-section steel
Frame i(4), cross U-steel frame i(4) center be fixed with the steel pipe body (3) being enclosed within reinforcing bar body (2), record steel pipe body
(3) observed reading on top;E, continuation back-filling in layers roll, by steel pipe body (3) top at reinforcing bar body (2) top and top
End is observed, and records the settling amount of each observation station;F, when the floor height of backfill is close to steel pipe body (3) top, in steel
Piece steel pipe body (3) of tube body (3) top continued access, makes steel pipe body (3) top at top be always positioned above back fill course;
When g, backfill reach the height that need to install the 3rd step observation station, roll to backfill by step d-f repeatable operation and complete, backfilling process
In, reinforcing bar body (2) top at top and steel pipe body (3) top of its outside top are in step condition all the time.
2. the high roadbed soil body layered settlement observation method device described in a kind of claim 1 it is characterised in that: include setting
Cross U-steel frame (1) at the initial absolute altitude of backfill, the center of cross U-steel frame (1) is fixed with is erected by some reinforcing bar bodies (2)
To the reinforcing bar being formed by connecting, outside reinforcing bar, it is provided with the steel pipe of some mutual sockets, and every steel pipe is all by some steel pipes originally
Body (3) is vertically formed by connecting, and steel pipe bottom from inside to outside is fixed with the cross U-steel frame i(4 arranging from down to up successively), and
All cross U-steel frame i(4) it is respectively positioned on above cross U-steel frame (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510120150.0A CN104697504B (en) | 2015-03-19 | 2015-03-19 | Method and device for observing layered settlement of high fill earth |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510120150.0A CN104697504B (en) | 2015-03-19 | 2015-03-19 | Method and device for observing layered settlement of high fill earth |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104697504A CN104697504A (en) | 2015-06-10 |
CN104697504B true CN104697504B (en) | 2017-02-01 |
Family
ID=53344875
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510120150.0A Active CN104697504B (en) | 2015-03-19 | 2015-03-19 | Method and device for observing layered settlement of high fill earth |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104697504B (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105424910B (en) * | 2015-12-11 | 2017-05-03 | 天津城建大学 | Device for measuring layered settlement of soil mass |
CN108225261B (en) * | 2017-12-13 | 2020-04-21 | 山东大学 | Pile top and pile end settlement simultaneous observation device and method for pile foundation model test |
CN109579658B (en) * | 2019-01-25 | 2024-05-24 | 国网安徽省电力有限公司建设分公司 | Device and method for monitoring layered settlement of high-fill soil body |
CN110029648A (en) * | 2019-03-26 | 2019-07-19 | 昆明理工大学 | A kind of deep settlement measurement device and application method for deep Backfill Foundation |
CN110595414A (en) * | 2019-09-27 | 2019-12-20 | 徐州中国矿大岩土工程新技术发展有限公司 | Rock-soil body layered monitoring mark and construction method |
CN112556640A (en) * | 2020-11-27 | 2021-03-26 | 杨锡武 | Testing arrangement that high fill road bed or earth and rockfill dam layered settlement |
CN114134763A (en) * | 2021-11-30 | 2022-03-04 | 中铁第四勘察设计院集团有限公司 | Short-circuit foundation structure of embankment and construction method thereof |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0344412A1 (en) * | 1988-05-28 | 1989-12-06 | Schmidt, Paul | Process and device for the continuous measuring of the relative height of a long object driven into the earth |
CN1570291A (en) * | 2004-04-23 | 2005-01-26 | 贵阳铝镁设计研究院 | Method for making foundation piles in high embankment region |
CN1673694A (en) * | 2005-04-25 | 2005-09-28 | 湖南大学 | Earthwork filling body settlement observation instrument |
CN202403703U (en) * | 2012-01-10 | 2012-08-29 | 中国建筑第八工程局有限公司 | Settlement observation mark |
CN202494442U (en) * | 2012-03-27 | 2012-10-17 | 上海市电力公司 | Stratum layering and settlement measuring device |
CN103994753A (en) * | 2014-06-13 | 2014-08-20 | 太原理工大学 | Layered settlement device and layered settlement measuring method for loess filler high fill embankment |
-
2015
- 2015-03-19 CN CN201510120150.0A patent/CN104697504B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0344412A1 (en) * | 1988-05-28 | 1989-12-06 | Schmidt, Paul | Process and device for the continuous measuring of the relative height of a long object driven into the earth |
CN1570291A (en) * | 2004-04-23 | 2005-01-26 | 贵阳铝镁设计研究院 | Method for making foundation piles in high embankment region |
CN1673694A (en) * | 2005-04-25 | 2005-09-28 | 湖南大学 | Earthwork filling body settlement observation instrument |
CN202403703U (en) * | 2012-01-10 | 2012-08-29 | 中国建筑第八工程局有限公司 | Settlement observation mark |
CN202494442U (en) * | 2012-03-27 | 2012-10-17 | 上海市电力公司 | Stratum layering and settlement measuring device |
CN103994753A (en) * | 2014-06-13 | 2014-08-20 | 太原理工大学 | Layered settlement device and layered settlement measuring method for loess filler high fill embankment |
Also Published As
Publication number | Publication date |
---|---|
CN104697504A (en) | 2015-06-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104697504B (en) | Method and device for observing layered settlement of high fill earth | |
CN202433536U (en) | Physical model testing system for tunnel-penetrated ground crack zone | |
CN104963705B (en) | A kind of underground space tunneling construction method | |
CN106066920A (en) | The overlapping tunnel shield-tunneling construction numerical analysis method to underpining Influence of Pile Foundation up and down | |
CN204257101U (en) | A kind of tunnel teaching experiment model | |
Yang et al. | Research of jacking force of densely arranged pipe jacks process in pipe-roof pre-construction method | |
CN103115821B (en) | The in-situ test system of lane side obturation load-carrying properties and method of testing thereof | |
CN113863330B (en) | Ultra-deep foundation pit narrow fertilizer groove concrete backfill structure and construction method | |
CN113339064B (en) | Multidimensional active control method for regulating and controlling tunnel vector deformation through flexible body expansion | |
CN103971585B (en) | The simulating test device of gob-side entry retaining anchoring pack wall load-carrying properties and method of testing | |
CN101967832B (en) | Method for treating bottom structure of building in substation | |
CN202814388U (en) | Device for tunnel pipe shed support deformation testing | |
CN204439062U (en) | High roadbed soil body layered settlement observation device | |
Ran et al. | Long-term monitoring and safety evaluation of a metro station during deep excavation | |
CN209841546U (en) | Pipe jacking experiment box | |
CN108930323B (en) | Pipe jacking construction method | |
CN204401485U (en) | The construction structure of high roadbed draining Steel Corrugated Pipe Culvert | |
CN110990929A (en) | Simple calculation method for radial maximum displacement of diaphragm wall in excavation stage | |
CN109187203B (en) | In-situ testing device and method for deep rock stress fidelity | |
CN115450267B (en) | Relay installation and burying structure and method for earth-rock dam settling tube | |
Wang et al. | Analysis of the influence of geometrical parameters of circular steel pipe with flange plate on the jacking force | |
CN204283440U (en) | Shallow-depth-excavation tunnel supporting status monitoring structure | |
CN210919057U (en) | Shield excavation and soil body settlement monitoring simulation test platform | |
CN110210145B (en) | Single pile settlement calculation method for grouting filling pile after squeezing and expanding support plate | |
CN203720032U (en) | Particle flow displacement regulation and uniform distribution load test device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |