CN104695416A - 路基强夯加固效果评价方法 - Google Patents

路基强夯加固效果评价方法 Download PDF

Info

Publication number
CN104695416A
CN104695416A CN201510105289.8A CN201510105289A CN104695416A CN 104695416 A CN104695416 A CN 104695416A CN 201510105289 A CN201510105289 A CN 201510105289A CN 104695416 A CN104695416 A CN 104695416A
Authority
CN
China
Prior art keywords
roadbed
point position
evaluation method
effect evaluation
dynamic modulus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510105289.8A
Other languages
English (en)
Other versions
CN104695416B (zh
Inventor
郑长安
姜华
陈宇亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Communications Research Institute Co ltd
Hunan Transportation And Water Conservancy Construction Group Co ltd
Original Assignee
HUNAN COMMUNICATIONS RESEARCH INSTITUTE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN COMMUNICATIONS RESEARCH INSTITUTE filed Critical HUNAN COMMUNICATIONS RESEARCH INSTITUTE
Priority to CN201510105289.8A priority Critical patent/CN104695416B/zh
Publication of CN104695416A publication Critical patent/CN104695416A/zh
Application granted granted Critical
Publication of CN104695416B publication Critical patent/CN104695416B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/046Improving by compacting by tamping or vibrating, e.g. with auxiliary watering of the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • E02D1/08Investigation of foundation soil in situ after finishing the foundation structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Analytical Chemistry (AREA)
  • Chemical & Material Sciences (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

本发明提供了一种路基强夯加固效果评价方法,包括以下步骤:(S1)整平测试点位,(S2)测定测试点位的路基动态模量EPi,(S3)强夯,(S4)整平强夯点位,测定强夯点位的路基动态模量EPi+1,以及(S5)计算动态模量比N=EPi+1/EPi,其中,若N≤1.05,则强夯工作结束;若N>1.05,重复步骤(S3)、(S4)、(S5),直至N≤1.05。本发明的目的在于提供一种应用简便、效率较高、费用较低的路基强夯加固效果评价方法。

Description

路基强夯加固效果评价方法
技术领域
本发明涉及公路路基、铁路路基建设领域,更具体地,涉及一种路基强夯加固效果评价方法。
背景技术
强夯法具有冲击力大、加固效果显著、施工方便快捷等特点,在路基处治中得到了广泛的应用。长期以来,科研人员和工程技术人员对强夯加固路基效果进行了很多研究,取得了一系列的研究成果。
目前,评价路基强夯加固效果主要采用以下试验方法:载荷板试验、动力触探试验和面波试验(瑞利波法)。采用载荷板试验可靠性高,但时间长、检测工程量大、成本高;而动力触探试验测试点间距过大时,容易漏测路基较薄弱部位,且受填料和路基性能影响大,特别土石混填路基和填石路基强夯处理后表层相当致密,不容易进尺,深层遇到未击碎的块石时,也会遭遇进尺困难问题,只有采用重型或超重型动力触探才具有可行性。瑞利波法作为一种快速无损检测技术,具有成本低、效率高、检测点可根据需要随意调节,检测结果直观易懂和可获取总貌等优点,作为大面积广泛检测的手段近年来得到了较为广泛的应用,但该方法需要建立波速和检测指标之间的回归关系,由于路基填料多样,变异性大,回归方程的代表性往往存在一定问题。
发明内容
针对相关技术中存在的问题,本发明的目的在于提供一种应用简便、效率较高、费用较低的路基强夯加固效果评价方法。
为实现上述目的,本发明提供了一种路基强夯加固效果评价方法,包括以下步骤:
(S1)整平测试点位,
(S2)测定测试点位的路基动态模量EPi
(S3)强夯,
(S4)整平强夯点位,测定强夯点位的路基动态模量EPi+1,以及
(S5)计算动态模量比N=EPi+1/EPi,其中,若N≤1.05,则强夯工作结束;若N>1.05,重复步骤(S3)、(S4)、(S5),直至N≤1.05。
根据本发明,采用PFWD测定测试点位的路基动态模量。
根据本发明,在采用PFWD测定测试点位的路基动态模量的步骤中还包括如下子步骤:
(S201)将10kg的落锤提升至固定高度,然后释放使得落锤自由下落,
(S202)使得落锤冲击承载板产生冲击荷载,在冲击荷载作用下,使得承载板产生竖向位移,以及
(S203)通过压力传感器和位移传感器分别记录冲击荷载和竖向位移,并根据冲击荷载和竖向位移的峰值确定路基动态模量。
根据本发明,路基包括地基、路堤、路堑或半填半挖路基。
根据本发明,路基的填料类型包括可以作为路基填料的土质。
根据本发明,路基填料包括黏性土、砂性土、砂、碎石土、碎石、红砂岩或红黏土。
本发明的有益技术效果在于:
本发明的路基强夯加固效果的评价方法,即利用动态模量比N来评价路基强夯加固效果,试验仪器采用PFWD,包括如下步骤:(S1)整平测试点位,(S2)测定测试点位的路基动态模量EPi,(S3)强夯,(S4)整平强夯点位,测定强夯点位的路基动态模量EPi+1,以及(S5)计算动态模量比N=EPi+1/EPi,其中,若N≤1.05,则强夯工作结束;若N>1.05,重复步骤(S3)、(S4)、(S5),直至N≤1.05。本发明的强夯加固效果评价方法具有概念清晰,应用简便,效率高、费用低等优点。
附图说明
图1是本发明路基强夯加固效果评价方法的流程图。
具体实施方式
现参照附图对本发明的路基强夯加固效果评价方法进行描述。
如图1所示,是本发明路基强夯加固效果评价方法的流程图,该方法具体包括以下步骤:
(S1)整平测试点位,
(S2)测定测试点位的路基动态模量EPi
(S3)强夯,
(S4)整平强夯点位,测定强夯点位的路基动态模量EPi+1,以及
(S5)计算动态模量比N=EPi+1/EPi,其中,若N≤1.05,则强夯工作结束;若N>1.05,重复步骤(3)、(4)、(5),直至N≤1.05。
具体地,在优选的实施例中,可以采用便携式落锤弯沉仪(PFWD)测定测试点位的路基动态模量。
当采用PFWD进行测定测试点位的路基动态模量时,本发明与其他强夯加固效果评价方法相比,具有主要以下优点:
1.测试仪器携带方便。标准配置的PFWD只有17kg重,1个人可很自由地携带,配上专用小拖车携带则更为方便。只要测试人员能达到施工现场,都可以携带PFWD进入现场测试。所以PFWD不受测试场地和运输的影响;同时,在长途运输时,将PFWD拆卸后可放入40cm×60cm的行李箱中,适当加以塑料泡沫保护就可以随身携带。
2.测试时无需专用动力电源。PFWD压力传感器和位移传感器的工作电源为直流电源,可采用干电池或计算机串口电源。同时,PFWD的落锤只有10kg,其提升和释放均由人工操作完成。另外,由于PFWD轻便,现场运输可采用手提或小拖车,非常方便。
3.测试速度快。将PFWD置于平整的测点,人工抬起落锤后释放即可进行测试,1个测点砸6锤,一般情况下1分钟以内即可完成。
4.操作简单。PFWD的数据采用双向传输,即压力传感器和位移传感器的测试数据可传输到笔记本电脑,笔记本电脑可以发出命令控制PFWD。所以,每次测试时,PFWD可由笔记本电脑控制,也可以由PFWD上的控制面板进行控制。因此,现场测试时,操作非常方便,所有测试工作可以由一个人完成。
5.测试结果可靠。PFWD的压力传感器和位移传感器都是采用高精度动态测试传感器,其中压力传感器的精度为0.1kN,频率为0~400Hz,位移传感器的精度为1μm,频率为0.2~300Hz。其精度和频率都满足冲击荷载测试的要求,相应的测试记过稳定可靠,重复性好。
具体来说,在采用PFWD测定测试点位的路基动态模量的步骤中还可以包括如下子步骤:
(S201)将10kg的落锤提升至固定高度,然后释放使得落锤自由下落,
(S202)使得落锤冲击承载板产生冲击荷载,在冲击荷载作用下,使得承载板产生竖向位移,以及
(S203)通过压力传感器和位移传感器分别记录冲击荷载和竖向位移,并根据冲击荷载和竖向位移的峰值确定路基动态模量。
进一步在可选的实施例中,路基可以包括地基、路堤、路堑或半填半挖路基。路基的填料类型包括可以作为路基填料的土质。在优选的实施例中,路基填料可以包括黏性土、砂性土、砂、碎石土、碎石、红砂岩或红黏土。当然应当理解,本发明路基、路基填料和填料类型均可以根据具体使用情况而定,本发明不局限于此。
综上所述,本发明的路基强夯加固效果的评价方法,即利用动态模量比N来评价路基强夯加固效果,试验仪器采用PFWD,包括如下步骤:(S1)整平测试点位,(S2)测定测试点位的路基动态模量EPi,(S3)强夯,(S4)整平强夯点位,测定强夯点位的路基动态模量EPi+1,以及(S5)计算动态模量比N=EPi+1/EPi,其中,若N≤1.05,则强夯工作结束;若N>1.05,重复步骤(S3)、(S4)、(S5),直至N≤1.05。本发明的强夯加固效果评价方法具有概念清晰,应用简便,效率高、费用低等优点。
以上所述仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。

Claims (6)

1.一种路基强夯加固效果评价方法,其特征在于,包括以下步骤:
(S1)整平测试点位,
(S2)测定所述测试点位的路基动态模量EPi
(S3)强夯,
(S4)整平强夯点位,测定所述强夯点位的路基动态模量EPi+1,以及
(S5)计算动态模量比N=EPi+1/EPi,其中,若N≤1.05,则强夯工作结束;若N>1.05,重复步骤(S3)、(S4)、(S5),直至N≤1.05。
2.根据权利要求1所述的路基强夯加固效果评价方法,其特征在于,采用PFWD测定所述测试点位的所述路基动态模量。
3.根据权利要求2所述的路基强夯加固效果评价方法,其特征在于,在采用PFWD测定所述测试点位的所述路基动态模量的步骤中还包括如下子步骤:
(S201)将10kg的落锤提升至固定高度,然后释放使得所述落锤自由下落,
(S202)使得所述落锤冲击承载板产生冲击荷载,在所述冲击荷载作用下,使得所述承载板产生竖向位移,以及
(S203)通过压力传感器和位移传感器分别记录所述冲击荷载和所述竖向位移,并根据所述冲击荷载和所述竖向位移的峰值确定所述路基动态模量。
4.根据权利要求1所述的路基强夯加固效果评价方法,其特征在于,所述路基包括地基、路堤、路堑或半填半挖路基。
5.根据权利要求1所述的路基强夯加固效果评价方法,其特征在于,所述路基的填料类型包括可以作为路基填料的土质。
6.根据权利要求5所述的路基强夯加固效果评价方法,其特征在于,所述路基填料包括黏性土、砂性土、砂、碎石土、碎石、红砂岩或红黏土。
CN201510105289.8A 2015-03-11 2015-03-11 路基强夯加固效果评价方法 Expired - Fee Related CN104695416B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510105289.8A CN104695416B (zh) 2015-03-11 2015-03-11 路基强夯加固效果评价方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510105289.8A CN104695416B (zh) 2015-03-11 2015-03-11 路基强夯加固效果评价方法

Publications (2)

Publication Number Publication Date
CN104695416A true CN104695416A (zh) 2015-06-10
CN104695416B CN104695416B (zh) 2017-09-15

Family

ID=53342932

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510105289.8A Expired - Fee Related CN104695416B (zh) 2015-03-11 2015-03-11 路基强夯加固效果评价方法

Country Status (1)

Country Link
CN (1) CN104695416B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105571959A (zh) * 2015-12-30 2016-05-11 哈尔滨工业大学 道路无机稳定粒料类基层压实质量快速检测与评价方法
CN105628518A (zh) * 2015-12-30 2016-06-01 哈尔滨工业大学 道路无机稳定粒料类基层压实均匀性检测与评价方法
CN107843711A (zh) * 2017-09-27 2018-03-27 上海申元岩土工程有限公司 一种基于冲击加速度的强夯施工效果检测方法
CN111472243A (zh) * 2020-04-22 2020-07-31 重庆交通大学 一种路基路面结构综合动态模量的测试方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4169633B2 (ja) * 2003-05-29 2008-10-22 東亜建設工業株式会社 比抵抗値を用いた砂質地盤の空洞・ゆるみ領域の評価方法
CN101597910A (zh) * 2008-08-29 2009-12-09 上海申元岩土工程有限公司 可用于检测碎石、块石等填土地基加固效果的方法
JP2013076220A (ja) * 2011-09-29 2013-04-25 Taisei Corp 土質試験装置、土質試験方法および締固め密度管理方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4169633B2 (ja) * 2003-05-29 2008-10-22 東亜建設工業株式会社 比抵抗値を用いた砂質地盤の空洞・ゆるみ領域の評価方法
CN101597910A (zh) * 2008-08-29 2009-12-09 上海申元岩土工程有限公司 可用于检测碎石、块石等填土地基加固效果的方法
JP2013076220A (ja) * 2011-09-29 2013-04-25 Taisei Corp 土質試験装置、土質試験方法および締固め密度管理方法

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
徐平等: "PFWD在路基强度评价中的应用", 《路基工程》 *
段丹军等: "应用便携式落锤弯沉仪测定路基回弹模量", 《交通运输工程学报》 *
袁剑波等: "红粘土填方路基强夯加固效果检测与分析", 《中外公路》 *
陈宇亮等: "赣中红砂岩填料路基动态模量现场影响因素研究", 《公路交通科技》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105571959A (zh) * 2015-12-30 2016-05-11 哈尔滨工业大学 道路无机稳定粒料类基层压实质量快速检测与评价方法
CN105628518A (zh) * 2015-12-30 2016-06-01 哈尔滨工业大学 道路无机稳定粒料类基层压实均匀性检测与评价方法
CN107843711A (zh) * 2017-09-27 2018-03-27 上海申元岩土工程有限公司 一种基于冲击加速度的强夯施工效果检测方法
CN111472243A (zh) * 2020-04-22 2020-07-31 重庆交通大学 一种路基路面结构综合动态模量的测试方法

Also Published As

Publication number Publication date
CN104695416B (zh) 2017-09-15

Similar Documents

Publication Publication Date Title
Hsiung et al. Three-dimensional effects of a deep excavation on wall deflections in loose to medium dense sands
Lisjak et al. The excavation of a circular tunnel in a bedded argillaceous rock (Opalinus Clay): short-term rock mass response and FDEM numerical analysis
Portelinha et al. Performance of nonwoven geotextile-reinforced walls under wetting conditions: laboratory and field investigations
CN100445516C (zh) 基于探地雷达的盾构隧道沉降控制方法
CN108717082A (zh) 一种基于集成声波检测技术的土石料压实质量连续评估方法
CN107831217A (zh) 一种填筑连续压实声波检测系统与方法
Cui et al. In situ tests simulating traffic-load-induced settlement of alluvial silt subsoil
Nazzal Field evaluation of in-situ test technology for Q (C)/Q (A) during construction of pavement layers and embankments
CN104695416A (zh) 路基强夯加固效果评价方法
Karlovsek et al. Investigation of voids and cavities in bored tunnels using GPR
Zhang et al. Study on slope stability due to the influence of excavation of the high-speed rail tunnel
Kim et al. Numerical simulation of impact rollers for estimating the influence depth of soil compaction
Nguyen et al. A new lightweight dynamic cone penetrometer for laboratory and field applications
Su Laboratory pull-out testing study on soil nails in compacted completely decomposed granite fill
Falkner et al. Rapid impact compaction for middle-deep improvement of the ground–numerical and experimental investigation
Kim et al. Use of dynamic cone penetration and clegg hammer tests for quality control of roadway compaction and construction
Yu et al. Analysis of application situation of continuous compaction control (CCC)
Chai et al. In situ assessment of pavement subgrade using Falling Weight Deflectometer
Tehrani An investigation of continuous compaction control systems
Lyman et al. Estimating System Stiffness of Soil Nailing Wall for Deep Excavation in Clay
Kianirad Development and testing of a portable in-situ near-surface soil characterization system
Asem et al. On the Use and Interpretation of In Situ Load Tests in Weak Rock Masses
Dandapat Application of Schmidt rebound number for estimating coal strength
CN204156900U (zh) 数位动能密实系统
Zhengjun et al. Review of Nondestructive Testing Technology for Compaction Quality of Soil

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 410015 472, Section 3, Furong Middle Road, Tianxin District, Changsha City, Hunan Province

Patentee after: HUNAN COMMUNICATIONS RESEARCH INSTITUTE CO.,LTD.

Address before: 410015 472, Section 3, Furong Middle Road, Tianxin District, Changsha City, Hunan Province

Patentee before: Hunan Communications Research Institute

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190107

Address after: 410005 No. 239 Shaoshan South Road, Yuhua District, Changsha City, Hunan Province

Patentee after: Hunan Transportation and Water Conservancy Construction Group Co.,Ltd.

Address before: 410015 472, Section 3, Furong Middle Road, Tianxin District, Changsha City, Hunan Province

Patentee before: HUNAN COMMUNICATIONS RESEARCH INSTITUTE CO.,LTD.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170915