CN104695331A - Construction building hoist - Google Patents

Construction building hoist Download PDF

Info

Publication number
CN104695331A
CN104695331A CN201410037915.XA CN201410037915A CN104695331A CN 104695331 A CN104695331 A CN 104695331A CN 201410037915 A CN201410037915 A CN 201410037915A CN 104695331 A CN104695331 A CN 104695331A
Authority
CN
China
Prior art keywords
driving wheel
building construction
manned platform
construction hoist
support
Prior art date
Application number
CN201410037915.XA
Other languages
Chinese (zh)
Other versions
CN104695331B (en
Inventor
朱革新
刘正权
陈天贵
Original Assignee
陈天贵
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority to CN201310663494 priority Critical
Priority to CN2013106634947 priority
Application filed by 陈天贵 filed Critical 陈天贵
Priority to CN201410037915.XA priority patent/CN104695331B/en
Publication of CN104695331A publication Critical patent/CN104695331A/en
Application granted granted Critical
Publication of CN104695331B publication Critical patent/CN104695331B/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The invention discloses a construction building hoist. The construction building hoist is formed by building an elevating platform surrounded by a plurality of small platforms end to end around a columnar building, wherein a plurality of radial sliding chutes are formed below the elevating platform; supports capable of radially sliding in the sliding chutes are mounted in the sliding chutes; driving wheels and driven wheels are mounted on the supports; the driving wheels between the adjacent supports are in transmission through a transmission mechanism and driven by a motor arranged below in the evaluating platform through a transmission gear; the motor comprises a brake device. The building hoist is simple in structure, high in safety performance, convenient to operate and maintain, capable of greatly improving the working efficiency, and low in cost, can be fit for various terrains, and uses the clean energy and the electric energy, so that the environment protection performance is good.

Description

A kind of building construction hoist
Technical field
The present invention relates to building machinery, especially a kind of surface-treated hoist for column buildings such as overhead bridge pier, high ferro bridge piers.
Background technology
At present, when processing the surface of the column buildings such as overhead bridge pier, high ferro bridge pier, all adopting proping, employing the manned process of mode such as motor crane or rising machine, this mode inefficiency, with high costs and mobility is poor.
Summary of the invention
The object of this invention is to provide a kind of surface-treated hoist for column buildings such as overhead bridge pier, high ferro bridge piers.
Technical scheme of the present invention: a kind of building construction hoist, it is characterized in that, build around column building one by multiple chain-wales head and the tail overlap joint around shape manned platform, there is below manned platform multiple radial groove and be arranged on the support that can radially slide in chute, support is provided with driving wheel and driven pulley, transmission is carried out by transmission mechanism between driving wheel on adjacent stent, be arranged on motor below manned platform by actuator drives driving wheel, motor has brake gear.
As preferably, between the outer end of described support and manned platform outer end, be provided with adjusting screw(rod).
As preferably, between the outer end of described support and manned platform outer end, be provided with compression spring.
As preferably, between two adjacent chain-waless, be provided with tensioning apparatus and water level positioner.
As preferably, described driving wheel external surface has the large rubber layer of friction factor.
As preferably, described manned platform is provided with protective guard.
As preferably, between the driving wheel on described adjacent stent, carry out transmission by cross connection spline housing and middle contiguous block.
Beneficial effect of the present invention: elevator structure of the present invention is simple, and security performance is high, operation, easy to maintenance, can greatly increase work efficiency; With low cost, can various landform be adapted to; Use clean energy resource: use electric energy, good environmental protection.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the invention will be further described.
Fig. 1 is the front view of hoist;
Fig. 2 is the top view of hoist;
Fig. 3 is the schematic diagram that in Fig. 2, partial cross connection spline housing is connected with middle contiguous block.
In figure: 1-adjusting screw(rod), 2-compression spring, 3-support, 4-driven pulley, 5-driving wheel, 6-cross connects spline housing, contiguous block in the middle of 7-, 8-driven sprocket, 9-drive sprocket, 10-motor (reductor), 11-horizontal positioning device, 12-tensioning bearing pin, 13-tensioning screw, 14-tensioning nut, 15-fixed pin shaft, 16-fixed connecting plate, 17-chain, 18-pin-and-hole seat, 19-bridge pier, 20-protective guard, 21-manned platform, 22-bearing.
Detailed description of the invention
As shown in Figure 1, Figure 2 and Figure 3, around pending bridge pier 19, build ring-type manned platform 21 with four pieces of fan-shaped chain-waless, manned platform 21 is arranged protective guard 20.The connecting portion of the fan-shaped chain-wales of every block is provided with pin-and-hole seat 18, first between adjacent pin-and-hole seat 18, with fixed pin shaft 15 and fixed connecting plate 16, two pieces of fan-shaped chain-waless are connected into semicircle shape platform, and then surround bridge pier with two semicircle shape platforms, adopt tensioning screw 13, tensioning nut 14 and tensioning pinned connection between two semicircle shape platforms, rotation tensioning screw 13 and tensioning nut 14 can regulate the internal diameter size of manned platform.For ensureing that four chain-waless of head and the tail connection are on same horizontal plane, are provided with the horizontal positioning device 11 be made up of horizontal bearing pin and horizontal pin-and-hole between adjacent two chain-waless.Have multiple chute and triangular supports 3 below manned platform, support 3 has horizontal arm, the vertical arm parallel with bridge pier and supports oblique arm, and the horizontal arm of support 3 is installed in chute and also can be slided in chute.Vertical arm is provided with driving wheel 5 and driven pulley 4, the external surface of driving wheel 5 has the rubber layer of friction factor.Be provided with motor (reductor) 10 below manned platform, motor 10 has brake gear.Motor (reductor) 10 drives a driving wheel 5 by drive sprocket 9, driven sprocket 8 and driving chain 17, carries out transmission, realize synchronous axial system between adjacent main driving wheel 5 by cross connection spline housing 6 and middle contiguous block 7.Chute outer end is provided with bearing 22, adjusting screw(rod) 1 and compression spring 2 are installed between the outer end of support 3 horizontal arm and bearing 22, adjusting screw(rod) 1 and support 3 horizontal arm outer end can disengage, turn adjusting screw(rod) 1 toward inward turning and can push support 3 to bridge pier, the elastic force of compression spring 2 can keep the driving wheel on support 3 and driven pulley and bridge pier surface to keep in touch in the moment.
During work, the brake gear of motor (reductor) 10 is opened, and is transferred torque on driving wheel 5 by drive sprocket 9, driving chain 17 and driven sprocket 8.Driving wheel 5 need overcome the gravity of less rolling frictional resistance and manned platform 21, just can scroll-up/down, whole manned platform 21 is moved up and down along bridge pier external surface and reaches required height.When not working, motor output shaft is fixed by the brake gear of motor, and driving wheel 5 can not be rolled on bridge pier 19 external surface, and driving wheel 5 makes manned platform 21 rest on arbitrary height with the frictional force of bridge pier 19 external surface.

Claims (7)

1. a building construction hoist, it is characterized in that, build around column building one by multiple chain-wales head and the tail overlap joint around shape manned platform (21), manned platform (21) below has multiple radial groove and is arranged on the support (3) that can radially slide in chute, support (3) is provided with driving wheel (5) and driven pulley (4), transmission is carried out by transmission mechanism between driving wheel (5) on adjacent stent (3), be arranged on the motor (10) of manned platform (21) below by actuator drives driving wheel (5), motor (10) has brake gear.
2. building construction hoist according to claim 1, is characterized in that, is provided with adjusting screw(rod) (1) between the outer end of described support (3) and manned platform (21) outer end.
3. building construction hoist according to claim 2, is characterized in that, is provided with compression spring (2) between the outer end of described support (3) and manned platform (21) outer end.
4. the building construction hoist according to claim 1 or 2 or 3, is characterized in that, is provided with tensioning apparatus and water level positioner between two adjacent chain-waless.
5. the building construction hoist according to claim 1 or 2 or 3, is characterized in that, described driving wheel (5) external surface has the large rubber layer of friction factor.
6. building construction hoist according to claim 1, is characterized in that, described manned platform (21) is provided with protective guard (20).
7. building construction hoist according to claim 1, it is characterized in that, connect spline housing (6) by cross between the driving wheel (5) on described adjacent stent (3) and middle contiguous block (7) carries out transmission.
CN201410037915.XA 2013-12-10 2014-01-20 A kind of building construction hoist CN104695331B (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN201310663494 2013-12-10
CN2013106634947 2013-12-10
CN201410037915.XA CN104695331B (en) 2013-12-10 2014-01-20 A kind of building construction hoist

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410037915.XA CN104695331B (en) 2013-12-10 2014-01-20 A kind of building construction hoist

Publications (2)

Publication Number Publication Date
CN104695331A true CN104695331A (en) 2015-06-10
CN104695331B CN104695331B (en) 2016-09-28

Family

ID=53342847

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410037915.XA CN104695331B (en) 2013-12-10 2014-01-20 A kind of building construction hoist

Country Status (1)

Country Link
CN (1) CN104695331B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107090776A (en) * 2017-05-26 2017-08-25 王燕 A kind of bridge pier climbs machine
CN107386113A (en) * 2017-06-23 2017-11-24 中建市政工程有限公司 Climb certainly safe operation platform and its construction method for pier column pouring construction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0681321A (en) * 1992-08-31 1994-03-22 Maeda Corp Moving device for construction
CN102230313A (en) * 2011-03-14 2011-11-02 中铁五局(集团)有限公司 Bridge thin-wall hollow-pier chain block hoisting operation platform and construction method thereof
CN202164546U (en) * 2011-07-28 2012-03-14 中铁一局集团有限公司 High pier bridge construction platform
CN202401397U (en) * 2011-12-05 2012-08-29 中国建筑第六工程局有限公司 Tool type movable outer frame for constructing pier stud
CN103046473A (en) * 2013-01-15 2013-04-17 中国土木工程集团有限公司 Construction method for constructing double-limb hollow high-pier mould side hydraulic jacking creeping formwork and double-limb hollow high-pier
CN203700966U (en) * 2013-12-10 2014-07-09 陈天贵 Building construction hoist

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0681321A (en) * 1992-08-31 1994-03-22 Maeda Corp Moving device for construction
CN102230313A (en) * 2011-03-14 2011-11-02 中铁五局(集团)有限公司 Bridge thin-wall hollow-pier chain block hoisting operation platform and construction method thereof
CN202164546U (en) * 2011-07-28 2012-03-14 中铁一局集团有限公司 High pier bridge construction platform
CN202401397U (en) * 2011-12-05 2012-08-29 中国建筑第六工程局有限公司 Tool type movable outer frame for constructing pier stud
CN103046473A (en) * 2013-01-15 2013-04-17 中国土木工程集团有限公司 Construction method for constructing double-limb hollow high-pier mould side hydraulic jacking creeping formwork and double-limb hollow high-pier
CN203700966U (en) * 2013-12-10 2014-07-09 陈天贵 Building construction hoist

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107090776A (en) * 2017-05-26 2017-08-25 王燕 A kind of bridge pier climbs machine
CN107386113A (en) * 2017-06-23 2017-11-24 中建市政工程有限公司 Climb certainly safe operation platform and its construction method for pier column pouring construction
CN107386113B (en) * 2017-06-23 2018-12-04 中建市政工程有限公司 Climb certainly safe operation platform and its construction method for pier column pouring construction

Also Published As

Publication number Publication date
CN104695331B (en) 2016-09-28

Similar Documents

Publication Publication Date Title
CN102729239B (en) All-dimensional manipulator
CN103624774A (en) Six-degree-of-freedom series-parallel connection robot
CN204281194U (en) The lifting mechanism that a kind of feed screw nut pair drives
CN202220943U (en) Carrying platform for pipeline repairing equipment
CN103174317B (en) Lifting drive system of parking appliance and lifting cross sliding type parking appliance
CN203921811U (en) Packaged type length is apart from pusher
CN102408061B (en) Wheel turning sling of high speed motor train unit
US8955582B2 (en) Beamless mechanic-reversing long stroke pumping unit
CN206357221U (en) A kind of workshop transfer robot
CN103588067A (en) Spiral safe cordless elevator
CN202099010U (en) Screw lifting mechanism and automatic lifting platform
CN203956471U (en) A kind of petroleum machinery nut changer
CN103806729A (en) External transverse movement system of mechanical parking equipment
CN105059417A (en) Pole climbing robot based on spring telescopic mechanism
WO2012018224A3 (en) Worm gear-type driving unit, and elevator and elevator system using worm gear-type driving unit
CN202296370U (en) Concrete building block carrying and turning device
CN103697133B (en) A kind of lifting device speed reducer
CN201871229U (en) Vertically lifting amusement device capable of rotating
WO2013022352A8 (en) Device for activation of gripping jaws in continuously rotating torque tongs for use under pulling and opening of threaded connections
CN204055185U (en) A kind of heavy vehicle tyre removing machine
CN101966911A (en) Conveying roller way
CN103848248A (en) Lifting grabbing and turning mechanism
CN201778522U (en) The lifting type multi-storied garage driving mechanism
CN201648963U (en) Continuous mobile cable robot creeping device
CN106144928A (en) A kind of durable hoisting device

Legal Events

Date Code Title Description
PB01 Publication
C06 Publication
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
CB03 Change of inventor or designer information

Inventor after: Gao Hongwang

Inventor after: Guo Zigui

Inventor after: Ni Shiyong

Inventor after: Zhu Gexin

Inventor after: Liu Zhengquan

Inventor after: Chen Tiangui

Inventor before: Zhu Gexin

Inventor before: Liu Zhengquan

Inventor before: Chen Tiangui

TA01 Transfer of patent application right

Effective date of registration: 20160505

Address after: 427000 Zhangjiajie City, Hunan province Yongding District Dayong Bridge Office water pit

Applicant after: Zhangjiajie Institute of Aeronautical Engineering

Address before: 411228 Hunan city of Xiangtan province to building up No. 8 Su River Day Avenue 10 floor

Applicant before: Chen Tiangui

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data
GR01 Patent grant
C14 Grant of patent or utility model
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160928

Termination date: 20180120

CF01 Termination of patent right due to non-payment of annual fee