CN104671057A - Major diameter steel bar integral vertical hoisting apparatus in high pier construction - Google Patents

Major diameter steel bar integral vertical hoisting apparatus in high pier construction Download PDF

Info

Publication number
CN104671057A
CN104671057A CN201310607552.4A CN201310607552A CN104671057A CN 104671057 A CN104671057 A CN 104671057A CN 201310607552 A CN201310607552 A CN 201310607552A CN 104671057 A CN104671057 A CN 104671057A
Authority
CN
China
Prior art keywords
section steel
hole plate
high pier
pier construction
vertical lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310607552.4A
Other languages
Chinese (zh)
Inventor
符强
路致远
刘胜利
李新
何瑞刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group No 5 Engineering Co Ltd
Original Assignee
China Gezhouba Group No 5 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group No 5 Engineering Co Ltd filed Critical China Gezhouba Group No 5 Engineering Co Ltd
Priority to CN201310607552.4A priority Critical patent/CN104671057A/en
Publication of CN104671057A publication Critical patent/CN104671057A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means

Abstract

A major diameter steel bar integral vertical hoisting apparatus in high pier construction is characterized in that the contact flange of two section steel clamps arranged in parallel is provided with a plurality of jaw grooves forming interference fit together with steel bars, two ends of the two section steel clamps are respectively provided with a left pin hole plate and a right pin hole plate, a latch bolt traverses through the left pin hole plate and the right pin hole plate to connect the two section steel clamps, and two ends of each of the section steel clamps are respectively provided with a hanger. The section steel clamps with the jaw grooves are arranged, so the major diameter steel bar integral vertical hoisting apparatus in high pier construction can realize one-shot vertical hoisting of a plurality of steel bars, ensures the quality of reinforced bars, and reduces the risk and cost of construction. The apparatus can guarantee the fastness and the safety of hoisting of major diameter steel bars, and greatly improves the installation efficiency of high pier construction steel bars.

Description

The overall vertical lifting device of Large-size rebar in high pier construction
Technical field
The present invention relates to the overall vertical lifting device of Large-size rebar in Large-size rebar vertical lifting field, particularly a kind of high pier construction.
Background technology
In high pier construction, often adopt the above major diameter of diameter 20mm and length at the reinforcing bar of more than 2.5m, because the single weight of this type of reinforcing bar is larger, in addition the high pier construction scope of operation is little, must by mechanical equipment during construction, use steel rope to carry out being wound around single lifting again and complete installation, this hanging method not only operates inconvenience, steel reinforcement abutting joints is installed and is often occurred tilting,, there is greatly potential safety hazard in steel reinforcement abutting joints difficult quality guarantee, and inefficiency.
Summary of the invention
Technical matters to be solved by this invention is to provide the overall vertical lifting device of Large-size rebar in a kind of high pier construction, and can ensure steel reinforcement abutting joints quality and construction safety, improves operating efficiency.
For solving the problems of the technologies described above, the technical solution adopted in the present invention is: the overall vertical lifting device of Large-size rebar in a kind of high pier construction, two section steel fixtures be arranged in parallel, multiple jaw groove forming interference fit with reinforcing bar is provided with on the edge of a wing contacted, left pin-and-hole plate and right pin-and-hole plate is respectively equipped with at the two ends of two section steel fixtures, two section steel fixtures link together through left pin-and-hole plate and right pin-and-hole plate by clevis bolt
Section steel fixture two ends are provided with hanger.
Described section steel fixture adopts I-beam section, and the edge of a wing of I-beam section is oppositely arranged.
Described jaw groove respectively has a semicircle on two section steel fixtures, snaps together formation complete circle.
Described jaw groove is provided with anti-slop serrations.
Described left pin-and-hole plate and right pin-and-hole plate are fixedly arranged on different section steel fixtures respectively, and left pin-and-hole plate and/or right pin-and-hole plate are multi-disc.
Described multiple jaw grooves are uniform along section steel fixture.
The overall vertical lifting device of Large-size rebar in a kind of high pier construction provided by the invention, by the section steel fixture with multiple jaw groove arranged, can a vertical lifting many reinforcing bars, guarantee steel reinforcement abutting joints quality, reduce construction risk and cost.The present invention can ensure quick, the safety of the lifting of Large-size rebar, greatly improves the efficiency of high pier construction reinforcement installation.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the invention will be further described.
Fig. 1 is integral structure schematic front view of the present invention.
Fig. 2 is integral structure schematic top plan view of the present invention.
Fig. 3 is integral structure schematic side view of the present invention.
In figure: section steel fixture 1, jaw groove 2, left pin-and-hole plate 3, right pin-and-hole plate 4, clevis bolt 5, hanger 6, steel rope 7, reinforcing bar 8.
Detailed description of the invention
As in Fig. 1 ~ 3, the overall vertical lifting device of Large-size rebar in a kind of high pier construction, two section steel fixtures be arranged in parallel 1, multiple jaw groove 2 forming interference fit with reinforcing bar 8 is provided with on the edge of a wing contacted, left pin-and-hole plate 3 and right pin-and-hole plate 4 is respectively equipped with at the two ends of two section steel fixtures 1, two section steel fixtures 1 link together through left pin-and-hole plate 3 and right pin-and-hole plate 4 by clevis bolt 5
Section steel fixture 1 two ends are provided with hanger 6.The hanger 6 arranged lifts by crane for connecting steel wire ropes 7.
Preferably, as in Fig. 3, described section steel fixture 1 adopts I-beam section, and the edge of a wing of I-beam section is oppositely arranged.Channel-section steel is adopted also to be feasible.
Optimize, as in Fig. 2, described jaw groove 2 respectively has a semicircle on two section steel fixtures 1, snaps together formation complete circle.Structure thus, is convenient to clamp reinforcing bar 8.
Preferably, described jaw groove 2 is provided with anti-slop serrations.Structure thus, for increasing friction force.
The structure optimized is as in Fig. 3, and described left pin-and-hole plate 3 and right pin-and-hole plate 4 are fixedly arranged on different section steel fixtures 1 respectively, and left pin-and-hole plate 3 and/or right pin-and-hole plate 4 are multi-disc.Structure thus, the section steel fixture 1 being convenient to two to be arranged in parallel is linked together by clevis bolt 5, and is convenient to clamping.
The structure optimized is as in Fig. 2, and described multiple jaw grooves 2 are uniform along section steel fixture 1.Structure thus, is beneficial to and keeps balance when lifting.
As in Fig. 1 ~ 3, in a kind of high pier construction, the method for the overall vertical lifting of Large-size rebar comprises the following steps:
One, the section steel fixture 1 with jaw groove 2 is made: get two i shaped steels, this routine shaped steel is work 10 shaped steel, the jaw groove 2 of the fixing reinforcing bar 8 of reinforcing bar 8 spacing processing is pressed in upper and lower flange plate position, the size of jaw groove 2 and the radius of reinforcing bar 8 smaller, and jaw groove 2 requires that the section steel fixture center line left and right at two is equal.Arrange left pin-and-hole plate 3 at section steel fixture two ends, another root two ends arrange right pin-and-hole plate 4.Respectively arrange one with the hanger 6 of section steel fixture seam symmetry at two section steel fixture 1 diagonal positions, hanger 6, as Heave Here, is connected with steel rope 7.With center line symmetry and arranging of hanger 6, jaw groove 2 requires that the requirement for section steel fixture 1 seam symmetry is the center-of-gravity position heart position wherein in order to section steel fixture 1 during satisfied lifting, ensure vertical lifting.Jaw groove 2 quantity arranges 8 ~ 12 usually.
Two, the left pin-and-hole plate 3 of two section steel fixture 1 one end and right pin-and-hole plate 4 run through by clevis bolt 5 be fixedly connected with, make section steel fixture 1 one-tenth hinge structure.
Three, is alignd in many reinforcing bars 8 one end, be positioned in a root type pucellas fixture 1 jaw groove 2, by another root section steel fixture make-up, the left pin-and-hole plate 3 of the two shaped steel other ends and right pin-and-hole plate 4 bolt pin 5 fixed.Hoisting wirerope 7 to reinforcing bar 8 docking location.
The overall vertical lifting that can be realized Large-size rebar by above step is installed.

Claims (6)

1. the overall vertical lifting device of Large-size rebar in a high pier construction, it is characterized in that: two section steel fixtures be arranged in parallel (1), multiple jaw groove (2) forming interference fit with reinforcing bar (8) is provided with on the edge of a wing contacted, left pin-and-hole plate (3) and right pin-and-hole plate (4) is respectively equipped with at the two ends of two section steel fixtures (1), two section steel fixtures (1) link together through left pin-and-hole plate (3) and right pin-and-hole plate (4) by clevis bolt (5), and section steel fixture (1) two ends are provided with hanger (6).
2. the overall vertical lifting device of Large-size rebar in a kind of high pier construction according to claim 1, is characterized in that: described section steel fixture (1) adopts I-beam section, and the edge of a wing of I-beam section is oppositely arranged.
3. the overall vertical lifting device of Large-size rebar in a kind of high pier construction according to claim 1, is characterized in that: described jaw groove (2) respectively has a semicircle on two section steel fixtures (1), snaps together formation complete circle.
4. the overall vertical lifting device of Large-size rebar in a kind of high pier construction according to claim 3, is characterized in that: described jaw groove (2) is provided with anti-slop serrations.
5. the overall vertical lifting device of Large-size rebar in a kind of high pier construction according to claim 1, it is characterized in that: described left pin-and-hole plate (3) and right pin-and-hole plate (4) are fixedly arranged on different section steel fixtures (1) respectively, and left pin-and-hole plate (3) and/or right pin-and-hole plate (4) are multi-disc.
6. the overall vertical lifting device of Large-size rebar in a kind of high pier construction according to claim 1, is characterized in that: described multiple jaw grooves (2) are uniform along section steel fixture (1).
CN201310607552.4A 2013-11-27 2013-11-27 Major diameter steel bar integral vertical hoisting apparatus in high pier construction Pending CN104671057A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310607552.4A CN104671057A (en) 2013-11-27 2013-11-27 Major diameter steel bar integral vertical hoisting apparatus in high pier construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310607552.4A CN104671057A (en) 2013-11-27 2013-11-27 Major diameter steel bar integral vertical hoisting apparatus in high pier construction

Publications (1)

Publication Number Publication Date
CN104671057A true CN104671057A (en) 2015-06-03

Family

ID=53306731

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310607552.4A Pending CN104671057A (en) 2013-11-27 2013-11-27 Major diameter steel bar integral vertical hoisting apparatus in high pier construction

Country Status (1)

Country Link
CN (1) CN104671057A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109279499A (en) * 2018-11-23 2019-01-29 新乡市豫新起重机械有限公司 It is a kind of to suffer from one's own actions balance hanging beam and crane for the dedicated of long materials lifting
CN113235826A (en) * 2021-05-19 2021-08-10 中建桥梁有限公司 Steel bar wire connection installation positioning method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109279499A (en) * 2018-11-23 2019-01-29 新乡市豫新起重机械有限公司 It is a kind of to suffer from one's own actions balance hanging beam and crane for the dedicated of long materials lifting
CN109279499B (en) * 2018-11-23 2023-08-22 新乡市豫新起重机械有限公司 Special self-balancing hanging beam for long object lifting and crane
CN113235826A (en) * 2021-05-19 2021-08-10 中建桥梁有限公司 Steel bar wire connection installation positioning method

Similar Documents

Publication Publication Date Title
CN202080812U (en) Dedicated sling system for large-scaled reinforcing cage
CN104671057A (en) Major diameter steel bar integral vertical hoisting apparatus in high pier construction
CN202644404U (en) Combined rope clip of suspension bridge
CN102767139A (en) Combined clip of double main cables of suspension bridge
CN102992203A (en) Simple hoisting device for steel structure bridge installation
CN205772932U (en) A kind of dry quenched coke boiler economizer coil installs suspender in place
CN203545431U (en) Device for vertically hoisting whole large-diameter rebar in high pier construction
CN205132903U (en) Steel wire slings
CN201809032U (en) Self-adjusting stay device with combinable hanger
CN202737386U (en) Insulator string fixing traction tool
CN201180056Y (en) Winch lift hook assembly
CN202124427U (en) Hoisting lift cover
CN202730652U (en) Combined type cable clip for two main cables of suspension bridge
CN202558463U (en) Hanging bracket for hoisting U-shaped beam
CN103738852A (en) Weight testing device of crane
CN205590168U (en) Overturning lifting device
CN203159109U (en) Profile steel lifting device
CN102496890B (en) Skid shoe guide rail type cable trailer
CN202989758U (en) Steel wire rope support structure used on horizontal drawing cable bridge
CN202936088U (en) T-shaped beam steel lifting bracket
CN216471715U (en) 150TON multipurpose hanging bar
CN109680611B (en) Cable-carrying crane with automatic alignment pressure-bearing shearing resistance
CN219860092U (en) Pipeline hoisting device
CN104108646A (en) Overhead hoist device
CN216004950U (en) Multipoint hoisting device for I-shaped steel member

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150603