CN104653192B - A kind of civil engineering shield machine - Google Patents

A kind of civil engineering shield machine Download PDF

Info

Publication number
CN104653192B
CN104653192B CN201510042949.2A CN201510042949A CN104653192B CN 104653192 B CN104653192 B CN 104653192B CN 201510042949 A CN201510042949 A CN 201510042949A CN 104653192 B CN104653192 B CN 104653192B
Authority
CN
China
Prior art keywords
support column
tool holder
conveyer
paragraph
shield machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510042949.2A
Other languages
Chinese (zh)
Other versions
CN104653192A (en
Inventor
翟劲松
崔晓燕
孙树炜
安杰
李鹏
武星
李耀
郜珲
翟昱婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Co., Ltd of Architectural Design Research Inst. Henan Prov.
Original Assignee
Co Ltd Of Architectural Design Research Inst Henan Prov
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Co Ltd Of Architectural Design Research Inst Henan Prov filed Critical Co Ltd Of Architectural Design Research Inst Henan Prov
Priority to CN201510042949.2A priority Critical patent/CN104653192B/en
Publication of CN104653192A publication Critical patent/CN104653192A/en
Application granted granted Critical
Publication of CN104653192B publication Critical patent/CN104653192B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The present invention relates to a kind of civil engineering shield machine, with cylinder steel construction housing, tool holder is set in the front end of cylinder steel construction housing, tool holder front end face is uniformly distributed several excavating tools, tool holder rear end sets the cutter drives motor for controlling excavating tool, cylinder steel construction enclosure interior is also sequentially provided with the first support column on rear side of tool holder, second support column and the 3rd support column, tool holder, it is common on first support column and the second support column that first paragraph conveyer is installed, it is common on second support column and the 3rd support column that second segment conveyer is installed, tool holder, first support column, it is parallel between two neighboring part in second support column and the 3rd support column to set some groups of propelling cylinders;First paragraph conveyer and second segment conveyer are parallel to each other and the oblique setting that is staggered, and first paragraph conveyer is spiral, and second segment conveyer is belt-type.Excavate operation good with casting procedure connection effect, work progress speed.

Description

A kind of civil engineering shield machine
Technical field
The present invention relates to the technical field of civil engineering, especially a kind of civil engineering shield machine.
Background technology
Shield machine is pushed ahead by the steel component of a cylinder along canal axes side and soil is excavated, the cylinder The shell of body steel component is shield, and it plays a part of temporary support to the also unlined Tunnel Section excavated, and bears week The pressure of soil layer is enclosed, sometimes also subject to ground water pressure and by underground water gear outside.The operations such as excavation, casting, lining cutting exist It is smoothed out under the shielding of shield.
Shield machine is generally divided into hand pick formula shield according to operation principle, compression concrete side wall, half mechanical shield and mechanical Shield.Half mechanical shield therein includes two kinds of forms of partial pressure and global air pressure, and mechanical shield is cut including open chest Cut shield, vapour-pressure type shield, Slurry Shield, earth pressure balanced shield, EPBS, mixed type shield and special-shaped shield.
However, existing most shield machines come with some shortcomings in structure design part, the excavation part of shield machine with Casting part is separate, causes shield machine to occur excavating the problem that operation does not go up with casting procedure connection often, once occur This problem, it is necessary to shutdown inspection, whole work progress speed is slower.
The content of the invention
The technical problem to be solved in the present invention is:In order in solving the problems, such as the prior art in above-mentioned background technology, A kind of improved civil engineering shield machine is provided, excavation operation is good with casting procedure connection effect, work progress speed.
The technical solution adopted for the present invention to solve the technical problems is:A kind of civil engineering shield machine, with cylinder Body steel construction housing, is provided with tool holder in the front end of described cylinder steel construction housing, described tool holder Several excavating tools are evenly distributed with front end face, the rear end of tool holder is provided with for controlling the cutter of excavating tool to drive Dynamic motor, the inside of described cylinder steel construction housing be also sequentially provided with the first support column on rear side of tool holder, Second support column and the 3rd support column, are provided with first paragraph defeated jointly on tool holder, the first support column and the second support column Machine is sent, second segment conveyer, tool holder, the first support are installed jointly on the second described support column and the 3rd support column Post, the second support column and parallel between two neighboring part in the 3rd support column it is provided with some groups of propelling cylinders;First paragraph is defeated Machine and second segment conveyer is sent to be parallel to each other and the oblique setting that is staggered, first paragraph conveyer is sped structure, second segment conveying Machine is belt-type structure.
For the ease of the soil after excavation is transitioned into second segment conveyer from first paragraph conveyer, and conveyed from second segment Successfully emitted on machine, therefore the rear end of described first paragraph conveyer is provided with auger motor, first paragraph conveyer it is near after End bottom is provided with the soil discharge that will excavate to the anterior soil discharge mouth of second segment conveyer.
In order to reduce the horizontal space size of shield machine, structure is compacter, therefore described cutter drives motor input The output shaft that the input shaft of connection is connected with tool holder output end is vertically arranged.
The beneficial effects of the invention are as follows:The civil engineering shield machine, by tool holder, the first support column and It is common on two support columns that first paragraph conveyer is installed, it is common on the second support column and the 3rd support column that second segment conveyer is installed, And in tool holder, the first support column, the second support column and parallel between two neighboring part in the 3rd support column set There are some groups of propelling cylinders so that together with the excavation part of shield machine is closely connected with casting part, that is, cause shield machine Excavate operation to be connected well with casting operation, be less prone to working condition, it is ensured that entirely everything goes well with your work, and ground is carried out.
Brief description of the drawings
The present invention is further described with reference to the accompanying drawings and examples.
Fig. 1 is structural representation of the invention.
In accompanying drawing marked as:1st, cylinder steel construction housing, 2, tool holder, 3, excavating tool,
4th, drive motor, the 5, first support column, the 6, second support column, the 7, the 3rd support column, 8, first paragraph conveyer, 9, Two sections of conveyers, 10, propelling cylinder, 11, auger motor, 12, soil discharge mouthful.
Specific embodiment
In conjunction with the accompanying drawings, the present invention is further explained in detail.These accompanying drawings are simplified schematic diagram, only with Illustration illustrates basic structure of the invention, therefore it only shows the composition relevant with the present invention.
As shown in figure 1, a kind of civil engineering shield machine, with cylinder steel construction housing 1, cylinder steel construction housing Tool holder 2 is provided with 1 front end, several excavating tools 3, cutter are evenly distributed with the front end face of tool holder 2 The rear end of fixed mount 2 is provided with the cutter drives motor 4 for controlling excavating tool 3, the inside of cylinder steel construction housing 1 also according to Secondary the first support column 5 being provided with positioned at the rear side of tool holder 2, the second support column 6 and the 3rd support column 7, tool holder 2, First paragraph conveyer 8 is installed jointly, on the second support column 6 and the 3rd support column 7 on first support column 5 and the second support column 6 Second segment conveyer 9, tool holder 2, the first support column 5, the second support column 6 and phase in the 3rd support column 7 are installed jointly It is parallel between adjacent two parts to be provided with two groups of propelling cylinders 10 so that the excavation part of shield machine is closely connected with casting part Together, that is, cause that the excavation operation of shield machine is connected well with casting operation.
Wherein, first paragraph conveyer 8 and second segment conveyer 9 are parallel to each other and the oblique setting that is staggered, first paragraph conveyer 8 Rear end be provided with auger motor 11, the nearly rear end bottom of first paragraph conveyer 8 is provided with the soil discharge that will excavate to second segment The soil discharge mouthful 12 of the front portion of conveyer 9, first paragraph conveyer 8 is sped structure, and second segment conveyer 9 is belt-type knot Structure, is so easy to for the soil after excavation to be transitioned into second segment conveyer 9 from first paragraph conveyer 8, and from second segment conveyer 9 On successfully emit.The output that the input shaft of the input of cutter drives motor 4 connection is connected with the output end of tool holder 2 Axle is vertically arranged, and reduces the horizontal space size of shield machine, and structure is compacter.
The specific work process of the shield machine is as follows:
Several excavating tools 3 installed on tool holder 2 are pushed ahead along canal axes side and soil are dug Pick, the soil after excavation carries out helical feed by the first paragraph conveyer 8 of sped structure, and first paragraph conveyer 8 passes through spiral shell Swing arm can carry out breaing up treatment to the soil after excavation, and from the soil discharge mouthful 12 of the nearly rear end of first paragraph conveyer 8 will beat , to the front portion of the second segment conveyer 9 of belt-type structure, soil is along the anterior suitable of second segment conveyer 9 for soil discharge after dissipating Emit sharply.
With above-mentioned according to desirable embodiment of the invention as enlightenment, by above-mentioned description, relevant staff is complete Various changes and amendments can be carried out without departing from the scope of the technological thought of the present invention' entirely.The technology of this invention Property scope is not limited to the content on specification, it is necessary to its technical scope is determined according to right.

Claims (3)

1. a kind of civil engineering shield machine, with cylinder steel construction housing(1), described cylinder steel construction housing(1) Front end in be provided with tool holder(2), described tool holder(2)Front end face on be evenly distributed with several digging cutters Tool(3), tool holder(2)Rear end be provided with for controlling excavating tool(3)Cutter drives motor(4), it is characterised in that: Described cylinder steel construction housing(1)Inside be also sequentially provided with positioned at tool holder(2)First support column of rear side (5), the second support column(6)And the 3rd support column(7), tool holder(2), the first support column(5)With the second support column(6)On First paragraph conveyer is installed jointly(8), described the second support column(6)With the 3rd support column(7)On be provided with second jointly Section conveyer(9), tool holder(2), the first support column(5), the second support column(6)And the 3rd support column(7)In adjacent two It is parallel between individual part to be provided with some groups of propelling cylinders(10);First paragraph conveyer(8)With second segment conveyer(9)It is mutually flat The capable and oblique setting that is staggered, first paragraph conveyer(8)It is sped structure, second segment conveyer(9)It is belt-type structure.
2. a kind of civil engineering shield machine according to claim 1, it is characterised in that:Described first paragraph conveyer (8)Rear end be provided with auger motor(11), first paragraph conveyer(8)Nearly rear end bottom be provided with the soil discharge that will be excavated and arrive Second segment conveyer(9)Anterior soil discharge mouthful(12).
3. a kind of civil engineering shield machine according to claim 1, it is characterised in that:Described cutter drives motor (4)The input shaft and tool holder of input connection(2)The output shaft of output end connection is vertically arranged.
CN201510042949.2A 2015-01-28 2015-01-28 A kind of civil engineering shield machine Expired - Fee Related CN104653192B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510042949.2A CN104653192B (en) 2015-01-28 2015-01-28 A kind of civil engineering shield machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510042949.2A CN104653192B (en) 2015-01-28 2015-01-28 A kind of civil engineering shield machine

Publications (2)

Publication Number Publication Date
CN104653192A CN104653192A (en) 2015-05-27
CN104653192B true CN104653192B (en) 2017-06-16

Family

ID=53244763

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510042949.2A Expired - Fee Related CN104653192B (en) 2015-01-28 2015-01-28 A kind of civil engineering shield machine

Country Status (1)

Country Link
CN (1) CN104653192B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202300409U (en) * 2011-09-22 2012-07-04 洛阳聚科特种工程机械有限公司 Tunnel excavation equipment
CN202483580U (en) * 2012-02-01 2012-10-10 上海力行工程技术发展有限公司 Device capable of changing between earth pressure balance shield and tunnel boring machine (TBM) hard rock tunneling
CN202645580U (en) * 2012-06-29 2013-01-02 中国铁建重工集团有限公司 Tunnel boring machine for long-distance big-gradient inclined shaft
CN202707070U (en) * 2012-08-09 2013-01-30 中铁隧道装备制造有限公司 Composite shield machine with earth pressure balance and slurry balance double modes
CN203756180U (en) * 2014-04-04 2014-08-06 天津市管道工程集团有限公司 Slurry and soil pressure dual use pipe jacking machine

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202300409U (en) * 2011-09-22 2012-07-04 洛阳聚科特种工程机械有限公司 Tunnel excavation equipment
CN202483580U (en) * 2012-02-01 2012-10-10 上海力行工程技术发展有限公司 Device capable of changing between earth pressure balance shield and tunnel boring machine (TBM) hard rock tunneling
CN202645580U (en) * 2012-06-29 2013-01-02 中国铁建重工集团有限公司 Tunnel boring machine for long-distance big-gradient inclined shaft
CN202707070U (en) * 2012-08-09 2013-01-30 中铁隧道装备制造有限公司 Composite shield machine with earth pressure balance and slurry balance double modes
CN203756180U (en) * 2014-04-04 2014-08-06 天津市管道工程集团有限公司 Slurry and soil pressure dual use pipe jacking machine

Also Published As

Publication number Publication date
CN104653192A (en) 2015-05-27

Similar Documents

Publication Publication Date Title
US3511539A (en) Frustoconical tunnel boring head having radial concave scoops
US3355215A (en) Oscillating tunneling machine
CN207407751U (en) A kind of novel axial does not couple joint-cutting cumulative hydraulic pressure presplit blasting device
WO2020042057A1 (en) Tunneling boring machine preventing mud cakes from forming at excavation part
US2967701A (en) Method of continuous low seam short wall mining using rotary auger cutters
JP6684922B2 (en) Zero-discharging short-faced pillarless coal mining method
CN104153784B (en) A kind of slurry-water balance type shape of a hoof shield machine
CN104153787B (en) A kind of chain type cutter assembly mechanism
JP2020504253A5 (en)
CN108979653A (en) A kind of no soil cabin auger micro-disturbance construction shield machine and its working method
CN105019912A (en) Shield tunneling method and shield tunneling machine
CN104653192B (en) A kind of civil engineering shield machine
CN109630149A (en) A kind of multi-mode shield machine
WO2018133744A1 (en) Trench-cutting device for underground construction and working method thereof
CN205975719U (en) Novel dredger
CN202810858U (en) Roadway heading machine
CN111927450B (en) Hard rock ore body mining equipment based on hole array advanced presplitting and mining method thereof
RU2456449C1 (en) Mining machine
CN105715278A (en) Novel tunneling robot
CN111622772A (en) Tunneller for tunnel full-face construction
CN218177230U (en) Rectangular pipe jacking machine suitable for rock stratum
CN214944261U (en) Combined cutter head system of rectangular pipe jacking machine
JP2014129666A (en) Tunnel excavator
CN111188626B (en) Advanced support system of open type soft rock heading machine and application method of advanced support system
CN212054680U (en) Big lane of track excavating equipment is used in construction of colliery underground drill site

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Di Jinsong

Inventor after: Cui Xiaoyan

Inventor after: Sun Shuwei

Inventor after: An Jie

Inventor after: Li Peng

Inventor after: Wu Xing

Inventor after: Li Yao

Inventor after: Gao Hui

Inventor after: Di Yuting

Inventor before: Li Kang

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20170511

Address after: 450014, No. 1, building 103, Jinshui Road, Jinshui District, Henan, Zhengzhou

Applicant after: Co., Ltd of Architectural Design Research Inst. Henan Prov.

Applicant after: Di Yuting

Applicant after: Di Jinsong

Applicant after: Cui Xiaoyan

Applicant after: Sun Shuwei

Applicant after: An Jie

Applicant after: Li Peng

Applicant after: Wu Xing

Applicant after: Li Yao

Applicant after: Gao Hui

Address before: Tongxing road Wenjiang District of Chengdu City, Sichuan province 610000 No. 88 Regent Hong Kong 19 Building No. 1702

Applicant before: Li Kang

TA01 Transfer of patent application right
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170616

Termination date: 20190128

CF01 Termination of patent right due to non-payment of annual fee