CN104612160B - 一种紧邻已有建筑物基坑维护结构及施工方法 - Google Patents
一种紧邻已有建筑物基坑维护结构及施工方法 Download PDFInfo
- Publication number
- CN104612160B CN104612160B CN201410657456.5A CN201410657456A CN104612160B CN 104612160 B CN104612160 B CN 104612160B CN 201410657456 A CN201410657456 A CN 201410657456A CN 104612160 B CN104612160 B CN 104612160B
- Authority
- CN
- China
- Prior art keywords
- pile
- soil
- construction
- stake
- excavation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000002689 soil Substances 0.000 title claims abstract description 69
- 238000010276 construction Methods 0.000 title claims description 38
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 37
- 239000010959 steel Substances 0.000 claims abstract description 37
- 238000009412 basement excavation Methods 0.000 claims abstract description 30
- 238000005056 compaction Methods 0.000 claims abstract description 27
- 239000004568 cement Substances 0.000 claims abstract description 26
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances data:image/svg+xml;base64,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 data:image/svg+xml;base64,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 O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 25
- 238000002156 mixing Methods 0.000 claims abstract description 13
- 238000000034 method Methods 0.000 claims description 15
- 238000007569 slipcasting Methods 0.000 claims description 11
- 238000005553 drilling Methods 0.000 claims description 6
- 239000000463 material Substances 0.000 claims description 6
- 239000004567 concrete Substances 0.000 claims description 5
- 238000002513 implantation Methods 0.000 claims description 4
- 230000003014 reinforcing Effects 0.000 claims description 4
- 238000005520 cutting process Methods 0.000 claims description 3
- 239000007943 implant Substances 0.000 claims description 3
- 238000002360 preparation method Methods 0.000 claims description 3
- 230000002787 reinforcement Effects 0.000 claims description 3
- 230000000694 effects Effects 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 2
- XEEYBQQBJWHFJM-UHFFFAOYSA-N iron Chemical compound data:image/svg+xml;base64,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 data:image/svg+xml;base64,PD94bWwgdmVyc2lvbj0nMS4wJyBlbmNvZGluZz0naXNvLTg4NTktMSc/Pgo8c3ZnIHZlcnNpb249JzEuMScgYmFzZVByb2ZpbGU9J2Z1bGwnCiAgICAgICAgICAgICAgeG1sbnM9J2h0dHA6Ly93d3cudzMub3JnLzIwMDAvc3ZnJwogICAgICAgICAgICAgICAgICAgICAgeG1sbnM6cmRraXQ9J2h0dHA6Ly93d3cucmRraXQub3JnL3htbCcKICAgICAgICAgICAgICAgICAgICAgIHhtbG5zOnhsaW5rPSdodHRwOi8vd3d3LnczLm9yZy8xOTk5L3hsaW5rJwogICAgICAgICAgICAgICAgICB4bWw6c3BhY2U9J3ByZXNlcnZlJwp3aWR0aD0nODVweCcgaGVpZ2h0PSc4NXB4JyB2aWV3Qm94PScwIDAgODUgODUnPgo8IS0tIEVORCBPRiBIRUFERVIgLS0+CjxyZWN0IHN0eWxlPSdvcGFjaXR5OjEuMDtmaWxsOiNGRkZGRkY7c3Ryb2tlOm5vbmUnIHdpZHRoPSc4NS4wJyBoZWlnaHQ9Jzg1LjAnIHg9JzAuMCcgeT0nMC4wJz4gPC9yZWN0Pgo8dGV4dCB4PSczNS4wJyB5PSc1My42JyBjbGFzcz0nYXRvbS0wJyBzdHlsZT0nZm9udC1zaXplOjIzcHg7Zm9udC1zdHlsZTpub3JtYWw7Zm9udC13ZWlnaHQ6bm9ybWFsO2ZpbGwtb3BhY2l0eToxO3N0cm9rZTpub25lO2ZvbnQtZmFtaWx5OnNhbnMtc2VyaWY7dGV4dC1hbmNob3I6c3RhcnQ7ZmlsbDojM0I0MTQzJyA+RjwvdGV4dD4KPHRleHQgeD0nNTEuMCcgeT0nNTMuNicgY2xhc3M9J2F0b20tMCcgc3R5bGU9J2ZvbnQtc2l6ZToyM3B4O2ZvbnQtc3R5bGU6bm9ybWFsO2ZvbnQtd2VpZ2h0Om5vcm1hbDtmaWxsLW9wYWNpdHk6MTtzdHJva2U6bm9uZTtmb250LWZhbWlseTpzYW5zLXNlcmlmO3RleHQtYW5jaG9yOnN0YXJ0O2ZpbGw6IzNCNDE0MycgPmU8L3RleHQ+Cjwvc3ZnPgo= [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 238000004537 pulping Methods 0.000 description 2
- 238000007789 sealing Methods 0.000 description 2
- 210000000282 Nails Anatomy 0.000 description 1
- 210000003800 Pharynx Anatomy 0.000 description 1
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000000280 densification Methods 0.000 description 1
- 230000002708 enhancing Effects 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 239000002893 slag Substances 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- 230000001360 synchronised Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
- 238000003079 width control Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
Abstract
Description
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410657456.5A CN104612160B (zh) | 2014-11-18 | 2014-11-18 | 一种紧邻已有建筑物基坑维护结构及施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410657456.5A CN104612160B (zh) | 2014-11-18 | 2014-11-18 | 一种紧邻已有建筑物基坑维护结构及施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104612160A CN104612160A (zh) | 2015-05-13 |
CN104612160B true CN104612160B (zh) | 2016-03-30 |
Family
ID=53146788
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410657456.5A Active CN104612160B (zh) | 2014-11-18 | 2014-11-18 | 一种紧邻已有建筑物基坑维护结构及施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104612160B (zh) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107574835A (zh) * | 2016-07-05 | 2018-01-12 | 辛德刚 | 水泥土土钉土墙 |
CN106400814B (zh) * | 2016-11-11 | 2021-03-16 | 天脊煤化工集团股份有限公司 | 一种基坑支护方法 |
CN107059940A (zh) * | 2017-01-25 | 2017-08-18 | 上海二十冶建设有限公司 | 临近深基坑既有建筑物浅基础的保护方法 |
CN107514003A (zh) * | 2017-10-23 | 2017-12-26 | 上海市城市建设设计研究总院(集团)有限公司 | 变截面钻孔灌注支护桩结构及其施工方法 |
CN112502139A (zh) * | 2020-11-25 | 2021-03-16 | 中铁八局集团有限公司 | 三轴搅拌桩帷幕止水与旋挖灌注桩支护深坑开挖施工方法 |
CN112709231A (zh) * | 2020-12-23 | 2021-04-27 | 广东省地质工程公司 | 一种地下室基坑支护结构及其施工方法 |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100465386C (zh) * | 2008-02-02 | 2009-03-04 | 浙江环宇建设集团有限公司 | 桩加锚基坑支护工法 |
CN102116030A (zh) * | 2011-01-17 | 2011-07-06 | 东南大学 | 一种组合基坑支护结构及其施工方法 |
JP2013136921A (ja) * | 2011-12-28 | 2013-07-11 | Ohbayashi Corp | 山留め壁の支持方法、山留め壁の支持構造、及び地下躯体の構築方法 |
CN103469800A (zh) * | 2012-06-06 | 2013-12-25 | 中国二十冶集团有限公司 | 外围设置混凝土构件的水泥搅拌桩复合支护体系 |
CN202745063U (zh) * | 2012-08-22 | 2013-02-20 | 中国建筑第六工程局有限公司 | 深基坑钢板桩加锚索支护体系施工结构 |
CN203307824U (zh) * | 2013-06-14 | 2013-11-27 | 李琳 | 高层建筑基坑支护结构 |
CN204326080U (zh) * | 2014-11-18 | 2015-05-13 | 中大建设有限公司 | 一种紧邻已有建筑物基坑维护结构 |
-
2014
- 2014-11-18 CN CN201410657456.5A patent/CN104612160B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN104612160A (zh) | 2015-05-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104612160B (zh) | 一种紧邻已有建筑物基坑维护结构及施工方法 | |
CN103741714A (zh) | 地下工程全盖挖逆作法施工方法 | |
CN105862930B (zh) | 一种对新建地下工程下方既有隧道的保护结构 | |
CN207891895U (zh) | 人行通道竖井开挖支护结构 | |
CN204326080U (zh) | 一种紧邻已有建筑物基坑维护结构 | |
CN103967504B (zh) | 一种电厂循环水系统隧洞口的支护结构及施工方法 | |
CN103938634B (zh) | 一种深基坑支护结构及施工方法 | |
CN110004991A (zh) | 基于外凸式翼脚板的地下结构抗浮体系及构建方法 | |
CN110387889A (zh) | 一种用于长条形深基坑的连拱式基坑支护方法 | |
CN110241828A (zh) | 一种排栅式管桩后注浆内锚外止水支护施工方法 | |
CN106677189B (zh) | 一种斜桩墙支承式基坑支护结构及其施工方法 | |
CN104895111B (zh) | 软土地中综合管沟的施工方法 | |
CN104652444A (zh) | 超大型深基坑中心岛式交替土方开挖的整体逆作施工方法 | |
CN101353896A (zh) | 超大直径、超埋深度调蓄池的半逆作施工方法 | |
CN105040707A (zh) | 用作地下室外墙的组合密排桩深基坑支护围护结构 | |
CN105239578B (zh) | 富水砂层深基坑水下施工方法 | |
CN207003499U (zh) | 一种地铁隧道上方基坑开挖的抗浮起装置 | |
CN105113513B (zh) | 一种防渗水基坑支护结构及施工方法 | |
CN205804366U (zh) | 一种渣沟结构 | |
CN108035360A (zh) | 一种用于基坑支护的方法 | |
CN212642730U (zh) | 一种湿陷性黄土地区隧道穿越人防结构 | |
CN210141142U (zh) | 一种洞桩暗挖顺筑地下结构 | |
CN203925514U (zh) | 一种电厂循环水系统隧洞口的支护结构 | |
CN106758890A (zh) | 排桩箱涵结构及其施工方法 | |
CN209687506U (zh) | 穿河浅埋暗挖电力隧道施工结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
C06 | Publication | ||
C53 | Correction of patent for invention or patent application | ||
C10 | Entry into substantive examination | ||
CB03 | Change of inventor or designer information |
Inventor after: Peng Jinlu Inventor after: Gao Wenfeng Inventor after: Hong Ning Inventor after: Wang Dajin Inventor after: Yan Ruiyong Inventor before: Peng Guolu Inventor before: Gao Wenfeng Inventor before: Hong Ning Inventor before: Wang Dajin Inventor before: Yan Ruiyong |
|
SE01 | Entry into force of request for substantive examination | ||
COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: PENG GUOLU GAO WENFENG HONG NING WANG DAJIN YAN RUIYONG TO: PENG JINLU GAOWENFENG HONG NING WANG DAJIN YAN RUIYONG |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee | ||
CP01 | Change in the name or title of a patent holder |
Address after: 330095 Jiangxi city of Shangrao province Xinzhou Zone Lake Road No. 92 Patentee after: Zhongda Construction Group Co Ltd Address before: 330095 Jiangxi city of Shangrao province Xinzhou Zone Lake Road No. 92 Patentee before: ZHONGDA CONSTRUCTION CO., LTD. Address after: 330095 Jiangxi city of Shangrao province Xinzhou Zone Lake Road No. 92 Patentee after: Zhongda Construction Co., Ltd. Address before: 330095 Jiangxi city of Shangrao province Xinzhou Zone Lake Road No. 92 Patentee before: Zhongda Construction Group Co Ltd |