CN104594816A - Stiffness reducing anti-drag device applied to horizontal well completion pipe column - Google Patents

Stiffness reducing anti-drag device applied to horizontal well completion pipe column Download PDF

Info

Publication number
CN104594816A
CN104594816A CN201310531219.XA CN201310531219A CN104594816A CN 104594816 A CN104594816 A CN 104594816A CN 201310531219 A CN201310531219 A CN 201310531219A CN 104594816 A CN104594816 A CN 104594816A
Authority
CN
China
Prior art keywords
work
processed
horizontal well
special material
inner core
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310531219.XA
Other languages
Chinese (zh)
Other versions
CN104594816B (en
Inventor
杨永青
于长录
王治华
张欣欣
吕双
张华�
彭超
洪亮
郑伟姣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Oil & Gas Cooperation And Development Branch Cnpc Bohai Drilling Engineering Co Ltd
Original Assignee
Oil & Gas Cooperation And Development Branch Cnpc Bohai Drilling Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Oil & Gas Cooperation And Development Branch Cnpc Bohai Drilling Engineering Co Ltd filed Critical Oil & Gas Cooperation And Development Branch Cnpc Bohai Drilling Engineering Co Ltd
Priority to CN201310531219.XA priority Critical patent/CN104594816B/en
Publication of CN104594816A publication Critical patent/CN104594816A/en
Application granted granted Critical
Publication of CN104594816B publication Critical patent/CN104594816B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/20Driving or forcing casings or pipes into boreholes, e.g. sinking; Simultaneously drilling and casing boreholes

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a stiffness reducing anti-drag device applied to a horizontal well completion pipe column. The stiffness reducing anti-drag device applied to the horizontal well completion pipe column comprises a working outer barrel, a special material barrel and a working inner barrel. The special material barrel is connected to the upper end of the working inner barrel and put into the working outer barrel with the working inner barrel from the bottom of the working outer barrel; a bottom hanging ring used for limiting positions is arranged at the lower end of the working outer barrel and the upper end of the working inner cylinder. The special material barrel is made from metal with smaller bending stiffness or non-metal materials. By means of the stiffness reducing anti-drag device applied to the horizontal well completion pipe column, the problem exists in a prior completion pipe column that the local stiffness is too large caused by overstocked connection of large size tools is solved, and the safety of a completion project is furthest improved. The stiffness reducing anti-drag device applied to the horizontal well completion pipe column has the advantages that the structure is simple, the working is reliable, the function is perfect, the applicability is wide, the cost is low, the requirements for working conditions are low, the field application is convenient, the technical requirements for a construction team are low, and the construction program is the same as a conventional completion process.

Description

A kind of being applied in falls firm resistance absorber in horizontal well completion tubular pile
Technical field
To the present invention relates in horizontal well completion tubular pile auxiliary under enter instrument, specifically a kind of being applied in falls firm resistance absorber in horizontal well completion tubular pile.
Background technology
Because horizontal well technology is in the large-scale promotion in oil field, the problem that some initial stages are not considered is also following, as Short Radius Horizontal Wells, the problem of difficulty is entered under the hole conditions such as long horizontal sections horizontal well or the larger horizontal well of the degree of depth all exist completion tubular column in Completion Operations, in the irregular well example of well track particularly caused because of misoperation in some complex geologic conditions and drilling process, enter under completion tubular column and be very easily hampered.Not in place under causing tubing string.This kind of situation is once occur, the instrument on tubing string will be caused to misplace, casing cementing mode is not bad in this way, just loss point oil layer section, but if special well, picture needs pressure break completion or screen casing crest water flooding bricklayer's skill completion all can cause packer card seal point to misplace, light then cause Party A to lose several sections of exploitation oil reservoirs, heavy then cause whole process failure, lower step construction cannot be carried out, even whole oil well is scrapped, and loses extremely serious.And in existing completion technique, still there is no the instrument that effectively can reduce tubing string local stiffness, local stiffness particularly between large scale work, therefore develop a kind of special tool that then can reduce tubing string excessive dog-leg degree in well track by reducing tubing string local stiffness and just seem particularly important.
Summary of the invention
The object of this invention is to provide a kind of being applied in and fall firm resistance absorber in horizontal well completion tubular pile, solving horizontal well completion tubular pile and enter difficult problem under causing because dog-leg in wellbore trajectory is spent large, reducing the overall frictional resistance of tubing string by reducing tubing string local stiffness.
In order to reach above-mentioned purpose, present invention employs following technical scheme, a kind of being applied in falls firm resistance absorber in horizontal well completion tubular pile, comprise work urceolus, special material cylinder, work inner core, described special material cylinder is connected to work inner core upper end, then loads work outer barrel by the bottom of work urceolus together; The lower end of described work urceolus is provided with spacing bottom hung ring with work inner core upper end position.
The standard of the described special material cylinder linked together and work inner core loading work outer barrel is at least will enter work outer barrel special material wound packages completely; Described special material cylinder is that metal that bending stiffness is less or nonmetals are made.
Described work inner core upper end outer wall processes the sphere that two convex-concaves are connected respectively, two spheres respectively with the sphere Corresponding matching that arranges on work urceolus and bottom hung ring.
Described work inner core internal diameter is identical with special material cylinder internal diameter, and upper end is processed with the screw thread matched with special material cylinder lower end screw thread; Work inner core bottom outer wall is processed with casing threads.
The inwall upper end of described work urceolus is processed with the limited step of casing threads and special material cylinder, and lower end inner wall is processed with the connecting thread that mates with bottom hung ring and its top is processed with the concave ball surfaces mated with the inner core spirogyrate sphere that works.
Described special material cylinder is the isometrical tubular of upper coarse and lower fine inwall, and external wall of upper portion is processed with at least 1 seal groove, lower end is processed with the coupling screw thread be connected with the inner core upper end that works.
Described bottom hung ring inwall upper end is processed with the convex spherical inside surface matched with the inner core top exterior walls concave outer surface that works, and inwall is processed as the upper coarse and lower fine conical surface of certain angle, and seal groove is processed with below inwall, outer wall upper end is processed with the connecting thread matched with the urceolus that works.
Compared to prior art, the present invention has following beneficial effect:
Solve the completion tubular column problem that local stiffness that is that cause is excessive because the connection of large scale instrument is overstocked in the past, improve the safety of Well Completion Engineering of Oil Reservoirs to greatest extent, and this tool construction is simple, reliable operation, perfect in shape and function, applicability is wide, and cost is low, requires low to service condition.On-the-spot application is convenient, and lower to the technical requirements of construction team, construction sequence is identical with conventional completed well process, this instrument can be placed any desired position of horizontal well completion tubular pile, without the need to any additional step.Therefore, there is significant economic benefit and larger popularization and application space.
Accompanying drawing explanation
Fig. 1 is a kind of structural representation falling firm resistance absorber be applied in horizontal well completion tubular pile of the present invention.
In figure: work urceolus 1, special material cylinder 2, work inner core 3, bottom hung ring 4.
Detailed description of the invention
Detailed description for the present invention and technology contents, coordinate accompanying drawing to be described as follows, but accompanying drawing only provides with reference to the use with explanation, is not used for being limited the present invention.
Shown in figure 1, a kind of being applied in falls firm resistance absorber in horizontal well completion tubular pile, special material cylinder 2 and work inner core 3 are by after screwed connection, loaded by the bottom of work urceolus 1, bottom hung ring 4 is inserted in from work inner core 3 bottom and is connected, by spacing for work inner core 3 by screw thread and working bottom urceolus 1.Wherein special material cylinder 2 is that metal that bending stiffness is less or nonmetals form (as abrasion resistance engineering plastics etc.), work inner core 3 outer wall top process respectively two convex-concaves be connected and respectively with the sphere of work urceolus 1 and bottom hung ring 4 Corresponding matching.
Work inner core internal diameter is identical with special material cylinder internal diameter, and upper end is processed with the screw thread matched with special material cylinder lower end screw thread; Work inner core bottom outer wall is processed with casing threads.The inwall upper end of described work urceolus is processed with the limited step of casing threads and special material cylinder, and lower end inner wall is processed with the connecting thread that mates with bottom hung ring and its top is processed with the concave ball surfaces mated with the inner core spirogyrate sphere that works.Described special material cylinder is the isometrical tubular of upper coarse and lower fine inwall, and external wall of upper portion is processed with at least two seal grooves, lower end is processed with the coupling screw thread be connected with the inner core upper end that works.Described bottom hung ring inwall upper end is processed with the convex spherical inside surface matched with the inner core top exterior walls concave outer surface that works, and inwall is processed as the upper coarse and lower fine conical surface of certain angle, and seal groove is processed with below inwall, outer wall upper end is processed with the connecting thread matched with the urceolus that works.
This tool construction is simple, reliable operation, perfect in shape and function, and applicability is wide, and cost is low, requires low to service condition.On-the-spot application is convenient, lower to the technical requirements of construction team, construction sequence is identical with conventional completed well process, without any and outside step, frictional resistance is entered under effectively reducing the local stiffness of horizontal segment completion tubular column and whole tubing string, improve the tripablity of completion tubular column, farthest ensure the safety of Well Completion Engineering of Oil Reservoirs.
The foregoing is only preferred embodiment of the present invention, be not used to limit the scope of the claims of the present invention, other use the equivalence of patent spirit of the present invention to change, and all should all belong to the scope of the claims of the present invention.

Claims (7)

1. one kind is applied in and falls firm resistance absorber in horizontal well completion tubular pile, it is characterized in that, comprise work urceolus, special material cylinder, work inner core, described special material cylinder is connected to work inner core upper end, then loads work outer barrel by the bottom of work urceolus together; The lower end of described work urceolus is provided with spacing bottom hung ring with work inner core upper end position.
2. a kind of being applied according to claim 1 falls firm resistance absorber in horizontal well completion tubular pile, it is characterized in that, described in the standard of the special material cylinder that links together and work inner core loading work outer barrel at least completely special material wound packages will be entered work outer barrel; Described special material cylinder is that metal that bending stiffness is less or nonmetals are made.
3. a kind of being applied according to claim 1 falls firm resistance absorber in horizontal well completion tubular pile, it is characterized in that, described work inner core upper end outer wall processes the sphere that two convex-concaves are connected respectively, two spheres respectively with the sphere Corresponding matching that arranges on work urceolus and bottom hung ring.
4. a kind of being applied according to claim 3 falls firm resistance absorber in horizontal well completion tubular pile, and it is characterized in that, described work inner core internal diameter is identical with special material cylinder internal diameter, and upper end is processed with the screw thread matched with special material cylinder lower end screw thread; Work inner core bottom outer wall is processed with casing threads.
5. a kind of being applied according to claim 1 falls firm resistance absorber in horizontal well completion tubular pile, it is characterized in that, the inwall upper end of described work urceolus is processed with the limited step of casing threads and special material cylinder, and lower end inner wall is processed with the connecting thread that mates with bottom hung ring and its top is processed with the concave ball surfaces mated with the inner core spirogyrate sphere that works.
6. a kind of being applied according to claim 1 falls firm resistance absorber in horizontal well completion tubular pile, it is characterized in that, described special material cylinder is the isometrical tubular of upper coarse and lower fine inwall, external wall of upper portion is processed with at least 1 seal groove, lower end is processed with the coupling screw thread be connected with the inner core upper end that works.
7. a kind of being applied according to claim 1 falls firm resistance absorber in horizontal well completion tubular pile, it is characterized in that, described bottom hung ring inwall upper end is processed with the convex spherical inside surface matched with the inner core top exterior walls concave outer surface that works, and inwall is processed as the upper coarse and lower fine conical surface of certain angle, and seal groove is processed with below inwall, outer wall upper end is processed with the connecting thread matched with the urceolus that works.
CN201310531219.XA 2013-11-01 2013-11-01 A kind of firm resistance absorber of the fall applied in horizontal well completion tubular pile Expired - Fee Related CN104594816B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310531219.XA CN104594816B (en) 2013-11-01 2013-11-01 A kind of firm resistance absorber of the fall applied in horizontal well completion tubular pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310531219.XA CN104594816B (en) 2013-11-01 2013-11-01 A kind of firm resistance absorber of the fall applied in horizontal well completion tubular pile

Publications (2)

Publication Number Publication Date
CN104594816A true CN104594816A (en) 2015-05-06
CN104594816B CN104594816B (en) 2016-09-14

Family

ID=53120826

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310531219.XA Expired - Fee Related CN104594816B (en) 2013-11-01 2013-11-01 A kind of firm resistance absorber of the fall applied in horizontal well completion tubular pile

Country Status (1)

Country Link
CN (1) CN104594816B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109973023A (en) * 2017-12-28 2019-07-05 中石化石油工程技术服务有限公司 A kind of telescopic setting of casing segmentation tool

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1484895A1 (en) * 1987-05-26 1989-06-07 Ukhtinskij Ind I Directional drilling device
CN2286494Y (en) * 1997-04-04 1998-07-22 新疆石油管理局钻井工艺研究院 Joint
CN2608672Y (en) * 2003-03-07 2004-03-31 中国石化胜利油田有限公司采油工艺研究院 Oil pumping rod flexible connecting device
CN2641267Y (en) * 2003-07-24 2004-09-15 辽河石油勘探局曙光工程技术处 Ball head shaped, hanging type jointing hoop
CN2674069Y (en) * 2004-01-08 2005-01-26 新疆石油管理局钻井工艺研究院 Actived joint for large curvature sleeve
CN2916099Y (en) * 2006-06-08 2007-06-27 辽河石油勘探局 Torsion type universal joint for horizontal well
CN200985748Y (en) * 2006-12-21 2007-12-05 新疆石油管理局钻井工艺研究院 Rotetable type casing tube flexible joint
CN201292782Y (en) * 2008-10-22 2009-08-19 中国石油集团长城钻探工程有限公司 Canula mobile type cardan joint
CN201581819U (en) * 2009-11-27 2010-09-15 中国石油集团长城钻探工程有限公司 Rotary joint for well completion
CN102635311A (en) * 2012-05-03 2012-08-15 西南石油大学 Orienting device for drilling of radial horizontal well
CN203531762U (en) * 2013-11-01 2014-04-09 中国石油集团渤海钻探工程有限公司油气合作开发分公司 Rigidity-reducing resistance reduction device applied to horizontal well completion tubular pile

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1484895A1 (en) * 1987-05-26 1989-06-07 Ukhtinskij Ind I Directional drilling device
CN2286494Y (en) * 1997-04-04 1998-07-22 新疆石油管理局钻井工艺研究院 Joint
CN2608672Y (en) * 2003-03-07 2004-03-31 中国石化胜利油田有限公司采油工艺研究院 Oil pumping rod flexible connecting device
CN2641267Y (en) * 2003-07-24 2004-09-15 辽河石油勘探局曙光工程技术处 Ball head shaped, hanging type jointing hoop
CN2674069Y (en) * 2004-01-08 2005-01-26 新疆石油管理局钻井工艺研究院 Actived joint for large curvature sleeve
CN2916099Y (en) * 2006-06-08 2007-06-27 辽河石油勘探局 Torsion type universal joint for horizontal well
CN200985748Y (en) * 2006-12-21 2007-12-05 新疆石油管理局钻井工艺研究院 Rotetable type casing tube flexible joint
CN201292782Y (en) * 2008-10-22 2009-08-19 中国石油集团长城钻探工程有限公司 Canula mobile type cardan joint
CN201581819U (en) * 2009-11-27 2010-09-15 中国石油集团长城钻探工程有限公司 Rotary joint for well completion
CN102635311A (en) * 2012-05-03 2012-08-15 西南石油大学 Orienting device for drilling of radial horizontal well
CN203531762U (en) * 2013-11-01 2014-04-09 中国石油集团渤海钻探工程有限公司油气合作开发分公司 Rigidity-reducing resistance reduction device applied to horizontal well completion tubular pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109973023A (en) * 2017-12-28 2019-07-05 中石化石油工程技术服务有限公司 A kind of telescopic setting of casing segmentation tool

Also Published As

Publication number Publication date
CN104594816B (en) 2016-09-14

Similar Documents

Publication Publication Date Title
CN104213861B (en) A kind of expansion tube expanding process and tool system
CN204386500U (en) A kind of radial variable casing tube centralizer
CN105484699A (en) Drilling-free milling bridge plug for fracturing
CN202900044U (en) Bistable device prebending dynamic pendulum drilling tool
CN104594816A (en) Stiffness reducing anti-drag device applied to horizontal well completion pipe column
CN201794527U (en) Casing float collar
CN101871332A (en) Multi-way releasing device
CN203756093U (en) Mechanized-operation constant bit pressure plug-drilling string
US9598924B2 (en) Wellhead hanger with spacer to reduce break-out torque
CN202659194U (en) Novel well wall restoring device with combined sleeve and corrugated pipe
CN203531762U (en) Rigidity-reducing resistance reduction device applied to horizontal well completion tubular pile
CN101555778B (en) External packer of high temperature pipe
CN209129577U (en) A kind of 7 " non-rotating gravity set packers of limited times
CN203603815U (en) Through scraping integration down well equipment
CN104963640A (en) Horizontal well coiled tubing lock type hydraulic bit feeding and alarming system
CN205422566U (en) Stone oil pipe utensil screw thread locking device
CN211474073U (en) Multifunctional bridge plug made of fully soluble metal
CN205259968U (en) Sleeve pipe centralizer is hindered to low rubbing
CN203441409U (en) Expansion type tail pipe hanging device of thermal production well
US10794140B2 (en) Systems and methods to reduce break-out torque
CN205135579U (en) Locking resistance-reducing centralizer for horizontal well casing type composite perforation
CN207177762U (en) Horizontal well centralizer
CN104088615A (en) Control valve for sleeve well cementation staged fracturing
CN103075114B (en) A kind of box cupling
CN204677140U (en) Multi-functional coiled tubing releasing tool

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160914