CN104538888B - A kind of distribution line straight line pole cross-arm charged for replacement method - Google Patents

A kind of distribution line straight line pole cross-arm charged for replacement method Download PDF

Info

Publication number
CN104538888B
CN104538888B CN201410721392.0A CN201410721392A CN104538888B CN 104538888 B CN104538888 B CN 104538888B CN 201410721392 A CN201410721392 A CN 201410721392A CN 104538888 B CN104538888 B CN 104538888B
Authority
CN
China
Prior art keywords
insulating
arm
arms
mast assembly
insulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410721392.0A
Other languages
Chinese (zh)
Other versions
CN104538888A (en
Inventor
丁翔
俞键
郦铁锋
陈挺
蒋表
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
STATE GRID ZHEJIANG ZHUJI POWER SUPPLY Co Ltd
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
STATE GRID ZHEJIANG ZHUJI POWER SUPPLY Co Ltd
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by STATE GRID ZHEJIANG ZHUJI POWER SUPPLY Co Ltd, State Grid Corp of China SGCC, State Grid Zhejiang Electric Power Co Ltd, Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical STATE GRID ZHEJIANG ZHUJI POWER SUPPLY Co Ltd
Priority to CN201410721392.0A priority Critical patent/CN104538888B/en
Publication of CN104538888A publication Critical patent/CN104538888A/en
Application granted granted Critical
Publication of CN104538888B publication Critical patent/CN104538888B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention discloses a kind of distribution line straight line pole cross-arm charged for replacement method, belong to distribution line live working field of engineering technology, by the use of insulated platform as major insulation, operating personnel is using a whole set of individual's insulating protection apparatus, use insulating glove direct maintenance, the masking of correlation is carried out to charging equipment using insulation masking Work tool, carry out changing so as to directly contact electrical body, installment work, and hold insulating bar working system librarian use insulating mast assembly and electrical body play a part of to undertake interim fixed and supported.The economic benefit of many power supplies so that operating distribution line with normal power supply, can reduce the frequency of power cut of main line, it is ensured that power supply reliability, can be realized, continued power is can ensure that again, is the more economic worths of social creativity.

Description

A kind of distribution line straight line pole cross-arm charged for replacement method
Technical field
The present invention relates to a kind of distribution line straight line pole cross-arm charged for replacement method, belongs to distribution line live working engineering Technical field.
Background technology
Distribution network live line work mainly has insulating glove working system and insulating bar working system, before not by the influence of topography Put, the area that aerial lift device with insulated arm can be reached all can be solving on distribution line using insulating glove direct maintenance Failure defect elimination, accident treatment, industry expand the work such as installation, and the area not reached in aerial lift device with insulated arm, also can be with absolutely Edge action bars working system carries out some simple projects, so the technology of distribution network live line work should be relatively perfect at present 's.But for the project of some complex class relies solely on insulating bar working system not only inefficiency, the labor of operation Fatigue resistance is big, and danger is also than larger.
In view of this, the present inventor is studied to this, specially develops a kind of distribution line straight line pole cross-arm powered more Method is changed, thus this case produces.
The content of the invention
It is an object of the invention to provide a kind of distribution line straight line pole cross-arm charged for replacement method, solves charged for replacement and matches somebody with somebody The defect elimination work of electric line straight line pole cross-arm, can eliminate the defect of distribution line in time, can ensure that the power supply reliability of distribution again Property, while work efficiency is improve using combination operational method again, reduce task difficulty, can safely and conveniently complete work Task, it is ensured that the power supply reliability of distribution.
To achieve these goals, solution of the invention is:
A kind of distribution line straight line pole cross-arm charged for replacement method, comprises the steps:
1)Insulated platform is installed in the position that safe distance is kept with electrical body first;
2)Insulation masking is carried out to the electrical body in working range, grounding body directly using insulating glove, it is ensured that operation area Domain construction safety, the electrical body, grounding body in working range are specially wire, cross-arm, insulator;
3)Both arms insulating mast assembly is installed:The top and bottom of both arms insulating mast assembly are fixed respectively;
4)Live wire is inserted in the wire draw-in groove of both arms insulating mast assembly, and lifting lead wire, receive both arms insulating mast assembly Power;
5)Binding of the colligation on linear rod insulator is released using insulating glove;
6)Lift live wire:Using insulation operation handle, the insulation rocking bar of both arms insulating mast assembly is operated, live wire is made In position high up in the air, live wire is more than 20 centimetres from linear rod insulator minimum safe distance, and then guarantees insulated platform Upper operating personnel's minimum job safety distance;
7)Linear rod insulator is removed by insulating glove, and has recovered the insulation masking of iron cross arm;
8)Transfer insulated platform:Insulated platform is gone to and do not remove linear rod insulator side;
9)Repeat the above steps 5)-7)Opposite side linear rod insulator is removed, and has recovered the insulation masking of iron cross arm;
10)Live wire on both arms insulating mast assembly temporary support straight line pole cross-arm, and carry out the insulation masking of electrical body;
11)Straight line pole cross-arm is changed, iron cross arm must be carried out all insulation maskings, there must not be larger bare spots before installing
12)It is fitted into the linear rod insulator of side;
13)By the operation handle of both arms insulating mast assembly, live wire is drop in linear rod insulator draw-in groove, and protect Hold in same horizontal line;
14)By live wire colligation on porcelain vase, and recover insulation masking;
15)Repeat the above steps 12)-14)The linear rod insulator for completing opposite side is installed;
16)Remove both arms insulating mast assembly:The insulation arm of both arms insulating mast assembly is retracted to initial position, removes both arms insulation and embraces The fixing device of bar top and bottom, and drop to ground;
17)The insulation masking of operating area is removed using insulating glove, dismounting order is by as far as near, from top to bottom, first Electrical body, rear grounding body;
18)Insulated platform is removed, whole straight line pole cross-arm charged for replacement process terminates.
Distribution line straight line pole cross-arm charged for replacement method of the present invention, by the use of insulated platform as major insulation, makees The a whole set of individual's insulating protection apparatus of industry librarian use, uses insulating glove direct maintenance, using insulation masking Work tool to powered Equipment carries out the masking of correlation, carries out changing so as to directly contact electrical body, installment work, and holds insulating bar operation legal person Member is play a part of to undertake interim fixed and is supported to electrical body using insulating mast assembly.Allow operating distribution line normal Power supply, reduces the frequency of power cut of main line, it is ensured that power supply reliability, can realize the economic benefit of many power supplies, and can be really Continued power is protected, is the more economic worths of social creativity.
Below in conjunction with and specific embodiment the present invention is described in further detail.
Specific embodiment
, so that XX becomes the needs replacing of XX10 KV 10# bar cross-arms seriously corroded as an example, current circuit is also not for the present embodiment Generation cross-arm severe bends phenomenon, is such as changed without causing straight line pole cross-arm to rupture, so as to causing line-to-earth fault, having a power failure, Influence area circuit has high voltage customer 30, and the load current of circuit is 200 amperes.Livewire work class is found at prospecting scene Aerial lift device with insulated arm can not reach job site, it is determined that using insulated platform and insulating tool indirect operating method straight line pole cross-arm.
A kind of distribution line straight line pole cross-arm charged for replacement method, comprises the steps:
1)Insulated platform is installed in the position that safe distance is kept with electrical body first;
2)Insulation masking is carried out to the electrical body in working range, grounding body directly using insulating glove, it is ensured that operation area Domain construction safety, the electrical body, grounding body in working range are specially wire, cross-arm, insulator;
3)Both arms insulating mast assembly is installed:The top and bottom of both arms insulating mast assembly are fixed respectively;
4)Live wire is inserted in the wire draw-in groove of both arms insulating mast assembly, and lifting lead wire, receive both arms insulating mast assembly Power;
5)Binding of the colligation on linear rod insulator is released using insulating glove;
6)Lift live wire:Using insulation operation handle, the insulation rocking bar of both arms insulating mast assembly is operated, live wire is made In position high up in the air, live wire is more than 20 centimetres from linear rod insulator minimum safe distance, and then guarantees insulated platform Upper operating personnel's minimum job safety distance;
7)Linear rod insulator is removed by insulating glove, and has recovered the insulation masking of iron cross arm;
8)Transfer insulated platform:Insulated platform is gone to and do not remove linear rod insulator side;
9)Repeat the above steps 5)-7)Opposite side linear rod insulator is removed, and has recovered the insulation masking of iron cross arm;
10)Live wire on both arms insulating mast assembly temporary support straight line pole cross-arm, and carry out the insulation masking of electrical body;
11)Straight line pole cross-arm is changed, iron cross arm must be carried out all insulation maskings, there must not be larger bare spots before installing
12)It is fitted into the linear rod insulator of side;
13)By the operation handle of both arms insulating mast assembly, live wire is drop in linear rod insulator draw-in groove, and protect Hold in same horizontal line;
14)By live wire colligation on porcelain vase, and recover insulation masking;
15)Repeat the above steps 12)-14)The linear rod insulator for completing opposite side is installed;
16)Remove both arms insulating mast assembly:The insulation arm of both arms insulating mast assembly is retracted to initial position, removes both arms insulation and embraces The fixing device of bar top and bottom, and drop to ground;
17)The insulation masking of operating area is removed using insulating glove, dismounting order is by as far as near, from top to bottom, first Electrical body, rear grounding body;
18)Insulated platform is removed, whole straight line pole cross-arm charged for replacement process terminates.
1 calculation on Construction, I=200A, U=10Kv, T=national grid regulation interruption maintenance time are 4 hours, COS= 0.9, can many delivery P=UICOST, W=PT, so being calculated many deliveries for 12470 kilowatts. when electricity, stop less When 105. amount.Regulation and control personnel, switch operation personnel, the workload of line maintenance personnel can be reduced simultaneously.
The product form and style of above-described embodiment the non-limiting present invention, the ordinary skill people of any art Appropriate change or modification that member is done to which, all should be regarded as the patent category without departing from the present invention.

Claims (1)

1. a kind of distribution line straight line pole cross-arm charged for replacement method, it is characterised in that:Comprise the steps:
1)Insulated platform is installed in the position that safe distance is kept with electrical body first;
2)Insulation masking is carried out to the electrical body in working range, grounding body directly using insulating glove, it is ensured that apply operating area Work safety, the electrical body, grounding body in working range are specially wire, cross-arm, insulator;
3)Both arms insulating mast assembly is installed:The top and bottom of both arms insulating mast assembly are fixed respectively;
4)Live wire is inserted in the wire draw-in groove of both arms insulating mast assembly, and lifting lead wire, make both arms insulating mast assembly stress;
5)Binding of the colligation on linear rod insulator is released using insulating glove;
6)Lift live wire:Using insulation operation handle, the insulation rocking bar of both arms insulating mast assembly is operated, is in live wire Position high up in the air, live wire are more than 20 centimetres from linear rod insulator minimum safe distance, and then guarantee to make on insulated platform Industry personnel minimum job safety distance;
7)Linear rod insulator is removed by insulating glove, and has recovered the insulation masking of cross-arm;
8)Transfer insulated platform:Insulated platform is gone to and do not remove linear rod insulator side;
9)Repeat the above steps 5)-7)Opposite side linear rod insulator is removed, and has recovered the insulation masking of cross-arm;
10)Live wire on both arms insulating mast assembly temporary support straight line pole cross-arm, and carry out the insulation masking of electrical body;
11)Straight line pole cross-arm is changed, cross-arm must be carried out all insulation maskings, there must not be larger bare spots before installing
12)It is fitted into the linear rod insulator of side;
13)By the operation handle of both arms insulating mast assembly, live wire is drop in linear rod insulator draw-in groove, and be maintained at Same horizontal line;
14)By live wire colligation on the insulator, and recover insulation masking;
15)Repeat the above steps 12)-14)The linear rod insulator for completing opposite side is installed;
16)Remove both arms insulating mast assembly:The insulation arm of both arms insulating mast assembly is retracted to initial position, removes on both arms insulating mast assembly End and the fixing device of lower end, and drop to ground;
17)The insulation masking of operating area is removed using insulating glove, dismounting order be by as far as near, it is from top to bottom, first powered Body, rear grounding body;
18)Insulated platform is removed, whole straight line pole cross-arm charged for replacement process terminates.
CN201410721392.0A 2014-12-03 2014-12-03 A kind of distribution line straight line pole cross-arm charged for replacement method Active CN104538888B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410721392.0A CN104538888B (en) 2014-12-03 2014-12-03 A kind of distribution line straight line pole cross-arm charged for replacement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410721392.0A CN104538888B (en) 2014-12-03 2014-12-03 A kind of distribution line straight line pole cross-arm charged for replacement method

Publications (2)

Publication Number Publication Date
CN104538888A CN104538888A (en) 2015-04-22
CN104538888B true CN104538888B (en) 2017-03-29

Family

ID=52854380

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410721392.0A Active CN104538888B (en) 2014-12-03 2014-12-03 A kind of distribution line straight line pole cross-arm charged for replacement method

Country Status (1)

Country Link
CN (1) CN104538888B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104947953B (en) * 2015-05-21 2017-06-06 国家电网公司 A kind of 10kV transmission line cement poles replacing options and the interim bar of replacing
CN112366590B (en) * 2020-10-30 2022-03-01 国网山东省电力公司青岛供电公司 Replacing tool and replacing method for replacing horizontally-arranged strain pole cross arm in electrified mode
CN113675770B (en) * 2021-08-18 2022-10-18 贵州电网有限责任公司 Distribution network hot-line work quick replacement isolating switch, link control auxiliary device and method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101043557B1 (en) * 2010-01-18 2011-06-22 대원전기 주식회사 Crossarm holder applied in uninterupted method for replacement of utility pole without temporary move of wire and crossarm
CN102185265A (en) * 2011-05-13 2011-09-14 四川省电力公司绵阳电业局 Construction method for replacing cross arm of 35kV line linear rod
JP5335034B2 (en) * 2011-06-20 2013-11-06 中国電力株式会社 Arm changer
CN104113006A (en) * 2013-04-22 2014-10-22 江苏省电力公司常州供电公司 Operation method for replacing linear rod angle steel cross arm of 35kV overhead distribution line in live state

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101043557B1 (en) * 2010-01-18 2011-06-22 대원전기 주식회사 Crossarm holder applied in uninterupted method for replacement of utility pole without temporary move of wire and crossarm
CN102185265A (en) * 2011-05-13 2011-09-14 四川省电力公司绵阳电业局 Construction method for replacing cross arm of 35kV line linear rod
JP5335034B2 (en) * 2011-06-20 2013-11-06 中国電力株式会社 Arm changer
CN104113006A (en) * 2013-04-22 2014-10-22 江苏省电力公司常州供电公司 Operation method for replacing linear rod angle steel cross arm of 35kV overhead distribution line in live state

Also Published As

Publication number Publication date
CN104538888A (en) 2015-04-22

Similar Documents

Publication Publication Date Title
MX359131B (en) Lightning protection system for wind turbine blades with an effective injection area to carbon fiber laminates and a balanced lightning current and voltage distribution between different conductive paths.
CN104538888B (en) A kind of distribution line straight line pole cross-arm charged for replacement method
CN104538889A (en) Live-line replacing method of straight pole insulator of distribution network line
CN102931609A (en) Operation method for replacing 10kV drop-out fuse in on-load manner
CN109309358A (en) A kind of replacing options for hot line robot metal oxide arrester
CN105186370B (en) Straight line pole overhead transmission line take-up
CN204045469U (en) A kind of outdoor low voltage isolating switch combination unit
CN103199483A (en) Lightning arrester device capable of being dismounted and installed in charged state
CN203607749U (en) Shielding cover for distribution-line disconnecting switch
CN104577831A (en) Diverting tool and electrical equipment hotline maintenance method
CN103675540B (en) Shunt capacitor bank discharge device
PH12018500314A1 (en) Live conductor stringing, maintenance and repair method
CN206022675U (en) Universal shaped cable clamp earth lead
CN104426088A (en) Voltage transformer handcart
CN204332890U (en) With the fuse switch of electricity-detection grounding device
CN105305311A (en) Safety protection method for distribution line live work
CN203774609U (en) Simple overvoltage protection device
CN103944070B (en) Simple and easy overvoltage protection
CN204927951U (en) Dedicated line pincers of secondary circuit stereoplasm wire
CN205452910U (en) Electrified disappearing of GW7 type plug -in strip lacks specialized tool
CN204028109U (en) Lightning arrester live-line test instrument
CN105977861A (en) Charged work method for distribution line in high altitude area
CN204088982U (en) A kind of ground protection pincers
CN204144676U (en) A kind of protector
CN203911308U (en) Insulated operation rod head for mounting of insulated knife switch protection cover

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant