CN104526301B - Annular steel belt mounting unit and process of floor glue continuous forming machine - Google Patents

Annular steel belt mounting unit and process of floor glue continuous forming machine Download PDF

Info

Publication number
CN104526301B
CN104526301B CN201410807094.3A CN201410807094A CN104526301B CN 104526301 B CN104526301 B CN 104526301B CN 201410807094 A CN201410807094 A CN 201410807094A CN 104526301 B CN104526301 B CN 104526301B
Authority
CN
China
Prior art keywords
main heating
heating roller
mainframe
roller
steel belt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410807094.3A
Other languages
Chinese (zh)
Other versions
CN104526301A (en
Inventor
魏金富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Forward Machinery Co
Original Assignee
TIANJIN MESSCCOER TECHNOLOGY CONSULTING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN MESSCCOER TECHNOLOGY CONSULTING Co Ltd filed Critical TIANJIN MESSCCOER TECHNOLOGY CONSULTING Co Ltd
Priority to CN201410807094.3A priority Critical patent/CN104526301B/en
Publication of CN104526301A publication Critical patent/CN104526301A/en
Application granted granted Critical
Publication of CN104526301B publication Critical patent/CN104526301B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P19/00Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Coating Apparatus (AREA)

Abstract

The invention discloses an annular steel belt mounting unit of a floor glue continuous forming machine. The annular steel belt mounting unit comprises a base, a main rack, a machine base and a preheating section steel frame, wherein the main rack, the machine base and the preheating section steel frame are arranged on the base. The machine base is provided with a preheating roller. The outer side end of the main rack is provided with a compression roller mounting groove. A hydraulic drive cylinder for adjusting the left-right position of a compression roller is arranged in the compression roller mounting groove. The side, facing the preheating section steel frame, of the main rack is provided with a lifting device for adjusting the up-down position of an adjusting roller. The side, facing the preheating section steel frame, of the main rack is provided with a main heating roller groove for mounting a main heating roller. The main heating roller is arranged in the main heating roller groove. The main heating roller groove is formed below the lifting device. According to the annular steel belt mounting unit and process of the floor glue continuous forming machine, the lifting device and the hydraulic lifting cylinder are arranged to replace a crane or workers to adjust an annular steel belt in the longitudinal direction or the transverse direction, manpower and material resources are saved, the cost is lowered, and efficiency is improved.

Description

The ring-like steel band of floor glue continuous forming machine installs unit and mounting process
Technical field
The present invention relates to continuous offset plate production field, relate in particular to a kind of ring-like steel band of floor glue continuous forming machine Mounting process.
Background technology
When producing flooring laminate and continuous offset plate, raw material is granule, and preheated and pressurization forms continuous band shape system after preheating Product, this technological requirement completes to preheat on ring steel belt outer surface, heat up, pressurize, drawing, batch several procedures completes.
The mounting means of existing ring steel belt is:Ring steel belt is first pulled into long waist formula ring steel belt to both sides, then It is installed in fixing frame, because frame itself does not have the function of adjusting ring steel belt, can only pass through to drive a vehicle or artificial Ring steel belt is carried out lengthwise position or the regulation of lateral attitude.
Content of the invention
For the problems referred to above, the present invention provides a kind of ring-like steel band of floor glue continuous forming machine to install unit and erector Skill, to solve the problems of the prior art.
To achieve these goals, technical scheme is as follows:
A kind of ring-like steel band of floor glue continuous forming machine installs unit it is characterised in that including base and being arranged on bottom The mainframe in order to mounting ring steel band of model on seat, support, preheating section steelframe, preheating section steelframe be located at mainframe and support it Between, described support is provided with pre- hot-rolling, the outboard end of described mainframe offers backer roll mounting groove, and described backer roll is installed It is provided with to adjust the hydraulic drive cylinder of backer roll right position, the side towards preheating section steelframe of described mainframe in groove It is provided with to adjust the lowering or hoisting gear of adjustment roller upper-lower position;The side towards preheating section steelframe of described mainframe is provided with In order to install the main heating roller groove of main heating roller, main heating roller is arranged in this main heating roller groove, and described main heating roller groove is located at The lower section of lowering or hoisting gear.
In a preferred embodiment of the invention, described support is provided with and slides in order to the channel-section steel that pre- hot-rolling is installed Road.
In a preferred embodiment of the invention, the side towards preheating section steelframe of described mainframe be provided with so that The channel-section steel slideway installed in adjustment roller.
Using the ring-like steel band of floor glue continuous forming machine install unit ring-like steel band mounting process it is characterised in that Comprise the following steps:
A, by ring steel belt first to two side stretchings, form long waist formula ring steel belt;
B, long waist formula ring steel belt is set with mainframe above base, support, on preheating section steelframe;
C, the backer roll assembling is inserted in the backer roll mounting groove of mainframe, is placed in long waist formula annular steel Side;The pre- hot-rolling assembling is inserted on support, is placed in inside long waist formula annular steel;The adjustment assembling roller is inserted into On mainframe, it is placed in inside long waist formula annular steel;
D, by lowering or hoisting gear adjust adjustment roller upper-lower position;Adjust the left and right position of backer roll by hydraulic drive cylinder Put;
E, by suspender belt by main heating wheel be placed on pre- hot-rolling and adjustment roller between ring steel belt section outer fix, and to Move in main heating roller groove, drive ring steel belt to move into main heating roller groove, until main heating roller is in place.
The present invention passes through in upper setting in order to adjust the lowering or hoisting gear of adjustment roller upper-lower position, in order to adjust about backer roll The hydraulic drive cylinder of position, to substitute existing by driving a vehicle or manually carrying out ring steel belt is carried out lengthwise position or laterally The regulation of position, uses manpower and material resources sparingly, and reduces cost improves efficiency.
The feature of the present invention see the detailed description of this case schema and following preferable embodiment and obtains clearly Solution.
Brief description
Fig. 1 is the schematic diagram of the ring-like steel band installation main heating roller of units' installation of the floor glue continuous forming machine of the present invention.
Fig. 2 is the schematic diagram of the ring-like steel band installation unit of the floor glue continuous forming machine of the present invention.
Wherein, 1- mainframe;2- support;3- preheats steelframe;4- ring steel belt;5- hydraulic cylinder;8- channel-section steel slideway;9- lifts Device;10- base;The pre- hot-rolling of A-;B- adjusts roller;C- backer roll;The main heating roller of D-.
Specific embodiment
In order that technological means, creation characteristic, reached purpose and effect that the present invention realizes are easy to understand, tie below Close specific embodiment and the present invention is expanded on further.
Referring to Fig. 2, a kind of ring-like steel band of floor glue continuous forming machine installs unit, includes base 10 and is arranged on base On the mainframe 1 in order to mounting ring steel band of model, support 2, preheating section steelframe 3, preheating section steelframe 3 be located at mainframe 1 and support 2 Between.
Pre- hot-rolling A is provided with support 2.The channel-section steel slideway installed in order to pre- hot-rolling is provided with support.
The outboard end of mainframe 1 offers backer roll mounting groove, is provided with to adjust backer roll C in backer roll mounting groove The hydraulic drive cylinder 5 of right position, the side towards preheating section steelframe of mainframe is provided with to adjust bottom on adjustment roller B The lowering or hoisting gear 9 put;The side towards preheating section steelframe of mainframe is provided with the channel-section steel slideway 8 in order to adjust roller installation. The side towards preheating section steelframe of mainframe is provided with to install the main heating roller groove of main heating roller, and main heating roller is arranged on In this main heating roller groove, main heating roller groove is located at the lower section of lowering or hoisting gear.
Referring to Fig. 1 and 2, the ring-like steel band mounting process of unit is installed using the ring-like steel band of floor glue continuous forming machine, Comprise the following steps:
A, by ring steel belt first to two side stretchings, form long waist formula ring steel belt;
B, long waist formula ring steel belt 4 is set with mainframe 1 above base, support 2, on preheating section steelframe 3;
C, the backer roll assembling C is inserted in the backer roll mounting groove of mainframe, is placed in long waist formula annular steel Side;The pre- hot-rolling assembling is inserted A be contained on support, be placed in inside long waist formula annular steel;By the adjustment assembling roller B plug-in mounting On mainframe, it is placed in inside long waist formula annular steel;
D, by lowering or hoisting gear 9 adjust adjustment roller B upper-lower position;Adjust the left and right of backer roll C by hydraulic drive cylinder 5 Position;
E, by suspender belt by main heating wheel D be placed on pre- hot-rolling and adjustment roller between ring steel belt section outer fix, and Move into main heating roller groove, drive ring steel belt to move into main heating roller groove, until main heating roller is in place.
The present invention passes through in upper setting in order to adjust the lowering or hoisting gear of adjustment roller upper-lower position, in order to adjust about backer roll The hydraulic drive cylinder of position, to substitute existing by driving a vehicle or manually carrying out ring steel belt is carried out lengthwise position or laterally The regulation of position, uses manpower and material resources sparingly, and reduces cost improves efficiency.
Ultimate principle, principal character and the advantages of the present invention of the present invention have been shown and described above.The technology of the industry The simply present invention it should be appreciated that the present invention is not restricted to the described embodiments, described in above-described embodiment and description for the personnel Principle, without departing from the spirit and scope of the present invention the present invention also have various changes and modifications, these change and Improvement both falls within the range of claimed invention.The protection domain of application claims by appending claims and its Equivalent defines.

Claims (2)

1. a kind of ring-like steel band of floor glue continuous forming machine installs unit it is characterised in that including base and being arranged on base On the mainframe in order to mounting ring steel band of model, support, preheating section steelframe, preheating section steelframe be located between mainframe and support, Pre- hot-rolling is provided with described support, the outboard end of described mainframe offers backer roll mounting groove, described backer roll mounting groove Inside it is provided with to adjust the hydraulic drive cylinder of backer roll right position, the side towards preheating section steelframe of described mainframe sets It is equipped with to adjust the lowering or hoisting gear of adjustment roller upper-lower position;The side towards preheating section steelframe of described mainframe is provided with use To install the main heating roller groove of main heating roller, main heating roller is arranged in this main heating roller groove, and described main heating roller groove is located at and rises The lower section of falling unit,
The channel-section steel slideway installed in order to pre- hot-rolling is provided with described support,
The side towards preheating section steelframe of described mainframe is provided with the channel-section steel slideway in order to adjust roller installation.
2. unit is installed come the peace of mounting ring steel band of model using the ring-like steel band of the floor glue continuous forming machine described in claim 1 Dress technique is it is characterised in that comprise the following steps:
A, by ring steel belt first to two side stretchings, form long waist formula ring steel belt;
B, long waist formula ring steel belt is set with mainframe above base, support, on preheating section steelframe;
C, the backer roll assembling is inserted in the backer roll mounting groove of mainframe, is placed in inside long waist formula annular steel;Will The pre- hot-rolling assembling is inserted on support, is placed in inside long waist formula annular steel;The adjustment assembling roller is inserted into main frame On frame, it is placed in inside long waist formula annular steel;
D, by lowering or hoisting gear adjust adjustment roller upper-lower position;Adjust the right position of backer roll by hydraulic drive cylinder;
E, main heating wheel is placed on by ring steel belt section outer fix between pre- hot-rolling and adjustment roller by suspender belt, and to main plus Move in hot-rolling groove, drive ring steel belt to move into main heating roller groove, until main heating roller is in place.
CN201410807094.3A 2014-12-23 2014-12-23 Annular steel belt mounting unit and process of floor glue continuous forming machine Active CN104526301B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410807094.3A CN104526301B (en) 2014-12-23 2014-12-23 Annular steel belt mounting unit and process of floor glue continuous forming machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410807094.3A CN104526301B (en) 2014-12-23 2014-12-23 Annular steel belt mounting unit and process of floor glue continuous forming machine

Publications (2)

Publication Number Publication Date
CN104526301A CN104526301A (en) 2015-04-22
CN104526301B true CN104526301B (en) 2017-02-22

Family

ID=52842029

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410807094.3A Active CN104526301B (en) 2014-12-23 2014-12-23 Annular steel belt mounting unit and process of floor glue continuous forming machine

Country Status (1)

Country Link
CN (1) CN104526301B (en)

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2496911A (en) * 1945-06-07 1950-02-07 Shellmar Products Corp Method and apparatus for forming plastic laminates
US2784763A (en) * 1952-10-02 1957-03-12 Shorts Calhoun Method and apparatus for making fiberreinforced sheet material
US3038828A (en) * 1958-03-31 1962-06-12 Goodyear Tire & Rubber Decorative plastic floor covering or the like and method of making the same
NL274041A (en) * 1961-02-07
GB1300434A (en) * 1970-06-03 1972-12-20 Percy Sheard Method of and apparatus for longitudinally cutting webs of thermoplastic synthetic plastics material
US5466320A (en) * 1994-05-09 1995-11-14 Oscoda Plastics, Inc. Making a cushiony decorative tile or cover product from extruded recycled membrane with discrete fibers randomly dispersed therein
CN102935688B (en) * 2011-08-15 2015-11-18 上海泓阳机械有限公司 Continuous production device for color plastic floor and color plastic floor continuous producing method
CN103214704B (en) * 2013-04-09 2015-06-17 陕西秦力橡胶有限责任公司 Matte surface and semi-matte surface rubber flooring and manufacturing method and special equipment
CN203739093U (en) * 2014-03-19 2014-07-30 河源市品格环保材料科技有限公司 Thin film production system
CN204321519U (en) * 2014-12-23 2015-05-13 天津麦世科尔科技咨询有限公司 The ring-like steel band of floor glue continuous forming machine installs unit

Also Published As

Publication number Publication date
CN104526301A (en) 2015-04-22

Similar Documents

Publication Publication Date Title
PL2058154T3 (en) Frame for special vehicles
CN105345420B (en) A kind of undercarriage attaching/detaching apparatus
CN105063317A (en) Furnace roller installation device and furnace roller installation method
CN205112532U (en) Filter core is heat setting device for paper folder
CN104526301B (en) Annular steel belt mounting unit and process of floor glue continuous forming machine
CN204321519U (en) The ring-like steel band of floor glue continuous forming machine installs unit
CN206665759U (en) A kind of automatic transport crosses film device
CN206383186U (en) A kind of PVC foam plate cutter device
CN205736696U (en) A kind of adjustable hub extrusion of centre-to-centre spacing disassembles mechanism
CN205531075U (en) Waterproof roll paving device
CN204413504U (en) The dismounting of milling train HGC device is special to be attached
CN108081164A (en) Hard grinding wheel production line
CN206570216U (en) A kind of efficient hollow glass hollow glass aluminum frame positioner
CN203922587U (en) A kind of portable machine for dismounting tyre
CN205021984U (en) Shaping electric stove with flexible function
CN103979260B (en) Mechanism for stably conveying glass
CN203113794U (en) Automatic surface finishing and film spreading integrated machine
CN205895273U (en) Shield constructs quick hoist device in quick -witted section of jurisdiction
CN105436384A (en) Die replacing vehicle
CN206550131U (en) A kind of two-way curvature of the spinal column arbor press of double layer composite board
CN106124273B (en) Make the simulation rolling molding machine and test specimen production method of bitumen mixture specimen
CN205763112U (en) A kind of automobile side covering forming equipment
CN204525749U (en) A kind of sheet material building block separator
CN207026185U (en) Roll leveller
CN205631155U (en) Design film scalds limit equipment for shoes

Legal Events

Date Code Title Description
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230518

Address after: 201800 No. 783, Chengliu Road, Jiading District, Shanghai

Patentee after: Shanghai Forward Machinery Co.

Address before: No. 80, Erma Road, Hebei District, Tianjin 300142

Patentee before: TIANJIN MESSCCOER TECHNOLOGY CONSULTING Co.,Ltd.

TR01 Transfer of patent right