CN104484768A - Transverse comparison post-evaluation method for oil and gas pipeline engineering project - Google Patents

Transverse comparison post-evaluation method for oil and gas pipeline engineering project Download PDF

Info

Publication number
CN104484768A
CN104484768A CN201410838059.8A CN201410838059A CN104484768A CN 104484768 A CN104484768 A CN 104484768A CN 201410838059 A CN201410838059 A CN 201410838059A CN 104484768 A CN104484768 A CN 104484768A
Authority
CN
China
Prior art keywords
oil
engineering project
gas pipes
project
evaluated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410838059.8A
Other languages
Chinese (zh)
Inventor
赵强
郭炳睿
钱成文
温文
牛国富
仝兰欣
冯伟
张玉志
张晶晶
徐磊
崔琳
王连军
林涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Natural Gas Co Ltd
Original Assignee
China Petroleum and Natural Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Natural Gas Co Ltd filed Critical China Petroleum and Natural Gas Co Ltd
Priority to CN201410838059.8A priority Critical patent/CN104484768A/en
Publication of CN104484768A publication Critical patent/CN104484768A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning
    • Y02P90/82Energy audits or management systems therefor

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Development Economics (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Educational Administration (AREA)
  • Operations Research (AREA)
  • Marketing (AREA)
  • Game Theory and Decision Science (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a transverse comparison post-evaluation method for an oil and gas pipeline engineering project. The transverse comparison post-evaluation method comprises the steps that a first evaluation index factor of the oil and gas pipeline engineering project to be evaluated is acquired; normalization processing is performed on the first evaluation index factor and a second evaluation index factor of a comparing oil and gas pipeline engineering project; in a normalized environment, transverse comparison post-evaluation is performed on the oil and gas pipeline engineering project to be evaluated and the comparing oil and gas pipeline engineering project, so that a transverse comparison result of the oil and gas pipeline engineering project to be evaluated is obtained. It can be seen that the transverse comparison post-evaluation method for the oil and gas pipeline engineering project satisfies the requirements for transverse comparison methods of oil and gas pipeline engineering projects in the prior art, the obtained transverse comparison result of the oil and gas pipeline engineering project to be evaluated is objective and fair, conforms to actual production and construction, and the method can provide accurate analysis data for projects to be constructed, project under construction and constructed projects.

Description

A kind of oil and gas pipes engineering project across comparison Post-assessment Method
Technical field
The present invention relates to Economic Evaluation of Engineering Projects technical field, particularly relate to a kind of oil and gas pipes engineering project across comparison Post-assessment Method.
Background technology
Oil and gas pipes engineering project has life cycle, by work in preliminary project stage, construct and implement, the link such as the production and operation forms according to time sequencing successively organic linking.Each link of the project life cycle all needs the evaluation of the science of carrying out to prove, and just can guarantee smooth construction and the operation of project, and reach the expection benefit of project.Postevaluation is the important step of oil and gas pipes project evaluation.Rock gas and plumbing installations are gone on along in industry prostatitis in postevaluation work.Traditional oil and gas pipes project post evaluation work is mainly for unitem, work in preliminary project stage, project construction enforcement and operation are carried out front and back longitudinally contrast, with the realization of goal degree of clear and definite project, sum up experience and lessons, for instructing projects awaiting construction, adjust project in construction, improve constructed item and advise.Along with the transformation that postevaluation work extends from post-project evaluating to Sources controlling and Whole Course Management, propose the business demand to thoroughly evaluatings such as mark analysis, vertical and horizontal evaluation combinations.
Existing oil and gas pipes project post evaluation index system and method embody following limitation: oil and gas pipes project post evaluation carries out the postevaluation of unitem mostly, rarely have and carry out lateral comparison with project of the same type, supvr cannot understand the relative position of oil and gas pipes engineering project in the same industry, therefore, need badly a kind of method can carrying out across comparison to oil and gas pipes engineering project is provided.
Summary of the invention
The embodiment of the present invention, by providing a kind of oil and gas pipes engineering project across comparison Post-assessment Method, meets the demand of the method for in prior art, oil and gas pipes engineering project being carried out to across comparison.
Embodiments provide a kind of oil and gas pipes engineering project across comparison Post-assessment Method, comprising:
Obtain the first evaluation index factor of oil and gas pipes engineering project to be evaluated, wherein, the described first evaluation index factor is for characterizing investment evaluation parameter, quality assessment parameter, progress evaluating, healthy and safe EMS evaluating, evaluation of economic benefit parameter, at least one satisfied the demands in merit rating parameter, efficiency evaluating, equipment dependability evaluating, social impact assessment's parameter, Sustainability Assessment parameter of described oil and gas pipes engineering project to be evaluated;
Carry out sameization to the described first evaluation index factor with the second evaluation index factor of contrast oil and gas pipes engineering project to process, to ensure that, when carrying out across comparison postevaluation to described oil and gas pipes engineering project to be evaluated and described contrast oil and gas pipes engineering project, described oil and gas pipes engineering project to be evaluated and described contrast oil and gas pipes engineering project are in sameization environment;
Under described sameization environment, across comparison postevaluation is carried out to described oil and gas pipes engineering project to be evaluated and described contrast oil and gas pipes engineering project, obtains the across comparison result of described oil and gas pipes engineering project to be evaluated.
Alternatively, the described first evaluation index factor comprises final accounts with can grind and gives an written reply investment changing ratio, final accounts with just establish estimate changing ratio, investment per unit capacity level, unit project expense, unit passes through expense, unit project acceptance rate, engineering welds first-time qualification rate completely, stand field welding first-time qualification rate, the unit project average duration, construction period rate of change, accident rate, casualty rate, pollute incidence, net present value (NPV), be in debt and stockholder's equity ratio, on average every kilometer of repairing expense, on average sell and overhead cost for every kilometer, on average every kilometer of wage and welfare fund, the defeated out-of-pocket cost of unit tube, unit volume of the circular flow out-of-pocket cost, pipe loadings rate, manage defeated completion rate of the plan, pipe loss rate, the unexpected shutdown time, unit volume of the circular flow comprehensive energy consumption, unit throughput rate comprehensive energy consumption, pipeline year leaks number of times, mean time between failures, mean time to repair, Perfectness ratio of critical equipments, key equipment utilization factor, newly-increased employment volume ratio, the support equipment localization rate of parts and components, Energy restructuring, public's support, resource guarantee degree, self competitive power, technical advance and applicability, the market demand potential, at least one in macro policy impact.
Alternatively, describedly with contrast oil and gas pipes engineering project, sameization is carried out to described oil and gas pipes engineering project to be evaluated process, specifically comprise: by relevant function method and/or regression analysis, remove uncontrollable evaluation index factor in the described first evaluation index factor of the described oil and gas pipes engineering project to be evaluated of impact.
Alternatively, described across comparison postevaluation is carried out to described oil and gas pipes engineering project to be evaluated and described contrast oil and gas pipes engineering project time, described method also comprises: the weight being determined each evaluation index factor in the described first evaluation index factor by expert graded and/or analytical hierarchy process.
The one or more technical schemes provided in the embodiment of the present invention, at least have following technique effect or advantage:
Owing to have employed the first evaluation index factor obtaining oil and gas pipes engineering project to be evaluated, and with the second evaluation index factor of contrast oil and gas pipes engineering project, sameization is carried out to the first evaluation index factor process, and under sameization environment, across comparison postevaluation is carried out to oil and gas pipes engineering project to be evaluated and contrast oil and gas pipes engineering project, obtain the technical scheme of the across comparison result of oil and gas pipes engineering project to be evaluated, meet the demand of the method for in prior art, oil and gas pipes engineering project being carried out to across comparison, the across comparison result of the oil and gas pipes engineering project to be evaluated obtained is comparatively objective and just, meet the reality of production and construction, can be projects awaiting construction, project in construction and constructed item provide analyzes data accurately.
Accompanying drawing explanation
The process flow diagram of the oil and gas pipes engineering project across comparison Post-assessment Method that Fig. 1 provides for the embodiment of the present invention;
What Fig. 2 provided for the embodiment of the present invention carries out to the first evaluation index factor and the second evaluation index factor of contrast oil and gas pipes engineering project the schematic diagram that sameization process;
The process flow diagram of the structure regression model that Fig. 3 provides for the embodiment of the present invention.
Embodiment
Embodiments provide a kind of across comparison Post-assessment Method of oil and gas pipes engineering project, meet the demand of the method for in prior art, oil and gas pipes engineering project being carried out to across comparison.
Please refer to Fig. 1, Fig. 1 is the schematic diagram of the across comparison Post-assessment Method of the oil and gas pipes engineering project that the embodiment of the present invention provides, and as shown in Figure 1, the method comprises:
S1: the first evaluation index factor obtaining oil and gas pipes engineering project to be evaluated, wherein, the first evaluation index factor is for characterizing investment evaluation parameter, quality assessment parameter, progress evaluating, healthy and safe EMS evaluating, evaluation of economic benefit parameter, at least one satisfied the demands in merit rating parameter, efficiency evaluating, equipment dependability evaluating, social impact assessment's parameter, Sustainability Assessment parameter of oil and gas pipes engineering project to be evaluated;
S2: with the second evaluation index factor of contrast oil and gas pipes engineering project, sameization is carried out to the first evaluation index factor and processes, to ensure that, when carrying out across comparison postevaluation to oil and gas pipes engineering project to be evaluated and contrast oil and gas pipes engineering project, oil and gas pipes engineering project to be evaluated and contrast oil and gas pipes engineering project are in sameization environment;
S3: under sameization environment, carries out across comparison postevaluation to oil and gas pipes engineering project to be evaluated and contrast oil and gas pipes engineering project, obtains the across comparison result of oil and gas pipes engineering project to be evaluated.
Before introducing the method that the embodiment of the present invention provides, need the assessment indicator system of the method setting up the postevaluation of oil and gas pipes engineering project across comparison, in specific implementation process, the System of Comprehensive Evaluation comprising destination layer, evaluate layer, analysis layer and operation layer can be set up, to the illustrated in table 1 of each index according to the principle such as independence, comprehensive, dynamic, operability, fixed guantity combining with fixed quality.
Table 1 assessment indicator system table
Certainly, assessment indicator system table shown in table 1 is an example, by the introduction of the present embodiment, technician belonging to this area can according to actual conditions, partial data is wherein adjusted, such as increase or delete some evaluation index etc., to meet the needs of actual conditions, not limiting at this.
After setting up above-mentioned assessment indicator system, the across comparison Post-assessment Method of the oil and gas pipes engineering project that the embodiment of the present invention provides, enters S1, that is: obtain the first evaluation index factor of oil and gas pipes engineering project to be evaluated.
In S1, specifically, namely according to the assessment indicator system shown in table 1, obtain the first evaluation index factor of oil and gas pipes engineering project to be evaluated, as shown in table 1, the first evaluation index factor comprises final accounts and can grind gives an written reply investment changing ratio, final accounts with just establish estimate changing ratio, investment per unit capacity level, unit project expense, unit passes through expense, unit project acceptance rate, engineering welds first-time qualification rate completely, stand field welding first-time qualification rate, the unit project average duration, construction period rate of change, accident rate, casualty rate, pollute incidence, net present value (NPV), be in debt and stockholder's equity ratio, on average every kilometer of repairing expense, on average sell and overhead cost for every kilometer, on average every kilometer of wage and welfare fund, the defeated out-of-pocket cost of unit tube, unit volume of the circular flow out-of-pocket cost, pipe loadings rate, manage defeated completion rate of the plan, pipe loss rate, the unexpected shutdown time, unit volume of the circular flow comprehensive energy consumption, unit throughput rate comprehensive energy consumption, pipeline year leaks number of times, mean time between failures, mean time to repair, Perfectness ratio of critical equipments, key equipment utilization factor, newly-increased employment volume ratio, the support equipment localization rate of parts and components, Energy restructuring, public's support, resource guarantee degree, self competitive power, technical advance and applicability, the market demand potential, at least one in macro policy impact, and the first evaluation index factor is for characterizing the investment evaluation parameter of oil and gas pipes engineering project to be evaluated, quality assessment parameter, progress evaluating, healthy and safe EMS evaluating, evaluation of economic benefit parameter, satisfy the demands merit rating parameter, efficiency evaluating, equipment dependability evaluating, social impact assessment's parameter, at least one in Sustainability Assessment parameter.
After S1, the across comparison Post-assessment Method of the oil and gas pipes engineering project that the embodiment of the present invention provides enters S2, that is: carry out sameization to the first evaluation index factor with the second evaluation index factor of contrast oil and gas pipes engineering project and process.
Oil and gas pipes project construction operation is a huge engineering, and the various aspects such as time, length, investment, trend of different pipe-line construction are not quite similar.Therefore, objective, just in order to ensure the evaluation result done by oil and gas pipes engineering project to be evaluated, need the second evaluation index factor of the first evaluation index Summing Factor contrast oil and gas pipes engineering project of oil and gas pipes engineering project to be evaluated to carry out sameization process.
Specifically, the factor of impact construction and operation link can be divided into two classes: controllable factor and uncontrollable factor.Sameization process is carried out to the second evaluation index factor of the first evaluation index Summing Factor contrast oil and gas pipes engineering project by oil and gas pipes engineering project to be evaluated, also namely by distinguishing and identifying this two classes factor, the uncontrollable factor affecting oil and gas pipes project operation effect is weeded out, remaining controllable factor, different oil and gas pipes is made to be compare in identical project external condition i.e. " sameization " environment, the comparability of oil and gas pipes project is improved, the result of lateral comparison is more objective, just, the actual conditions of project operation of more fitting.
In actual applications, the controlled evaluation index factor in macroscopic view exactly by people the evaluation index factor variable that can control, constantly can adjust in the process of social change the evaluation index factor.As the term suggests uncontrollable evaluation index factor be namely " people " can not and variable, condition can not be waited by experiment to carry out changing the factor.Then be present in microcosmic point for oil and gas pipes project or oil and gas pipes Project business, the controlled evaluation index factor is exactly the variable that can be taken on a new look by enterprise's self-condition and control.Because enterprise is present in microcosmic point, its existence can be subject to the impact of higher level department or national strategy after all, uncontrollable evaluation index factor of enterprise level then contains some controlled evaluation index factor macroscopically, such as " policy ", " price " etc.
Certainly, it is to be noted: one is that some controlled evaluation index factor macroscopically becomes uncontrollable evaluation index factor in the microcosmic point of enterprise, even if two is that we have marked off the controlled uncontrollable evaluation index factor of evaluation index Summing Factor in microcosmic point, but along with the transformation of national policy or economic situation, some the evaluation index factor may controlled and uncontrollable between occur " conversion ", such as " price ", it is uncontrollable evaluation index factor at present, it is the result of government macro-control, along with deepening continuously of China market process, market will play decisive role, when accounting for leading role in future market, price is possible just forward controlled evaluation index to because of sub-queue by uncontrollable evaluation index factor.
Please refer to table 2, table 2 is the controllability sorted tables of the evaluation index factor that the embodiment of the present invention provides.
The controllability classification of the table 2 evaluation index factor
Of course, the classification results shown in table 2 is also only used to introduce the across comparison Post-assessment Method of the oil and gas pipes engineering project that the embodiment of the present invention provides and the example provided, instead of for limiting the present invention.
In specific implementation process, please refer to Fig. 2, Fig. 2 be the embodiment of the present invention provide the schematic diagram that sameization process is carried out to the first evaluation index factor and the second evaluation index factor of contrast oil and gas pipes engineering project, as shown in Figure 2, first, project original case and data are obtained; Then, project influence factor is identified, distinguish project oneself factor and project environment factor; Then, carry out regretional analysis to the oneself factor of project and environmental factor, and determine regression coefficient by statistical significance inspection, namely the index do not checked by statistical significance rejects failure; Finally, data are rejected and revises, namely can obtain the comparable data of " purely " oil and gas pipes engineering project oneself factor, carry out the data of across comparison postevaluation by these comparable data as oil and gas pipes engineering project to be evaluated and contrast oil and gas pipes engineering project.
In ensuing part, for price factor and other factors, the process of data being carried out to sameization process will be explained.
Price factor is carried out to the process of sameization process: two are mainly contained to the price index relevant with petroleum gas, one is fixed assets devaluation preparation, one is PPI (petroleum industry price index), cost standardised theory is used to set up the benchmark of across comparison, the price index of nineteen ninety-five is set to 100, wherein convert according to chain rate ratio, derive each year price index, please refer to table 3, table 3 is price index tables that the embodiment of the present invention provides, convert according to the price factor of the price index table shown in table 3 to oil and gas pipes engineering project to be evaluated, namely complete and sameization of this evaluation index factor of price is processed.
Table 3 price index table
Other factors are carried out to the process of sameization process:
By the method for econometrics, find the explanation variable and explained variable, some needs dummy variable.Select suitable sample to carry out regretional analysis, its regression model (being main in linear form) can be:
Y=α 01X 12X 23X 3+…+u
Y is explained variable, and X is explanatory variable, and u is Disturbance, α 0constant term, α i(i=1,2,3 ...) be regression coefficient.
Certainly, it should be noted that, above-mentioned regression model is an example, the concrete building process of regression model please refer to Fig. 3, Fig. 3 is the process flow diagram of the structure regression model that the embodiment of the present invention provides, and as shown in Figure 3, the building process of regression model can comprise: first, choose variable, variable here comprises explained variable and explanatory variable; Then, regression model is set; Then, carry out model estimation, if model is estimated not pass through, then model is adjusted, reset model; Secondly, if model is estimated to pass through, then carry out model testing, also substitute into by sample data, if model testing is not passed through, then model is re-started and estimate or reset regression model, until model testing is passed through.
When selecting econometric model, be analyze a certain explained variable, finding out the several explanatory variables relevant to explained variable, is the investigation of single index or object, is not the analysis to project entirety.Like this, just need from regression coefficient in the influence factor (explanatory variable rejecting) to single index.
Carry out according to model form returning the regression forms obtaining model:
Y ‾ = α 0 + α 1 X ‾ 1 + α 2 X ‾ 2 + α 3 X ‾ 3 + α 4 X ‾ 4 + · · · + u ‾ ;
Wherein, α i(i=1,2,3 ...) then illustrate relation between Y and X.
As: α 1 = dY dX , Being write as difference form is then: α 1 = dY dX = Y 2 - Y 1 X 2 - X 1
That is: Y 2-Y 11(X 2-X 1), Y 21(X 2-X 1)+Y 1
After recurrence then: Y ‾ 2 = α ‾ 1 ( X 2 - X 1 ) + Y 1
Explained variable Y original like this 2just " sameization " is
When next step contrasts, contrast according to the data after " sameization " exactly.
Of course, in specific implementation process, objective and just in order to what ensure the evaluation result done by oil and gas pipes engineering project to be evaluated further, when carrying out across comparison postevaluation to oil and gas pipes engineering project to be evaluated and contrast oil and gas pipes engineering project, the across comparison Post-assessment Method of the oil and gas pipes engineering project that the embodiment of the present invention provides also comprises:
The weight of each evaluation index factor in the first evaluation index factor is determined by expert graded and/or analytical hierarchy process.
Specifically, in conjunction with oil and gas pipes project post evaluation experience, by expert graded and/or analytical hierarchy process, the each level significance level of oil and gas pipes project post evaluation index system is calculated, analyzed, determine the weight of each level, please refer to table 4, table 4 is weight schematic diagram of the oil and gas pipes engineering project of the oil and gas pipes engineering project that the embodiment of the present invention provides.
Table 4 assessment indicator system weight distribution
When carrying out across comparison postevaluation to oil and gas pipes engineering project to be evaluated and contrast oil and gas pipes engineering project, the first evaluation index factor of weight distribution shown in employing table 4 to oil and gas pipes engineering project to be evaluated adjusts, make the more realistic ratio of importance that in the first evaluation index factor, each index factor is shared when evaluating, thus make the final across comparison evaluation result obtained more objective and just.
After carrying out sameization process by the second evaluation index factor of S2 to the first evaluation index Summing Factor contrast oil and gas pipes engineering project of oil and gas pipes engineering project to be evaluated, the across comparison Post-assessment Method of the oil and gas pipes engineering project that the embodiment of the present invention provides enters S3, that is: under sameization environment, across comparison postevaluation is carried out to oil and gas pipes engineering project to be evaluated and contrast oil and gas pipes engineering project, obtains the across comparison result of oil and gas pipes engineering project to be evaluated.
Specifically, in " sameization " environment, the index factor in index for selection system, across comparison similar pumped (conveying) medium pipework project implementation effect, draws comprehensive evaluation result.
For certain West Products Pipeline and certain east products pipeline, choose the defeated income of unit tube in economic benefit for contrast index, according to the result of calculation of certain West Products Pipeline and certain east products pipeline oneself factor separately, certain West Products Pipeline and certain east defeated income of products pipeline unit tube are 129.69 ten thousand yuan/ton and 132.08 ten thousand yuan/ton respectively, difference is-2.39 ten thousand yuan/ton, is also that the defeated income of unit tube of West Products Pipeline is lower than the defeated income of east products pipeline unit tube 2.39 ten thousand yuan/ton.
Using region as dummy variable, regression model is built according to the flow process shown in Fig. 3, the difference calculating certain West Products Pipeline and the defeated income of certain east products pipeline unit tube is 12.5 ten thousand yuan/ton (" sameization " values), namely the defeated income difference of unit tube rejected after regional effect is-2.39+12.5=10.11 (ten thousand yuan/ton), is also that the defeated income of unit tube of West Products Pipeline is higher than the defeated income of east products pipeline unit tube 10.11 ten thousand yuan/ton.
Can find out, owing to have employed the first evaluation index factor obtaining oil and gas pipes engineering project to be evaluated, and with the second evaluation index factor of contrast oil and gas pipes engineering project, sameization is carried out to the first evaluation index factor process, and under sameization environment, across comparison postevaluation is carried out to oil and gas pipes engineering project to be evaluated and contrast oil and gas pipes engineering project, obtain the technical scheme of the across comparison result of oil and gas pipes engineering project to be evaluated, meet the demand of the method for in prior art, oil and gas pipes engineering project being carried out to across comparison, the across comparison result of the oil and gas pipes engineering project to be evaluated obtained is comparatively objective and just, meet the reality of production and construction, can be projects awaiting construction, project in construction and constructed item provide analyzes data accurately.
Technical scheme in the invention described above embodiment, at least has following technique effect or advantage:
Owing to have employed the first evaluation index factor obtaining oil and gas pipes engineering project to be evaluated, and with the second evaluation index factor of contrast oil and gas pipes engineering project, sameization is carried out to the first evaluation index factor process, and under sameization environment, across comparison postevaluation is carried out to oil and gas pipes engineering project to be evaluated and contrast oil and gas pipes engineering project, obtain the technical scheme of the across comparison result of oil and gas pipes engineering project to be evaluated, meet the demand of the method for in prior art, oil and gas pipes engineering project being carried out to across comparison, the across comparison result of the oil and gas pipes engineering project to be evaluated obtained is comparatively objective and just, meet the reality of production and construction, can be projects awaiting construction, project in construction and constructed item provide analyzes data accurately.
Obviously, those skilled in the art can carry out various change and modification to the present invention and not depart from the spirit and scope of the present invention.Like this, if these amendments of the present invention and modification belong within the scope of the claims in the present invention and equivalent technologies thereof, then the present invention is also intended to comprise these change and modification.

Claims (4)

1. an across comparison Post-assessment Method for oil and gas pipes engineering project, is characterized in that, comprising:
Obtain the first evaluation index factor of oil and gas pipes engineering project to be evaluated, wherein, the described first evaluation index factor is for characterizing investment evaluation parameter, quality assessment parameter, progress evaluating, healthy and safe EMS evaluating, evaluation of economic benefit parameter, at least one satisfied the demands in merit rating parameter, efficiency evaluating, equipment dependability evaluating, social impact assessment's parameter, Sustainability Assessment parameter of described oil and gas pipes engineering project to be evaluated;
Carry out sameization to the described first evaluation index factor with the second evaluation index factor of contrast oil and gas pipes engineering project to process, to ensure that, when carrying out across comparison postevaluation to described oil and gas pipes engineering project to be evaluated and described contrast oil and gas pipes engineering project, described oil and gas pipes engineering project to be evaluated and described contrast oil and gas pipes engineering project are in sameization environment;
Under described sameization environment, across comparison postevaluation is carried out to described oil and gas pipes engineering project to be evaluated and described contrast oil and gas pipes engineering project, obtains the across comparison result of described oil and gas pipes engineering project to be evaluated.
2. the method for claim 1, is characterized in that, the described first evaluation index factor comprises final accounts and can grind gives an written reply investment changing ratio, final accounts with just establish estimate changing ratio, investment per unit capacity level, unit project expense, unit passes through expense, unit project acceptance rate, engineering welds first-time qualification rate completely, stand field welding first-time qualification rate, the unit project average duration, construction period rate of change, accident rate, casualty rate, pollute incidence, net present value (NPV), be in debt and stockholder's equity ratio, on average every kilometer of repairing expense, on average sell and overhead cost for every kilometer, on average every kilometer of wage and welfare fund, the defeated out-of-pocket cost of unit tube, unit volume of the circular flow out-of-pocket cost, pipe loadings rate, manage defeated completion rate of the plan, pipe loss rate, the unexpected shutdown time, unit volume of the circular flow comprehensive energy consumption, unit throughput rate comprehensive energy consumption, pipeline year leaks number of times, mean time between failures, mean time to repair, Perfectness ratio of critical equipments, key equipment utilization factor, newly-increased employment volume ratio, the support equipment localization rate of parts and components, Energy restructuring, public's support, resource guarantee degree, self competitive power, technical advance and applicability, the market demand potential, at least one in macro policy impact.
3. method as claimed in claim 2, is characterized in that, describedly carries out sameization to described oil and gas pipes engineering project to be evaluated with contrast oil and gas pipes engineering project and processes, and specifically comprises:
By relevant function method and/or regression analysis, remove uncontrollable evaluation index factor in the described first evaluation index factor of the described oil and gas pipes engineering project to be evaluated of impact.
4. method as claimed in claim 2, is characterized in that, described across comparison postevaluation is carried out to described oil and gas pipes engineering project to be evaluated and described contrast oil and gas pipes engineering project time, described method also comprises:
The weight of each evaluation index factor in the described first evaluation index factor is determined by expert graded and/or analytical hierarchy process.
CN201410838059.8A 2014-12-29 2014-12-29 Transverse comparison post-evaluation method for oil and gas pipeline engineering project Pending CN104484768A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410838059.8A CN104484768A (en) 2014-12-29 2014-12-29 Transverse comparison post-evaluation method for oil and gas pipeline engineering project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410838059.8A CN104484768A (en) 2014-12-29 2014-12-29 Transverse comparison post-evaluation method for oil and gas pipeline engineering project

Publications (1)

Publication Number Publication Date
CN104484768A true CN104484768A (en) 2015-04-01

Family

ID=52759309

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410838059.8A Pending CN104484768A (en) 2014-12-29 2014-12-29 Transverse comparison post-evaluation method for oil and gas pipeline engineering project

Country Status (1)

Country Link
CN (1) CN104484768A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113869787A (en) * 2021-10-19 2021-12-31 中国电建集团成都勘测设计研究院有限公司 Engineering project comprehensive management and control and evaluation method based on information system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113869787A (en) * 2021-10-19 2021-12-31 中国电建集团成都勘测设计研究院有限公司 Engineering project comprehensive management and control and evaluation method based on information system

Similar Documents

Publication Publication Date Title
Wang et al. The design and implementation of risk assessment model for hazard installations based on AHP–FCE method: A case study of Nansi Lake Basin
Wicher et al. A computer simulation-based analysis of supply chains resilience in industrial environment
Hu et al. BIM-based data mining approach to estimating job man-hour requirements in structural steel fabrication
CN111859779A (en) Early warning method and device for preventing third-party construction damage risk of gas pipe network
Jafarpour et al. Analysis of environmental costs’ effect in green mining strategy using a system dynamics approach: a case study
Sajwani et al. The application of the environmental management system at the aluminum industry in UAE
Teh et al. Integrated carbon metrics and assessment for the built environment
CN104484768A (en) Transverse comparison post-evaluation method for oil and gas pipeline engineering project
Sheng et al. Risk assessment of urban gas pipeline based on different unknown measure functions
Dragan Fuzzy-DEA model for measuring the efficiency of transport quality
Zheng et al. A set pair analysis approach for dynamic risk assessment of tailings dam failure
Christodoulou et al. Urban water distribution networks: assessing systems vulnerabilities, failures, and risks
Dong et al. Application of causal analysis method in quality management of the Maozhou River rehabilitation project
Ghaleb et al. Using fuzzy logic and discrete event simulation to enhance production lines performance: case study
Sarhangian et al. Optimizing inspection strategies for multi-stage manufacturing processes using simulation optimization
Ganji et al. Identifying and Assessing the Risks in the Supply Chain
Akinyemi et al. Development of system dynamics based simulation models for runway safety planning
Kulińska et al. New application of FMEA analysis in the heavy industry supply chain
Susanti et al. Factor and Barrier Implementing Building Information Modelling (BIM) in Green Construction in Indonesia
Kralikova et al. Framework for applying six sigma methods within environmental management
Mokhira DEVELOPMENT OF EFFECTIVE METHODS AS A RESULT OF THE USE OF INSTRUMENTAL TECHNICAL TECHNIQUES AND TECHNOLOGICAL SOLUTIONS TO IDENTIFY THE DEPRECIATION OF RESIDENTIAL BUILDINGS
CN112785206B (en) Metal industry pollution enterprise influence range simulation and risk assessment method
Mousa et al. APPLYING SUSTAINABILITY BY MULTIDISCIPLINARY TARGETS
Suo et al. A Study on Evaluating Water Resources System Vulnerability by Reinforced Ordered Weighted Averaging Operator
Jahanikia et al. Decision-Making for Crisis Management of Power Distribution Networks.

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150401