CN104481541B - One-inclined multi-vertical cascaded well group salt mine mining method - Google Patents

One-inclined multi-vertical cascaded well group salt mine mining method Download PDF

Info

Publication number
CN104481541B
CN104481541B CN201410692019.7A CN201410692019A CN104481541B CN 104481541 B CN104481541 B CN 104481541B CN 201410692019 A CN201410692019 A CN 201410692019A CN 104481541 B CN104481541 B CN 104481541B
Authority
CN
China
Prior art keywords
well
straight
salt
group
axis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410692019.7A
Other languages
Chinese (zh)
Other versions
CN104481541A (en
Inventor
樊传忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA SALT PROSPECTING DESIGN INSTITUTE Co Ltd
Original Assignee
CHINA SALT PROSPECTING DESIGN INSTITUTE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA SALT PROSPECTING DESIGN INSTITUTE Co Ltd filed Critical CHINA SALT PROSPECTING DESIGN INSTITUTE Co Ltd
Priority to CN201410692019.7A priority Critical patent/CN104481541B/en
Publication of CN104481541A publication Critical patent/CN104481541A/en
Application granted granted Critical
Publication of CN104481541B publication Critical patent/CN104481541B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/20Methods of underground mining; Layouts therefor for rock salt or potash salt

Abstract

The invention discloses a one-inclined multi-vertical cascaded well group salt mine mining method. A well group axis is designed according to the mine bed depth of a salt mine; a first vertical well at the end part of the axis is drilled to establish a first salt groove; an oriented horizontal well is drilled at the other end of the axis; drilling is carried in a salt layer along the axis, and the oriented horizontal well is in butt joint communication with the first vertical well; a second salt groove is established and a second vertical well is drilled so that a pair of communicated wells are formed by the first vertical well and the second vertical well; and one or more pairs of communicated wells are reconstructed until the final vertical well is established, so that a pair of circulating wells is formed by the final vertical well and the oriented horizontal well. According to the one-inclined multi-straight cascaded well group salt mine mining method, the oriented horizontal well with the large displacement is drilled and is communicated with the plurality of vertical wells to form a plurality of double-well well sets, so that the inclined section construction of a drilling well is reduced, and the respective advantages of the vertical walls and the oriented horizontal well are sufficiently developed; the problems that the oriented horizontal well occupies excessive resources and a well shaft is easy to damage are solved; and an accident that the oriented well is blocked in a salt mining process is reduced, and the safety production level and the mining efficiency of the salt well are improved.

Description

How one tiltedly directly concatenate well group salt well accident methods
Technical field
The present invention relates to a kind of salt deposit drilling solution mining technology, how specifically a kind of one tiltedly directly concatenate well group salt mines Recovery method.
Background technology
Horizontally-butted wells recovery method is to utilize directed-drilling technique, and Drilling straight well and directional horizontal wellss are in salt deposit Form lysate circulation canal exploitation salts resources.At present in well mine salt industry dissolution mining by drilling technical field, level is docked Well recovery method has been widely used.
In existing level butt shaft technology, typically using a bevelled halving well always, or diclinic butt shaft.Salt mine level In butt shaft mining Practice, typically with directional horizontal wellss, that is, directional well often breaks down, such as the destruction of inclination section middle sleeve, Inclination section is exposed the problems such as collapse, block, and the problems referred to above constrain the mining progress of salt mine significantly.
Content of the invention
It is an object of the invention to provide how a kind of one tiltedly directly concatenate well group salt well accident methods, by boring a bite big displacement Directional horizontal wellss, connect with many mouthfuls of straight wells, formed multiple twin-well well groups, greatly reduce drilling well inclination section construction, fully Play straight well and the respective advantage of directional horizontal wellss, the occupancy resource solving directional horizontal wellss is excessively more easily damaged with pit shaft Problem, reduce occur during salt adopted by directional well block accident, improve salt well safety in production level and mining effect Rate.
For achieving the above object, the present invention provides following technical scheme:
How a kind of one tiltedly directly concatenate well group salt well accident methods, concretely comprises the following steps:
1) the mineral deposit depth according to salt mine, designs a well group axis, determines the logarithm of halogen well on axis, subdrilling axis end The first straight well Z1 in portion, and correspondence builds first salt bath in salt deposit;
2) other end in above-mentioned axis bores directional horizontal wellss X1, creeps into along axis, with first straight well Z1 in salt deposit It is docked and connected;
3) drilling tool in directional horizontal wellss X1 is returned and drag a well spacing, build second salt bath, away from first on well group axis At mouthful mono- well spacing of straight well Z1, bore second straight well Z2, be docked and connected with second salt bath so that first straight well Z1 and second Mouth straight well Z2 constitutes a pair of connected well, enters circulation and adopts halogen production;
4) drilling tool in directional horizontal wellss X1 is returned to drag and reach a well group distance, build the 3rd salt bath, on well group axis At mono- well group distance of second mouthful of straight well Z2, bore the 3rd mouthful of straight well Z3;
5) drilling tool in directional horizontal wellss X1 is returned and drag a well spacing, build the 4th salt bath, away from the 3rd on well group axis At mouth mono- well spacing of straight well Z3, bore the 4th mouthful of straight well Z4 so that the 3rd mouthful of straight well Z3 and the 4th mouthful of straight well Z4 constitutes a pair of connection Well, enters circulation and adopts halogen production;
6) repeat to build one or more pairs of connected wells, until last a bite straight well Zn, constitute a pair with directional horizontal wellss X1 Circulation well, realizes once orientation big displacement directional horizontal wellss X1 and multiple straight well Z1~Zn and is docked and connected, constitute multipair circulation and adopt Halogen well.
As the further scheme of the present invention:Described step 3) and step 5) in, well spacing is constitute a pair of connected well two The distance between mouth straight well, well spacing is 50-150 rice.
As the further scheme of the present invention:Described step 3) and step 5) in, well group distance for adjacent connected well it Between distance, well group distance is 100-300 rice.
As the further scheme of the present invention:Described step 6) in, between last a bite straight well Zn and directional horizontal wellss X1 Distance be 150-350 rice.
As the further scheme of the present invention:Described step 4) and step 6) it is additionally included in water between adjacent connected well In flat section, injection cement mortar forms cement plug, for blocking the passage in salt deposit, it is to avoid adopt interfering of halogen between well group.
As the further scheme of the present invention:The length of described cement plug is less than well group distance.
As the further scheme of the present invention:The length of described cement plug is the half of well group distance.
Compared with prior art, the invention has the beneficial effects as follows:
In drilling engineering technology, extended reach directional well technology is highly developed, and bottom hole displacement can reach thousands of rice To a myriametre.The present invention passes through to bore the directional horizontal wellss of a bite big displacement, connects with many mouthfuls of straight wells, forms multiple twin-well well groups, Greatly reduce the inclination section construction of drilling well, give full play to straight well and the respective advantage of directional horizontal wellss, solve orientation level The problem that the occupancy resource of well is excessive and pit shaft is more easily damaged, reduces the accident blocking during salt adopted by directional well, Improve safety in production level and the mining efficiency of salt well.
Most of well groups of the present invention are all straight wells, and casing setting depth is not limited by drillhole curvature, ensure that salt The abundant sealing of bed top, improves the length of service of salt well;The well group sleeve opening discrepancy in elevation is little simultaneously, can improve brine quality, can Arbitrarily switch the halogen direction that intakes out, to ensure the balanced development in molten chamber, and reach and extend well group life-span raising ore recovery ratio Purpose.
Brief description
Fig. 1 is the schematic diagrames tiltedly how directly concatenating well group salt well accident methods;
In figure:1- salt bath, 2- fluid course, 3- cement plug.
Specific embodiment
Below in conjunction with the embodiment of the present invention and accompanying drawing, the technical scheme in the embodiment of the present invention is carried out clear, complete Ground description is it is clear that described embodiment is only a part of embodiment of the present invention, rather than whole embodiments.Based on this Embodiment in invention, the every other reality that those of ordinary skill in the art are obtained under the premise of not making creative work Apply example, broadly fall into the scope of protection of the invention.
Refer to Fig. 1, in the embodiment of the present invention, how a kind of one tiltedly directly concatenate well group salt well accident methods, concretely comprises the following steps:
1) the mineral deposit depth according to salt mine, designs a well group axis, determines the logarithm of halogen well on axis, subdrilling axis end The first straight well Z1 in portion, and correspondence builds first salt bath 1 in salt deposit;
2) other end in above-mentioned axis bores directional horizontal wellss X1, creeps into along axis, with first straight well Z1 in salt deposit It is docked and connected;
3) drilling tool in directional horizontal wellss X1 is returned and drag a well spacing, build second salt bath 1, away from first on well group axis At mouthful mono- well spacing of straight well Z1, bore second straight well Z2, be docked and connected with second salt bath 1 so that first straight well Z1 and the Two mouthfuls of straight well Z2 constitute a pair of connected well, and the horizontal channel between first salt bath 1 and second salt bath 1 is fluid course 2, enters Enter circulation and adopt halogen production;
4) drilling tool in directional horizontal wellss X1 is returned to drag and reach a well group distance, build the 3rd salt bath 1, on well group axis At mono- well group distance of second mouthful of straight well Z2, bore the 3rd mouthful of straight well Z3;
5) drilling tool in directional horizontal wellss X1 is returned and drag a well spacing, build the 4th salt bath 1, away from the 3rd on well group axis At mouth mono- well spacing of straight well Z3, bore the 4th mouthful of straight well Z4 so that the 3rd mouthful of straight well Z3 and the 4th mouthful of straight well Z4 constitutes a pair of connection Well, the horizontal channel between the 3rd salt bath 1 and the 4th salt bath 1 is also fluid course 2, enters circulation and adopts halogen production;
6) repeat to build one or more pairs of connected wells, until last a bite straight well Zn, constitute a pair with directional horizontal wellss X1 Circulation well, realizes once orientation big displacement directional horizontal wellss X1 and multiple straight well Z1~Zn and is docked and connected, constitute multipair circulation and adopt Halogen well.
In above-mentioned steps, step 4) and step 6) in, can also inject in the horizontal channel between adjacent connected well Cement mortar forms cement plug 3, for blocking the passage in salt deposit, it is to avoid adopt interfering of halogen between well group.Not tight for requiring The mine of lattice can not also cementing plug 3.
Embodiment 1
Certain salt mine, 1000 meters of mineral deposit buried depth, 60 meters about of seam thickness, originally using the horizontally-butted wells of " is oblique always " Group exploitation, because inclined shaft is more, causes the waste of ample resources near border, meanwhile, increased drilling cost deflecting more, and Often blocking or even scraps inclined shaft in halogen well in process of production.
In the embodiment of the present invention, well group string is designed as 6 mouthfuls of wells, is divided into 3 groups of wells, two ends well head distance is 850 meters.First Group, second group of well spacing are 100 meters, and the 3rd group for always one tiltedly, and well spacing is 250 meters, and inclination section circular curve radius is 150 Rice.200 meters of the distance between well group, in horizontal segment, 100 meters of the length of cement plug 3, concretely comprises the following steps:
1) construction method of mean level butt shaft, the first straight well Z1 of subdrilling distalmost end are pressed, setting of casing is cemented the well, and goes forward side by side Salt bath 1 is built in row short-term convection circulation;
2) bore directional horizontal wellss X1 again, method is consistent with mean level butt shaft, and only horizontal segment is longer, it is straight that brill reaches first The salt bath 1 of well Z1;
3) above carry 100 meters of drilling tool, that is, the drilling tool in horizontal channel returns and drags 100 meters, second salt is built in water filling from drilling rod Groove 1;Bore second mouthful of straight well Z2 simultaneously, dock with second salt bath 1 in horizontal channel;Above carry 50 to 150 meters of drilling tool, in level Cement plug 3 is built in passage;Press connected well water filling simultaneously and row's halogen produces in first straight well Z1, second mouthful of straight well Z2;
4) in the same way and program, above carry 100 meters of drilling tool, that is, the drilling tool in horizontal channel returns and drags 100 meters, from drilling rod The 3rd salt bath 1 is built in middle water filling;Bore the 3rd mouthful of straight well Z3 simultaneously, dock with the 3rd salt bath 1 in horizontal channel;
5) drilling tool in directional horizontal wellss X1 is returned and drag 100 meters, the 4th salt bath 1 is built in water filling from drilling rod;Bore simultaneously 4th mouthful of straight well Z4, is docked with the 4th salt bath 1 in horizontal channel;Above carry 50 to 150 meters of drilling tool, build in horizontal channel Cement plug 3;Press connected well water filling simultaneously and row's halogen produces in the 3rd mouthful of straight well Z3, the 4th mouthful of straight well Z4;
6) in the same way and program, above carry 100 meters of drilling tool, that is, the drilling tool in horizontal channel returns and drags 100 meters, from drilling rod The 5th salt bath 1 is built in middle water filling;Bore the 5th mouthful of straight well Z3 simultaneously, dock with the 5th salt bath 1 in horizontal channel;5th mouthful Straight well Z5 and directional horizontal wellss X1 constitutes well group.
In the embodiment of the present invention, concatenation well group can be 4 mouthful two to or 6 mouthful 3 right, can also be that many wells are multipair.
The present invention passes through to bore the directional horizontal wellss X1 of a bite big displacement, connects with many mouthfuls of straight well Z1-Zn, forms multiple twin-wells Well group, greatly reduces the inclination section construction of drilling well, gives full play to straight well and the respective advantage of directional horizontal wellss, solve orientation The problem that the occupancy resource of horizontal well is excessive and pit shaft is more easily damaged, reduces the thing blocking during salt adopted by directional well Therefore, improve safety in production level and the mining efficiency of salt well.
Most of well groups of the present invention are all straight wells, and casing setting depth is not limited by drillhole curvature, ensure that salt The abundant sealing of bed top, improves the length of service of salt well;The well group sleeve opening discrepancy in elevation is little simultaneously, can improve brine quality, can Arbitrarily switch the halogen direction that intakes out, to ensure the balanced development in molten chamber, and reach and extend well group life-span raising ore recovery ratio Purpose.
It is obvious to a person skilled in the art that the invention is not restricted to the details of above-mentioned one exemplary embodiment, Er Qie In the case of the spirit or essential attributes of the present invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, embodiment all should be regarded as exemplary, and be nonrestrictive, the scope of the present invention is by appended power Profit requires rather than described above limits, it is intended that all in the implication and scope of the equivalency of claim by falling Change is included in the present invention.
Moreover, it will be appreciated that although this specification is been described by according to embodiment, not each embodiment only wraps Containing an independent technical scheme, only for clarity, those skilled in the art should for this narrating mode of specification Using specification as an entirety, the technical scheme in each embodiment can also form those skilled in the art through appropriately combined Understandable other embodiment.

Claims (5)

1. tiltedly how straight concatenation well group salt well accident methods are it is characterised in that concretely comprise the following steps for one kind one:
1) the mineral deposit depth according to salt mine, designs a well group axis, determines the logarithm of halogen well on axis, subdrilling axis end First straight well Z1, and correspondence builds first salt bath in salt deposit;
2) other end in above-mentioned axis bores directional horizontal wellss X1, creeps into along axis, dock with first straight well Z1 in salt deposit Connection;
3) drilling tool in directional horizontal wellss X1 is returned and drag a well spacing, build second salt bath, straight away from first on well group axis At mono- well spacing of well Z1, bore second straight well Z2, be docked and connected with second salt bath so that first straight well Z1 and second mouthful are straight Well Z2 constitutes a pair of connected well, enters circulation and adopts halogen production;
4) drilling tool in directional horizontal wellss X1 is returned to drag and reach a well group distance, build the 3rd salt bath, away from well group axis At mono- well group distance of two mouthfuls of straight well Z2, bore the 3rd mouthful of straight well Z3;
5) drilling tool in directional horizontal wellss X1 is returned and drag a well spacing, build the 4th salt bath, straight away from the 3rd mouthful on well group axis At mono- well spacing of well Z3, bore the 4th mouthful of straight well Z4 so that the 3rd mouthful of straight well Z3 and the 4th mouthful of straight well Z4 constitutes a pair of connected well, enter Enter circulation and adopt halogen production;
6) repeat to build one or more pairs of connected wells, until last a bite straight well Zn, constitute a pair of circulation with directional horizontal wellss X1 Well, realizes once orientation big displacement directional horizontal wellss X1 and multiple straight well Z1~Zn and is docked and connected, constitute multipair circulation halogen mining well;
The distance between last a bite straight well Zn and directional horizontal wellss X1 is 150-350 rice;
Described step 4) and step 6) it is additionally included in injection cement mortar formation cement plug in the horizontal segment between adjacent connected well, For blocking the passage in salt deposit, it is to avoid adopt interfering of halogen between well group.
2. according to claim 1 a kind of one tiltedly many straight concatenation well group salt well accident methods it is characterised in that described step 3) and step 5) in, well spacing is to constitute the distance between two mouthfuls of straight wells of a pair of connected well, and well spacing is 50-150 rice.
3. according to claim 1 a kind of one tiltedly many straight concatenation well group salt well accident methods it is characterised in that described step 4) in, well group distance is the distance between adjacent connected well, and well group distance is 100-300 rice.
4. according to claim 1 a kind of one tiltedly many straight concatenation well group salt well accident methods it is characterised in that described cement The length of plug is less than well group distance.
5. the one kind one according to claim 1 or 4 tiltedly many straight concatenation well group salt well accident methods it is characterised in that described The length of cement plug is the half of well group distance.
CN201410692019.7A 2014-11-27 2014-11-27 One-inclined multi-vertical cascaded well group salt mine mining method Expired - Fee Related CN104481541B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410692019.7A CN104481541B (en) 2014-11-27 2014-11-27 One-inclined multi-vertical cascaded well group salt mine mining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410692019.7A CN104481541B (en) 2014-11-27 2014-11-27 One-inclined multi-vertical cascaded well group salt mine mining method

Publications (2)

Publication Number Publication Date
CN104481541A CN104481541A (en) 2015-04-01
CN104481541B true CN104481541B (en) 2017-02-22

Family

ID=52756133

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410692019.7A Expired - Fee Related CN104481541B (en) 2014-11-27 2014-11-27 One-inclined multi-vertical cascaded well group salt mine mining method

Country Status (1)

Country Link
CN (1) CN104481541B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105927193B (en) * 2016-07-19 2018-07-06 中盐勘察设计院有限公司 A kind of recovery method of deep playa halite ore bed
CN109026002B (en) * 2018-09-20 2020-04-07 中盐勘察设计院有限公司 Salt mine mining method adopting horizontal branch hole butt-joint well group
CN109506850A (en) * 2018-11-19 2019-03-22 湖北双环科技股份有限公司 A kind of salt well method for testing tightness
CN110566176A (en) * 2019-09-26 2019-12-13 四川盐业地质钻井大队 Rock salt mine mining method
CN111395980B (en) * 2020-03-30 2022-10-11 河南永银化工实业有限公司 Method for solving sand blockage in casing of brine well
CN113417641A (en) * 2021-07-21 2021-09-21 江苏淮盐矿业有限公司 Mine three-dimensional mining process

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5690390A (en) * 1996-04-19 1997-11-25 Fmc Corporation Process for solution mining underground evaporite ore formations such as trona
CN1415841A (en) * 2002-12-01 2003-05-07 化学工业部连云港设计研究院 Drilling method for exploiting soluble salt mine through dissolution method
RU2244107C1 (en) * 2003-09-22 2005-01-10 ОАО "Уральский научно-исследовательский и проектный институт галургии" (ОАО "Галургия") Method of joined development of oil and potassium deposits
CN1300443C (en) * 2004-02-09 2007-02-14 太原理工大学 Group-well fracture pressure steeping control aqueous fusion exploitation method of glauberite bal
CN102852490A (en) * 2012-09-07 2013-01-02 北京九尊能源技术股份有限公司 High gas suction and discharge process method for complex well
CN102828777B (en) * 2012-09-19 2015-07-29 重庆大学 Double-vertical shaft horizontal butt joint salt cavern deposit construction method
CN103161468B (en) * 2013-03-28 2015-06-17 江苏井神盐化股份有限公司 Well and rock salt solution mining-well recharging filling circulation mining method
CN103216234B (en) * 2013-04-23 2015-11-18 中国地质科学院勘探技术研究所 A kind of construction method of horizontal branch many well groups butt shaft

Also Published As

Publication number Publication date
CN104481541A (en) 2015-04-01

Similar Documents

Publication Publication Date Title
CN104481541B (en) One-inclined multi-vertical cascaded well group salt mine mining method
CN101832149B (en) Method for extracting coal seam gas by underground heat injection
CN104806217B (en) Combined separated layer fracturing, grouping and layer-combining mining method for coal bed well group
CN101915083B (en) Method for extracting coalbed gases from coal mines by upper and lower combination
CN103850711B (en) Salt hole air reserved storeroom twin-well banking process
CN107701189A (en) The high large-scale gas storage twin-well method of construction of impurity salt mine
CN103233738B (en) Comprehensive weakening method of top coal of heavy-pitch super high seam
CN109236186B (en) Well drilling casing and rapid well drilling and completion method for multilateral well of large well
CN105134286B (en) L-type well goaf gas pumping method
CN102392678A (en) Gas drainage method combining surface and underground fracturing and permeability improvement
CN104612691B (en) Single borehole multilateral directional butted well salt mining method
CN105909246B (en) A kind of chemical weakening method of high seam moderate heat diagenesis horizontal fragmentation blast cracking
CN104405283A (en) Technique for extracting gas from L-shaped ground drilling well in mining area
CN206860155U (en) Coal-series gas U-shaped well drilling and fracturing structure
CN108678722B (en) Multi-well combined dry-hot rock artificial thermal storage building system and building method
CN106499368A (en) A kind of deep seafloor top layer gas hydrate mining methods
CN103498680A (en) Method for increasing top-coal recovery rate in primary mining period of fully-mechanized caving face
CN103147734A (en) Method for multi-section hydraulic fracture along coal layer of underground coal mine
CN104196453B (en) Coalbed methane development well
CN106223956A (en) Medium-length hole courtyard mining afterwards filling method
CN102561950A (en) Process for realizing grouting consolidation for aggregates filled in cavities of strata and jetting drill bit
CN102877857A (en) Deep hole pre-grouting top plate reinforcement method for large-mining height working face under special geological conditions
CN104265357B (en) Anti-burst method is taken out in a kind of strong prominent coal seam in advance
CN104454001A (en) In-tunnel dewatering system and method for tunnel in low-permeability silty-fine sand stratum
CN109026002B (en) Salt mine mining method adopting horizontal branch hole butt-joint well group

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170222

Termination date: 20181127