CN104453960B - 含软夹矸层厚煤层外错滑移变形巷道支护方法 - Google Patents
含软夹矸层厚煤层外错滑移变形巷道支护方法 Download PDFInfo
- Publication number
- CN104453960B CN104453960B CN201410544663.XA CN201410544663A CN104453960B CN 104453960 B CN104453960 B CN 104453960B CN 201410544663 A CN201410544663 A CN 201410544663A CN 104453960 B CN104453960 B CN 104453960B
- Authority
- CN
- China
- Prior art keywords
- anchor pole
- anchor
- length
- top board
- dirt band
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
Abstract
本发明公开了一种含软夹矸层厚煤层外错滑移变形巷道支护方法,包括如下步骤:S1、确定顶板松弛拱的高度;S2、选择支护方法;S3、确定巷道顶板锚杆长和锚索长度,正帮采用玻璃钢锚杆配合塑料网支护副帮,副帮采用钢筋锚杆支护,夹矸层附近较大塑性区采用加长锚杆进行加固,将上帮加长锚杆用横向钢带或钢筋钢筋连为一体,加强副帮上帮的整体性控制。本发明在通过现场钻孔内窥实测基础上,通过物理模拟和数值计算,掌握了巷道外错机滑移破坏的机理,巷道变形破坏的最严重的部位是夹矸层之上的巷道上帮,采用沿软夹层上部打一排加长锚杆,长锚杆间用钢带相连,控制巷道变形破坏最严重的上帮稳定性,实现经济支护。
Description
技术领域
本发明涉及一种支护方法,具体涉及一种含软夹矸层厚煤层外错滑移变形巷道支护方法。
背景技术
现有支护技术,没有考虑软夹矸层的影响,没有针对巷帮外错滑移变形破坏进行支护控制,而是按照全煤层巷帮进行设计,对于外错滑移带来的片帮、沿夹矸层附近的锚杆脱锚不能够有效控制。对于顶板的锚索过度支护带来浪费,却不能提高巷帮的稳定性。本项发明的目的是通过揭示巷帮外错滑移机理,提出控制含软夹层巷道外错滑移变形破坏的支护原理和方法。
发明内容
为解决上述问题,本发明提供了一种含软夹矸层厚煤层外错滑移变形巷道支护方法,通过数值计算和物理模拟,揭示了相邻工作面侧方支承压力导致顶板产生向垂直裂隙并引起顶板与巷道上帮沿软夹层“滑面”侧向滑移的机理。建立了含软夹矸层巷道自稳平衡拱支护模型,阐明了加强帮部支护对巷道整体稳定性的重要作用,提出了“加强软夹矸层之上的巷道上帮支护,上帮与下帮分段控制,适应外错变形,分别控制以软夹矸层为界的上、下巷帮的完整性,实现巷帮的经济合理控制”的巷道锚索与锚杆参数设计原则,给出了加强巷道上帮支护的锚网索支护方法,工程实践取得了成功。
为实现上述目的,本发明采取的技术方案为:
含软夹矸层厚煤层外错滑移变形巷道支护方法,包括如下步骤:
S1、确定顶板松弛拱的高度:
设巷帮高度为H(单位:m),煤帮内摩擦角为(单位:°),则煤帮松弛深度为:
顶板松弛拱高度h为:
式中,W-巷道宽度,m;σt-顶板抗拉强度,MPa;L-煤帮松弛深度,m;P0-原岩应力,MPa;
S2、选择支护方法:当顶板松弛拱高度小于2.5m,可采用锚杆支护,锚杆的长度按照松弛拱的高度确定,锚杆的间距和排拒不大于锚杆长度的一半;
当顶板的松弛拱的高度大于2.5m,可采用锚杆和锚索联合支护,锚索的长度按照松弛拱高度确定,锚索的间排距为锚杆间排距的2-3倍;
S3、确定巷道顶板锚杆长和锚索长度,正帮(实体帮)采用玻璃钢锚杆配合塑料网支护副帮,可实现正帮无拆卸割煤,提高采煤效率,副帮(煤柱帮,含泥岩夹矸)采用钢筋锚杆支护,夹矸层附近较大塑性区在夹矸层上部0.6m处采用一排加长锚杆进行加固,将上帮加长锚杆用横向钢带或钢筋连为一体,加强副帮上帮的整体性控制。
本发明在通过现场钻孔内窥实测基础上,通过物理模拟和数值计算,掌握了巷道外错机滑移破坏的机理,巷道变形破坏的最严重的部位是夹矸层之上的巷道上帮,提出了“加强软夹矸层之上的巷道上帮支护,上帮与下帮分段控制,适应外错变形,分别控制以软夹矸层为界的上、下巷帮的完整性,实现巷帮的经济合理控制”的原则。采用沿软夹层上部打一排长锚杆,长锚杆间用钢带相连,控制巷道变形破坏最严重的上帮稳定性,实现经济支护。
附图说明
图1为本发明实施例巷道向相邻采空区外错变形示意图。
图2为本发明实施例围岩裂隙分布范围示意图。
图3为本发明实施例巷道顶板集中垂直应力数值计算图。
图4为本发明实施例巷道顶板垂直裂隙和外错滑移物理模拟图。
图5为本发明实施例含软夹层煤巷自稳平衡拱支护模型图。
图6为本发明实施例巷道支护方案图。
具体实施方式
为了使本发明的目的及优点更加清楚明白,以下结合实施例对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。
实施例
以神东某矿八盘区为例,煤层埋深116~206m,厚6m,倾角1~3°。采用走向长壁大采高工作面开采,回采巷道为矩形,巷道高4.6m,宽度6.2m,巷道煤帮距底板1.6m含有一层20cm厚的泥岩软夹矸层,夹矸层具有遇水膨胀性、流变性和水软化性。实测表明:
(1)含泥岩软夹层巷道变形特征是煤帮“外错”变形(图1)。即巷道煤帮中,软夹层上部的煤体发生整体向相邻采空区侧运动,出现外错式变形。滑移距离20-40cm。
(2)巷道煤帮在夹层附近变形破坏明显,出现了夹矸层挤出、片帮和脱锚现象。
(3)巷道顶板6m以内分布有垂直裂隙,巷道两帮变形不对称,靠工作面内侧的“正帮”变形较小,靠煤柱侧的“副帮”变形较大,见图2。巷道两帮的破碎区主要集中于软夹层附近,夹矸层上部大于下部。正帮中部裂隙区深度最大为2.5m,副帮裂隙区深度最大达到3m。
数值计算得出,由于受相邻工作面开采的影响,工作面回风巷道及巷帮煤柱上方顶板30m范围存在应力集中区,见图3。顶板的垂直裂隙,与这种集中应力有关。受相邻采空区和煤柱影响,巷道副帮塑性区大于正帮,夹矸层上部发育最深,达到3m。
物理模拟揭示出,巷道和煤柱顶板存在集中应力时,顶板出现垂直裂隙。随着垂直裂隙的发育和导致的岩层裂胀扩容,顶板出现向右侧相邻采空区的水平运动,软夹层提供了运动的滑面,顶板带动软夹层以上煤体沿软夹层滑移,形成巷道煤帮外错变形和破坏,如图4所示。
针对神东矿区某矿八盘区含软夹层煤层巷道情况,根据上述支护原则(其原理见支护模型图5),确定了巷道顶板锚杆长和锚索长度。正帮塑性区较小,可采用玻璃钢锚杆配合塑料网支护,便于无拆卸割煤,提高工作面采煤机割煤效率。副帮是支护的重点,采用钢筋锚杆支护,夹矸层附近较大塑性区采用加长锚杆进行加固,将上帮加长锚杆用横向钢带或钢筋连为一体,加强副帮上帮的整体性控制。
提出支护方案如下:
顶板支护:采用Φ17.8mm锚索,长度由原支护设计的8m优化为6m,锚固段长度1.5m,每套锚索配3卷树脂药卷(从外至里为Z2360、K2360、CK2360)。锚索预紧力170KN,最大工作载荷280KN。顶板锚杆采用Φ20mm,长度为2.4m钢筋锚杆,每套锚杆配1卷CK2360树脂药卷,预紧力25kN,锚固强度不小于70KN。
帮部支护:副帮夹层附近塑性区达3m,设一排4m、间距2m的长锚杆加强支护。每2根长锚杆中间补一根Φ20mm,长2.4m钢筋锚杆,配套一条横向钢筋梁,加强对夹矸层附近巷帮的整体控制。正帮采用Φ27mm玻璃钢锚杆,长度2.4m,锚杆强度不小于50KN,预紧力20kN。配陪套塑料复合网,用木托板替代钢筋钢筋,实现采煤机割煤时可切割。具体支护方案和参数如图6所示。
矿区采用上述方案支护后,两帮移近量减小为7.1%,顶底变形量减小为7.7%。采用顶板锚索和锚杆支护后,巷道顶板原有的拉应力区消失,两帮稳定性明显提高。
巷道支护后正帮松弛区缩小了50%,副帮泥岩夹层上部松弛区缩小了75%。实践表明,虽然仍有外错滑移,但巷帮得到明显控制,巷道围岩收敛变形很小,巷道安全稳定,降低了支护费用,实现了巷道无维修使用。
综上所述,本发明在通过现场钻孔内窥实测基础上,通过物理模拟和数值计算,掌握了巷道外错机滑移破坏的机理,巷道变形破坏的最严重的部位是夹矸层之上的巷道上帮,提出了“加强软夹矸层之上的巷道上帮支护,上帮与下帮分段控制,适应外错变形,分别控制以软夹矸层为界的上、下巷帮的完整性,实现巷帮的经济合理控制”的原则。采用沿软夹层上部打一排长锚杆,长锚杆间用钢带相连,控制巷道变形破坏最严重的上帮稳定性,实现经济支护。
以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以作出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。
Claims (1)
1.含软夹矸层厚煤层外错滑移变形巷道支护方法,其特征在于,包括如下步骤:
S1、确定顶板松弛拱的高度:
设巷帮高度为H,则煤帮松弛深度为:
顶板松弛拱高度h为:
式中,W-巷道宽度,m;σt-顶板抗拉强度,MPa;L-煤帮松弛深度,m;P0-原岩应力,MPa;-煤帮内摩擦角,°;
S2、选择支护方法:当顶板松弛拱高度小于2.5m,可采用锚杆支护,锚杆的长度按照松弛拱的高度确定,锚杆的间距和排拒不大于锚杆长度的一半,锚杆杆体强度和直径按照承担岩体重量确定;
当顶板的松弛拱的高度大于2.5m,可采用锚杆和锚索联合支护,锚索的长度按照松弛拱高度确定,锚索的间排距为锚杆间排距的2-3倍;
S3、确定巷道顶板锚杆长和锚索长度,正帮采用玻璃钢锚杆配合塑料网支护副帮,副帮采用钢筋锚杆支护,夹矸层附近较大塑性区采用加长锚杆进行加固,将上帮加长锚杆用横向钢带或钢筋连为一体,加强副帮上帮的整体性控制。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410544663.XA CN104453960B (zh) | 2014-10-01 | 2014-10-01 | 含软夹矸层厚煤层外错滑移变形巷道支护方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410544663.XA CN104453960B (zh) | 2014-10-01 | 2014-10-01 | 含软夹矸层厚煤层外错滑移变形巷道支护方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104453960A CN104453960A (zh) | 2015-03-25 |
CN104453960B true CN104453960B (zh) | 2016-10-05 |
Family
ID=52900630
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410544663.XA Expired - Fee Related CN104453960B (zh) | 2014-10-01 | 2014-10-01 | 含软夹矸层厚煤层外错滑移变形巷道支护方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104453960B (zh) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107869350A (zh) * | 2017-10-25 | 2018-04-03 | 山东科技大学 | 一种新型降冲煤矿锚网支护方法 |
CN109339834B (zh) * | 2018-11-02 | 2019-09-24 | 山东科技大学 | 一种锚杆-锚索协同变形受力的支护方法 |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102733836B (zh) * | 2012-07-05 | 2015-01-28 | 大同煤矿集团有限责任公司 | 软弱特厚煤层综放回采巷道支护方法 |
CN103195441B (zh) * | 2013-04-01 | 2016-08-31 | 平顶山天安煤业股份有限公司 | 一种煤矿巷道支护固结构及其施工工艺 |
CN103277114A (zh) * | 2013-04-23 | 2013-09-04 | 西南科技大学 | 地下工程破碎围岩的无喷砼锚网支护方法 |
CN103352707B (zh) * | 2013-07-19 | 2015-12-02 | 山西潞安环保能源开发股份有限公司常村煤矿 | 一种多维多级支护方法 |
CN103470289A (zh) * | 2013-09-25 | 2013-12-25 | 大同煤矿集团有限责任公司 | 极近距离煤层开采支护方法 |
CN103670470B (zh) * | 2013-12-31 | 2015-07-15 | 大同煤矿集团有限责任公司 | 全煤巷道安全快速掘进支护方法 |
-
2014
- 2014-10-01 CN CN201410544663.XA patent/CN104453960B/zh not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN104453960A (zh) | 2015-03-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Huang et al. | The reasonable breaking location of overhanging hard roof for directional hydraulic fracturing to control strong strata behaviors of gob-side entry | |
CN104358572B (zh) | 大倾角急倾斜煤层自然垮落充填护巷无煤柱开采技术 | |
CN111305876A (zh) | 深部巷道锚固-劈裂注浆-水力压裂卸压协同控制方法 | |
CN104832198B (zh) | 巷道围岩变形、冲击矿压、煤与瓦斯突出综合治理方法 | |
CN105825018B (zh) | 煤矿采空区下近距离煤巷支护参数设计方法 | |
CN106194196B (zh) | 一种横穿隧道洞身的大型溶洞处理与开挖方法 | |
CN103775084B (zh) | 大倾角、大采高综采设备过地质构造破碎带施工工艺 | |
CN104763425A (zh) | 一种卸压预裂爆破沿空留巷无煤柱开采方法 | |
CN108894784A (zh) | 一种坚硬顶板定向酸化压裂控顶卸压方法 | |
CN103195443B (zh) | 深部开采优化支护参数预防巷道滞后突水的方法 | |
CN205013013U (zh) | 适用于上软下硬地层的暗挖车站支护结构 | |
CN103216244B (zh) | 巷道软弱顶板锚固梁-拱组合结构支护系统及支护方法 | |
AU2015387618B2 (en) | Method for fracturing filler wall left behind in adjacent coal-mining face | |
CN103397905A (zh) | 煤层自然跨落充填、柔性护巷、完全沿空留巷系统及方法 | |
CN110529151A (zh) | 一种综掘工作面分级分区综合加固过陷落柱方法 | |
Zhang et al. | Spontaneous caving and gob-side entry retaining of thin seam with large inclined angle | |
CN105569726A (zh) | Gfrp管混凝土墩柱及矸石混凝土墙沿空留巷的方法 | |
CN104265295A (zh) | 倾斜中厚煤层无人工巷旁充填及无煤柱沿空留巷方法 | |
CN105756702A (zh) | 一种巷旁网笼充填支护沿空留巷方法 | |
Xue et al. | Deformation failure mechanism and application of the backfill along the goaf-side retained roadway | |
CN106089207A (zh) | 特厚煤层工作面沿空掘巷窄煤柱留设方法 | |
CN104453960B (zh) | 含软夹矸层厚煤层外错滑移变形巷道支护方法 | |
CN205349380U (zh) | 一种防止沿空留巷底鼓的整体切顶支架 | |
CN106150522A (zh) | 一种利用钻孔窥视仪探测冒落区的顶板塌陷治理方法 | |
CN105134287A (zh) | 一种预留变形阶段型分级让压沿空留巷巷旁充填体及其构筑方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161005 Termination date: 20181001 |
|
CF01 | Termination of patent right due to non-payment of annual fee |