CN104452833A - 一种模型桩埋设方法 - Google Patents

一种模型桩埋设方法 Download PDF

Info

Publication number
CN104452833A
CN104452833A CN201410725491.6A CN201410725491A CN104452833A CN 104452833 A CN104452833 A CN 104452833A CN 201410725491 A CN201410725491 A CN 201410725491A CN 104452833 A CN104452833 A CN 104452833A
Authority
CN
China
Prior art keywords
pile
burying
pvc sleeve
sleeve pipe
mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410725491.6A
Other languages
English (en)
Other versions
CN104452833B (zh
Inventor
李哲
王荆
李又云
王开强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201410725491.6A priority Critical patent/CN104452833B/zh
Publication of CN104452833A publication Critical patent/CN104452833A/zh
Application granted granted Critical
Publication of CN104452833B publication Critical patent/CN104452833B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明公开了一种模型桩埋设方法,包括如下步骤:将PVC套管竖向切为两半,然后试桩装进PVC套管,在上中下三个位置由金属卡扣固定;放入模型桩位,分层埋设;每层埋设后,将PVC套管拔出一部分,边拔套管边进行桩周地基击实,以免因套管缝隙使得桩周土不够密实;将模型桩埋设至标高后,将金属卡扣解开,将PVC套管拔出,进行模型试验。本发明采用PVC套管对模型桩进行保护,在埋设过程中套管承担了绝大部分桩侧土压力,从而有效的保护了模型桩。经试验表明,这种方法埋设模型桩,效果良好,埋设中无断裂现象,满足试验要求。

Description

一种模型桩埋设方法
技术领域
本发明涉及地基模型试验领域,具体涉及一种模型桩埋设方法。
背景技术
对于长细比较大的实体桩在模型试验中的埋设,一般没有保护措施,这样造成模型桩在埋设过程中受到桩侧土不均匀的侧向压力,使得模型桩极易断裂,而无法进行模型试验。
发明内容
为解决上述问题,本发明提供了一种模型桩埋设方法,采用PVC套管对模型桩进行保护,在埋设过程中套管承担了绝大部分桩侧土压力,从而有效的保护了模型桩。
为实现上述目的,本发明采取的技术方案为:
一种模型桩埋设方法,包括如下步骤:
S1、将PVC套管竖向切为两半,然后试桩装进PVC套管,在上中下三个位置由金属卡扣固定;
S2、将步骤S1所得的试桩放入模型桩位,分层埋设;
S3、每层埋设后,将PVC套管拔出一部分,边拔套管边进行桩周地基击实,以免因套管缝隙使得桩周土不够密实;
S4、将模型桩埋设至标高后,将金属卡扣解开,将PVC套管拔出,进行模型试验。
本发明具有以下有益效果:
上述方案,采用PVC套管对模型桩进行保护,在埋设过程中套管承担了绝大部分桩侧土压力,从而有效的保护了模型桩。经试验表明,这种方法埋设模型桩,效果良好,埋设中无断裂现象,满足试验要求。
具体实施方式
为了使本发明的目的及优点更加清楚明白,以下结合实施例对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。
本发明实施例提供了一种模型桩埋设方法,包括如下步骤:
S1、将PVC套管竖向切为两半,然后试桩装进PVC套管,在上中下三个位置由金属卡扣固定;
S2、将步骤S1所得的试桩放入模型桩位,分层埋设;
S3、每层埋设后,将PVC套管拔出一部分,边拔套管边进行桩周地基击实,以免因套管缝隙使得桩周土不够密实;
S4、将模型桩埋设至标高后,将金属卡扣解开,将PVC套管拔出,进行模型试验。
实施例1
2014年5月3日,水泥搅拌桩模型试验采用该方法埋设模型桩,成桩40根,桩径5cm,桩长1.5m,无断裂现象,下桩效果良好。
实施例2
2014年8月5日,CFG桩模型试验采用该方法埋设模型桩,成桩40根,桩径5cm,桩长1.5m,无断裂现象,下桩效果良好。
综上所述,本发明效果良好,埋设中无断裂现象,满足试验要求。
以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以作出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。

Claims (1)

1.一种模型桩埋设方法,其特征在于,包括如下步骤:
S1、将PVC套管竖向切为两半,然后试桩装进PVC套管,在上中下三个位置由金属卡扣固定;
S2、将步骤S1所得的试桩放入模型桩位,分层埋设;
S3、每层埋设后,将PVC套管拔出一部分,边拔套管边进行桩周地基击实,以免因套管缝隙使得桩周土不够密实;
S4、将模型桩埋设至标高后,将金属卡扣解开,将PVC套管拔出,进行模型试验。
CN201410725491.6A 2014-11-28 2014-11-28 一种模型桩埋设方法 Expired - Fee Related CN104452833B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410725491.6A CN104452833B (zh) 2014-11-28 2014-11-28 一种模型桩埋设方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410725491.6A CN104452833B (zh) 2014-11-28 2014-11-28 一种模型桩埋设方法

Publications (2)

Publication Number Publication Date
CN104452833A true CN104452833A (zh) 2015-03-25
CN104452833B CN104452833B (zh) 2016-06-01

Family

ID=52899533

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410725491.6A Expired - Fee Related CN104452833B (zh) 2014-11-28 2014-11-28 一种模型桩埋设方法

Country Status (1)

Country Link
CN (1) CN104452833B (zh)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1078281A (zh) * 1992-05-08 1993-11-10 深圳市建筑科学中心 桩基消除负摩阻力装置
CN201411685Y (zh) * 2009-05-21 2010-02-24 朱奎 一种防止负摩阻力的装置
JP2012184596A (ja) * 2011-03-07 2012-09-27 Taisei Corp 杭の載荷試験方法
CN203452069U (zh) * 2013-09-05 2014-02-26 长沙学院 一种能减少灌注桩负摩阻力的装置

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1078281A (zh) * 1992-05-08 1993-11-10 深圳市建筑科学中心 桩基消除负摩阻力装置
CN201411685Y (zh) * 2009-05-21 2010-02-24 朱奎 一种防止负摩阻力的装置
JP2012184596A (ja) * 2011-03-07 2012-09-27 Taisei Corp 杭の載荷試験方法
CN203452069U (zh) * 2013-09-05 2014-02-26 长沙学院 一种能减少灌注桩负摩阻力的装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
江浩等: "钙质砂中模型桩的试验研究", 《岩土力学》, vol. 31, no. 3, 31 March 2010 (2010-03-31) *

Also Published As

Publication number Publication date
CN104452833B (zh) 2016-06-01

Similar Documents

Publication Publication Date Title
CN104278993B (zh) 一种偏压隧道斜交进洞的施工方法
CN102996136A (zh) 盾构近距离下穿复合地基建筑物的变形控制方法
PH12018550061A1 (en) Method for forming a stable foundation ground
CN103590836A (zh) 一种浅埋暗挖隧道塌方处理方法
MX2019002727A (es) Cinta de señalización.
CN104404960B (zh) 一种地下连续墙接缝注浆装置及施工方法
CN105672326A (zh) 一种露天矿边坡治理方法
CN104452833A (zh) 一种模型桩埋设方法
CN104912122B (zh) 基坑工程监测数据报警级别的判定方法
CN104372801A (zh) 一种边坡防滑构件
CN203891045U (zh) 深基坑围护桩间的堵漏注浆装置
CN104452827B (zh) 一种混凝土坝坝基泉眼的处理方法
CN208762896U (zh) 一种大流量地下水引排结构
Kang Behavior of buried geo-structures due to increase of excess pore water pressure ratio during earthquakes
CN204266257U (zh) 一种应力释放孔的支护装置
Chuan-zheng et al. Deformation analysis of foundation pit of a subject station of Metro Line 6 in Wuhan
Dzyuba et al. Experience of designing natural gas transmission pipelines in super challenging geological and environmental conditions of eastern siberia and the far east
Nicolas et al. Geotechnical Mitigation Strategies for Earthquake Surface Fault Rupture
Wang et al. Notice of Retraction: The study on supervision in deep foundation excavation
CN103541370A (zh) 地源热泵垂直地埋管系统的导槽施工法
Kim et al. A Study on the Gap Parameter in Sand by Scale Model Test
Sáez Robert et al. Liquefaction mitigation using secant piles wall under a large water tank
PL410478A1 (pl) Sposób zabezpieczenia wałów przeciwpowodziowych
Yu et al. Finite Layer Method for Solving Ground Subsidence Induced by Dewatering in Deep Excavation
Liang et al. Analysis of Effect Factors about the Ground Settlement during Foundation Pit Excavation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160601

Termination date: 20161128

CF01 Termination of patent right due to non-payment of annual fee