CN104389595A - 一种低压煤层气盆地地层参数的获取方法 - Google Patents

一种低压煤层气盆地地层参数的获取方法 Download PDF

Info

Publication number
CN104389595A
CN104389595A CN201410663331.3A CN201410663331A CN104389595A CN 104389595 A CN104389595 A CN 104389595A CN 201410663331 A CN201410663331 A CN 201410663331A CN 104389595 A CN104389595 A CN 104389595A
Authority
CN
China
Prior art keywords
pressure
well
test
injection
test string
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410663331.3A
Other languages
English (en)
Inventor
刘同吉
曹运兴
曹永恒
冯培文
张大庆
石玢
周丹
贾猛
田林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENAN ARK NEW ENERGY Co Ltd
Henan University of Technology
Shanxi Luan Environmental Energy Development Co Ltd
Original Assignee
HENAN ARK NEW ENERGY Co Ltd
Henan University of Technology
Shanxi Luan Environmental Energy Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENAN ARK NEW ENERGY Co Ltd, Henan University of Technology, Shanxi Luan Environmental Energy Development Co Ltd filed Critical HENAN ARK NEW ENERGY Co Ltd
Priority to CN201410663331.3A priority Critical patent/CN104389595A/zh
Publication of CN104389595A publication Critical patent/CN104389595A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B49/00Testing the nature of borehole walls; Formation testing; Methods or apparatus for obtaining samples of soil or well fluids, specially adapted to earth drilling or wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/06Measuring temperature or pressure

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geophysics (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

本发明涉及一种低压煤层气盆地地层参数的获取方法,主要包括以下步骤,下完测试管柱,开井24小时,使井底压力趋于新的平衡;注入前,做一次微破裂实验;采用进口稳压稳流的高压泵注入;数据采集使用计算机连续高密度采集数据;井下监测系统使用高精度存储式电子压力计监测井底压力和温度。本发明可以更准确全面的获取地层参数,是认识储层、进行储层评价和生产动态监测的关键。

Description

一种低压煤层气盆地地层参数的获取方法
技术领域
本发明属于一种煤层气盆地地层参数获取方法,特别是公开了一种低压煤层气盆地地层参数的获取方法。
背景技术
目前的试井技术对于低压低渗储层不太适应,注入量小,渗透半径小,再之钻井过程中的地层污染,使得获取参数失真,从而误导对储层的认识及评价。
因此,急需一种新的煤层气盆地地层参数获取方法,更准确全面的获取地层参数。
发明内容
本发明的目的在于提供一种低压煤层气盆地地层参数的获取方法,可以更准确全面的获取地层参数。
为达到上述目的,本发明采用如下的技术方案:一种低压煤层气盆地地层参数的获取方法,其特征在于,包括以下步骤:
a.测试管柱下井
压力计录取数据编程,在通过检验程序后,装入测试管柱中的压力计托筒;如果配备钢丝或电缆绞车,可在测试管柱下入井底以后,使用绞车下入压力计;所述压力计为高精度存储式电子压力计;下井过程测试管柱连接丝扣必须拧紧,防止渗漏;下井过程应平稳,遇阻则上提测试管柱,排除遇阻情况后方可继续下入;记录下入测试管柱的根数及长度,计算测试管柱总重量;
b.安装和连接地面装置
测试管柱下至预定深度后,校正下入测试管柱的长度,确保深度无误;安装井口设备,连接地面测试管汇,检测地面记录装置;
c.测试管柱试压
实施井下关井,向测试管柱注水,加压15MPa,关闭井口阀门;稳压15min无泄漏为合格;如发现泄漏,应查明原因重新试压;
d.封隔器坐封
根据封隔器的型号及坐封形式,选择合适的坐封参数;实施封隔器坐封;观察环空液面,检查漏失情况,如发现漏失,需查明原因重新坐封;
e.稳定压力
开井24小时,使井底压力波动趋于新的平衡,然后进行测试工作;
f.微破裂测试
注入前,做一个微破裂实验,记录破裂压力;
g.注入/压降测试
启动地面注水泵开始注入,注入泵采用稳压稳流高压泵;根据设计的注入排量进行调节,观察压力和排量变化,选择合适的排量进行持续注入,注入排量应尽量保持稳定,波动值不超百分之十;调节排量的时间不应超过整个注入时间的三分之一;井口压力应不超过地层破裂压力;记录注入排量、井口压力和累积注入量,记录间隔不大于10min,同时观察环空液面变化,以监测封隔器坐封情况;按设计的注入时间持续注入;
h.注入结束,采用井下关井,同时关闭井口阀门,观察井口压力变化,以检验井下关井工具密封情况;按设计的关井时间进行关井测压降;关井结束后开井;现场录取数据,经检验合格后数据备份,进行下一步的原地应力测试;
i.原地应力测试
启动地面注水泵,以最大排量注入,观察井口压力显示;关井20min测压力递降;开井,记录返排水量;保持注入排量不变,按设计加倍注入时间,进行二至四循环周期的测试;现场录取分析数据,检验合格后数据备份;封隔器解封,起出测试管柱。
本发明的有益效果为:
a注入前开井24小时,使井内形成新的压力平衡,避免了因入井管柱而储层受到的干扰。
b地面注入,采用进口稳压稳流的高压注入泵,在注入过程中避免了流量波动。
c数据采集,采用了先进的计算机数据采集系统,数据采集连续稳定,避免了人为记录的不连续性,影响后期数据分析。
d注入前,先做一个微破裂实验,可以有效的突破因钻井过程中储层污染带,较真实的获取原始地层参数。
e井下采用高精度存储式电子压力计,实时记录储层温度和压力变化,更详尽的数据采集,为后期数据分析提供依据。
具体实施方式
下面将结合实施例,来详细说明本发明。
一种低压煤层气盆地地层参数的获取方法,其特征在于,包括以下步骤:
a.测试管柱下井
压力计录取数据编程,在通过检验程序后,装入测试管柱中的压力计托筒;如果配备钢丝或电缆绞车,可在测试管柱下入井底以后,使用绞车下入压力计;所述压力计为高精度存储式电子压力计;下井过程测试管柱连接丝扣必须拧紧,防止渗漏;下井过程应平稳,遇阻则上提测试管柱,排除遇阻情况后方可继续下入;记录下入测试管柱的根数及长度,计算测试管柱总重量;
b.安装和连接地面装置
测试管柱下至预定深度后,校正下入测试管柱的长度,确保深度无误;安装井口设备,连接地面测试管汇,检测地面记录装置;
c.测试管柱试压
实施井下关井,向测试管柱注水,加压15MPa,关闭井口阀门;稳压15min无泄漏为合格;如发现泄漏,应查明原因重新试压;
d.封隔器坐封
根据封隔器的型号及坐封形式,选择合适的坐封参数;实施封隔器坐封;观察环空液面,检查漏失情况,如发现漏失,需查明原因重新坐封;
e.稳定压力
开井24小时,使井底压力波动趋于新的平衡,然后进行测试工作;
f.微破裂测试
注入前,做一个微破裂实验,记录破裂压力;
g.注入/压降测试
启动地面注水泵开始注入,注入泵采用稳压稳流高压泵;根据设计的注入排量进行调节,观察压力和排量变化,选择合适的排量进行持续注入,注入排量应尽量保持稳定,波动值不超百分之十;调节排量的时间不应超过整个注入时间的三分之一;井口压力应不超过地层破裂压力;记录注入排量、井口压力和累积注入量,记录间隔不大于10min,同时观察环空液面变化,以监测封隔器坐封情况;按设计的注入时间持续注入;
h.注入结束,采用井下关井,同时关闭井口阀门,观察井口压力变化,以检验井下关井工具密封情况;按设计的关井时间进行关井测压降;关井结束后开井;现场录取数据,经检验合格后数据备份,进行下一步的原地应力测试;
i.原地应力测试
启动地面注水泵,以最大排量注入,观察井口压力显示;关井20min测压力递降;开井,记录返排水量;保持注入排量不变,按设计加倍注入时间,进行二至四循环周期的测试;现场录取分析数据,检验合格后数据备份;封隔器解封,起出测试管柱。

Claims (1)

1.一种低压煤层气盆地地层参数的获取方法,其特征在于,包括以下步骤:
a.测试管柱下井
压力计录取数据编程,在通过检验程序后,装入测试管柱中的压力计托筒;如果配备钢丝或电缆绞车,可在测试管柱下入井底以后,使用绞车下入压力计;所述压力计为高精度存储式电子压力计;下井过程测试管柱连接丝扣必须拧紧,防止渗漏;下井过程应平稳,遇阻则上提测试管柱,排除遇阻情况后方可继续下入;记录下入测试管柱的根数及长度,计算测试管柱总重量;
b.安装和连接地面装置
测试管柱下至预定深度后,校正下入测试管柱的长度,确保深度无误;安装井口设备,连接地面测试管汇,检测地面记录装置;
c.测试管柱试压
实施井下关井,向测试管柱注水,加压15MPa,关闭井口阀门;稳压15min无泄漏为合格;如发现泄漏,应查明原因重新试压;
d.封隔器坐封
根据封隔器的型号及坐封形式,选择合适的坐封参数;实施封隔器坐封;观察环空液面,检查漏失情况,如发现漏失,需查明原因重新坐封;
e.稳定压力
开井24小时,使井底压力波动趋于新的平衡,然后进行测试工作;
f.微破裂测试
注入前,做一个微破裂实验,记录破裂压力;
g.注入/压降测试
启动地面注水泵开始注入,注入泵采用稳压稳流高压泵;根据设计的注入排量进行调节,观察压力和排量变化,选择合适的排量进行持续注入,注入排量应尽量保持稳定,波动值不超百分之十;调节排量的时间不应超过整个注入时间的三分之一;井口压力应不超过地层破裂压力;记录注入排量、井口压力和累积注入量,记录间隔不大于10min,同时观察环空液面变化,以监测封隔器坐封情况;按设计的注入时间持续注入;
h.注入结束,采用井下关井,同时关闭井口阀门,观察井口压力变化,以检验井下关井工具密封情况;按设计的关井时间进行关井测压降;关井结束后开井;现场录取数据,经检验合格后数据备份,进行下一步的原地应力测试;
i.原地应力测试
启动地面注水泵,以最大排量注入,观察井口压力显示;关井20min测压力递降;开井,记录返排水量;保持注入排量不变,按设计加倍注入时间,进行二至四循环周期的测试;现场录取分析数据,检验合格后数据备份;封隔器解封,起出测试管柱。
CN201410663331.3A 2014-11-18 2014-11-18 一种低压煤层气盆地地层参数的获取方法 Pending CN104389595A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410663331.3A CN104389595A (zh) 2014-11-18 2014-11-18 一种低压煤层气盆地地层参数的获取方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410663331.3A CN104389595A (zh) 2014-11-18 2014-11-18 一种低压煤层气盆地地层参数的获取方法

Publications (1)

Publication Number Publication Date
CN104389595A true CN104389595A (zh) 2015-03-04

Family

ID=52607544

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410663331.3A Pending CN104389595A (zh) 2014-11-18 2014-11-18 一种低压煤层气盆地地层参数的获取方法

Country Status (1)

Country Link
CN (1) CN104389595A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104912549A (zh) * 2015-05-05 2015-09-16 中煤科工集团西安研究院有限公司 煤层气区域参数测试方法
CN104963683A (zh) * 2015-07-14 2015-10-07 北京博达瑞恒科技有限公司 一种基于微压裂泵注的地层测试方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5303582A (en) * 1992-10-30 1994-04-19 New Mexico Tech Research Foundation Pressure-transient testing while drilling
US20090126475A1 (en) * 2007-11-21 2009-05-21 Schlumberger Technology Corporation Determining Permeability Using Formation Testing Data
EP2065556A1 (en) * 2007-11-30 2009-06-03 Services Pétroliers Schlumberger Retrievable downhole testing tool
CN101845949A (zh) * 2010-04-28 2010-09-29 中国科学院力学研究所 一种煤层气注入压降测试的室内模拟装置
CN102434135A (zh) * 2011-12-02 2012-05-02 河南理工大学 多煤层发育区合层排采设备
CN102477864A (zh) * 2010-11-25 2012-05-30 中国石油天然气股份有限公司 一种煤层气注入压降测试的室内实验模拟方法
CN203570308U (zh) * 2013-10-11 2014-04-30 中煤科工集团西安研究院有限公司 一种地层测试系统

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5303582A (en) * 1992-10-30 1994-04-19 New Mexico Tech Research Foundation Pressure-transient testing while drilling
US20090126475A1 (en) * 2007-11-21 2009-05-21 Schlumberger Technology Corporation Determining Permeability Using Formation Testing Data
EP2065556A1 (en) * 2007-11-30 2009-06-03 Services Pétroliers Schlumberger Retrievable downhole testing tool
CN101845949A (zh) * 2010-04-28 2010-09-29 中国科学院力学研究所 一种煤层气注入压降测试的室内模拟装置
CN102477864A (zh) * 2010-11-25 2012-05-30 中国石油天然气股份有限公司 一种煤层气注入压降测试的室内实验模拟方法
CN102434135A (zh) * 2011-12-02 2012-05-02 河南理工大学 多煤层发育区合层排采设备
CN203570308U (zh) * 2013-10-11 2014-04-30 中煤科工集团西安研究院有限公司 一种地层测试系统

Non-Patent Citations (12)

* Cited by examiner, † Cited by third party
Title
C. ÖZGEN KARACAN: ""Reconciling longwall gob gas reservoirs and venthole production performances using multiple rate drawdown well test analysis"", 《INTERNATIONAL JOURNAL OF COAL GEOLOGY》 *
SHIMIN LIU: ""Permeability prediction of coalbed methane reservoirs during primary depletion"", 《INTERNATIONAL JOURNAL OF COAL GEOLOGY》 *
刘曰武,等: ""煤层注入/压降测试的设备及工艺问题"", 《油气井测试》 *
周丹: ""潞安矿区山西组3#煤层储层特征及成因机理"", 《中国优秀硕士论文全文库工程科技I辑》 *
孙连凤: ""煤层气井注入压降/试井测试技术研究"", 《科技与企业》 *
张世富,等: ""煤层气注入/压降测试技术应用"", 《探矿工程(岩土钻掘工程)》 *
武楗棠,等: ""煤层气井试井工艺"", 《断块油气田》 *
胡均,等: ""煤层气井试井测试中常见问题与技术对策"", 《油气藏评价与开发》 *
袁超,等: ""常规测试与注入/压降测试在煤层气测试中的对比分析"", 《油气井测试》 *
赵培华,等: ""煤层气测试方法的分析评价"", 《油气井测试》 *
陈志胜,等: "《GB_T 24504-2009煤层气井注入/压降试井方法》", 30 October 2009 *
黄天朋: "《煤层气注入/压降测试方法分析及应用》", 《价值工程》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104912549A (zh) * 2015-05-05 2015-09-16 中煤科工集团西安研究院有限公司 煤层气区域参数测试方法
CN104912549B (zh) * 2015-05-05 2017-12-15 中煤科工集团西安研究院有限公司 煤层气区域参数测试方法
CN104963683A (zh) * 2015-07-14 2015-10-07 北京博达瑞恒科技有限公司 一种基于微压裂泵注的地层测试方法

Similar Documents

Publication Publication Date Title
US11054405B2 (en) Testing device and method for simulating the flowback in the shut-in period of fractured wells
He et al. Current status and trend of separated layer water flooding in China
CN106522928B (zh) 一种酸化压裂后停泵测井口压降不稳定试井方法
CN110837116B (zh) 盐穴储气库运行上限压力的确定方法
CN103628865B (zh) 天然裂隙注入测试
US20150205004A1 (en) Three-dimensional simulating device for the stratum stability in the natural hydrate exploitation
CN107830907B (zh) 一种地下水封洞库水幕系统结构动态设计方法
US11274543B2 (en) Method for accurately measuring reopening pressure of hydraulic fracturing induced fracture in deep borehole
CN101245701A (zh) 井下导高观测仪及其观测方法
CN102720473A (zh) 开采煤层气的方法
CN109269955B (zh) 一种煤岩层渗透率原位测试装置及方法
CN104237025A (zh) 一种封闭钻孔采动破坏模拟试验方法
CN108036985B (zh) 一种劈裂注浆浆脉制作及渗透系数检测装置及方法
CN104898178A (zh) 一种煤层采动裂隙发育程度的测定装置以及测定方法
CN107567532A (zh) 通过氮气举升、生产测井和恢复测试以单次连续油管延伸进行试井操作的方法
CN101050699B (zh) 一种利用同层垂向干扰试井获取厚油层垂向渗透率的方法及测试管柱
CN101769149B (zh) Co2注入剖面测井方法
CN104389595A (zh) 一种低压煤层气盆地地层参数的获取方法
Ladner et al. Hydraulic characteristics of the basel 1 enhanced geothermal system
He et al. A new concentric zonal water injection technique for highly-deviated wells
CN105804713A (zh) 一种快速确定注水井各小层井口注水启动压力的方法
CN105569623B (zh) 用于注水井的井口组合测试装置及其方法
CN115653536B (zh) 一种钻井过程中液体胶塞封隔产层循环控压方法及系统
CN105909240A (zh) 井底压力测试、聚合物驱替前缘位置监测和储层评价方法
CN104912545A (zh) 电控式油管内封隔器与直读压力计组合试井系统及方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150304

WD01 Invention patent application deemed withdrawn after publication