CN104389317A - Ultralarge-sized oblique single-pile foundation structure of large-span arch bridge - Google Patents

Ultralarge-sized oblique single-pile foundation structure of large-span arch bridge Download PDF

Info

Publication number
CN104389317A
CN104389317A CN201410620062.2A CN201410620062A CN104389317A CN 104389317 A CN104389317 A CN 104389317A CN 201410620062 A CN201410620062 A CN 201410620062A CN 104389317 A CN104389317 A CN 104389317A
Authority
CN
China
Prior art keywords
pile foundation
pile
foundation
arch bridge
foundation structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410620062.2A
Other languages
Chinese (zh)
Other versions
CN104389317B (en
Inventor
宋随弟
马庭林
廖成强
郭伦波
杨毅
袁明
徐捷
游云川
吴春雷
冯振兴
陈玉刚
刘明
赵启华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201410620062.2A priority Critical patent/CN104389317B/en
Publication of CN104389317A publication Critical patent/CN104389317A/en
Application granted granted Critical
Publication of CN104389317B publication Critical patent/CN104389317B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to an ultralarge-sized oblique single-pile foundation structure of a large-span arch bridge, which solves the construction safety problem of a bridge foundation under unfavorable geographic situation such as bedding or under high environmental protection requirement, reduces the excavation amount of the foundation, alleviates the construction risk, alleviates the affection on the environment and reduces the engineering cost. The ultralarge-sized oblique single-pile foundation structure comprises a pile foundation, wherein the pile foundation is an integral single pile foundation and is directly combined with an arch ring into a whole, and a pile body goes deep into a rock layer along the extension direction of the axis of the arch ring.

Description

The only pile foundation structure of large-span arch bridge ultra-large type tilting
Technical field
The present invention relates to bridge, a kind of especially only pile foundation structure of large-span arch bridge ultra-large type tilting being applied to the poor and environmental requirement of geological conditions district higher.
Background technology
As everyone knows, large-span arch bridge, when not arranging self-balancing tie-rod, will produce very large horizontal thrust usually, as long as its basis is not anti-support vertical load, also will resist powerful horizontal thrust.So, there is thrust large-span arch bridge basis usually to adopt Analysis on Large-scale Group Piles Foundation or large-scale Extended chemotherapy.
Analysis on Large-scale Group Piles Foundation is made up of jointly more pile foundation and the cushion cap being connected to stake top.This arch bridge base is by after vertical load, and the interaction due to cushion cap, stake, soil makes the proterties such as its pile side resistance, end resistance, sedimentation change and different from common single pile, and bearing capacity is often not equal to each bearing capacity of single pile sum, and this is called efficiency of pile groups.Meanwhile, owing to not arranging inter-tie, the horizontal thrust that arch springing transmits is resisted from experiencing to cut primarily of pile foundation.Under special circumstances, also horizontal thrust can be resisted by arranging horizontal pile foundation.Because arch bridge level, vertical load are very large, pile foundation quantity is also a lot, therefore dimension of platform general also more common beam bridge pier cap in stake top is large many, and when side slope is comparatively steep or just matter condition is poor, during slope construction, excavated volume is also very large.
Large-scale Extended chemotherapy is load pier (platform) and superstructure transmitted directly is passed to more shallow supporting ground a kind of base form by it, and the general method of open cut foundation that adopts is constructed, therefore is referred to as again Open-cut Foundation or shallow foundation.It is thinner that Extended chemotherapy is generally applicable to covering layer, and the good bridge pier of base bearing capacity (platform), often applies to Bridges in Mountainous Areas basis, particularly large across abut basis.Extended chemotherapy generally adopts stairstepping, and its size comparatively multi-column pier foundation cushion cap wants large, and when side slope is comparatively steep or geology is poor, during slope construction, excavated volume is also very large.
In sum, although Analysis on Large-scale Group Piles Foundation or Extended chemotherapy use very general in arch bridge, also having individual prerequisite, is exactly that before large-scale cushion cap or Extended chemotherapy are constructed, the safety of slope excavation should ensure.General soil, stone class side slope allow ratio of slope excavation according to construction, and its safety all easily meets.If but the situation such as geological condition is poor, side slope is comparatively steep, as smashed to pieces in bedding rock sloper, rock, the excavation difficulty of large-scale cushion cap, Extended chemotherapy is large, risk is high, and engineering measure expense is high, simultaneously also very large to the destruction of environment.
Therefore, for geological conditions, the large-span arch bridge in poor and environmental requirement district higher, creates the innovation that a kind of novel base form will be a kind of property changed, significant.
Summary of the invention
Technical problem to be solved by this invention is the only pile foundation structure of a kind of large-span arch bridge ultra-large type tilting of invention, to solve adverse geological condition or environmental requirement district's bridge foundation construction safety issues higher such as concordant, reduce foundation excavation amount, reduce construction risk, reduce the impact on environment and reduction construction costs.
The technical solution adopted for the present invention to solve the technical problems is as follows:
The only pile foundation structure of large-span arch bridge ultra-large type tilting of the present invention, comprise pile foundation, it is characterized in that: described pile foundation is the only pile foundation of monolithic, direct and arch ring consolidation is integrated, and its pile body gos deep into rock-soil layer along the bearing of trend of arch ring axis.
The invention has the beneficial effects as follows, because pile foundation is direct and arch ring consolidation is integrated, horizontal force and vertical force are born in basis simultaneously, do not need to arrange cushion cap again and carry out internal force conversion, and therefore basic stress is succinct, and abut reaches Internal force of foundation, stress is continuous; During foundation construction, the relative multi-column pier foundation cushion cap of excavated section and Extended chemotherapy are much smaller, and significantly reduce construction risk; Construction method can use for reference method for tunnel construction, and technique is relatively simple.
Accompanying drawing explanation
This manual comprises following five width accompanying drawings:
Fig. 1 is the elevation of the only pile foundation structure of large-span arch bridge ultra-large type tilting of the present invention;
Fig. 2 is the profile of the only pile foundation structure of large-span arch bridge ultra-large type tilting of the present invention;
Fig. 3 is the construction pipe canopy protection figure of the only pile foundation structure of large-span arch bridge ultra-large type tilting of the present invention;
Fig. 4 is the construction profile of the only pile foundation structure of large-span arch bridge ultra-large type tilting of the present invention;
Component shown in figure and corresponding mark: arch ring 10, pile foundation 20, anchor cable 30, pipe canopy 41, anchor pole 42, steel erect support 43, steel arch-shelf 44, steel longeron 45, steel stull 46.
Detailed description of the invention
Below in conjunction with drawings and Examples, the present invention is further described.
With reference to Fig. 1,2, the only pile foundation structure of large-span arch bridge ultra-large type tilting of the present invention, comprise pile foundation 20, this pile foundation 20 is the only pile foundation of monolithic, and direct and arch ring 10 consolidation is integrated, and its pile body gos deep into rock-soil layer along the bearing of trend of arch ring 10 axis.Because pile foundation 20 is direct and arch ring 10 consolidation is integrated, horizontal force and vertical force are born in basis simultaneously, do not need to arrange cushion cap again and carry out internal force conversion, and therefore basic stress is succinct, and abut reaches Internal force of foundation, stress is continuous.During foundation construction, the relative multi-column pier foundation cushion cap of excavated section and Extended chemotherapy are much smaller, therefore effectively can reduce construction risk.
With reference to Fig. 2, described pile foundation 20 section configuration is similar to tunnel cross-section, and axially adopt uniform section or variable cross-section shape along pile body, pile body section is solid or hollow.Construction method can use for reference method for tunnel construction, and technique is relatively simple.
With reference to Fig. 1, the only pile foundation structure of large-span arch bridge ultra-large type tilting of the present invention is implemented according to the following steps:
1. clear up base top surface covering layer, in the certain limit of top, corresponding basis, apply anchor cable 30;
2. at ultra-large type tilting only pile foundation construction pipe canopy 41, excavation base top portion rock, then construction anchor pole 42, steel arch-shelf 44, steel longeron 45, steel erect support 43 and steel stull 46 according to the order of sequence; Construct along basic axial order by above flow process, until the end, basis;
3. concreting, completes foundation construction.Construct concrete near basic end face time note pre-buried arch ring steel pipe, reinforcing bar.
The present invention has that structure stress is clear and definite, the reliable feature of construction safety, applicant by its Successful utilization in the design of Chongqing-Guichow Railway youth at night river grand bridge and construction.The main bridge of this bridge adopts 1-370m reinforced concrete arch bridge.This bridge limits by geological conditions, and primary abutment plinth adopts form of structure of the present invention.
Some principles of the only pile foundation structure of the above large-span arch bridge ultra-large type tilting of the present invention that just explains through diagrams, be not the present invention to be confined to shown in and in described concrete structure and the scope of application, therefore every corresponding modify of being likely utilized and equivalent, all belong to the scope of the claims that the present invention applies for.

Claims (2)

1. the only pile foundation structure of large-span arch bridge ultra-large type tilting, comprise pile foundation (20), it is characterized in that: described pile foundation (20) is the only pile foundation of monolithic, direct and arch ring (10) consolidation is integrated, and its pile body gos deep into rock-soil layer along the bearing of trend of arch ring (10) axis.
2. the only pile foundation structure of large-span arch bridge ultra-large type tilting as claimed in claim 1, it is characterized in that: described pile foundation (20) section configuration is similar to tunnel cross-section, axially adopt uniform section or variable cross-section shape along pile body, pile body section is solid or hollow.
CN201410620062.2A 2014-11-06 2014-11-06 The only pile foundation construction of large-span arch bridge ultra-large type tilting Active CN104389317B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410620062.2A CN104389317B (en) 2014-11-06 2014-11-06 The only pile foundation construction of large-span arch bridge ultra-large type tilting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410620062.2A CN104389317B (en) 2014-11-06 2014-11-06 The only pile foundation construction of large-span arch bridge ultra-large type tilting

Publications (2)

Publication Number Publication Date
CN104389317A true CN104389317A (en) 2015-03-04
CN104389317B CN104389317B (en) 2017-10-10

Family

ID=52607270

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410620062.2A Active CN104389317B (en) 2014-11-06 2014-11-06 The only pile foundation construction of large-span arch bridge ultra-large type tilting

Country Status (1)

Country Link
CN (1) CN104389317B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105970992A (en) * 2016-05-31 2016-09-28 中铁局集团有限公司 Construction process for superlarge-section and large-dip-angle tunnel type pile foundation
CN105970990A (en) * 2016-05-31 2016-09-28 中铁局集团有限公司 Excavation and dado construction process for tilting type superlarge-section single-pile foundation
CN105970991A (en) * 2016-05-31 2016-09-28 中铁局集团有限公司 Excavation and mucking construction process for tilting type superlarge-section single-pile foundation
CN107761718A (en) * 2017-09-20 2018-03-06 中铁二院工程集团有限责任公司 Super-section tilting pile foundation self-supporting excavation construction method
CN109868746A (en) * 2019-01-31 2019-06-11 中铁广州工程局集团桥梁工程有限公司 A kind of entirety build-in type skewback foundation excavation method
CN112482228A (en) * 2020-11-20 2021-03-12 浙江省交通规划设计研究院有限公司 Arch bridge arch foot foundation structure and construction method thereof and arch bridge

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101638883A (en) * 2008-07-30 2010-02-03 上海市城市建设设计研究院 Arch bridge
KR20100138122A (en) * 2009-06-24 2010-12-31 (주)청석엔지니어링 Base of arch rigid frame structure including composite covering arch structure and constructing method thereof
CN102425103A (en) * 2011-08-22 2012-04-25 彭凯 Reinforced combined arch ring for arch bridge
CN102797218A (en) * 2012-08-22 2012-11-28 中铁二院工程集团有限责任公司 Large-span railway desk type concrete arch bridge structure
CN103088749A (en) * 2013-03-01 2013-05-08 天津市市政工程设计研究院 Deck type open shoulder arch bridge and constructing method thereof
CN203270438U (en) * 2013-04-24 2013-11-06 中铁工程设计咨询集团有限公司 Arch bridge foundation used for poor geological conditions
CN204185873U (en) * 2014-11-06 2015-03-04 中铁二院工程集团有限责任公司 The only pile foundation structure of large-span arch bridge ultra-large type tilting

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101638883A (en) * 2008-07-30 2010-02-03 上海市城市建设设计研究院 Arch bridge
KR20100138122A (en) * 2009-06-24 2010-12-31 (주)청석엔지니어링 Base of arch rigid frame structure including composite covering arch structure and constructing method thereof
CN102425103A (en) * 2011-08-22 2012-04-25 彭凯 Reinforced combined arch ring for arch bridge
CN102797218A (en) * 2012-08-22 2012-11-28 中铁二院工程集团有限责任公司 Large-span railway desk type concrete arch bridge structure
CN103088749A (en) * 2013-03-01 2013-05-08 天津市市政工程设计研究院 Deck type open shoulder arch bridge and constructing method thereof
CN203270438U (en) * 2013-04-24 2013-11-06 中铁工程设计咨询集团有限公司 Arch bridge foundation used for poor geological conditions
CN204185873U (en) * 2014-11-06 2015-03-04 中铁二院工程集团有限责任公司 The only pile foundation structure of large-span arch bridge ultra-large type tilting

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
马光瑞等: "高压喷射注射法及在公路建设中应用之探讨", 《湖南交通科技》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105970992A (en) * 2016-05-31 2016-09-28 中铁局集团有限公司 Construction process for superlarge-section and large-dip-angle tunnel type pile foundation
CN105970990A (en) * 2016-05-31 2016-09-28 中铁局集团有限公司 Excavation and dado construction process for tilting type superlarge-section single-pile foundation
CN105970991A (en) * 2016-05-31 2016-09-28 中铁局集团有限公司 Excavation and mucking construction process for tilting type superlarge-section single-pile foundation
CN105970991B (en) * 2016-05-31 2018-04-03 中铁一局集团有限公司 Large section tilting single-pile foundation excavates and muck removal construction technology
CN105970990B (en) * 2016-05-31 2018-08-03 中铁一局集团有限公司 Large section tilting single-pile foundation excavates and panelling construction technique
CN107761718A (en) * 2017-09-20 2018-03-06 中铁二院工程集团有限责任公司 Super-section tilting pile foundation self-supporting excavation construction method
CN109868746A (en) * 2019-01-31 2019-06-11 中铁广州工程局集团桥梁工程有限公司 A kind of entirety build-in type skewback foundation excavation method
CN112482228A (en) * 2020-11-20 2021-03-12 浙江省交通规划设计研究院有限公司 Arch bridge arch foot foundation structure and construction method thereof and arch bridge

Also Published As

Publication number Publication date
CN104389317B (en) 2017-10-10

Similar Documents

Publication Publication Date Title
CN104389317A (en) Ultralarge-sized oblique single-pile foundation structure of large-span arch bridge
CN101338678B (en) Supporting arch hidden digging top-down construction method
CN104532868B (en) High abrupt change shape sloped region bridge anchor pull-type high cap pile group basis construction method
CN204370431U (en) A kind of occlusion long-short pile space enclosing structure
CN104404861A (en) Steel trestle provided with steel anchor pile and construction method of steel trestle
CN202323970U (en) Combined reinforcement system for side slope
CN103306289A (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN103321234B (en) Constructing method of load-bearing structure built on high slope or geological complex area
CN105239586A (en) Support structure for supporting foundation pit and method for supporting foundation pit
CN103215889B (en) A kind of arch bridge base for poor geological conditions and construction method thereof
CN105155602A (en) Multi-support foundation strengthening comprehensive controlling method
CN102650212A (en) Construction method for protecting partition wall in double-arch tunnel through temporary support of middle pilot tunnel
CN104389315A (en) Consolidation grouting drilled pile wall and construction method thereof
CN103711139A (en) Semi-rigid connection structure between pile foundation and bearing platform
CN109457721B (en) Bridge foundation space protection structure on rock cone slope
CN203716046U (en) Steel trestle for earthwork transportation of foundation pit
CN204185873U (en) The only pile foundation structure of large-span arch bridge ultra-large type tilting
CN106759270A (en) A kind of prefabricated reinforced concrete resistance to plucking pile construction method with ribbing
CN104499501A (en) Narrow-foundation-tower single-pile pier-type self-stabilized foundation for power transmission line
CN206418509U (en) A kind of anchored pile supporting of high gradient slope
CN109487793A (en) Inner support of pile foundation pit permanent support structure is perfused in a kind of solid matter under complex environment
CN203270588U (en) Mini-pile antiskid structure
CN106087996A (en) Manual digging pile construction method based on oneself's leveling backpressure device
CN201738286U (en) Tetrapod pier type structure
CN212175363U (en) Frame-type anti-skidding structure with road system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant