CN104358412B - A kind of method of composite material building mould board mortar leakage prevention - Google Patents

A kind of method of composite material building mould board mortar leakage prevention Download PDF

Info

Publication number
CN104358412B
CN104358412B CN201410712071.4A CN201410712071A CN104358412B CN 104358412 B CN104358412 B CN 104358412B CN 201410712071 A CN201410712071 A CN 201410712071A CN 104358412 B CN104358412 B CN 104358412B
Authority
CN
China
Prior art keywords
composite material
mould board
seal groove
silica gel
material building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410712071.4A
Other languages
Chinese (zh)
Other versions
CN104358412A (en
Inventor
王永刚
吴冬生
陈威
蔡秋红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Haiyuan New Material Science & Technology Co Ltd
Original Assignee
Fujian Haiyuan New Material Science & Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Haiyuan New Material Science & Technology Co Ltd filed Critical Fujian Haiyuan New Material Science & Technology Co Ltd
Priority to CN201410712071.4A priority Critical patent/CN104358412B/en
Publication of CN104358412A publication Critical patent/CN104358412A/en
Application granted granted Critical
Publication of CN104358412B publication Critical patent/CN104358412B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Finishing Walls (AREA)
  • Building Environments (AREA)

Abstract

The present invention provides a kind of method of composite material building mould board mortar leakage prevention, and step is as follows: process seal groove in composite material building mould board surrounding;Coating adhesive water treatment agent in each seal groove;Coating adhesive water treatment agent on the silica gel strip corresponding with the seal groove of composite material building mould board surrounding, described glue inorganic agent coated weight is 1.2 1.8g/m;Coating glue at the seal groove being coated with glue inorganic agent with selecting one on corresponding silica gel strip, the coated weight of described glue is 2.0 2.8g/m;Finally silica gel strip is adhered in the seal groove of correspondence, ambient temperature curing 10 15min, and described silica gel strip exceeds composite material building mould board surface 0.6mm 0.8mm.The present invention can reduce the template difficulty caused because of spillage and tear the problem blocked by concrete with handle hole open, and reduces the problems such as cleaning difficulty when template reclaims is big and improve metope tidiness after template grouting.

Description

A kind of method of composite material building mould board mortar leakage prevention
[technical field]
A kind of method that the present invention relates to composite material building mould board mortar leakage prevention.
[background technology]
In recent years, dissipate that to spell plywood form easy to operate because of having, scene can the advantage such as Optional assembling, must Arrive increasing application, especially in the vertical structure templates such as body of wall;But due to material itself and The reason of the aspects such as execute-in-place, easily occurs the phenomenons such as spillage at form joint, causes seam crossing to go out The mass defect such as now connect stubble, flatness exceeds standard, and have a strong impact on the presentation quality of concrete.
In the template support of in-situ concrete wall, it is typically employed in template boring, and will be to drawing spiral shell Bolt passes from hole, then is fixed on two side templates by this split bolt.This mode greatest drawback Be be difficult to avoid that when cast-in-place concrete occur spillage image, if hole in template less and with to drawing It is then few that bolt mates tighter spillage, only affects the perception of in-situ concrete wall alien invasion, if in template The excessive spillage of upper boring is the most, easily causes the quality such as in-situ concrete wall honeycomb, pitted skin, dew muscle to lead to Disease, affects the quality of in-situ concrete wall, particularly In Great Basement body of wall or skyscraper body of wall Or in the project construction such as cable duct, frequently can lead to serious concrete wall quality problems.
[summary of the invention]
The technical problem to be solved in the present invention, is to provide the side of a kind of composite material building mould board mortar leakage prevention Method, it is possible to reduce the template difficulty caused because of spillage and tear the problem blocked by concrete with handle hole open, and reduce Clean the problems such as difficulty is big when template reclaims and improve metope tidiness after template grouting.
The present invention is achieved in that
A kind of method of composite material building mould board mortar leakage prevention, described method step is as follows:
Step 10, composite material building mould board surrounding process specification for (2mm ± 0.5mm) × The seal groove of (5mm ± 0.5mm);
Step 20, in each seal groove coating adhesive water treatment agent, described glue inorganic agent coated weight is 1.2-1.8g/m;
Step 30, painting on each silica gel strip corresponding with the seal groove of composite material building mould board surrounding Covering glue inorganic agent, described glue inorganic agent coated weight is 1.2-1.8g/m;The shore of described silica gel strip is hard Degree is for 30-40 °, and specification is (2.5mm ± 0.5m) × (4.5mm ± 0.5mm);
Step 40, be coated with glue inorganic agent seal groove and on corresponding silica gel strip select one be coated with Being covered with glue, the coated weight of described glue is 2.0-2.8g/m;
Step 50, finally silica gel strip is adhered to correspondence seal groove in, ambient temperature curing 10-15min, And described silica gel strip exceeds composite material building mould board surface 0.6mm-0.8mm.
Further, the normal temperature cure temperature of described step 50 is 18-27 DEG C.
Present invention have the advantage that
1. silica gel strip has compression stroke, on product piece without affecting after controlling fluting height;2. sealing effectiveness Well;3. silica gel strip is good with composite material building mould board adhesive, the most tear-away in addition to manual breakage; 4. breakage exists only in local, and follow-up useable glass glue is repaired.
In a word, the present invention can solve the problem that the piece produced because of deformation between composite material building mould board product is led Cause the impact on template total quality that spillage causes, it is possible to reduce the template difficulty caused because of spillage and tear open and hands The problem that delthyrium is blocked by concrete, and reduce the problems such as cleaning difficulty when template reclaims is big and improve mould Metope tidiness after plate grouting.
[detailed description of the invention]
A kind of method that the present invention relates to composite material building mould board mortar leakage prevention, described method step is as follows:
Step 10, composite material building mould board surrounding process specification for wide (2mm ± 0.5mm) × The seal groove of long (5mm ± 0.5mm);
Step 20, in each seal groove coating adhesive water treatment agent, described glue inorganic agent coated weight is 1.2-1.8g/m;
Step 30, painting on each silica gel strip corresponding with the seal groove of composite material building mould board surrounding Covering glue inorganic agent, described glue inorganic agent coated weight is 1.2-1.8g/m;The shore of described silica gel strip is hard Degree is for 30-40 °, and specification is wide (2.5mm ± 0.5m) × long (4.5mm ± 0.5mm);
Step 40, be coated with glue inorganic agent seal groove and on corresponding silica gel strip select one be coated with Being covered with glue, the coated weight of described glue is 2.0-2.8g/m;
Step 50, finally silica gel strip is adhered to correspondence seal groove in, ambient temperature curing 10-15min, And described silica gel strip exceeds composite material building mould board surface 0.6mm-0.8mm.
The normal temperature cure temperature of described step 50 is 18-27 DEG C.
Below in conjunction with detailed description of the invention, the present invention is further illustrated.
Embodiment
Present invention have the advantage that 1. silica gel strip has compression stroke, after controlling fluting height, product is spelled Seam is without impact;2. sealing effectiveness is good;3. silica gel strip is good with composite material building mould board adhesive, removes Outside manual breakage the most tear-away;4. breakage exists only in local, and follow-up useable glass glue is repaired.
In a word, the present invention can solve the problem that the piece produced because of deformation between composite material building mould board product is led Cause the impact on template total quality that spillage causes, it is possible to reduce the template difficulty caused because of spillage and tear open and hands The problem that delthyrium is blocked by concrete, and reduce the problems such as cleaning difficulty when template reclaims is big and improve mould Metope tidiness after plate grouting.
Although the foregoing describing the detailed description of the invention of the present invention, but it is familiar with the technology people of the art Member should be appreciated that our described specific embodiment is merely exemplary rather than for this The restriction of bright scope, those of ordinary skill in the art are in the equivalence made according to the spirit of the present invention Modify and change, all should contain in the scope of the claimed protection of the present invention.

Claims (2)

1. the method for a composite material building mould board mortar leakage prevention, it is characterised in that: described method step As follows:
Step 10, composite material building mould board surrounding process specification for (2mm ± 0.5mm) × The seal groove of (5mm ± 0.5mm);
Step 20, in each seal groove coating adhesive water treatment agent, described glue inorganic agent coated weight is 1.2-1.8g/m;
Step 30, painting on each silica gel strip corresponding with the seal groove of composite material building mould board surrounding Covering glue inorganic agent, described glue inorganic agent coated weight is 1.2-1.8g/m;The shore of described silica gel strip is hard Degree is for 30-40 °, and specification is (2.5mm ± 0.5m) × (4.5mm ± 0.5mm);
Step 40, be coated with glue inorganic agent seal groove and on corresponding silica gel strip select one be coated with Being covered with glue, the coated weight of described glue is 2.0-2.8g/m;
Step 50, finally silica gel strip is adhered to correspondence seal groove in, ambient temperature curing 10-15min, And described silica gel strip exceeds composite material building mould board surface 0.6mm-0.8mm.
The method of a kind of composite material building mould board mortar leakage prevention the most according to claim 1, it is special Levy and be: the normal temperature cure temperature of described step 50 is 18-27 DEG C.
CN201410712071.4A 2014-12-01 2014-12-01 A kind of method of composite material building mould board mortar leakage prevention Active CN104358412B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410712071.4A CN104358412B (en) 2014-12-01 2014-12-01 A kind of method of composite material building mould board mortar leakage prevention

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410712071.4A CN104358412B (en) 2014-12-01 2014-12-01 A kind of method of composite material building mould board mortar leakage prevention

Publications (2)

Publication Number Publication Date
CN104358412A CN104358412A (en) 2015-02-18
CN104358412B true CN104358412B (en) 2016-09-14

Family

ID=52525709

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410712071.4A Active CN104358412B (en) 2014-12-01 2014-12-01 A kind of method of composite material building mould board mortar leakage prevention

Country Status (1)

Country Link
CN (1) CN104358412B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105178601B (en) * 2015-06-04 2017-07-11 福建海源新材料科技有限公司 A kind of fluting gluing sealing technology of building template
CN111318748A (en) * 2020-03-30 2020-06-23 许广明 Grooving, gluing and sealing process for building template

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2005010290A1 (en) * 2003-07-23 2005-02-03 Stephen Peter Mcgregor Formwork
CN103015702A (en) * 2012-12-20 2013-04-03 南宁铁路局房产管理所 Method for splicing and repairing construction glued die plate
CN203334671U (en) * 2013-06-27 2013-12-11 贵州中建建筑科研设计院有限公司 Device for preventing slurry leakage at joint position of wood plastic formworks

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2005010290A1 (en) * 2003-07-23 2005-02-03 Stephen Peter Mcgregor Formwork
CN103015702A (en) * 2012-12-20 2013-04-03 南宁铁路局房产管理所 Method for splicing and repairing construction glued die plate
CN203334671U (en) * 2013-06-27 2013-12-11 贵州中建建筑科研设计院有限公司 Device for preventing slurry leakage at joint position of wood plastic formworks

Also Published As

Publication number Publication date
CN104358412A (en) 2015-02-18

Similar Documents

Publication Publication Date Title
CN104358412B (en) A kind of method of composite material building mould board mortar leakage prevention
CN204343722U (en) swimming pool gutter
CN105003009B (en) Space enclosed construction and its construction method between curtain wall and floor structure
US10385607B2 (en) Fixed glazing
CN206503231U (en) Section bar and the glass sunlight house with the section bar
CN204370794U (en) A kind of composite material building mould board structure of mortar leakage prevention
CN203846934U (en) Thin-wall light steel building window frame mounting structure
US9556616B2 (en) Light roofing system
KR101552593B1 (en) Waterproofing sheet having image printing layer for an inner wall and an outer wall and insulating construction method for preventing dew condensation on the wall by using it
CN106639083B (en) Profile formula aluminum facade and its installation method
CN202148627U (en) Point-type glass curtain wall provided with double-seal opening window
CN205224362U (en) Open type aluminum plate curtain wall
CN204139863U (en) A kind of concealed frame glass curtain wall casement window system
CN104234284B (en) A kind of copper plate curtain wall
CN202788470U (en) Hook opening mechanism for hidden-frame glass curtain wall
CN207194251U (en) Split curtain wall system waterproof construction
CN206035235U (en) Flat -open window inner frame section bar
CN205857462U (en) Wood siding wall structure
CN105735830B (en) Integrated artificial stone window frame and rapid mounting method of integrated artificial stone window frame and wall plate
CN112031594A (en) Installation and construction method for passive building external-hanging door and window
CN204385973U (en) A kind of unit curtain wall system being provided with cantilevered structure
CN202810528U (en) Hinge opening mechanism for frame-hidden glass curtain wall
CN206352472U (en) A kind of exterior window integrated guardrail
CN206468189U (en) A kind of joint filling adhesive tape special of door and window aluminium alloy decorative cover
CN208347075U (en) Connection component and open stone curtain wall for open stone curtain wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant