CN104217293A - Effective method for solving multi-target resource-constrained project scheduling - Google Patents
Effective method for solving multi-target resource-constrained project scheduling Download PDFInfo
- Publication number
- CN104217293A CN104217293A CN201410449558.8A CN201410449558A CN104217293A CN 104217293 A CN104217293 A CN 104217293A CN 201410449558 A CN201410449558 A CN 201410449558A CN 104217293 A CN104217293 A CN 104217293A
- Authority
- CN
- China
- Prior art keywords
- work
- sequence
- project
- scheduling
- resource
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses an effective method for solving multi-target resource-constrained project scheduling. The method comprises the following steps: (1) establishing a multi-target resource-constrained project scheduling mathematical model based on duration-cost optimization; (2) generating an initial feasible scheduling sequence; (3) evaluating the scheduling sequence; (4) updating the scheduling sequence; (5) configuring non-dominated disaggregation operation; (6) maintaining an external archive set; and (7) performing updating iteration till an optimal solution set is output. According to the method disclosed by the invention, each intelligent body corresponds to a linked list sequence in a scheduling problem, the scheduling sequence of a task linked list and a corresponding execution mode sequence are coded respectively, decoding operation is performed by adopting a serial method, and evolution and update are performed among the linked list sequences through competition, intersection and self-learning; and a project scheduling plan is adjusted, so that comprehensive optimal duration and cost are realized within a control period on the premise of satisfying conditions such as timing constraint and resource constraint.
Description
Technical field
The invention belongs to system call and control technology field, relate to a kind of effective ways that solve multiple goal Resource-constrained Project Scheduling Problem.
Background technology
Resource constrained project scheduling problem is widely used in the scheduling fields such as construction work, communications and transportation, software development, production, electric system, its difficult point is to meet under the prerequisite of temporal constraint and resource constraint, according to the task of certain regular reasonable arrangement project, and in the implementation of project, include multiple patterns, require between multiple conflicting targets, to weigh in cost resource optimal utilization, find the optimal balance point between each target, be met one group of optimal solution set of project demand.Therefore consider the research of the multiple goal Resource-constrained Project Scheduling Problem of project duration and project cost, not only have important theory significance, and be the most real selection of scheduling problem, therefore formulating rational operation plan is the emphasis of studying at present.
Multi-Agent evolutionary Algorithm is as a branch of intelligent optimization algorithm, it is the angle from multiagent system, individuality in evolution algorithm is used as to an intelligent body that has local sensing, competition cooperation and self-learning capability, reaches and optimize overall object by the interaction between intelligent body self and intelligent body.Due to independence, distributivity, harmony and self organization ability, learning ability and the inferential capability of multiple agent, make it in the time of solving practical problems, there is stronger reliability and higher solution efficiency, but multi-Agent evolutionary Algorithm is used for greatly single goal aspect at present.
Summary of the invention
The object of this invention is to provide a kind of effective ways that solve multiple goal Resource-constrained Project Scheduling Problem, solved existing dispatching method and in scheduling, between the limit for a project and the cost, be difficult to regulate, be difficult for obtaining the problem of optimum efficiency.
The technical solution adopted in the present invention is: a kind of effective ways that solve multiple goal Resource-constrained Project Scheduling Problem, implement according to following steps:
Step 1, the multiple goal Resource-constrained Project Scheduling Problem mathematical model of foundation based on time-cost trade-off
Suppose that the work number in project is J, the temporal constraint before and after having between each work j, has j=1, and 2 ..., J, note Q
jthe j set before of and then working, H
jit is the j set afterwards of and then working; Set maximum iteration time H, iterations initial value h=1, work 1 is unique work of early start, work J is the unique work completing the latest; In project, renewable resources species number is K, and unrenewable resource species number is N, k=1, and 2 ... K, n=1,2 ... N, k kind renewable resources in the aggregate supply in each stage is
, n kind unrenewable resource total amount is
; Each work has various modes available, and work j need select M
jone of the pattern of kind operates, and can not interrupt or change in operational process; When work j moves under m kind pattern, m=1,2 ... M
j, the demand of k kind renewable resources is
, the demand of n kind unrenewable resource is
, be d working time
jm, the work resource sum used moving can not exceed the aggregate supply of resource, above each value round numbers,
Model of creation is as follows accordingly:
One of formula (1) is target, and this target is the expression formula that minimizes Project duration, [ED in formula
j, LD
j] for work J the earliest with Late Finish section; T represents t stage, x
j1Tthe completion status in T stage that is work j under the first pattern, if complete x
j1T=1, otherwise x
j1T=0;
Formula (2) is target two, and this target is the expression formula that minimizes project cost, M in formula
jwhat represent is the execution pattern number of work j; c
jmthe cost of work j under mode m; J is all working number of project;
Formula (3) represents that each work can only realize once in one mode, x in formula
jmtwhat represent is the state that work j carried out in the m kind pattern t stage; [ED
j, LD
j] represent be work j the earliest with Late Finish section;
Formula (4) represents the tight front restriction relation of project, x
imtand x
jmtit is respectively work i and the work j executing state in the m kind pattern t stage; d
jmit is the execution time of work j under m kind pattern;
Formula (5) is inequality constrain, has ensured that the renewable resources amount of each work use is no more than the aggregate supply in this stage,
be the demand of k kind renewable resources,
be k kind renewable resources in the aggregate supply in each stage,
for the duration upper limit;
Formula (6) is to ensure that the unrenewable resource amount that all working uses can not exceed the total quantity delivered of whole project,
be the demand of n kind unrenewable resource,
it is n kind unrenewable resource total amount;
x
jmt={0,1},j=1,2,...,J,m=1,2,...,M
j,t=ED
j,...,LD
j; (7)
Formula (7) is the span of correlated variables in model, x
jmtthe completion status of expression work j under m kind pattern, has x if complete
jmt=1, otherwise x
jmt=0;
Step 2, produce initial feasible schedule sequence
Each work in project is made up of two parts, that is:
Wherein, S
i=j
1, j
2... j
j, S
ibeing the scheduling sequence that meets temporal constraint in i Task-list, is the execution sequence table of each work in project; M
i=m
1, m
2..., m
j, M
ibe the corresponding mode sequences of each task in this Task-list, the mode sequences in project is one to one with scheduling sequence, generates at random in the process of implementation the corresponding pattern M of S, and ensures that the pattern count generating is not more than the assemble mode number of this work,
Determined the preceding activity collection p of work j by temporal constraint
jwith tight rear working set s
j, use adjacency matrix G=[g
ij]
j × Jrepresent the tight front tight rear relation of workplace, wherein as i ∈ P
jtime, g
i,j=1, otherwise g
i,j=0;
Initialization project scheduling sequence S and executed work sequence number s
1=1, making Job is blank vector, k=1, the s of retrieve stored adjacency matrix
hoK, search in-degree and be 1 working set, add in Job sequence, from Job, delete a work sequence number u with highest priority, and this sequence number u is assigned to s
h+1, element a in adjacency matrix simultaneously
iu(i=s
h+1) subtract 1, make k=k+1, if k<J continues to calculate, otherwise output S;
Step 3, to scheduling sequence evaluate
The scheduling sequence S and the mode sequences M that generate according to project, carry out decode operation by serial scheme, makes T
stthe start time of expression project, T
i=t
i1, t
i2..., t
ij..., t
iJand C
i=c
i1, c
i2..., c
ij..., c
iJstart time and the cost of corresponding work in i the chained list that represents respectively to obtain through coding, judgement is operated under its execution pattern whether have resource contention, finds the t on earliest finish time of this chained list
iJ=max{t
ij+ d
jmand corresponding cost c
iJ=∑ c
jm;
Step 4, to scheduling sequence upgrade
Adopt multi-Agent evolutionary Algorithm to upgrade scheduling sequence, by with its neighborhood in work competition, intersect, three kinds of modes of operation of self study complete renewal;
Step 5, construct the operation of non-domination disaggregation;
Step 6, outside filing collection is safeguarded;
Step 7, renewal iterations h=h+1, if h < is J, continue repeating step 2 to step 6, otherwise output Pareto optimal solution set.
The invention has the beneficial effects as follows, utilize the data analysis to the resource-constrained project problem collecting, in conjunction with multi-Agent evolutionary Algorithm, realize solving resource constrained project scheduling problem.A chained list sequence in the corresponding scheduling problem of each intelligent body in algorithm, scheduling sequence to Task-list and execution pattern sequence are corresponding thereto encoded respectively, adopt serial approach to carry out decode operation, between each chained list sequence, realize and evolve and upgrade by operations such as competition, intersection, self studies.By the operation plan of adjusted iterm, under the condition that meets temporal constraint and resource constraint etc., the feasible schedule of the each work of reasonable arrangement day part, for the operation and control of dispatching system provides multiple feasible program, decision maker can therefrom determine final scheme according to different requirements, makes duration and cost in this control cycle reach comprehensive optimum.
The advantage of the inventive method specifically comprises:
1) J is counted in the work that pre-determines out project, renewable resources species number K, unrenewable resource species number N, sequential relationship between each work, the required number of resources of each work, and be provided with temporal constraint and resource constraint according to these preset values, the iteration for the first time of Shi Ge working group vector meets above-mentioned constraint condition, then from the iteration for the first time of each working group vector, carry out loop iteration h-1 time, it is iterative vectorized as global optimum that the final target function value of determining T the period of sening as an envoy to reaches optimum working group's vector, therefore the inventive method takes into full account that Liao Ge working group is in the different resource requirement of day part, the randomness of feasible schedule sequence, on this basis, realize continuing to optimize of project duration by h-1 vectorial iteration, finally obtain the optimal value of working group at day part project duration.
2) there is good global convergence performance and speed of convergence faster, use it for and solve project duration and project cost multiple goal resource constrained project scheduling problem, can effectively realize the scheduling real-time of project.
3) relation between allocate resource use amount and work schedule sufficiently and reasonably, is conducive to find fast optimal solution set.
4) optimum that can automatically obtain working group is allocated scheme, does not need people's participation in optimizing process, and this is conducive to reduce the impact of human factor on optimal speed, optimization quality, improves the gentle optimization quality of Automated water.
Embodiment
Below in conjunction with embodiment, the present invention is described in detail.
The target of the resource constrained project scheduling problem of time-cost trade-off to be solved by this invention is, under the prerequisite that meets work schedule constraint and resource constraint, generate feasible scheduling sequence and mode sequences, the duration of identifying project and corresponding cost, make project duration the shortest, integrated cost minimum.
The present invention solves the effective ways of multiple goal Resource-constrained Project Scheduling Problem, specifically implements according to following steps:
Step 1, the multiple goal Resource-constrained Project Scheduling Problem mathematical model of foundation based on time-cost trade-off
Suppose that the work number in project is J, the temporal constraint before and after having between each work j, has j=1, and 2 ..., J, note Q
jthe j set before of and then working, H
jit is the j set afterwards of and then working; Set maximum iteration time H (H is integer), iterations initial value h=1, work 1 is unique work of early start, work J is the unique work completing the latest, be dummy activity, consumption of natural resource not in the process of implementation, also holding time not; In project, renewable resources species number is K, and unrenewable resource species number is N, k=1, and 2 ... K, n=1,2 ... N, k kind renewable resources in the aggregate supply in each stage is
, n kind unrenewable resource total amount is
; Each work has various modes available, and work j need select M
jone of the pattern of kind operates, and can not interrupt or change in operational process; When work j moves under m kind pattern, m=1,2 ... M
j, the demand of k kind renewable resources is
, the demand of n kind unrenewable resource is
, be d working time
jm, the work resource sum used moving can not exceed the aggregate supply of resource, above each value round numbers.
Model of creation is as follows accordingly:
One of formula (1) is target, and this target is the expression formula that minimizes Project duration, [ED in formula
j, LD
j] for work J the earliest with Late Finish section; T represents t stage, x
j1Tthe completion status in T stage that is work j under the first pattern, if complete x
j1T=1, otherwise x
j1T=0;
Formula (2) is target two, and this target is the expression formula that minimizes project cost, M in formula
jwhat represent is the execution pattern number of work j; c
jmthe cost of work j under mode m; J is all working number of project;
Formula (3) represents that each work can only realize once in one mode, x in formula
jmtwhat represent is the state that work j carries out in the time of the m kind pattern t stage; [ED
j, LD
j] represent be work j the earliest with Late Finish section;
Formula (4) represents the tight front restriction relation of project, before tight, restriction relation refers to and between work in every, exists ordinal relation, other are operated in this work and can not start before completing, the deadline of work is the summation of its start time and execution time, and the work after this work all must be after this end-of-job and met under the condition of resource constraint and could start execution; x
imtand x
jmtrespectively work i and the executing state of work j in the time of the m kind pattern t stage; d
jmit is the execution time of work j under m kind pattern;
Formula (5) is inequality constrain, has ensured that the renewable resources amount of each work use is no more than the aggregate supply in this stage; In formula
be the demand of k kind renewable resources,
be k kind renewable resources in the aggregate supply in each stage,
for the duration upper limit;
Formula (6) is to ensure that the unrenewable resource amount that all working uses can not exceed the total quantity delivered of whole project,
be the demand of n kind unrenewable resource,
it is n kind unrenewable resource total amount;
x
jmt={0,1},j=1,2,...,J,m=1,2,...,M
j,t=ED
j,...,LD
j; (7)
Formula (7) is the span of correlated variables in model, x
jmtthe completion status of expression work j under m kind pattern, has x if complete
jmt=1, otherwise x
jmt=0;
Step 2, produce initial feasible schedule sequence (i.e. coding)
Each work in project is made up of two parts, that is:
Wherein, S
i=j
1, j
2... j
j, S
ibeing the scheduling sequence that meets temporal constraint in i Task-list, is the execution sequence table of each work in project; M
i=m
1, m
2..., m
j, M
ibe the corresponding mode sequences of each task in this Task-list, the mode sequences in project is one to one with scheduling sequence, generates at random in the process of implementation the corresponding pattern M of S, and ensures that the pattern count generating is not more than the assemble mode number of this work,
Determined the preceding activity collection p of work j by temporal constraint
jwith tight rear working set s
j, use adjacency matrix G=[g
ij]
j × Jrepresent the tight front tight rear relation of workplace, wherein as i ∈ P
jtime, g
i,j=1, otherwise g
i,j=0;
Initialization project scheduling sequence S and executed work sequence number s
1=1, making Job is blank vector, k=1, the s of retrieve stored adjacency matrix
hoK, search in-degree and be 1 working set, add in Job sequence, from Job, delete a work sequence number u with highest priority, and this sequence number u is assigned to s
h+1, element a in adjacency matrix simultaneously
iu(i=s
h+1) subtract 1, make k=k+1, if k<J continues to calculate, otherwise output S;
Step 3, to scheduling sequence evaluate
The target of resource constrained project scheduling problem is the duration-cost minimization of project, and the scheduling sequence S and the mode sequences M that generate according to project, carry out decode operation by serial scheme,
Make T
stthe start time of expression project, T
i=t
i1, t
i2..., t
ij..., t
iJand C
i=c
i1, c
i2..., c
ij..., c
iJstart time and the cost of corresponding work in i the chained list that represents respectively to obtain through coding, judgement is operated under its execution pattern whether have resource contention, finds the t on earliest finish time of this chained list
iJ=max{t
ij+ d
jmand corresponding cost c
iJ=∑ c
jm;
Step 4, to scheduling sequence upgrade
Start to adopt multi-Agent evolutionary Algorithm to upgrade scheduling sequence from step 4, by with its neighborhood in work competition, intersect, three kinds of modes of operation of self study complete renewal,
4.1) contention operation
Suppose i chained list { S
i, M
icorresponding duration-cost is { t
i, c
i, duration-cost optimum in its neighborhood is
if,
and
(this symbol is not is less than, is a kind of symbol that represents precedence relationship), this chained list continues survival in grid, otherwise is removed grid, and with the new chained list of generation S '
i, M '
ireplace P
0∈ (0,1) is occupation probability, and detailed process is:
Step1: initialization S '
i, M '
i, by { S
i, M
ibe assigned to S '
i, M '
i, make k=1;
Step2: produce at random u ∈ (0,1), if u≤P
0, turn Step4, otherwise make k=k+1;
Step3: if k < is J, turn Step2, otherwise turn Step6;
Step4: a random integer r who is not equal to k, the exchange j of selecting between (1, J)
rand j
kobtain S '
iif, S '
imeet tight front relation constraint, turn Step5, otherwise recover, make k=k+1, turn Step3;
Step5: the pattern of a certain work j of randomly changing, obtains M '
i, check whether this pattern dispatching sequence meets resource constraint, if meet, turn Step6, otherwise recover;
Step6: upgrade chained list, calculate corresponding duration-cost, obtain new sequence;
4.2) interlace operation
Suppose i chained list sequence { S
i, M
icarry out interlace operation with the chained list in its neighborhood, and 1≤i≤Popsize, that participate in intersecting is { S
f, M
fand { S
m, M
m, after intersecting, generate respectively { S
d, M
dand { S
s, M
s, two integer r of random generation between (1, J)
1and r
2, specific operation process is:
4.2.1) scheduling sequence is intersected
If point of crossing is r
1, S
dfront r
1individual sequence k=1,2 ..., r
1derive from S
m, rear J-r
1individual sequence k=r
1+ 1 ..., J derives from S
f, and S
din existing sequence no longer consider, maintain all the other sequences at S
fin relative position constant, S
sgeneration in contrast;
4.2.2) mode sequences is intersected
If point of crossing is r
2, M
dfront r
2individual sequence k=1,2 ..., r
2derive from M
m, rear J-r
2individual sequence k=r
2+ 1 ..., J derives from M
f, M
sgeneration in contrast;
4.3) self study operation
Self study operation is used for realizing Local Search operation, increases the diversity of population,, under the restriction that meets temporal constraint, some work in chained list is carried out to the displacement of position, and the change of pattern, according to probability P
s1carry out task scheduling sequence self study operation, according to probability P
s2carry out mission mode sequence self study operation, detailed process is:
Step1 produces w ∈ (0,1) at random, if w < is P
s1, turn Step2, the scheduling sequence in chained list is carried out to self study operation; If w < is P
s2, turn Step3, the mode sequences in chained list is carried out to self study operation; Otherwise, turn Step4;
Step2 is the random a certain position V that generates scheduling sequence S between (1, J), finds all tight front nodal point of this position at the rearmost position u dispatching in sequence
1, and all tight posterior nodal points in scheduling the front position u in sequence
2, between front position and rearmost position, position u of random choose, is inserted into u place v, is newly dispatched sequence S ';
The pattern of Step3 randomly changing task j, obtains M', checks the work under this pattern whether to meet the constraint of resource, if meet, turns Step4, otherwise regenerates a group mode;
Step4 upgrades chained list sequence, calculates corresponding duration-cost;
Step 5, construct the operation of non-domination disaggregation
Prior art generally adopts NSGA-II[14] in non-dominated Sorting constructing tactics Pareto disaggregation, but this strategy is easily lost the individuality of not arranging mutually.
The present invention adopts following methods to form Pareto disaggregation, and concrete steps are:
5.1) all individual sequence numbers are initialized as to rank (a)=1;
5.2) to any individual a, b,
If
, rank (b)=rank (b)+1;
If
, rank (a)=rank (a)+1; If both do not arrange mutually, individual a, the sequence number of b is constant;
5.3) individuality that is 1 by sequence number is put into non-domination solution and is concentrated, and forms contemporary Pareto disaggregation;
Step 6, outside filing collection is safeguarded
Utilize extraction, analysis to relevant information in resource scheduling system, in conjunction with multiple goal multi-Agent evolutionary Algorithm, realize the optimization of scheduling sequence; Because target is that project duration and project cost are simultaneously optimum, therefore the non-bad feasible schedule solution that relatively duration and cost obtain being each time stored in to outside filing concentrates, outside the renewal of outside filing collection except the non-domination scheduling in population, also combine existing crowding distance method and make the outside filing obtaining collect more even, detailed process is:
The active power of the non-domination feasible schedule in population is put into outside filing one by one to be concentrated, if the active power that the active power of this feasible schedule is filed concentrated feasible schedule by outside is arranged, the active power of this feasible schedule is deleted from filing to concentrate, otherwise the active power of this feasible schedule adds filing collection; Be less than max cap. if file the active power number of concentrated feasible schedule, do not carry out deletion action, otherwise the crowding distance that calculates the active power of the concentrated all feasible schedule of current filing, the active power of deleting that feasible schedule of crowding distance minimum makes to file concentrated feasible schedule and remains on the number that is less than or equal to max cap.;
Step 7, renewal iterations h=h+1, if h < is J, continue repeating step 2 to step 6, otherwise output Pareto optimal solution set.
The inventive method is for the multiple goal multi-mode resource constrained project scheduling problem of duration-cost, a kind of new multiple goal multi-Agent evolutionary Algorithm has been proposed, utilize intelligent body Distributed and parallel structure and neighbour structure, not only effectively avoid algorithm to enter precocity, also maintain the diversity of population, realized the Resource-constrained Project Scheduling Problem taking the shortest and cost minimization of duration as target.
Claims (4)
1. solve effective ways for multiple goal Resource-constrained Project Scheduling Problem, its feature is, implements according to following steps:
Step 1, the multiple goal Resource-constrained Project Scheduling Problem mathematical model of foundation based on time-cost trade-off
Suppose that the work number in project is J, the temporal constraint before and after having between each work j, has j=1, and 2 ..., J, note Q
jthe j set before of and then working, H
jit is the j set afterwards of and then working; Set maximum iteration time H, iterations initial value h=1, work 1 is unique work of early start, work J is the unique work completing the latest; In project, renewable resources species number is K, and unrenewable resource species number is N, k=1, and 2 ... K, n=1,2 ... N, k kind renewable resources in the aggregate supply in each stage is
n kind unrenewable resource total amount is
each work has various modes available, and work j need select M
jone of the pattern of kind operates, and can not interrupt or change in operational process; When work j moves under m kind pattern, m=1,2 ... M
j, the demand of k kind renewable resources is
the demand of n kind unrenewable resource is
be d working time
jm, the work resource sum used moving can not exceed the aggregate supply of resource, above each value round numbers,
Model of creation is as follows accordingly:
One of formula (1) is target, and this target is the expression formula that minimizes Project duration, [ED in formula
j, LD
j] for work J the earliest with Late Finish section; T represents t stage, x
j1Tthe completion status in T stage that is work j under the first pattern, if complete x
j1T=1, otherwise x
j1T=0;
Formula (2) is target two, and this target is the expression formula that minimizes project cost, M in formula
jwhat represent is the execution pattern number of work j; c
jmthe cost of work j under mode m; J is all working number of project;
Formula (3) represents that each work can only realize once in one mode, x in formula
jmtwhat represent is the state that work j carries out in the time of the m kind pattern t stage; [ED
j, LD
j] represent be work j the earliest with Late Finish section;
Formula (4) represents the tight front restriction relation of project, x
imtand x
jmtrespectively work i and the executing state of work j in the time of the m kind pattern t stage; d
jmit is the execution time of work j under m kind pattern;
Formula (5) is inequality constrain, has ensured that the renewable resources amount of each work use is no more than the aggregate supply in this stage,
be the demand of k kind renewable resources,
be k kind renewable resources in the aggregate supply in each stage,
for the duration upper limit;
Formula (6) is to ensure that the unrenewable resource amount that all working uses can not exceed the total quantity delivered of whole project,
be the demand of n kind unrenewable resource,
it is n kind unrenewable resource total amount;
x
jmt={0,1},j=1,2,...,J,m=1,2,...,M
j,t=ED
j,...,LD
j; (7)
Formula (7) is the span of correlated variables in model, x
jmtthe completion status of expression work j under m kind pattern, has x if complete
jmt=1, otherwise x
jmt=0;
Step 2, produce initial feasible schedule sequence
Each work in project is made up of two parts, that is:
Wherein, S
i=j
1, j
2... j
j, S
ibeing the scheduling sequence that meets temporal constraint in i Task-list, is the execution sequence table of each work in project; M
i=m
1, m
2..., m
j, M
ibe the corresponding mode sequences of each task in this Task-list, the mode sequences in project is one to one with scheduling sequence, generates at random in the process of implementation the corresponding pattern M of S, and ensures that the pattern count generating is not more than the assemble mode number of this work,
Determined the preceding activity collection p of work j by temporal constraint
jwith tight rear working set s
j, use adjacency matrix G=[g
ij]
j × Jrepresent the tight front tight rear relation of workplace, wherein as i ∈ P
jtime, g
i,j=1, otherwise g
i,j=0;
Initialization project scheduling sequence S and executed work sequence number s
1=1, making Job is blank vector, k=1, the s of retrieve stored adjacency matrix
hoK, search in-degree and be 1 working set, add in Job sequence, from Job, delete a work sequence number u with highest priority, and this sequence number u is assigned to s
h+1, element a in adjacency matrix simultaneously
iu(i=s
h+1) subtract 1, make k=k+1, if k<J continues to calculate, otherwise output S;
Step 3, to scheduling sequence evaluate
The scheduling sequence S and the mode sequences M that generate according to project, carry out decode operation by serial scheme, makes T
stthe start time of expression project, T
i=t
i1, t
i2..., t
ij..., t
iJand C
i=c
i1, c
i2..., c
ij..., c
iJstart time and the cost of corresponding work in i the chained list that represents respectively to obtain through coding, judgement is operated under its execution pattern whether have resource contention, finds the t on earliest finish time of this chained list
iJ=max{t
ij+ d
jmand corresponding cost c
iJ=∑ c
jm;
Step 4, to scheduling sequence upgrade
Adopt multi-Agent evolutionary Algorithm to upgrade scheduling sequence, by with its neighborhood in work competition, intersect, three kinds of modes of operation of self study complete renewal;
Step 5, construct the operation of non-domination disaggregation;
Step 6, outside filing collection is safeguarded;
Step 7, renewal iterations h=h+1, if h < is J, continue repeating step 2 to step 6, otherwise output Pareto optimal solution set.
2. the effective ways that solve multiple goal Resource-constrained Project Scheduling Problem according to claim 1, its feature is, in described step 4, competition, intersection, three kinds of mode of operation detailed processes of self study are:
4.1) contention operation
Suppose i chained list { S
i, M
icorresponding duration-cost is { t
i, c
i, duration-cost optimum in its neighborhood is
if
and
this chained list continues survival in grid, otherwise is removed grid, and with the new chained list of generation S '
i, M '
ireplace P
0∈ (0,1) is occupation probability, and detailed process is:
Step1: initialization S '
i, M '
i, by { S
i, M
ibe assigned to S '
i, M '
i, make k=1;
Step2: produce at random u ∈ (0,1), if u≤P
0, turn Step4, otherwise make k=k+1;
Step3: if k < is J, turn Step2, otherwise turn Step6;
Step4: a random integer r who is not equal to k, the exchange j of selecting between (1, J)
rand j
kobtain S '
iif, S '
imeet tight front relation constraint, turn Step5, otherwise recover, make k=k+1, turn Step3;
Step5: the pattern of a certain work j of randomly changing, obtains M '
i, check whether this pattern dispatching sequence meets resource constraint, if meet, turn Step6, otherwise recover;
Step6: upgrade chained list, calculate corresponding duration-cost, obtain new sequence;
4.2) interlace operation
Suppose i chained list sequence { S
i, M
icarry out interlace operation with the chained list in its neighborhood, and 1≤i≤Popsize, that participate in intersecting is { S
f, M
fand { S
m, M
m, after intersecting, generate respectively { S
d, M
dand { S
s, M
s, two integer r of random generation between (1, J)
1and r
2, specific operation process is:
4.2.1) scheduling sequence is intersected
If point of crossing is r
1, S
dfront r
1individual sequence k=1,2 ..., r
1derive from S
m, rear J-r
1individual sequence k=r
1+ 1 ..., J derives from S
f, and S
din existing sequence no longer consider, maintain all the other sequences at S
fin relative position constant, S
sgeneration in contrast;
4.2.2) mode sequences is intersected
If point of crossing is r
2, M
dfront r
2individual sequence k=1,2 ..., r
2derive from M
m, rear J-r
2individual sequence k=r
2+ 1 ..., J derives from M
f, M
sgeneration in contrast;
4.3) self study operation
Self study operation is used for realizing Local Search operation, increases the diversity of population,, under the restriction that meets temporal constraint, some work in chained list is carried out to the displacement of position, and the change of pattern, according to probability P
s1carry out task scheduling sequence self study operation, according to probability P
s2carry out mission mode sequence self study operation, detailed process is:
Step1 produces w ∈ (0,1) at random, if w < is P
s1, turn Step2, the scheduling sequence in chained list is carried out to self study operation; If w < is P
s2, turn Step3, the mode sequences in chained list is carried out to self study operation; Otherwise, turn Step4;
Step2 is the random a certain position V that generates scheduling sequence S between (1, J), finds all tight front nodal point of this position at the rearmost position u dispatching in sequence
1, and all tight posterior nodal points in scheduling the front position u in sequence
2, between front position and rearmost position, position u of random choose, is inserted into u place v, is newly dispatched sequence S ';
The pattern of Step3 randomly changing task j, obtains M', checks the work under this pattern whether to meet the constraint of resource, if meet, turns Step4, otherwise regenerates a group mode;
Step4 upgrades chained list sequence, calculates corresponding duration-cost.
3. the effective ways that solve multiple goal Resource-constrained Project Scheduling Problem according to claim 1, its feature is, in described step 5, adopts following methods to form Pareto disaggregation, concrete steps are:
5.1) all individual sequence numbers are initialized as to rank (a)=1;
5.2) to any individual a, b,
If
rank (b)=rank (b)+1;
If
rank (a)=rank (a)+1; If both do not arrange mutually, individual a, the sequence number of b is constant;
5.3) individuality that is 1 by sequence number is put into non-domination solution and is concentrated, and forms contemporary Pareto disaggregation.
4. the effective ways that solve multiple goal Resource-constrained Project Scheduling Problem according to claim 1, its feature is, in described step 6, utilizes extraction, analysis to relevant information in resource scheduling system, in conjunction with multiple goal multi-Agent evolutionary Algorithm, realize the optimization of scheduling sequence, because target is that project duration and project cost are simultaneously optimum, therefore the non-bad feasible schedule solution that relatively duration and cost obtain being each time stored in to outside filing concentrates, outside the renewal of outside filing collection except the non-domination scheduling in population, also combining existing crowding distance method makes the outside filing obtaining collect more even, detailed process is: the active power of the non-domination feasible schedule in population is put into outside filing one by one and concentrate, if the active power that the active power of this feasible schedule is filed concentrated feasible schedule by outside is arranged, the active power of this feasible schedule is deleted from filing to concentrate, otherwise the active power of this feasible schedule adds filing collection, be less than max cap. if file the active power number of concentrated feasible schedule, do not carry out deletion action, otherwise the crowding distance that calculates the active power of the concentrated all feasible schedule of current filing, the active power of deleting that feasible schedule of crowding distance minimum makes to file concentrated feasible schedule and remains on the number that is less than or equal to max cap..
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410449558.8A CN104217293A (en) | 2014-09-04 | 2014-09-04 | Effective method for solving multi-target resource-constrained project scheduling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410449558.8A CN104217293A (en) | 2014-09-04 | 2014-09-04 | Effective method for solving multi-target resource-constrained project scheduling |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104217293A true CN104217293A (en) | 2014-12-17 |
Family
ID=52098752
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410449558.8A Pending CN104217293A (en) | 2014-09-04 | 2014-09-04 | Effective method for solving multi-target resource-constrained project scheduling |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104217293A (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105183640A (en) * | 2015-08-07 | 2015-12-23 | 黑龙江大学 | Real-time task schedulability test copying simulation method based on linear linked list |
CN108446852A (en) * | 2018-03-23 | 2018-08-24 | 西北工业大学 | A kind of multiagent schedule fragments formula coordination optimizing method |
CN109190857A (en) * | 2018-10-30 | 2019-01-11 | 武汉大学 | A kind of optimization algorithm based on multiple target Resource-constrained Project Scheduling Problem model |
CN110070248A (en) * | 2018-01-19 | 2019-07-30 | 财团法人工业技术研究院 | Dynamic and intelligent dispatching method and device |
CN110866586A (en) * | 2019-10-14 | 2020-03-06 | 西南交通大学 | Improved genetic programming algorithm optimization method for resource-constrained multi-project scheduling |
CN110991917A (en) * | 2019-12-10 | 2020-04-10 | 浙江工业大学 | Multi-mode resource-limited project scheduling optimization method adopting two-stage genetic algorithm |
CN111027856A (en) * | 2019-12-10 | 2020-04-17 | 浙江工业大学 | Multi-mode resource-limited project scheduling method based on two-dimensional multi-population genetic algorithm |
CN113344383A (en) * | 2021-06-04 | 2021-09-03 | 兰州理工大学 | Energy-saving workshop scheduling system for distributed heterogeneous factory |
CN115375193A (en) * | 2022-10-24 | 2022-11-22 | 埃克斯工业有限公司 | Method, device and equipment for optimizing double-target production scheduling and readable storage medium |
CN118569609A (en) * | 2024-08-01 | 2024-08-30 | 四川公路桥梁建设集团有限公司 | Large-span bridge construction resource scheduling optimization method |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102945510A (en) * | 2012-10-23 | 2013-02-27 | 西安理工大学 | Effective method for solving complex resource-constrained project scheduling problem |
-
2014
- 2014-09-04 CN CN201410449558.8A patent/CN104217293A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102945510A (en) * | 2012-10-23 | 2013-02-27 | 西安理工大学 | Effective method for solving complex resource-constrained project scheduling problem |
Non-Patent Citations (2)
Title |
---|
徐丽青等: "求解环境经济调度问题的多目标差分粒子群优化算法", 《西安理工大学学报》 * |
范丽霞: "离散差分进化算法在柔性作业车间调度中的应用研究", 《中国优秀硕士学位论文全文数据库(电子期刊)》 * |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105183640A (en) * | 2015-08-07 | 2015-12-23 | 黑龙江大学 | Real-time task schedulability test copying simulation method based on linear linked list |
CN105183640B (en) * | 2015-08-07 | 2018-06-12 | 黑龙江大学 | Real-time task schedulability test copy analogy method based on linear linked list |
CN110070248A (en) * | 2018-01-19 | 2019-07-30 | 财团法人工业技术研究院 | Dynamic and intelligent dispatching method and device |
CN108446852A (en) * | 2018-03-23 | 2018-08-24 | 西北工业大学 | A kind of multiagent schedule fragments formula coordination optimizing method |
CN108446852B (en) * | 2018-03-23 | 2021-07-30 | 西北工业大学 | Multi-main-body scheduling sectional type coordination optimization method |
CN109190857A (en) * | 2018-10-30 | 2019-01-11 | 武汉大学 | A kind of optimization algorithm based on multiple target Resource-constrained Project Scheduling Problem model |
CN109190857B (en) * | 2018-10-30 | 2021-10-22 | 武汉大学 | Optimization algorithm based on multi-target resource limited project scheduling model |
CN110866586B (en) * | 2019-10-14 | 2021-03-16 | 西南交通大学 | Improved genetic programming algorithm optimization method for resource-constrained multi-project scheduling |
CN110866586A (en) * | 2019-10-14 | 2020-03-06 | 西南交通大学 | Improved genetic programming algorithm optimization method for resource-constrained multi-project scheduling |
CN111027856A (en) * | 2019-12-10 | 2020-04-17 | 浙江工业大学 | Multi-mode resource-limited project scheduling method based on two-dimensional multi-population genetic algorithm |
CN110991917A (en) * | 2019-12-10 | 2020-04-10 | 浙江工业大学 | Multi-mode resource-limited project scheduling optimization method adopting two-stage genetic algorithm |
CN110991917B (en) * | 2019-12-10 | 2022-07-15 | 浙江工业大学 | Multi-mode resource-limited project scheduling optimization method adopting two-stage genetic algorithm |
CN111027856B (en) * | 2019-12-10 | 2022-07-15 | 浙江工业大学 | Multimode resource-constrained project scheduling method based on two-dimensional multi-population genetic algorithm |
CN113344383A (en) * | 2021-06-04 | 2021-09-03 | 兰州理工大学 | Energy-saving workshop scheduling system for distributed heterogeneous factory |
CN115375193A (en) * | 2022-10-24 | 2022-11-22 | 埃克斯工业有限公司 | Method, device and equipment for optimizing double-target production scheduling and readable storage medium |
CN115375193B (en) * | 2022-10-24 | 2023-02-10 | 埃克斯工业有限公司 | Method, device and equipment for optimizing double-target production scheduling and readable storage medium |
CN118569609A (en) * | 2024-08-01 | 2024-08-30 | 四川公路桥梁建设集团有限公司 | Large-span bridge construction resource scheduling optimization method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104217293A (en) | Effective method for solving multi-target resource-constrained project scheduling | |
CN105243458B (en) | A kind of reservoir operation method mixing the difference algorithm that leapfrogs based on multiple target | |
CN107168267B (en) | Based on the production scheduled production method and system for improving population and heuristic strategies | |
CN104866898A (en) | Multi-target flexible job shop scheduling method based on cooperative hybrid artificial fish swarm model | |
Luo et al. | Solving TSP with shuffled frog-leaping algorithm | |
CN111047272B (en) | Project scheduling method and device for multi-language collaborative development | |
CN105629927A (en) | Hybrid genetic algorithm-based MES (Manufacturing Execution System) production planning and scheduling method | |
CN108846570A (en) | A method of solving resource constrained project scheduling problem | |
CN101901425A (en) | Flexible job shop scheduling method based on multi-species coevolution | |
CN102097866A (en) | Mid-long-term unit commitment optimizing method | |
CN102945510B (en) | A kind of effective ways solving complicated resource virtual item scheduling problem | |
CN104331749A (en) | AGV optimization scheduling method based on simulated annealing particle swarm | |
CN103473465B (en) | Land resource spatial configuration optimal method based on multiple target artificial immune system | |
CN103489031A (en) | Method for optimized dispatching in raw material evaporation process of chemical production | |
CN101901426A (en) | Dynamic rolling scheduling method based on ant colony algorithm | |
CN106326987A (en) | Multi-objective optimization method and multi-objective optimization device | |
Zhang et al. | Multi-hive artificial bee colony algorithm for constrained multi-objective optimization | |
CN103592920A (en) | Hybrid flow shop scheduling method with finite buffers | |
CN103020730A (en) | Resource-constrained project scheduling method based on multi-agent evolutionary algorithm | |
CN104392317A (en) | Project scheduling method based on genetic culture gene algorithm | |
CN116957219A (en) | Cement production line construction operation scheduling method based on genetic algorithm | |
CN108830483B (en) | Task planning method for multi-agent system | |
CN111260500B (en) | Hadoop-based distributed differential evolution scheduling method for small hydropower station | |
CN103246923A (en) | Self-adaptive genetic algorithm-based flexible workshop dispatching technology | |
Zhang et al. | The comparative research of solving multi-task scheduling problems with GA and PSO |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20141217 |
|
RJ01 | Rejection of invention patent application after publication |